| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.3 CrAccepted-AOC | ₹1.3 Cr | L1 | Accepted-AOC L1 |
| Sl No | Description | Qty | Unit | RAJAN P L1 |
|---|---|---|---|---|
| 1.00Repair work | ||||
| 1.00 | 15.31:Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead. | 1,526 | sqm | 170 ₹2,59,420 Lowest |
| 1.00 | 15.41:Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead. | 1,326 | sqm | 40 ₹53,040 Lowest |
| 1.00 | 15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | 10 | cum | 1,400 ₹14,000 Lowest |
| 1.00 | 14.15.1:Renewing wooden battens in roofs, including making good the holes in wall and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete asper direction of Engineer-in-Charge.Sal wood battens | 7.09 | cum | 90,000 ₹6,38,460 Lowest |
| 1.00 | 50.9.13.1:Supplying and fixing Anjily wood wrought and put up for roof members including cost and conveyance of materials etc. complete . | 11.7 | cum | 1,00,000 ₹11,70,400 Lowest |
| 1.01 | OD55889/2024-2025:Re-roofing with departmental MP roofing tiles including all materials to site and all labour charges etc. complete. | 50 | sqm | 70 ₹3,500 Lowest |
| 1.01 | 12.5.1:Providing valleys of 90 cm wide overall in plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limper and bitumen washers complete:1.60 mm thick with zinc coating not less than 350 gm/ m2 | 135 | metre | 1,500 ₹2,02,500 Lowest |
| 1.01 | OD55890/2024-2025:Setting MP hip and ridge tiles sets in lime mortar 1:2 (One lime two sand) including finishing the edges with cost and conveyance of all materials to site and all labour charges etc.complete | 20 | metre | 175 ₹3,500 Lowest |
| 1.01 | OD55891/2024-2025:Pointing the M.P tiles with lime mortar 1:2 (One lime two sand) over tiled roof including preparing mortar, cost and conveyance of all materials to site and all labour charges etc. complete. | 1,400 | sqm | 150 ₹2,10,000 Lowest |
Tender Value
₹1.6 Cr
EMD Value
₹50,000
Closing Date
4 Jun 2026, 3:00 pmClosed
O/o The SE JBC Edappally
O/o The Superintending Engineer,PWD Judicial Blds
repairs of dismantling roof tiles, battens, relaying roof tiles supplying and laying new roof tiles dismantling concrete works
2026_PWD_846878_2
PWD/BLDG/TR/10153/2024_5_1_1/1
Open Tender
Civil Works - Buildings
Item Rate
365 days
Kozhikode
Please refer Tender documents
11 documents required · 11 mandatory
₹5,515
₹50,000
Yes
18 Sept 2026
29 May 2026
6 Jun 2026
29 May 2026
4 Jun 2026
29 May 2026
29 May 2026 - 4 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Repair work | |||||
| 1.001 | 15.31:Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead. | - | sqm | - | - |
| 1.002 | 15.41:Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of unserviceable materials within 50 metres lead. | - | sqm | - | - |
| 1.003 | 15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | - | cum | - | - |
| 1.004 | 14.15.1:Renewing wooden battens in roofs, including making good the holes in wall and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete asper direction of Engineer-in-Charge.Sal wood battens | - | cum | - | - |
| 1.005 | 50.9.13.1:Supplying and fixing Anjily wood wrought and put up for roof members including cost and conveyance of materials etc. complete . | - | cum | - | - |
| 1.006 | OD55889/2024-2025:Re-roofing with departmental MP roofing tiles including all materials to site and all labour charges etc. complete. | - | sqm | - | - |
| 1.007 | 12.5.1:Providing valleys of 90 cm wide overall in plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limper and bitumen washers complete:1.60 mm thick with zinc coating not less than 350 gm/ m2 | - | metre | - | - |
| 1.008 | OD55890/2024-2025:Setting MP hip and ridge tiles sets in lime mortar 1:2 (One lime two sand) including finishing the edges with cost and conveyance of all materials to site and all labour charges etc.complete | - | metre | - | - |
| 1.009 | OD55891/2024-2025:Pointing the M.P tiles with lime mortar 1:2 (One lime two sand) over tiled roof including preparing mortar, cost and conveyance of all materials to site and all labour charges etc. complete. | - | sqm | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1442137.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.05 MB
sbd.pdf
Tender Documents • 1.64 MB
nit.pdf
Other Document • 0.03 MB
BOQ_1442137.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .