| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.9 LAccepted-AOC INFRA HOUSE CHURCH ROAD PALLINADA ERNAKULAM KERALA 682025 | ERNAKULAM | KERALA | 682025 | L1 | Accepted-AOC Agreement Executed | |
| 2 | L2₹21.0 L+₹3.1 L (17.3%)Rejected-AOC | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | Axis Elevators L2 | INFRA ELEVATORS INDIA PVT LTD L1 |
|---|---|---|---|---|---|
| 1.00lift work | |||||
| 1.00 | OD52412/2024-2025:SITC of Passenger Lift- 8 Passenger . Detailed specifications - (1). Type of Lift - Passenger Lift (8 passenger) , Machine room less, (2).No of lifts required : One number (3). Load or persons 544 kg , 8-persons (4). Rate speed 0.60m/s / as per standard (5). Control Microprocessor based V3.F with ARD (6). Travel 12m approx (7). No of floors and entrances served - 4 Nos. (8) No of floors served - 4 Nos. G + 3 floor (9). Method of control Microprocessor based V V V .F with ARD (10). machine room less type (11) Size of lift well 210.mm {Width } X 2080 mm { Depth } (12). Position of counter weight side/Rear side of car (13) Size of car platform As per ISS (14) Drive Variable voltage and variable frequency (15). Operation Collective selective with ON/OFF switch (16). Construction , design and finishing of car body work Stain less steel Vandal proof cabinet with push to talk, emergency light, alarm, music, flooring Granite.Anti skid flooring, hand rail, LCD display car with stainless steel door with half portion glass (900 mm) , indirect led light fitting, fan (17). Car entrance Centre Opening/Automatic Telescopic sliding stainless steel vandal proof doors as per ISS with INFRARED CURTAIN and Clear opening about 900 MM WIDE X 2000 MM HIGHT (18) Hoist way entrance As detailed above. (19). Call and position indicators Up/down direction indication shall be provided at all landings . (20). Electric supply ( power ) Suitable for operating in 415V 50Hz AC supply. (21). Electric supply ( light ) 230V 50Hz single phase 2 wire system (22). Indications, push buttons and other requirements. a. Car position ( Inside the car and at all landings) b. Call indicator( inside the car) c. Push buttons for door close and door open( inside the car) d. Emergency stop button( inside the car) e. Flush mounted switch for fan and light ( inside the car) f. Non stop push button ( Inside the car) g. Battery operated emergency lamp with rechargeable battery ( Inside the car) h. Battery operated alarm bell i. Intercom wiring with one number master unit and 2 slaves j. Fireman's switch at main lobby k. stop/Auto / attendant control key switch( Inside the car ) (23). Winding handle Manual winding wheel /liver for car in case of an emergency. (24). Safeties 1. Over speed governor. 2. Safety gear , Buffers 3. Motor over speed protection 4. Phase reversal protection 5. Final limit switches 6. Other safeties as per ISS 7. Single phase preventer (25). Leveling Automatic leveling at all landings (26). Control panel be accommodated in dust proof sheet metal enclosure. (27). Tests At site as per IS 4666 / 88 to be carried out before handing over. (28). Door opening system Infrared door opening system to be provided for the entire length. (29). ARD Automatic rescue device with an electronic controller and with necessary maintenance free batteries . The rescue shall act within 10 seconds of power failure. (30). Scope work 1. Supply of lift materials 2. Minor / required civil works, including core cutting, channels, angle irons, MS plates, etc as required 3. Scaffolding 4. Quoted Rate shall be inclussive of charges for 3 year CAMC after completion of one year free service (Total 4 years after handing over the lift to authorities.). 5. Battery operated alarm. 6. Battery operated light 7. Architraves 8. Intercom facilities with one master and two slaves 9. Door frames 10.Supporting steel 11.Temporary electric supply for installation of lift. Electric supply for testing and commissioning of lift is to be arranged by the firm on their own account. 12.Supply of booklet with complete details of maintenance schedule and control diagram. 13.Giving training to department staff for attending trouble shooting. 14. Formation and construction of buffer block. 15. Supply of tool kit ( List to be furnished along with tender) 16.Obtaining scheme approval as well as energization certificate from the Electrical Inspectorate including preparation of necessary drawings for the same. Necessary fee shall be remitted to the Inspectorate by the firm for which no refund will be made from the department. (31). Guarantee Company shall carried out free maintenance during warranty period which shall include 1. Cleaning lift equipment 2. Lubricating all required places 3. Replacing of Lubricating Oil when required 4. Checking and adjusting contacts 5. Replacing fusible items , alarms etc 6. Recharging / replacing batteries in case of such requirements 7. Replacing/Rewinding motor if required. 8. Replacing/Rewinding all defective part of the lift including V3F unit if found necessary . | 1 | each | 20,24,975 ₹20,24,975 | 17,68,500 ₹17,68,500 Lowest |
| 1.00 | OD52413/2024-2025:Charges for preparation of Electrical/fire Drawing per A3 sheet first copy | 3 | each | 25,000 ₹75,000 | 7,600 ₹22,800 Lowest |
| 1.00 | OD52414/2024-2025:Copying charges of Electrical/fire Drawing per A3 sheet additional copies | 9 | each | 500 ₹4,500 | 300 ₹2,700 Lowest |
Tender Value
₹21.8 L
EMD Value
₹50,000
Closing Date
19 Mar 2026, 3:00 pmClosed
Assistant Executive Engineer
LID and EW Division, Pathanamthitta
Annual Plan- JP-Pr. No.S1005/24-Providing Lift at District Panchayath Office- General Electrical Work
2026_LSGD_833060_2
12/2025-26/AEE/LID and EW/PTA
Open Tender
Electrical Works
Item Rate
90 days
Pathanamthitta
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
₹50,000
31 Jul 2026
11 Mar 2026
23 Mar 2026
11 Mar 2026
19 Mar 2026
11 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1lift work | |||||
| 1.001 | OD52412/2024-2025:SITC of Passenger Lift- 8 Passenger . Detailed specifications - (1). Type of Lift - Passenger Lift (8 passenger) , Machine room less, (2).No of lifts required : One number (3). Load or persons 544 kg , 8-persons (4). Rate speed 0.60m/s / as per standard (5). Control Microprocessor based V3.F with ARD (6). Travel 12m approx (7). No of floors and entrances served - 4 Nos. (8) No of floors served - 4 Nos. G + 3 floor (9). Method of control Microprocessor based V V V .F with ARD (10). machine room less type (11) Size of lift well 210.mm {Width } X 2080 mm { Depth } (12). Position of counter weight side/Rear side of car (13) Size of car platform As per ISS (14) Drive Variable voltage and variable frequency (15). Operation Collective selective with ON/OFF switch (16). Construction , design and finishing of car body work Stain less steel Vandal proof cabinet with push to talk, emergency light, alarm, music, flooring Granite.Anti skid flooring, hand rail, LCD display car with stainless steel door with half portion glass (900 mm) , indirect led light fitting, fan (17). Car entrance Centre Opening/Automatic Telescopic sliding stainless steel vandal proof doors as per ISS with INFRARED CURTAIN and Clear opening about 900 MM WIDE X 2000 MM HIGHT (18) Hoist way entrance As detailed above. (19). Call and position indicators Up/down direction indication shall be provided at all landings . (20). Electric supply ( power ) Suitable for operating in 415V 50Hz AC supply. (21). Electric supply ( light ) 230V 50Hz single phase 2 wire system (22). Indications, push buttons and other requirements. a. Car position ( Inside the car and at all landings) b. Call indicator( inside the car) c. Push buttons for door close and door open( inside the car) d. Emergency stop button( inside the car) e. Flush mounted switch for fan and light ( inside the car) f. Non stop push button ( Inside the car) g. Battery operated emergency lamp with rechargeable battery ( Inside the car) h. Battery operated alarm bell i. Intercom wiring with one number master unit and 2 slaves j. Fireman's switch at main lobby k. stop/Auto / attendant control key switch( Inside the car ) (23). Winding handle Manual winding wheel /liver for car in case of an emergency. (24). Safeties 1. Over speed governor. 2. Safety gear , Buffers 3. Motor over speed protection 4. Phase reversal protection 5. Final limit switches 6. Other safeties as per ISS 7. Single phase preventer (25). Leveling Automatic leveling at all landings (26). Control panel be accommodated in dust proof sheet metal enclosure. (27). Tests At site as per IS 4666 / 88 to be carried out before handing over. (28). Door opening system Infrared door opening system to be provided for the entire length. (29). ARD Automatic rescue device with an electronic controller and with necessary maintenance free batteries . The rescue shall act within 10 seconds of power failure. (30). Scope work 1. Supply of lift materials 2. Minor / required civil works, including core cutting, channels, angle irons, MS plates, etc as required 3. Scaffolding 4. Quoted Rate shall be inclussive of charges for 3 year CAMC after completion of one year free service (Total 4 years after handing over the lift to authorities.). 5. Battery operated alarm. 6. Battery operated light 7. Architraves 8. Intercom facilities with one master and two slaves 9. Door frames 10.Supporting steel 11.Temporary electric supply for installation of lift. Electric supply for testing and commissioning of lift is to be arranged by the firm on their own account. 12.Supply of booklet with complete details of maintenance schedule and control diagram. 13.Giving training to department staff for attending trouble shooting. 14. Formation and construction of buffer block. 15. Supply of tool kit ( List to be furnished along with tender) 16.Obtaining scheme approval as well as energization certificate from the Electrical Inspectorate including preparation of necessary drawings for the same. Necessary fee shall be remitted to the Inspectorate by the firm for which no refund will be made from the department. (31). Guarantee Company shall carried out free maintenance during warranty period which shall include 1. Cleaning lift equipment 2. Lubricating all required places 3. Replacing of Lubricating Oil when required 4. Checking and adjusting contacts 5. Replacing fusible items , alarms etc 6. Recharging / replacing batteries in case of such requirements 7. Replacing/Rewinding motor if required. 8. Replacing/Rewinding all defective part of the lift including V3F unit if found necessary . | - | each | - | - |
| 1.002 | OD52413/2024-2025:Charges for preparation of Electrical/fire Drawing per A3 sheet first copy | - | each | - | - |
| 1.003 | OD52414/2024-2025:Copying charges of Electrical/fire Drawing per A3 sheet additional copies | - | each | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1430291.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.40 MB
FOT029.pdf
Tender Documents • 0.25 MB
PRE029.pdf
Tender Documents • 0.19 MB
SBD029.pdf
Tender Documents • 4.75 MB
BOQ_1430291.xls
BOQ • 0.30 MB
EPAY.pdf
Tender Documents • 0.24 MB
IPACT.pdf
Tender Documents • 0.24 MB
Affidavit029.pdf
Tender Documents • 0.23 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .