| 1 | L1₹83,982Accepted-AOC | L1 | Accepted-AOC Lowest 1st | |
| 2 | L2₹1.0 L+₹16,338 (19.5%)Rejected-AOC MOHALLA DESHNAGAR PILIBHIT | PILIBHIT | PILIBHIT | UTTAR PRADESH | L2 | Rejected-AOC Lowest 2nd | |
| 3 | L3₹1.1 L+₹21,818 (26.0%)Rejected-AOC | L3 | Rejected-AOC Lowest 3rd |
Tender Value
₹1.2 L
EMD Value
₹1,180
Closing Date
2 Dec 2023, 12:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE EDC PILIBHIT
NEAR ROADWAYS PILIBHIT
The increasing capacity of 05 nos over loaded distribution transformers from 25 KVA to 63 KVA and 02 nos. new 100 KVA TF installation at different places under EDC-Pilibhit and Bisalpur in Additional Business Plan 2023-24.
2023_MVVNL_836606_2
T-20/EDCP/2023-24
Open Tender
Miscellaneous Works
Item Rate
90 days
Pilibhit/Bisalpur
As per tender form
3 documents required · 3 mandatory
₹1,180
SE EDC
₹1,180
3 Apr 2024
10 Oct 2023
2 Dec 2023
10 Oct 2023
2 Dec 2023
10 Oct 2023
Amount
Safe carriage of healthy transformers from store centre under Electricity Store Division Bareilly to site (Kanjanath Patti, Mudsena Madari, Shahi, Baratbod and Kaichutanda-2) in area of EDD-Pilibhit including loading & unloading and proper mounting of transformers on double pole and laying of cable jumpering and making all HT/LT connections complete work in all respect as transformers as capasity given bellow including loading & unloading.
11/0.4 KV, 63 KVA T/F for increasing capacity from 25 KVA to 63 KVA.
Opening/dismantling of HT/LT all connections from over loaded transfomers , landed of transformers by crane with loading, unloading and safe carriage of released trnasformers from different sites (Kanjanath Patti, Mudsena Madari, Shahi, Baratbod and Kaichutanda-2) under EDD-Pilibhit to store centre-Pilibhit including loading & unloading upto 0-35 Km.
11/0.4 KV, 25 KVA T/F. (Released transformer)
Carriage of following material for installation of 02 nos. new 100 KVA T/F from store centre under Electricity Store Division Bareilly to site of work including loading, unloading and proper stacking at safe site under EDD-Bisalpur Distance.
11/0.4 KV 100 KVA Transformer
PCC Pole 8.5Mtr. Long
Balance material As: - base angle, disk insulator, pin insulator, LT XLPE cable, stay set, earthing rod, T-off channel, clamps, distribution box, AB Cable etc. as per estemate.
Erection of the Double pole structure on PCC. Pole 8.5mtr long complete for 100 KVA T/F including cutting, making holes, fixing of all types of accessories digging of pits complete in all respect, as per RESSPO drawing. Nut, bolt washers would be provided by the contractor.
Concreting of supports at the time of erection of pole in 1:4:8 concrete ratio from bottom of pole to ground level and plinthing of supports upto 300mm above ground level by using cement, sand & coarse aggregate in ratio 1:4:8 as per RESSPO drawing with watering/curing properly upto proper setting of plinthing. All matrial would be provided by the contractor.
Mounting of transformers on double pole and laying of cable jumpering and making all HT/LT connections complete work in all respect.
Erection of stay set with stay wire, stay clamp & stay insulator including with grouting of stay set by concrete of ratio 1:4:8 as per RESSPO norms before back fitting of the pits including binding, climbing, clamping, tightening and nozzeling of stay wire in all respect as per RESSPO norms. Cement. Brick, ballast, sand etc would be provided by the contractor.
Earthing of each PCC Poles of the line is to be done by inserting the MS earth rod (1800x20mm) into soil by hammering and properly fastning with GI wire to each support by nut & bolt. Earthing rod must be 0.15 Mtr.above from the plinth of the support. All type nut & bolt would be given by the contractor.
Fixing of 3 Phase distribution box on pole including proper clamping.
Providing and fixing of danger board on each pole including proper clamping. All material would be provided by firm.
Laying of LT ABC (3X50+1X35+1X16) sq.mm for L.T Line.
Laying of LT XLPE cable (3X70) sq.mm from transformer to L.T Line.
Providing and fixing of I hook with I hook clamp for AB cable
Providing and fixing of ded end clam with for AB cable
Providing and fixing of suspension clamp for AB cable
Providing and fixing of IPC connector for AB cable
POWER AND POWER CONSULTANTS
BARKATI ASSOCIATES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .