Loading…
Loading…
Tender ID
Tender Value
₹50.0 L
EMD Value
₹50,000
Closing Date
6 Mar 2026, 6:00 pmClosed
Dy.Minicipal Commissioner - West Zone
Const,. of RCC Road and Paver Block in Ekta Nagar, Shivshankar Nagar, Hariom Nagar, Gupta Nagar, from the budget of the Municipal Councilor, MP/MLA and others. different chalis o n the P. Zone Vasana ward, in West Zone ARC)
281936
8/25-26 (T.N.64)
Open
Civil Works - Others
Works
Ahmedabad
4 documents required · 0 mandatory · 4 optional
₹1,500
Yes
Municipal Commissioner, Ahmedabad
₹50,000
Yes
3 Mar 2026
3 Mar 2026
3 Mar 2026
6 Mar 2026
3 Mar 2026
Item DISCRIPTION Quantity Unit Rate Amount
Box cutting the road surface to proper slope
and camber for making a base for road work
1 including removing the excavated stuff and 1010.00 127.13 ₹
depositing on the road side slope as directed
upto 200 Mt.lead
Dismantling the following including loading,
unloading and disposal of unserviceable
material for all lead or as directed by
Engineer-In-Charge and stacking the
serviceable material and backfilling the
resulting trenches and pits complete.
a central verge -kerb stone 155.00 8 8.00 ₹
Dismantling tiled or stone floors laid in
mortar including stacking of serviceable
material and disposal of uservicalble material
with all lead and lifts.
Conveyance charge of earth,lime,murrum,
building rubbish,manual garbage,sludge
,excavated rock,fly ash, aggregate of any
kind etc. comp. up to 5 Km. lead
Repairing damaged M.H. and rasing M.H. up to
road level incl. removing damaged brick work
and repairing by brick masonry in C.M. 1:5
and plaster in C.M. 1:3 and fixing C.I. steps and
existing MH sheet cover, removing the debris
from MH and carting the same as directed.
(A) up to 0.15 mt. (@ Two Coarse)
(B) up to 0.35mt. (@ Four Coarse)
Repairing damaged I.C./ Raising removing
damaged brick work and repairing by brick
masonry in C.M. 1:5 and plaster in C.M. 1:3
and fixing C.I. steps and existing chamber Nos.
sheet cover, removing the debris from
chamber and carting the same as directed.
Supplying and fixing of 300 mm-L x 150 mm-
B x 380 mm-H Kerb block for Footpath in M-
20 grade using 20 mm nominal size black trap
aggregate of Sevaliya/Timba or equivalent
quality for pre-cast blocks, reasonably
exposed finish/ formwork , mould with well
equipped with vibratory system for kerb
stones of approved design including curing,
etc. complete, including the cost of formwork
etc. complete. The rate shall also include
necessary cutting of asphalt, fixing the Kerb
stones in line and level on 5 cm thick sand Rmt
bedding with necessary equipments and
materials. The rate shall also include the flush
pointing in CM (1:3) for all joints of the
kerbstones. Filling of zari alone the sides of
the kerb stone fixed with Bituminous concrete
mixed in proper position as directed by
Engineer in change to form a portable
mixture. In any case Gravel or such type of
materials shall not be allowed for production.
a) Laying on 5 cm thick Sand Bedding
Providing and Laying of Rubber Moulded
Paver Block Grey/Coloured 60 mm thick, M-
35 Grade of any size ; shape (Usually Uni-
Paver Blocks) using black trap good quality
aggragate of 20 mm nominal size for footpath,
parking areas, service lanes and other
areas as mentioned in the drawing /
instruction of engineer in charge. Cost
includes formworks using rubber mould, Rate
providing and laying paver blocks as per
required grading and specification. The paver
block shall be mechanically compacted. The
work of paving blocks shall be executed in
line and level by skill mason of flooring work
only. It should be laid in such a way that the
no cutting of the paver block to be necessary.
if cutting of paver block necessary then it
should be cut by machine only and carting.
The finished surface of the paver block shall
have resonably good, plain finished. Paver
blocks shall be compacted and shall be relaid
if necessary. Gravel or such type of materials
shall not be allowed for production. Laying
on 5cms thick sand beddding.
Providing and laying cement concrete 1:4:8
(1- Cement : 4 - Coarse aggregate : 8-Hand
8 broken stone aggregates 40 mm nominal size) 180.00 2105.71 ₹
and curing complete excluding formwork in
(A) Foundation and plinth.
Providing and laying cement concrete
1:3:6 (1- Cement : 3- Coarse sand : 6-
Hand broken stone aggregates 40mm 150.00 4006.15 ₹
nominal size) and curing complete.
SOR 23-24 IT NO :05005A
Providing F.R.C. MH seat cover incl. carting
9 to the work site etc. comp. Directed.(AMC 0.00 0.00 ₹ -
approved Rate Central Store 2023)
F.R.C. Extra Heavy Duty (EHD-35)
Manhole Covers & Frames Cover :
728mm ø & 100 mm thick circular
cover, 35.00 MT load design, 100x2mm MS
flat allround, 16mm ø plain round bar for
lifting the cover & should be fitted with
plastic cups. Frame : 560 mm ø clear
opening, outer size- 888x888x175 mm. On
the upper periphery of frame 25 x 3 mm wide
MS flat should be well embed in concrete
to protect the edges of frame. FRC E.H.D.-35
manhole cover & frame described as above.
FRC heavy duty cover size 730 mm. &
mm thick circular Cover20 M.T. design load
and frame size 560 mm clear opening size
FRC medium duty cover size 670 mm dia &
70 mm thick 10 M.T. load design and
frame size 560 mm clear opening outer
size 780 x 780 x 120 mm
FRC light duty Chamber seat cover (FRC)
E cover with rectangular frame (LD-2.5) Cover 20.00 No. 1631.00 ₹
& Frame - 600 x 450mm clear opening,
Providing, laying, spreading and compacting
graded stone aggregate to wet mix macadam
specification including premixing the Material
with water at OMC in mechanical mix plant
9 carriage of mixed Material by tipper to site, ₹ -
laying in uniform layers in sub- base / base
course on well prepared surface and
compacting with vibratory roller to achieve
the desired density as per Codal Provision.
A Production & Supply of WMM 150.00 Cmt 1975.00 ₹
B Laying of WMM 150.00 Cmt 35.00 ₹
Providing and laying in position Ready Mixed
M-200 grade concrete for reinforced cement
conctere work, using cement content as per
approved Design Mix manufactured in fully
automatic batching plant and transported to
site of work in transit mixer for a lead up to
10 kms having continuous agitated mixer,
manufactured as per mix design of specified
grade for reinforced cement concrete work
10 including pumping of R.M.C. from transit 240.00 Cmt 3980.17 ₹
mixer to site of laying, excluding the cost of
centering shuttering finishing and
reinforcement including cost of admixtures in
recommended proportions as per IS: 9103 to
accelerate/retard setting of concrete, improve
workability without impairing strength and
durability as per direction of the Engineer - in
- charge. Without Fly Ash (Mincement level as
per latest IS 456 shall be maintained)
Providing formwork of ordinary timber
planking so as to give a rough finish including
centering shuttering strutting and propping
etc. Height of propping and centering below
11 supporting floor to ceiling not exceeding 4 M. 200.00 Smt 102.19 ₹
and removal of the same for in situ reinforced
concrete and plain concrete work in. (A)
Foundations Footings Bases of Columns
etc.and Mass concrete
Providing TMT Bar FE500D reinforcement for
R.C.C. Work including bending,binding and
placing in position complete upto floor two
P/A Tremix with dewartering machine and
floater machine on constructed CC work for
finishing the surface as per requirement. The
rate including allmachinaries, labor, loading,
unloading, ransportaion etc complete as per
direction given by engineer in charge.
Making 15 mm. Groove in RCC work on road
& filling it with polysulfied selant & finished
ot good incl. all labour charges etc. comp.as
Extra Rate Over Item of Excavation of Earth
for excavation of asphalt pavement / RCC of
thickness up to 0.20 meter including
demolishing the asphalt carpet, metal,s
oiling/cutting Reinforcement etc.comp. with
stacking the material as directed.
a up to 0.20 meter thickness (By Manual) 144.00 Smt 71.10 ₹
0.20 to 0.30 meter (By any type of Breaker
Machine or R.C.C.Cutter machine including
cost of operator, fuel, & transportation etc
0.30 meter & above (By any type of Breaker
Machine or R.C.C.Cutter machine including
cost of operator, fuel, & transportation etc
Supplying Pneumatic Breaker Machine for
RCC Slab or Asphalt Demolishing Work on site
by using Operator, fuel, power Supply etc.
Complete as Directed.
Contractor signature Addi. City Engineer
AHMEDABAD MUNICIPAL CORPORATION
West Zone, Zonal Office", 2nd Floor, A.M. Office, Dr. Ramanbhai Patel Bhavan, Usmanpura,
Ahmedabad Municipal Corporation, W.Z. Office, Ahmedabad-380013.
Municipal Commissioner invites Percentage Rate sealed tenders from interested
MEMORANDUM OF WORKS IN BRIEF
1 Name of work v.Ítul JtmKt Jtuzobtk yuf<t ldh,rNJNkfh ldh,nheytub ldh,dwÃ<tldh le swœe swœe
atjeytubtk søgtyu Bgw.ftWLmejh, yuub.ve/yub.yuj.yu <&t yLg csuxbtk&e yth.me.me
htuz <&t vuJh jdtJJtlt ftb ctc<. (ARC)
2 Time Limit 12 Months
3 Tender Validity Period 120 Days from the date of opening of the tender
4 Eligibility Criteria Register “E1” class in PWD in Govt. R&B/CPWD/AMC or equivalent
registration with any other state Govt. or institutions.
5 Estimated Cost put to ₹
6 Earnest Money Deposit Rs. 50,000/- (Demand Draft or pay order in favour of Municipal Commissioner,
Ahmedabad /) To be submitted as prescribed in 9.0 below. Demand Draft or Bank
Guarantee shall be from Nationalized Bank / Sheduled Bank and valid for 120 days. (As
per AMC finance dept.circular No-5 Dt.5/5/07 & F.D. Circular No. 29 Dt. 7/08/2010).
.(As per AMC finance dept.circular No-5 Dt.5/5/07 & F.D. Circular No.
Dt.7/08/2010) & attched ANNEXURE - 1 finance dept.circular No- 14 Dt.4/6/13,
Circular No. 12 Dt.14/06/2021) & attched ANNEXURE - 1 finance dept.circular No-
7 Security Deposit 5% of the Sanctioned Tender Amount in form of Bank Guarantee/
Demand Draft / Local MICR Cheque.
8 Tender fees Rs.1500.00/-Demand Draft in favour of Municipal Commissioner,
(Non refundable) Ahmedabad)
9 Submission of EMD and In separate sealed cover each for EMD and Tender Fees along with
Tender Fees Tender as described in the invitation of tender and submitted to Assistant
Manager (west zone),Ahmedabad Municipal Corporation, West Zone,
Zonal Office", Dr. Ramanbhai Patel Bhavan, Usmanpura, Ahmedabad.
10 Tenders issue date Tenders from the AMC website www.egovamc.com shall be down loaded
from AS PER TENDER NOTICE INVITED
11 Last date of receiving As per Notic inviting Tender / Addendum / Corrigendum.. The
Tenders. tenders received after latest schedule date and time will not be entertained
under any circumstances.
12 Date of Opening As per Notic inviting Tender / Addendum / Corrigendum (only
Techanical Bid) to Assistant Manager / Dy.C.E.(W/Z) office, 2nd Floor,
Dr. Ramanbhai Patel Bhavan,Usmanpura, Ahmedabad Municipal
Corporation, W.Z. Office, Ahmedabad-380013
13 Mode of sending the This is a two bid System Tender Hence Financial Bid shall be Opened
Tender Documents and only for the Technically Qualified Bidders.
evalution of tender Document shall be physically submitted in sealed envelope (two-bid
system) By RPAD/Speed post/ Hand Delivery in sealed covers in
Duplicate (One Original & One Duplicate) duly sign & seal by contractor
EMD in the form of Demand Draft/ Bank Guarantee shall be sealed in
separate envelope and along with Volume-I marked Envelope ‘A’ only
(Technical Bid). and Volume-II shall be sealed in another separate
envelope, marked envelope ‘B (Financial Bid). Both envelopes ‘A’ and
‘B’ shall then be sealed in one large envelope.
The first envelope ‘A’ containing technical bids from the bidders received,
shall be opened in the presence of the bidder’s representatives as per NIT
and the technical bids shall be scrutinized by AMC for satisfying eligibility
criteria for the bidders for this work. Then, the financial bids – Volume-II
(envelope ‘B’) from the eligible tenderers only shall be opened. The actual
date of opening of financial bids shall be communicated to technically
qualified bidders at a later date.
Tenders received without EMD shall be considered as Non-Responsive and
shall be rejected outright. ..
14 Terms, Condition, & All general condition of contract of Form B1 condition of contract shall
Specification be applicable..
15 Defect &Liability Period The contractor shall be responsible to make good and remedy at his own expense
any defect which may develop or may be noticed before the period mentioned
hereunder from the certified date of completion, The within 15 days of receipt of
the notice. In the case of failure on the part of the contractor, the Engineer-in-
charge may rectify or remove or re-execute the work at the risk & cost of the
contractor. The Engineer-in-charge shall be entitled to appropriate the whole or
any part of the amount of security deposit towards the expenses, if any, Incurred
by him in rectification, removal or re-execution. The Defects Liability period
shall be as under(a) for all works costing upto Rs. 50,000 ( amount put to
tender), the period shall be 3 months from the certified date of completion.
(b) for all works costing more than Rs. 50,000 and upto Rs. 1 crore (amount put
tender), the period shall be 6 months from the certified date of completion or one
monsoon, whichever is later.
(c) for major projects costing more than Rs. 1 crore, the period shall be
months from the certified date of completion which should include one
(d) For building works, the period specified in (a), (b) or (c) above OR elapse of
monsoon period following the certified date of completion, whichever is later.
For the purpose of deciding the monsoon period, the 30th September may be
treated as the last date.
16 Time permitted to start Whenever a work is allotted by Engineering staff, whether minor or major
parts of work of part thereof of any amount, the contractor shall be bound to start the
works within 48 hours of intimation of work. Communication done
telephonically via SMS, Via Whatsapp and through letter / E-mail shall be
considered legal and binding for the same. Failure of comply to start the
works in 48 hours of intimation as above by contractor the contractor shall
be levied penalty of (1) Rs.1000/- per day (for tenders amounting upto
Lakhs), (2) Rs.2500 per day (for tenders amounting above 10 Lakhs and
upto 30 Lakhs), (3) Rs.5000 per day (for all tenders amounting above
Lakhs). Three times failures by contractor shall make contractor
responsible to be black listed unless and otherwise justified properly in
writing / binding within 15 days of last notice of penalty.
17 Compensation for Delay 10% of Remaining work
18 Addendum/Corrigendum Addendum/Corrigendum If any Shall be Published 48 Hrs. Price To the
Final Submission Time And Date. The Same Shall From a part Of Tender
And The Same As to be Attached Along With The Tender Document.
19 EPF Act As per Acoount Department circular no-37 Date:09/08/2018
Conditional tenders will not be accepted. Municipal Commissioner reserves the rights to reject any or all
the tenders without assigning any reasons thereof.
Seal and Signature of the Bidder Add City Engineer
(West Zone) (West Zone)
As per account department(A.M.C.) circular no. 12, Dt.14/06/2021 Bank guarantee of
said work must be of Ahmedabad city branch, which mentioned as bellow.
(A) Guarantee issued by following bankswill be accepted as SD/EMD on permanentbasis.
(1) All Nationalized Banks including the Public Sector Bank-IDBI LYF.
(B). Guarantees issued by following banks will be accepted as SD/EMD for the period up
to March- 31, 2022. The validity cut-off date in the GR is with respect to the date of
issue of Bank Guarantee irrespective of the date of termination of Bank Guarantee.
1 Commercial Banks :-
5. Kotak Mahindra Bank
6. IndusInd Bank
8. Tamilnadu Mercantile Bank
9. Ujjivan Small Finance Bank
10. A U Small Finance Bank
11. Federal Bank
12. Equitas Small Finance Bank
13. Bandhan Bank
14. Standard Chartered Bank
15. City Union Bank
2 Co-operative and Rural Banks Of Gujarat :-
1. The Mehsana Urban Co-operative Bank Ltd
2. The Ahmedabad Mercantile Co-Operative Bank Ltd
3. Nutan nagrik Sahakari Bank Ltd
4. The Kalupur Commerical Co-operative Bank Ltd
5. Rajkot Nagarik Sahakari Bank Limited
6. The Gujarat State Co-Operative Bank
7. Sarswat Bank
8. Saurashtra Gramin Bank
Seal and Signature of the Bidder Addl City Engineer
AHMEDABAD MUNICIPAL CORPORATION
Invitation for Bid (IFB)
1. The AHMEDABAD MUNICIPAL CORPORATION, (hereinafter called “the Employer”) invites
sealed Tender document from reputed and qualified bidders for the construction of Works detailed in the
Sr. Name of Works Approximate Earnest Completi
No. value of works Money on
(Rs.) Deposit (Rs.) Period
1 v.Ítul JtmKt Jtuzobtk yuf<t ldh,rNJNkfh ₹ 49,99,998.42 Rs. 50,000/-
ldh,nheytub ldh,dwÃ<tldh le swœe swœe Months
atjeytubtk søgtyu Bgw.ftWLmejh,
yuub.ve/yub.yuj.yu <&t yLg csuxbtk&e
yth.me.me htuz <&t vuJh jdtJJtlt ftb ctc<.
2. Interested bidders shall download the tender documents from AMC’s website
www. amcnprocure.com/ www.nprocure.com.
3. Tender (a complete set of bidding document) fee shall be Rs. 1500.00 in the form of Demand Draft /
Pay Order from any Nationalised Bank in favour of MUNICIPAL COMMISSIONER, Ahmedabad,
payable at Ahmedabad, which shall be non refundable. The Details of Tender fees shall be submit with
scan copy at the time of Quoting price bid of the tender and Physically to be submitted along with
technical bid Vol.-1 with other enclosure.
4. All bids must be accompanied by Earnest Money Deposit of the amount specified for the Works in the
above Table payable at Ahmedabad and drawn in favour of MUNICIPAL COMMISSIONER,
Ahmedabad, payable at Ahmedabad,. Earnest Money Deposit will have to be specified in Clause 2 of
Financial Condition.
5. Physical submission must be delivered to Asst. Manager (Admin) West Zone, 2nd Floor,Dr.
Ramanbhai Patel Bhavan, Usmanpura, Ahmedabad Municipal Corporation, W.Z. Office,
Ahmedabad-380013.
6. The Bids will be opened at the office of Addl.City Engineer (W/Z) , Ahmedabad Municipal
Corporation, 2nd Floor, Dr. Ramanbhai Patel Bhavan, Usmanpura, Ahmedabad Municipal Corporation,
W.Z. Office, Ahmedabad-380013. in the presence of bidders or their representatives who choose to attend.
In the event of the specified date of bid submission/opening being declared a holiday for the Employer,
the bids shall be received /opened on the next working day at the same place and the same time.
TERMS & CONDITIONS
( A ) INSTRUCTIONS TO BIDDERS (ITB)
( B ) GENERAL TERMS & CONDITIONS
( C ) FINACIAL TERMS & CONDITIONS
( D ) MAIN CONDITION / FETURES OF THE WORK
AHMEDABAD MUNICIPAL CORPORATION
TERMS & CONDITION
( A ) INSTRUCTIONS TO BIDDERS (ITB)
1. Procedure for Submission of Tender
a).This is a Two bid System Tender.The Bidder should quote the price bid in tender form before schedule
time Tender Document Vol. 1 , tender fee & EMD (Draft /DD) and all other enclosures as asked in tender.
b).The bidder shall submit the following Tender documents physically in hard copy in two separate
envelope (marked as “original” and other marked as “Duplicate”) in schedule time by RPAD/ Speed
Post/ Hand Delivery in duplicate.Seprate envolup to be submitted by the bidder clearly marked as
“Technical Bid” and “Financial/Price bid” Price bid shall Remain Only the Price bid, Whenever
all othe Documents to be submitted Under The envolup of “ Technical Bid” This envelope shall be
sealed in an outer envelope. The Bid envelopes shall be marked as follows:-
Tender Document
Registration certificate of class
c).The envelope shall be addressed to the Employer at the following address:
Asst. Manager (Admin) West Zone,
2nd Floor,Dr. Ramanbhai Patel Bhavan,
Usmanpura, Ahmedabad Municipal Corporation,
W.Z. Office, Ahmedabad-380013
d).Bear the following identification:
“TO BE OPENED ONLY IN PRESENCE OF THE EVALUATION COMMITTEE”
e). Indicate the name and address of the bidder.
If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility
for the misplacement or premature opening of the bid.
f).All information has to be typed or hand written legibly. All pages of the Bid have to be initialed by the
g) All The Bid Document Essentially Needs to be Properly binded/steppled
2. Assessment of Submission
2.1The Employer will open the technical bid of physically submitted document of all the bids received
for the package (except those received late) containing the sealed Tender volume and other enclosures
then announce the names of bidders in the presence of bidders or their representatives who choose to
attend on the date and time mentioned in the NIT In the event of specified date of bid opening being
declared as a holiday for the Employer, the Tender will be opened at the appointed time and location
on the next working day.
2.2 In Physical submission, Bidders detailed and tender fee, E.M.D. shall be opened first. The Employer at
the opening will announce bidder’s names, , the presence/or absence of EMD, the amount and validity
of EMD furnished with each bid, is valid registration and such other details, as the Employer may
consider appropriate. As per the checklist.
2.3 The Employer will determine whether the bid is accompanied by the required EMD.
2.4 If the EMD furnished does not conform to the amount and validity period as specified in the Invitation
for Bid and has not been furnished in the form, the bid shall be rejected by the Employer as non-
responsive and the Tender volume will be returned to the bidder.
2.5 Subject to confirmation of the EMD by the issuing bank, the Tender volume accompanied with valid
EMD will be taken up for further evaluation. In case, the Bank does not confirm the EMD, the bid
shall be rejected as non-responsive and no further evaluation carried out.
2.6 The tender volume will further be examined to determine whether the bid has been properly
signed, meets the eligibility and qualification criteria, has the required available bid capacity, is
accompanied by the requisite certificates, undertaking and other relevant information specified in the
bid documents and is substantially responsive to the requirement of the bidding documents and
provides any clarification for ascertaining the correctness of the information/details.
2.7 If the Tender volume is not substantially responsive, it will be rejected by the Employer and will not
subsequently be made responsive by correction or modification or withdrawal of the nonconforming
deviation or reservation.
3. Evaluation and Comparison of Tender volume
The Employer will evaluate and compare only those Tender volumes which are determined to be
substantially responsive in accordance with Clause 2 and qualified for award of Contract in
accordance with Clause 5(General Terms and Condition).
4. Procedure for Tender Opening
Received copies of tender in physical form with in schedule time, will be open on schedule date and
time. In the event of specified date of bid opening being declared bidders who qualify the criteria then
bidder bid will be considered for opening of price bid.(Following clause no. 5 of ITB).
5.1 The Employer will award the Contract to the bidder whose bid has been determined to be substantially
responsive to the bidding documents and who has offered the lowest Evaluated Bid Price, provided
that such bidder has been determined to be (i) eligible in accordance with the provisions of Clause
3(General Terms and Condition); and (ii) qualified in accordance with the provisions of Clause
5(General Terms and Condition).
6. Notification of Award
6.1 Prior to expiration of the period of bid validity prescribed by the Employer, the Employer will notify
the successful bidder by cable/fax and confirmed by registered letter that his bid has been accepted.
This letter shall name the sum which the Employer will pay the Contractor in consideration of the
execution, completion and maintenance of the Works by the Contractor as prescribed by the Contract.
6.2 The notification of award will constitute the formation of the Contract.
7. A successful Bidder has to deposit security deposit / Bank Guarantee as per As per City Engineer
Circular (WRM) no. 6 2011/12 DT: 24/06/2011 after receiving letter of Indent. Time limit of
work will commence from the date of issue of work order.
8. Clarification of Bids
8.1 To assist in the examination, evaluation and comparison of bids, the Employer may, at his
discretion, ask any bidder for authentication the correctness of the information/details furnished by
him in his bid. Such request by the Employer and the response by bidder shall be in writing or by
8.2 Subject to above clause, no bidders shall contact the Employer on any matter relating to his bid
from the time of bid opening to the time contract is awarded.
8.3 Any effort by the bidder to influence the Employer in the Employer’s bid evaluation, bid
comparison or contract award decisions may result in the rejection of his bid.
9.1 Information relating to the examination, clarification, evaluation and comparison of bids and
recommendations for the award of a contract shall not be disclosed to bidders or any other persons not
officially concerned with such process until the award to the successful bidder has been announced.
Any effort by a bidder to influence the Employer's processing of bids or award decisions may result in
the rejection of his bid.
10.1 The bidder is advised to visit and examine the Site of Works and its surroundings and obtain for itself
on its own responsibility all information that may be necessary for preparing the bid and entering into
a contract for construction of the Works. The costs of visiting the Site shall be at the bidder’s own
10.2 The bidder and any of its personnel or agents will be granted permission by the Employer to enter its
premises and lands for the purpose of such inspection, but only upon the express condition that the
bidder, its personnel and agents, will release and indemnify the Employer and its personnel and
agents from and against all liability in respect thereof and will be responsible for death or personal
injury, loss of or damage to property and any other loss, damage, costs and expenses incurred as a
result of the inspection.
11.0 Cheklist for submition of Technical Bid.
11.2 valid Registration Copy.
11.3 Valid E.M.D
AHMEDABAD MUNICIPAL CORPORATION
TERMS & CONDITION
( B ) GENERAL TERMS & CONDITIONS
1. Scope of Bid
1.1 The Ahmedabad Municipal Corporation hereinafter called "the Employer" invites Tender document
for the construction of works (as defined in these documents, hereinafter referred to as "the Works")
detailed in the table given in the IFB.
1.2 The Works consist of: “as Above "
Source of Funds
1.1 The expenditure on these Works will be met by AHMEDABAD MUNICIPAL CORPORATION.
3. Eligible Bidders
3.1 This invitation for bids is open to bidders who has necessary bid capacity and who meet the following
A bidder shall not be under a declaration of ineligibility for corrupt or fraudulent practice.
The bidders shall have a registration with State PWD, and/or CPWD for "E1" class and or
equivalent. If contractor is not registered with AMC in the relevant class, on award of contract he
shall be required to register himself with AMC within 3 month's time.
Bidders shall provide such evidence of their continued eligibility satisfactory to the Employer, as the
Employer shall reasonably request.Subject to Submition of Succsesful Submition as per Clause –II of
4. Eligible Material, Equipment and Services
4.1 At the Employer's request, the bidder having offered the lowest evaluated financial bid may be
required to provide evidence of the origin of materials, equipment, and services to the satisfaction of the
4.2 For purposes of Sub Clause 4.1, "origin" means the place where the materials are mined, grown,
produced or manufactured; similarly for equipments and from where the services are provided.
5. Qualification of the Bidder
To be qualified for award of Contract, bidders shall:
a) Submit a written power of attorney authorizing the signatory of the bid to commit the
General information
All individual firms must complete the information in this form. Nationality information shall be provided
for all owner(s) or applicant(s) that are partnership or individually owned firms.
1 Name of firm:
2 Head office address With Contact no.:
3 Local office address (if any) With Contact no.:
4 Telephone/ Contact With name :
5 E-mail address:
6 Place of incorporation/registration:
7 Year of incorporation/registration:
Additional information regarding litigation, debarment, arbitration, etc.
Authorised Signeture Bidder
5.3 Disqualification
Even though the Bidders may meet the above criteria, they are subject to be disqualified for any of the
following reasons:
a) Misleading or false representation in the forms, statements and attachments submitted and included in
b) Record of poor performance such as abandoning the work, rescinding of contract for which the reasons
are attributable to the non-performance of the contractor, consistent history of litigation awarded
against the applicant or financial failure due to bankruptcy.
c) Has been identified by the Employer as poor performer in implementation of ongoing AMC works.
d) The bidder fill (tender) in percentage rate above or below and total amount (both in figures and words)
d) The bidder fill (tender) in percentage rate above or below and total amount (both in figures and words)
only in E-Tender (Online) Not to fill in hard copy of Tender documents
5.4 Debarment/Black listing
Notwithstanding the above, the Employer may debar or blacklist any of the bidder(s) for their misleading
or false representations in the forms statements etc. for the period to be decided by the Employer.
6. One Bid per Bidder
6.1 Each bidder shall submit only one bid per contract package either by himself or as a partner in a joint
venture. A bidder who submits or participates in more than one bid for a contract package will be
7. Bidding Documents
The bidder is expected to examine carefully the contents of all the above bid documents. Failures to
comply with the requirements of bid documents will be at the bidder's own risk. Pursuant to Clause
bids which are not substantially responsive to the requirements of the bidding documents will be rejected.
8. Language of Bid
The bid, and all correspondence and documents related to the bid exchanged between the bidder and the
Employer shall be written in the English language. Supporting documents and printed literature furnished
by the bidder may be in another language provided they are accompanied by an accurate translation of the
relevant passages in the English language, in which case, for purposes of interpretation of the bid, the
English translation shall prevail.
9.1. Unless stated otherwise in the bidding documents, the Contract shall be for the whole works as
described in bidding documents, based on the percentage rate amount in the Bill of Quantities
submitted online by the bidder.
9.2. The bidder shall fill (tender) in percentage rate above or below and total amount (both in figures and
9.2. The bidder shall fill (tender) in percentage rate above or below and total amount (both in figures and
words) for overall items of the Works provided in the Bill of Quantities
10. Bid Validity
10.1 Bids shall remain valid as per Instruction to Bidders (ITB) after that deadline date for bid submission
specified in Clause. The Employer as non-responsive shall reject a bid valid for a shorter period.
10.2 In exceptional circumstances, prior to expiry of the original bid validity period, the Employer may
request the bidders to extend the period of validity for a specified additional period. The request and
the responses thereto shall be made in writing or by fax. A bidder may refuse the request without
forfeiting his bidder agreeing to the request will not be required or permitted to modify his bid but
will be required to extend the validity of his Bid Security for the period of the extension, and in
compliance with Clause 2 ( Financial Terms & Conditions) in all respects.
11. Format and Signing of Bid
11.1 The bidder shall prepare two copies of the documents comprising the bid as described in Instructions
11.2 The bid shall be typed or written in indelible ink and shall be signed by a person or persons duly
authorized to sign on behalf of the bidder.
11.3 The bid shall contain no alterations, omissions or additions, except those to comply with instructions
issued by the Employer, or as necessary to correct errors made by the bidder, in which case the
person or persons signing the bid shall initial all such corrections.
11.4 All witnesses and sureties shall be persons of status and probity and their full names,
Occupations and addresses shall be printed below their signatures.
12. Deadline for Submission of Bids
Bids must be received by the Employer at the address specified above not later than the time and date
specified in the NIT.
Any bid received by the Employer after the deadline for submission of bids will be returned unopened to
14. Signing of Agreement
At the same time that the Employer notifies the successful bidder that his bid has been accepted, the
Employer will direct him to submit the Performance Security and attend the Employer's office on a date
determined by the Employer for signing the Form of Agreement.
15. The selection process will lay high emphasis on the ability and competency of contractors to do high
quality work within the given time schedule.
16. The onus of providing, all necessary company / project related information, in appropriate manner and
medium, so as to demonstrate the competency of the bidder and to allow proper evaluation, will rest
entirely on the Bidder.
17. All clause shall be operative from the date of issue of work order and up to the expiry of original and
extended time limit.
18. Legal Condition:-
Corrupt or Fraudulent Practices
The Employer will reject a proposal for award if he determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in competing for the contract in question. The
Employer will declare the firm ineligible, either indefinitely or for a stated period of time, to be
awarded a contract by AHMEDABAD MUNICIPAL CORPORATION if it at any time determines
that the firm has engaged in corrupt or fraudulent practices in competing for the contract, or during
“corrupt practice” means behavior on the part of officials in the public or private sectors by which
they improperly and unlawfully enrich themselves and/or those close to them, or induce others to
do so, by misusing the position in which they are placed, and it includes the offering, giving,
receiving, or soliciting of anything of value to influence the action of any such official in the
procurement process or in contract execution; and
“fraudulent practice” means a misrepresentation of facts in order to influence a Procurement
process or the execution of a contract to the detriment of the Borrower, and includes collusive
practice among bidders (prior to or after bid submission) designed to establish bid prices at
artificial non-competitive levels and to deprive the Borrower of the benefits of free and open
Municipal Commissioner reserves the rights to reduce/increase the scope of work and contract without
assigning any reason thereof.
If Ahmedabad Municipal Corporation is convinced that the Bidder has resorted to material
misrepresentation or provided fraudulent information / statement, the said Bidder will be liable for
disqualification / rejection at any stage.
Proof for fulfillment of eligibility criteria should be submitted along with Tender volume. If the
Tender volume is submitted without valid documents and without proof of eligibility criteria it will be
Those who do not meet with the eligibility criteria need not submit the Tender document.
Tenders, which do not fulfill all or any of condition or are submitted incomplete in any respect or are
conditional tenders, will be rejected.
Contractor shall be responsible to obey all Labour Laws, Environmental and Safety Laws.(the existing
laws as well as framed from time to time). Any penalties laid due to violation of such laws shall be
directly deducted from the contractor's outstanding.
19. Administrative Conditions:-
Safety and Signage
Contractor has to arrange for the complete safety of the persons working for project, users of the road
i.e. public and vehicles also. All the arrangements of traffic drums, metal / fiber cones, traffic blinkers,
traffic signs as per design, safety tapes etc. to be arranged at site. Necessary florescent marking on
traffic signs to be provided so that it should be visible at night. During night working hours safety in
charge personnel shall be provided with florescent jackets. This shall be Provided at no extra cost
by the bidder under attaché with specified in the tender documents under payable iteme.
Liaison with local authority for electrical connections for the AMC
The contractor is responsible for liaison with local authority for change in supply connection or new
connection on behalf of AMC. It includes filling the necessary application to power Supply Company,
follow up and getting the supply, filling the necessary test reports to the power supply company. All
official fees including security deposits and other expenses shall be of initially paid by the contractor.
AMC may support to get the temporary connection and may at its diseretien get the same
converted to permanent connection at the same of AMC if desired do,and contractor shall as no
extra cost support the same. In this case AMC my be as the remaining cost subject to approval.
20 :- CONTINGENT FEE:
The Contractor warrants that he has not employed any person to solicit or secure the contract upon
any agreement for a commission, percentage, brokerage or contingent fee. Breach of this warranty
shall give the Municipal Commissioner the right to cancel the contract or to take any other
measure as the Municipal Commissioner may deem fit. The warranty does not apply to
commissions payable by the contractor to establish commercial or selling agent for the purpose of
securing business.
No officer, employer of the Municipal Corporation be admitted to any share or part of this contract
or to any benefit that may rise there from.
21:- OVERPAYMENT AND UNDERPAYMENT:
Whenever any claim fourths payment of a sum to the Municipal Corporation arises out of or under
this Contract against the contractor the same may be deducted by the Municipal Corporation from
any sum then due or which at any time thereafter may become due to the contractor under this
contract and failing that under any other contract with the Municipal Corporation or from any sum
due to the contractor with the Municipal Corporation (which may be available with Municipal
Corporation), or from his retention money, or he shall pay the claim on demand. The Municipal
Corporation reserves the right to carry out post payment audit and technical examination of the final
bill including all supporting vouchers, abstracts, etc.
The Municipal Corporation further reserves the right to enforce recovery of any over payment when
detected not withstanding the fact that the amount of the final bill may be included by the Contractor.
If as a result of such audit and technical examination any over payment is discovered in respect of
any work done by the Contractor or alleged to have been done by him under the contract, it shall be
recovered by the Municipal Corporation from the contractor by way of all the means prescribed
above or if any under payment is discovered by the Municipal Corporation, any amount due to the
contractor under this contract or under payment may be adjusted against any amount then due or
which may at any time thereafter become due before payment is made to the contractor from him to
the Municipal Corporation on any other contract account whatsoever.
If, at any time, there should be evidence of any lien or claim for which owner might have become
liable and which is chargeable to the contractor, the owner shall have the right to retain out of any
payment then due or thereafter to become due an amount sufficient to completely indemnify the
owner against such lien or claim or if such lien or claim be valid the owner may be or become due
and payable to the contractor. If any lien or claims remaining, unsettled after all payments are made,
the contractor shall refund or pay to the owner all money that the latter may be compelled to pay in
discharging such lien or claim including all cost and reasonable expenses.
Contractor shall not sub-let the work without permission of the authority.
Joint venture and subcontracting shall not be allowed under this tender
Addendum or corrigendum conveying any change or correction in respect of the work shall
form the part of the contract documents. The full consideration shall be given to such addendum or
corrigendum before submission of tender duly filled in by the contractor. Therefore, the contractors
shall have to kindly refer the tender for such addendum or corrigendum published by AMC through
its website www.egovamc.com 48 hours prior to the deadline of submission of the tender.
Tenderers shall verify the number of addendum issued and enclose the same with the tender
documents , failing which the tenders shall be liable for rejection and no any complaint in respect to
this shall be entertained under any circumstances.
Seal and Signature of the Bidder Addl. City Engineer
Date: (West Zone)
AHMEDABAD MUNICIPAL CORPORATION
TERMS & CONDITION
( C ) FINACIAL CONDITION
1. Cost and Currencies of Bidding
The bidder shall bear all costs associated with the preparation and submission of his bid and the
Employer will in no case be responsible or liable for those costs.
Currencies of Bid and Payment
The rates and the prices shall be quoted by the bidder entirely in Indian Rupees
All payments including advances, if any, shall be made in Indian Rupees.
2. Earnest Money Deposit :-
2.1 Bank guarantees (and other instruments having fixed validity) issued as surety for the bid shall be
valid for 28 days beyond the validity of the bid.
2.2 The EMD of the unsuccessful bidders, except for L1,L2 and L3 bidders, will be returned as promptly
as Early as possible as but not later than 28 days after the expiration of the period of bid validity.
2.3 The EMD of the successful bidder, along with second and third lowest tenders, will be returned when
the bidder has furnished the required performance security and signed the agreement.
2.4 Earnest Money Deposit may be forfeited
a) if the bidder withdraws his bid during the period of bid validity;
b) in the case of a successful bidder, if the bidder fails within the specified time limit to
i) Furnish the required Performance Security or
ii) Sign the Agreement.
3. (A) Security Deposit :-
Within 15 (fifteen) Working days of the date of receipt of the Letter of Intent (LOI) the successful
bidder shall deliver to the Employer, a Initial Security Deposit Shall be submitted as per C.E.
Circular.in the form of a Bank Guarantee/ DD/Locle MICR cheque for an amount equivalent to 5%
(five percent) of the Contract Price .
Failure of the same shall make the contractor liable for any penalty as decided by AMC. At present a
policy is framed by Audit department of AMC to charge 4% interest for the balance period and
discontinuity period.
The Security Deposit to be provided by the successful bidder in the form of a bank guarantee as per
format shall be issued as per Memorendum of work.
(E) Retention :-
a). Retention @ 2% of the value of work done will be deducted from each RA bill. It will be released
along with release of payment of Final Bill.
4. Approved Bank: - As per Annexer -I
5. No advance for machinery or materials will be given.
6. Mobilization advance will not be given.
7. Quantities in B.O.Q. may vary up to any extent and contractor shall not claim any extra rate for the
8. Penalty: - 10 percent of the balance work on Date of Completion Date or extended time limit. &
As per AMC Rule
9. Tax, Duties on Materials
All charge on account of Octroi ,excise duties, terminal tax, sales tax. Service tax, VAT etc. on material
procurement or any other component for the works from any source shall be borne by the contractors.
All duties, taxes, Service Tax and other levies payable by the Contractor under the Contract, or for any
other cause as of the date 28 days prior to the deadline for submission of the bids, shall be included in
the rates and prices and the total bid price submitted by the bidder and the evaluation and comparison
of bids by the Employer shall be made accordingly.
Special Clause:
As per construction works welfare cess Act – 1996 non-refundable one percent of tender amount shall
be deducted against works welfare cess.
Seal and Signature of the Bidder Addl. City Engineer
Date: (West Zone)
General terms & conditions
1. Tenderer should be registered in PWD/ in Govt. R&B /CPWD / AMC or equivalent registration with
any other state Govt. or institutions. Copy of registration should be attached with tender document.
Tenderer who was not registred in AMC must be get registred in panel of approved AMC contractor.
2. A booklet of FORM B-1 of Gujarat State Roads & Building Department / Water Resources
Department with the correction slips made up to 15-08-1999 may be referred. (only English version)
Clause No. -2 liquidated damages for delay shall be overrule by A.M.C.’s M.C.circular no.- 9 dt.
3. In the specification “as directed" / "approved" shall be taken to mean "as directed / "approved" by the
Engineering in charge.
4. Wherever a reference to any Indian standard appears in the specifications, it shall be taken to mean as
reference to the latest edition of the same of force on the date of agreement.
5. In "Mode of measurement" in the specifications wherever a dispute arises in the absence of specific
mention for a particulars point / aspect, the same in the relevant Indian Standards shall be referred to.
6. All measurement and computations, unless otherwise specified shall be carried out nearest to the
following limits :-
i) Length, width and depth, Height 0.01 Meter
ii) Areas 0.01 Sq.mts.
iii) Cubic contents 0.01 Cu. mts.
In recording dimensions of work, the sequence of length, width and height (Depth) or thickness shall be
7. Definite particulars covered in the items of work, though not mentioned or elucidate in its
specifications shall be deemed to be included therein.
8. Approval of the samples of various materials given by the Engineer in charge or AMC's Consultant
shall not absolve the contractor from the responsibility of replacing defective materials brought on
site or materials used in the work found defective at a later date. The contractor shall have no claim to
any payment or compensation whatsoever on account of any such materials being rejected by the
Engineer in charge.
9. The contractor’s rate for the item of work shall be for the work completed in all respect.
10. All materials including those of electrical shall be got approved by the Engineer in charge/ Architect
before using them in the work.
11. Materials as and when rejected by the Engineer in charge or AMC's Consultant shall be removed from
the site of work within 24 hours.
12. All work shall be carried out in a manner as per standard engineering practice.
13. All tools, templates, machinery and equipment for correct execution of the work as well as for
checking lines, levels, alignment of the works & all precautionary measures during execution shall
have to be kept in sufficient numbers and in good working condition at the site of the work. All
excavated trench shall be kept covered with barricade and caution tap.
14. Special modes of the construction not adopted in general Engineering practice, if proposed to be
adopted by the contractor shall be considered only if the contractor provided satisfactory evidence
that such special mode of construction and completion of work to the required strength and quality.
Acceptance of the same by the Engineer in charge shall not however, absolve the contractor from the
responsibility of any adverse effect and concordance of adopting the same in the course of exaction or
completion of the work.
15. The contractor shall be responsible for observing the rules and regulation imposed under the "Minor
Mineral Act", and such other laws and rules prescribed by the Government from time to time.
16. All necessary safety measures and precautions (incl. those laid down in the various relevant Indian
Standard) shall be taken to engrave the safety of men, materials and machinery on the work and also
of the work itself.
17. Quantity measured in the tender is approximate. It may increase or decrease looking to the quantum
of actual work for which no any claim shall be entertained by A.M.C.
18. Contractor shall have to execute extra item if required or as per need of AMC.
19. The work in general shall be carried out as per standard specifications of the relevant items to be
executed & as per the instruction of Engineer in charge & as per the guidance of AMC's Consultant
for this project.
20. The general terms & conditions of the contract shall be applicable & shall be binding on the
contractor. The contract agreement shall have to be executed between AMC & the agency to which
work is awarded for execution.
21. For Tender amounting below 10 lakh LOI shall be issues within 3 days after received of sanctioned
tender and resolution.Within 10 days contractor has to submit SD and after reciveing SD Work order
shall be issue to contractor and the time limit shall be start from the date of issue of the written work
order to the contractor.
For Tender amounting above 10 lakh LOI shall be issues within 3 days after received of sanctioned
tender and resolution .Within 15 days contractor has to submit SD and after reciveing SD work order
shall be issue to contractor and the time limit shall be start from the date of issue of the written work
order to the contractor.
Security Deposit of 5% of sanctioned tender amount shall be deposited by pay order / demand
draft / cheque or Bank Guarntee of nationalized bank/scheduled bank only. Contractor shall have to
sign contract paper with AMC. The contractor shall be fined 4% of interest per year for delay in
submission of S.D and shall be deducted from contractor’s bill.
22. In case of any ambiguity in specifications mentioned in this tender, the interpretation given by M.C.
Or His Designeted Officer will be final and binding to the Contractor.
23. The contractor shall take no advantage of any apparent error or omission in drawing or specification
and the Engineer -in-charge shall make such corrections and interpretations as necessary to fulfill the
intent of the plants and specifications.
24. The quantities of items in BOQ (Bill of Quantities) may vary in case of necessity arises.
25. All prevailing taxes/duties chargeable by State Govt./Central Govt. and the Municipal Corporation.
will be payable by the contractor.
26. No any kind of price rise / price escalation / price variation for cement, steel or labour shall be
27. Contractor is requested to see the site physically before tendering. He is also requested to quote the
rates keeping in view of all the points mentioned in relevant pages of tender documents.
28. Water Supply: The contractor shall arrange at his own cost, a suitable supply of piped water for the
construction of the works and provide a satisfactory supply of potable water for drinking, washing,
sanitation and cleaning down. The contractor will be responsible for all the costs where applicable of
connection, meter installation, water consumed, water required for testing purposes, disconnection
and the laying, maintenances and ultimate removal of any distribution system around the site.
29. Electricity: Electric supply will be made available at the site by the Contractor and the contractor
must make his own arrangements with the Corporation and Electricity Supply Authorities and with
other contractors to connect and to take a supply from such services, paying all costs in connection
The Contractor shall be entitled to use supply Electricity as may be available on the site for purpose
of the work and shall pay such charges as is fixed by the appropriate supply Authorities.
In case there is any delay in supply of power site of any interruption or fault in the power during the
work. No compensation shall be paid for idle labor staff, machineries and for use of diesel operating
sets etc. as the case may be.
30. Tenders shall submit all the valid/certified documents in support of their initial/eligibility criteria
mentioned above along with the bid. They shall have also to submit the income tax clearance
certificate and solvency certificate.
31. No advance such as secured advance machinery advance, mobilization advance or materials advance
32. The contractor shall get the electrical works executed through the authorized Government approved
licensed electrical person or firm in appropriate category in accordance to contractual provisions.
33. The electrical works shall be carried out strictly in accordance with the directives issued by Engineer
34. Contractors shall not have any dispute or claim for any kind of compensations
(i) If the quantity stipulated in the tender items varies or the scope of work changes & thereby total
amount of work increases/ decreases.
(ii) If the work gets delayed/ postponed for some administrative/ technical decision what so ever.
35. In case of any dispute, decision of Municipal Commissioner shall be final and binding on the
36. Tenders which do not fulfill all or any of conditions or are submitted incomplete in any respect will
be rejected. Municipal Commissioner reserves the right to increase/decrease the scope of work. No
any claim to that effect shall be entertained. The Municipal Commissioner also reserves the right to
reject any or all the tenders without assigning any reason thereof.
37. The contractors are requested to quote their rates considering above tender conditions.
38. The contractor shall have to execute the contract agreement after received work order.
Even though in special case, If work is not started because of monsoon or any other special reason (like
site is not available and due to unavoidable circumstances arise), after evaluation of situation the
actual date of starting of work will be consider after approval of Dy.M.C. (West zone)
39. The Contractor shall not claim for increase or decrease in the quantity of the BOQ item or the scope
40. The R.A bill / final bill payment shall be made as per the latest A.M.C policy / circular for the work
done by the contractor.
41. Conditional tenders will not be accepted.
Signature of contractor with seal Additional City Engineer (W.Z)
Date Ahmadabad Municipal Corporation
ybœtJtœ BGþrlrmvj ftuvotuhuNl
ftb btxulwk xftJthe œh Jt¤wk xuLzh ylu ftuLx[tfx
xuLzhh btxule Nh<tuu
1 y: yt xuLzh su <u Jdolt y.Bgw.ftu y&Jt fuLî{ y&Jt htsg mhfthle btLg gtœelt ftuLx[fxhtu Che NfNu.dJobuLxlt btLg
ftuLx[[tfxhu y.Bgw.ftuvtuo. bt btLg ftuLx[[tfxhtu le gtœebtkk hSMxuNl fhtJJtlwk hnuNu.
1 c: btLg ©uKelt ftuLx[tfxh <hefu ltuk^Kelwk «btKvºtle MJ «btKe< fhuj lfj xuLzh mt&u stuzJtle hnuNu.
1 f: xuLzhhle jtgft<
ftb sJtcœth xuLzhh <ubs su xuLzhh mwaJuj ftuLx[tfxhle ©uKebtk ytJ<t ntug <ubs ftb fhJt mûtb ntug <ublu s ytvJtbtkk
ytJNu. ftb yvt<t vnujt ftuLx[tfxhu ftb mkk<tu»tfthf <ubs xtRb jebexbtkk vwÁk fhJt sYhe mJj<,ylwCJ, ûtb<t ylu
VtgltLmegj hemtumo hsw fhJtlt hnuNu.
1 z: ybœtJtœ Bgwrlrmvj ctuzo XhtJ lk - 3836,<t.25/11/2011 &e b¤uj bkswhe ylwmth <&t mexe.Rsluh mh¾gwjh,lk -
17,<t.09/12/2012 bwsc ybœtJtœ Bgwrlrmvj ftuvtuohuNlbtk ftuLx[t¾xh hSMxuNl Ve,heLgwyj Ve <&t yvd{uzuNl Ve
ylu btv œkztu ægtlbtk htFe <u bwsc ybj fhJtltu hnuNu.
1 R: xuLzh Ch<t vnujt xuLzhhu mtRx rlheûtK fhe juJwk. xuLzhh ftblt «fth, ngt< hM<t, vtKe btdo, mkkath ylu JvhtNlt ceò
hM<tytu&e mkk<wÐ ntuJtlwk btle juJtbtkk ytJNu. xuLzhhu ftblu mtRx ylu rcÕzekkd(fu su ftb fhJt, ftb vwhwk fhJt <&t ftblt
buRxulLm btxu cltJuj ntug).<ubs xuLzhhu yt mtRxlt ftb btxu, rcÕzekkd btxu, gtzo, zevtu btxule søgt vtu<tle he<u bu¤Je
juJtle hnuNu. (xuLzhlwk ftb fhJt, ftb vwhwk fhJt <&t ftblt buRxulLm btxule søgt)
2: yt ftble mbg bgtoœt xuLzhbtk sKtÔgt bwscle hnuNu. (bubtuhuLzbbt sKtJuj «btKu)
3: xuLzh Jujezexe rvhegz xuLzhbtk sKtÔgt bwsc hnuNu. (bubtuhuLzbbt sKtJuj «btKu)
4: xuLzh Ch<e JF<u yluoMxble ChJtle hnuNu.
xuLzh Vtubo ylu ylwmwrabtkkle œhufu œhuf Ftje søgt xuLzh Chlthu Chuje yt mt&u btufjujt œM<tJus vh< fhJtlt hnuNu.
6: ftuLx[tfxhtuyu leaule ctc<tu ft¤SvwJof JtkkaJt rJlkk<e Au.
1) J^w fu ytuAtle xftJthelt œh Nçœtu <ubs ytkkfztbtkk ytvJt.
2) ftuR fkkvlelu ltbu xuLzh juJtbkkt ytÔgwk ntug <tu fkkvle J<e xuLzh vh mne fhlth Ôgrf<lu yr^f]< fh<wk bwFðgthltbwk xuLzh
mt&u hsw fhJtlwk hnuNu.
3) Bgwrl.ftuvtuohuNllt «J<obtl rlgbtu ylwmth yluMxble ChJtle hnuNu.ylu xuLzh mt&u cezJtle hnuNu.
4) ftuLx[tfxhu RLfbxuût mkkckr^< vtl lkch <&t cukf zexuRj ytvJtle hnuNu.
5) ftuLx[tfxh vtmu ydtWlt ylwCJt ykdult «btKvºttule lfj xuLzh mt&u hsw fhe NfNu.
6) xuLzh Nh<tu ylu MvuNeVefuNl <&t CtJ vºtflt œhuf vtlt ylu rJd<tu vh ftuLx[tfxhu mne fhJe.
7) <btb mw^tht, AufAtf ylu Dwkxujt jFtK vh ftuLx[tfxhu xwkfe mne fhJe.
7: AufAtf xuLzh Chlthlu sKtJJtbtkk ytJu Au fu xuLzh œM<tJustult jFtKbtk ftuR AufAtf fu VhuVth fhJt œuJtNu lrn ylu ytJe
ftuR AufAtf fu VuhVth juJtNu lrn, <ultkk jFtKbtkk ftuR Cwwj ntug <tu <ult vh l Dwkx<t Ftuxt jFtK fu ytkkfzt vh Auftu bthelu
<ult mtawk jFtK fu ytkkfzt MvÐ Wfju <u he<u jFJt. «ðguf mw^tht vh xwkfe mne fhJe.
8 y: xuLzh hsw fh<tkk vnujt Ftm fhelu xuLzhbtk œNtoJuj mwaltytulwk vtjl fhJtbtkk ytÔgw lrn ntug <tu xuLzh ybtLg dKJtbkkt
ytJNu <ule ltuk^ juJt rJlk<e Au. J¤e yt Vtubolwk bwFv]ƒ ylu ftuLx[tfxhtult btdoœNol btxu mtbtLg rlgbtu ylu mwaltytu
vK ft¤SvwJof JtkkaJt rJlkk<e Au.
1) ftuRvK fthK œNtoÔgt rmJtg ftuRvK fu c^t xuLzhtu yMJefth fhJtltu nf yctr^< hnu Au.
8 c: Wvhle ctc<tu Wvhtkk< xuLzh leault mkkstudtubtkk <h< ybtLg XhJtlu vtºt &Nu.
1) xuLzh Chlth, rlg< ftb y&Jt ftb btxu bkswh fhuj y&Jt CtJ vºtflt ftuR ftuz y&Jt vîr< y&Jt rJd<tubtkk bwfuj Nh<
y&Jt mw^thtbtkk ftuR VuhVth mwaJ<t ntug.
2) xuLzhlwk ftuR vtlwk fu vtlt ftZe ltkkÏgwk/ltkkÏgt ntug fu cœÕgwk/cœÕgt ntug.
3) c^t mw^tht J^tht y&Jt atukxtzuje ftvjeytu Wvh xuLzh Chlthu xwkfe mne l fhe ntug.
4) xuLzhbtk <ubKu ftuR AufAtf fhe ntug, ylu
5) xuLzh Chlth y&Jt vuZele ctc<btkk œhuf Ctdeœth y&Jt <u ykkdulwk bwFðgthltbwk ^htJlth Ôgrf< mne l fhu y&Jt
xuLzhbt <u btxu htFJtbtkk ytJuje søgtbtkk mne/mneytu Wvh ftuR mtûteyu mtF fhe l ntug.
8 f: Nh<e xuLzh MJefthJtbtk ytJNu lne.
8 z: xuLzh MJefthJw , hœ fhJw, ftulu ytvJw ylu fgt CtJ&e ytvJw <u ykdu Bgwrl. frb§h©eltu rlKog ytFhe hnuNu. ftuR
fthKmh stu ftuLx[tfxhlu ftb l ytve Nftg <tu <u ykkdu ftuLx[tfxh ftuRvK «fthltu lwfNtle fu J¤<hltu nff œtJtu fhe NfNu
lrn fu ftgœtfeg ftgoJtne yt ykkdu &R NfNu lrn. xuLzh bkswh >ltu y&o ftb ytve s œuJtlwk Au <uJtu &R NfNu lrn.
9: rJmkkdr< ylu rnmtc stud:
nt& ^hJtlt ftbtule ctc< œNtoJ<t CtJ vºtf btklt sÚ&t ylu hfble ftuRvK Cwjawf leault rlgbtu ylwmth mhCh fhJtbtkk
1) xuLzh Chlthu œhlt Ftltbtkk sKtJuj Nçœtu ylu ytkkfzt Jåau ftuR ymkkdr<lt fumbtkk Nçœtubtkk sKtJuj hfb btLg htFJtbtkk
2) yufb œh ylu sÚ&tlt Ftuxt dwKtfthlt fthKu ftble ctc<tu œNtoJ<e CtJ vºtf lt Ftltbtkk&e hfbbtkk Cwj sKtg <tu yufb
œh btLg htFJtbkkt ytJNu ylu œhlt yt^thu dwKtfth mw^thJtbkkt ytJNu.
3) yufblt Ftltbtkk&e <ubs ytd¤ Fuka<t mhJt¤tle <btb Cwjtu mw^thJtbkkt ytJNu.
4) ctc<tu y&Jt mhJt¤t mtbu vwhu ytkkfzu fhuj ftuR vK ctc< ægtlbtkk juJtbtkk ytJNu lrn.
10y: ftbltu «tud{um mbg bgtoœt bwsc fhJtltu hnuNu.
xuLzhbtk ftuLx[t¾xh îtht Chujt CtJ <btb «fthlt su <u «J<o<t mhfthe xuût mrn<lt CtJ dKJtbtk ytJNu. ylu <ubtk atjw ftb
œhBgtl su ftuR VuhVth &Nu <ultu J^thtu awfJJtbtk ytJNu lrnk.
10c: mûtb m•tt îtht xuLzhle bkswheltu XhtJ vtzgt ctœ ( LOI) ytvJtbtk ytJNu ðgth ctœ rœl - 15 btk rm¾gtuhexe zevtuÍex
sbt fhtJJtle hnuNu. rm¾gtuhexe zevtuÍex btuze ChJtlt rfMmtbtk Bgwrl.ftuvtuohuNlbtk «J<obtl rlgb ylwmth ftgoJtne
10f: bkswh &guj xuLzhle mbgbgtoœtbtk ftbdehe vqKo l &tg <tu mbgbgtoœt ctœlt FhuFh ctfe ftble hfblt 10% juFu
(jefJezexe zubuSm) vulÕxe Jmwj fhJtbtk ytJNu.
xuLzh Chlthu yu Jt< mbS juJtle hnuNu fu <uKu xtkkfujt œh vwhtk &gujt ftb btxult Au ylu <ubtk bswhe, vtjF, ÃjtLx,
œuFhuF,mhJem-ftbdehe, Jes¤e, htugÕxe ylu ytufx[tug Jduhu ykkNu <btb Faoltu <&t sYh sKtg <tu ylu ðgthu ht<vt¤elt
ftblu juJt c^t J^thtlt Faoltu mbtJuN &Nu ylu xtkkfujt CtJ fu œh fh<t J^thtle ftuR awfJKe ykkdult <ublt ftuR œtJt
ægtlbtkk juJtNu lnekk ylu xuLzh Chlth Ftuxe hswyt<lu fthKu y&Jt ftuR Ôgrf<yu(vAe<u ctkk^ftb rJCtdltu fboathe ntug fu
l ntug)<ublu ytvuje btne<elu yt^thu vtA¤&e ftuR œtJt hsw fhJt nfœth hnuNu lnekk. <ublw xuLzh ChJt <&t <ubtkk swœt
swœt CtJ ylu œh ChJt btxu sYhe yuJe <btb btne<e vtu<tlt vûtu l bu¤Je NfJtlu fthKu vtu<u xuLzh hsw fhJtlu je^u
y&Jt <ubtkk&e WCt &<t ftuR stuFb fu sJtcœthebtkk&e Axfe NfNu lnekk. mœh ftbbtk ftuR vK ò<lt ctk^ftblt bxehegj
Wvh CtJ J^thtu ytvJtbtk ytJNu lrnk.
11 c: ftuLx[tfxhtulu vubuLx / hlekd cej Bgwrl. frb§h©elt su <u «J<obtl rlgb bwsc fhJtbt ytJNu.<&t Bgwrl.
frb§h©e/mexe Rsluh©e lt su <u JF<ltk mh¾gwjh «btKu ftbdehe/ybj fhJt ckDlf<ot hnuNu.
11 f: ftuLx[t¾xhlt œhuf hlekd cejbtk&e ftuLx[t¾xhlu awfJJtle &<e fwj hfb Wvh (xuLzh bwsclwk vubuLx +
yu¾x[t ytRxb) 2 % juFu hexulNl ble ftvJtbtk ytJNu su VtRlj cejbtk vh< ytvJtbtk ytJNu.
11 z: htsg / fuL÷ mhfth©elt JF<tuJF<lt ftgœt bwsc su ftuR hfble fvt< fhJtle &Nu <u bwsc ftuLx[[tfxhlt cejbtkk&e fvt<
12: yu)fhth mkkc^e œM<tJustu fhthlt ydðglt Ctd dKtNu ylu <u mD¤t mne<lt fhth mbd{ ftblu jtdw vzNu.
ce)xuLzhbtk œNtoJuj ftb mkkck^e œM<tJusbtkk œNtoJuj rJd<btkk rJmkkd<<tlt rfMmtbtk leau œNtoJuj ¢btlwmth
œM<tJusbtkk œNtoJuj rJd< d{tng htFJtbkkt ytJNu.
yu) yufb ylu fœ
2) xuLzh Vtubolwk CtJvºtf
z[tuRkdbtk fœ, ytfth, ytkkfzt fœta Ftuxt ntug <tu btvujtkk fœ, ytfthlu ylwmhJwk.
2) xuLzh Vtubole ylwmwra-ce
Cwj Chujt fu Ftuxt JKollt rfMmtbtkk yt mkkck^e Wvhefûttyu rJmkkd<<t ykdule ltuk^ bwfe
yuze.me.R/zu.Bgwrl.frb./Bgwrl.frb.le bkswhe bu¤JJtbtk ytJNu ylu <u bwsc fhJtbkt ytJuj rlKog ykkr<b dKJtbkkt ytJNu.
13 : xuLzhhu z[tuRkd fu MvuNeVefuNlbtkk hnuje ftuR ûtr< fu Ftbeltu duhjtC juJtle fturNN l fhJe ylu Rsluh Rl-atsuo Ãjtl <&t
MvuNeVefuNlle ûtr<ytu mw^thJe <&t <ulwk mtawk y&oDxl fhtJJwk.
14 : yt Wvhtk< y.Bgw. ftuvtuo. lt slhj ftuLx[tfx fLzeNl vK btLg htFJle hnuNu.
15 : yufe JF<u yuf fh<t J^w søgtytuyu ftb NY fhJtltu Jfo ytuzoh b¤u <tu ftb yuf mt&u s c^u NY fhJw vzNu.
16 :atjw ftbu mrJom jtRllu lwfNtl l &tg <u he<u ftb fhJtlw hnuNu. stu ftuR mrJom jtRllu lwfNtl &Nu <tu <ule mkvwKo
sJtcœthe (òlbtj) ftuLx[tfxhle vtu<tle hnuNu. mtRx Wvh ftb œhBgtl bswhtu fu sl<tlt ftuR btKmlt òlbtj lu
lwfNtl &tg <ule sJtcœthe ftuLx[tfxhle hnuNu.vtujem Vhegtœ &tg <tu <ule sJtcœthe vK ftuLxtfxhle hnuNu. CuFz Dme
l vzu <ule sJtcœthe vK vtujem Vhegtœbt ftuLx[tfxhle hnuNu.CuFz Dme l vzu <u btxu mjtb<elt vdjt (suJt fu œtuhzwk
ctk^e bswh Ftztbtkk W<thJt, mtuhekkd ylu Mx[[xekkd fhJt rJduhu) je^t Jdh bsqhlu Ftztbtkk W<thNu <tu ftuLx[[tfxh s vtujem
Vhegtœbt sJtcœth hnuNu ylu Bgwrl.ftuvtuohuNlltu ftuRvK MxtV ytlt btxu sJtcœth hnuNu lrn.ytxjwk mbSlu s xuLzh
ChJwk. Bswhtultu rJbtu vK W<thJtu.
17 : ftuLx[tfxh îtht xuLzhbt œNtoJuj MveNeVefuNl bwsc MxtLzzo bxehegÕm MvuNeVefuNl bwsc jtJJtlt hnuNu.<&t sYh sKtg <tu
xuMxekd fhtJJtlwk hnuNu.<&t yt ykdu «Joðbtl Bgwrl.ftuvtuohuNlt rlgb bwsc bxehegÕm fu ceò xuMxed hevtuxo ftuLx[tfxhu
vtu<tlt Fauo ftuvtuohuNl sKtJu <u søgtyu fhtJJtlt hnuNu. bxehegÕm jtJJt fu jR sJtltu mkvwKo Fao ftuLx[tfxhu
CtudJJtltu hnuNu.
18 : M&¤ vrhrM&r< / sYhegt< bwsc ftb fhtJ<t xuLzhlt ytRxblt sÚ&tbtk J^ ^x &tg <tu rlgb ylwmth <u ykdu ftb fhJt
ftuLx[tfxh ck^tgujt Au.
19: mtRx vh jtJJtbtk ytJuj btj mtbtl hesufx fhJtbt ytJu <tu <whk< rœl 1btk vh< jR sJtltu hnuNu.
yLg&t <ule lwfNtlle sJtcœthe ftuLx[tfxhle hnuNu.
20 :ftuLx[tfxhlu su ftuLx[tfx ytvJtbtk ytJu Au.<ubt mhfth©elt «Joðbtl rlgb bwsc ve.yuV/juch
yufx/vtujemlt ftgœtlw vtjl fhJtlwk hnuNu <&t yt ykdu Bgwrl.ftuvtuohuNl îtht su btne<e btkdJtbtk ytJu <u ytvJtle hnuNu.
21: ftuRvK ftgœtfeg jexeduNl ybœtJtœ Nnuhle ftuxobt hnuNu.
22: btj su <u Mxtumo Wvh y&Jt mtRx Wvh jtuftulu lz<h l &tg <u he<u mwalt bwsc W<thJtltu <ubs dtuXJJtltu hnuNu.
23: ftuR vK mhfthe fhJuht ChJtle <btb sJtcœthe ftuLx[tfxhle hnuNu.
24: yt xuLzhbtkk stu ftuR ytRxb hne dR ntug <tu <u y&tJ M&¤ M&e<e bwsc xuLzhbtk mbtJuN l ntug <uJe J^thtle ftbdehe
fhJtle &tg <uJt rfMmbtk Bgwrl.ftuvtuohuNlt «Joðbtl rlgb ylwmth J^thtle ytRxblt CtJ lffe fhJtbtk ytJNu ylu <u
bwsc awkfJKe fhJtbtk ytJNu.
25: atjw ftb œhBgtl «tuxufNlle mkvwKo sJtcœthe ftuLx[[tfxhle hnuNu. subtkk vevzt,œtuhzt, Cgmwaf ctuzo,ÃjtMxef vxe,rJ.
ftuLx[tfxhu jtJJtlwk ylu mtaJJtlwwk hnuNu. ylu ftuRvK yfMbt< &Nu <tu <ule mkkvwKo sJtcœthe ftuLx[tfxhle hnuNu.
26: M&¤ Wvh atjw ftbdehe œhBgtl ftb fhlth ftuLx[tfxhlt bswh / fboathe y&Jt yLg Ôgrf<lt yfMbt<lt rfMmbtk juch
yufx bwsc fhJtle &<e ftgoJtne <&t vtujem ftgoJtnele sJtcœthe ftuLx[tfxhle hnuNu.
27: stu MxtV mqalt ytvu <u bwsc mwalt vtu&e ftuLx[tfxhu htFJtle hnuNu. <ubt œhhtus fhuj ftbdehe <&t yr^ftheytuyu ftb
mw^thJt fu vtu{d{um J^thJtlt ltuk^ fhuj ntug <tu <ulwk ftuBÃjtgLm ytvJtlwk hnuNu ytJe ltu^lt sJtc l &gu fu <u «btKu M&¤
Wvh ybj l &gu ftuLx[tfxhlu vulÕxe fhJtle mððtt yuze.mexe yuLSlehgh©elu hnuNu.
28: œhuf ytRxblt MvuNeVefuNl ybœtJtœ Bgwrlrmvj ftuvtuohuNlltk bkswh &guj <&t btLg htFuj MvuNeVefuNl Nh<tu bwsc hnuNu
su ytRxbbtk MvuNeVefuNl l ntug <uJt mkstudtubtk yuze. mexe.yuLSlegh©eltu rlKog ytFhe hnuNu. Jtuxhekd fhJtbtk lrn
ytJu fu œhhtus J^thtltu zucheÍ WvtzJtbtk lrn ytJu <tu ftuLx[tfxhlt Fauo ylu sutFbu Jdh ltuxemu Jtuxhekd fhtJJtbtk <&t
zucheÍ WvtzJtbtk ytJNu ylu cejbtkk&e hfb ftve juJtbtk ytJNu.
29: juch JuÕVuh Vkkz btxu ntjbtkk htsg mhfth©eyu fhuj nwfb bwsc 1%(yuf xft) hfb cejbtk&e ftve juJtbt ytJNu.
30: su ftbtubtk atubtmtlt mbgdt¤tlu ctœ ytvJtle Nh<tultu WÕjuF ntug ðgtk atubtmtltu vehegz <t.15 swl &e 30 mÃxuBch
Mþ^eltu dKJtbtk ytJNu. yt mbg œhBgtl ftuLx[tfxh îtht ftbdehe fhe Nftg <ub l ntug <tu <u mbgdt¤tu ctœ fhe ftble
mbgbgtoœt dKJtbtk ytJNu <&t sYhegt< Bþscle xtEb jebex J^the vK ytvJtbtk ytJNu.
31: ftuLx[tfxhu «J<obtl ybœtJtœ Bgw. ftuvtuohuNl lt JF<tuJF< lt mhfgwjh bwsc ve yuV,Jux <&t ylu muÕm xuût lu jd<t
vwhtJt vubuLx fh<e JF<u sYh vzu&e hsw fhJtlt hnuNu.
yufhthlwk Vtubo
1) nwk/ybu yt&e yufhth fhwk Awk/fheyu Aeyu fu yt xuLzh hsw fh<tkk vnujtkk buk/ybu M&¤le bwjtft< je^e Au ylu
ftblu jd<t btjmtbtl, bswhe ylu ceS ctc<tulu jd<e M&trlf vrhrM&r<le ò<-btne<e bu¤Je Au.
2) nwk/ybu yt&e yufhth fhwk Awk/fheyu Aeyu fu yt ftuLx[tfxhtule Nh<tu rJd<tu ylu xuLzhlu jd<t œM<tJustu
ft¤SvwJof yÇgtm fgtuo Au ylu <u bwsc <ultu ybj fhJt mkkb< Awk/Aeyu.
ftuLx[tfxhle mne - rm¬tu yuze.mexe yuLSlegh
btuctEj lkch mt&u (vrùb Ítul)
AHMEDABAD MUNICIPAL CORPORATION
ENGGNIERING DEPARTMENT
GENERAL SPECIFICATION
Time limit for the work shall be 12 months after the order to start the works. Progress of work should be
in proportion to time limit. The details of reinforcement of R.C.C. work shall be as per design and
instructions of Add. City Engineer and his order will be considered final.
The contractor shall have to maintain account of steel, cement and other materials that may be
brought by him on site. This account shall be regularly maintained and kept open for inspection by
Municipal Staff. Watering of all the items shall be as per instructions otherwise no payment shall be made
to contractors. Mixing of concrete shall be done by concrete mixer machine. Arrangements of binding
vibrator for R.C.C. works if required shall have to be made by the contractor .
The contractor shall be remain responsible for Workmen’s compensation if any accident. The
contractor shall arrange for barricading at night and arrangement of Pagi at night to direct the traffic. He
shall be responsible for any damage to public. If any incident happen, during the execution of work. In
case of dispute for unseen or overlooked items the decision of the Dy. City Engineer shall be final. The
contractor shall have to give site clean of all rubbish during the work and at the time of completion of
work and hand over the site with final finishing of the work as directed. All the rejected materials shall be
removed from site within 24 hours by contractor at this risk and cost. Debris shall have to cart daily from
For mixing mortar either for masonry or for plaster or for any other purpose contractor shall have to
prepare through of bigger size and mix the mortar in the required proportion. In on case he shall be
allowed to mix the mortar either on floor or any finished surfaces. The contractor shall have to make his
own arrangement for water required for the work.
If any extra item crops up during the progress of work the same shall be carried out by the contractor and
he shall be paid at the rate fixed by Add.C.E. as per the rate analysis based on latest SOR or if item is not
available in SOR than based on current market rates. In case of extra item decision of Add. City Engg.
shall remain final regarding rate.
If in the interest of the Corporation it is necessary to change either any site or the design of the propose
work the contractor shall carry out the same at his quoted rates without charges any extra and the
contractor will have to carry out the works and he will be paid at the rate quoted by him. No claim for
extra rate for subsequent changes in site and design is entertained.
The cubical contents of the cement bag shall be taken as 1-20 cft. Per bag and the contractors shall have
to prepare the measures boxes according to this measure.
Octroi exemption passes shall not be given for any materials required for the work. Contractor will be
fully responsible for compliance of the various provisions under contract Act. 1970 and the Rules framed
The tender for the work shall remain open for a period (180) days from the date of opening of the tenders
for this work and that the tenderer shall not be allowed to withdraw on modify the offer on his own during
the period. If any tenderer withdraw or makes any modifications or addition in the terms and conditions
of his tender not acceptable to the Municipal Corporation the Municipal Corporation shall without
prejudice to any right or remedy be at liberty to forfeit in full the said earnest money and black list the
If work is not started within specified time limit the penalty as per rule & tender condition delay of start
shall be recovered separately from the immediate bills payable to the contractor. Contractor has to make
his own arrangement for procurement of steel and cement.
Contractors should note the following conditions carefully:-
i) Conditional tender shall not be accepted.
ii) All tenders are to be submitted in duplicate without which the tenders are liable to be rejected.
iii) In case of tender downloaded from website, tender fee & EMD should be submitted in form of
iv) Condition of Form - B1 Standard Specification of material & code of practice will be applicable.
Form B1 can be is available in website. Specification shall be as per ' R& B Dept. - Govt. of
Gujarat booklets of Building Works & and Road Works Specifications published by Gujarat
Book Depot, Sector-21. Gandhinagar.
CONTRACTOR'SSIGNATURE ADDL.CITYENGINEER
& STAMP (West Zone)
TECHNICAL SPECIFICATIONS
AHMEDABAD MUNI CIPAL CORPO RATI ON ENGI NEER DEP ARTMENT
TECHNICAL SPECIFICATION
Name of Work :- v.Ítul JtmKt Jtuzobtk yuf<t ldh,rNJNkfh ldh,nheytub ldh,dwÃ<tldh le swœe swœe atjeytubtk
søgtyu Bgw.ftWLmejh, yuub.ve/yub.yuj.yu <&t yLg csuxbtk&e yth.me.me htuz <&t vuJh
jdtJJtlt ftb ctc<. (yu.yth.me)
Box cutting the road surface to proper slope and camber for making a base for road
work including removing the excavated stuff and depositing on the road side slope
as directed upto 200 Mt.lead.
Any soil which generally yields to the application of pickaxes and shovels, spades,
rakes or any such ordinary excavating implement or organic soil, gravel, silt, sand turf loam,
clay, peat etc. falls under this category. For materials and workmanship for earthwork and
excavation, relevant specification IS: 3764 & IS 1200 (Part I) shall be followed.
To protect persons from injury and to avoid damage to property, adequate barricades,
construction signs, red lanterns and guards as required shall be placed and maintained during
the progress of the construction work and until it is safe for the traffic to use the roadways.
The relevant Indian standards and the rules and regulations of local authorities in regards to
safety provisions shall be observed.
The depth of the excavation shall be as required. The site shall be cleared and all
obstructions, loose stones, materials and rubbish of all kind, bush; wood and all type trees
shall be removed, as directed. The materials so obtained shall be the property of AMC and
shall be conveyed and stacked as directed, within 50-m. lead. The roots of the trees coming
in the sides of the trenches shall be cut and coated with hot Bitumen.
All types of trees, woods etc. which requires prior permission of Govt./ Forest
Authority / Municipal Commissioner, before cutting shall be cut after obtaining such
permission from them. The rate of site clearance is deemed to be included in the rate of
The excavation shall be carried out in true line and level and having width and depth,
as shown in the drawings or as directed. The Contractor shall do the necessary shoring and
strutting or shall provide necessary slopes to a safe angle or steps, as required or directed, at
his own cost. No extra payment shall be made for such precautionary measures, taken. The
bottom of the excavated area shall be leveled both longitudinally and transversely, as
directed, by removing excess soil and watering, as required. No earth filling will be allowed
for bringing it to level, if by mistake or any other reason, excavation is made deeper or wider
than shown on the drawings or as directed. The extra depth or width shall be made up with
sand filling, as specified for the bottom level of the subsequent finishing at the cost of the
Contractor or as directed by Engineer-In-Charge.
The Contractor shall at his own expense and without extra charge make provision of
supporting all utility services, lighting the excavated areas, separating and stacking
serviceable materials nearly, shoring, timbering, strutting, bailing out water either sub-soil or
rainwater, including pumping at any stage of the work. all Excavation work must executed
with manual labour only.
1.2. Precautions :
The blasting operation shall remain in charge of competent and experienced supervisor and
workman who are thoroughly acquainted with the details of handling explosives and blasting
operations. The blasting shall be carried out during fixed hours of the day, preferably during
the mid-day-lunch hours or at the close of the work as ordered in writing by the Engineer-in-
charge. The hours of blasting shall be notified in advance to the people in the vicinity. All the
charges shall be prepared by the man in charge only.
Red danger flags shall be displayed prominently in all directions during the blasting
People except this who actually light the fuse shall be prohibited from entering into this area.
The flag shall be stationed as 200 m. from the firing site in all directions and all persons
including workmen shall be excluded from the flagged area at least 10 minutes before the
firing warning whistle being sounded for this purpose.
During excavation in rock by blasting, the lowest 15 cm. of the stratas shall be blasted with
light charges so as not to shatter or weaken the underlying rock on which the foundation will
be actually laid. If excavation in rock is done to larger width and lengths than those shown on
the drawings or as directed, no payment shall be made for such over break. If excavation is
done to depth grater than shown on the drawings or directed, excess depth shall be made up
with foundation grade concrete as directed at the contractor’s cost.
The charged hole shall be drilled to the required depth and in suitable places when blasting Is
done with powder, the fuse cut to the required length shall be inserted in the holes and the
powder dropped in. The powder shall be gently tamped with copper rod with rounded ends.
The explosive powder shall then be covered with trapping materials which shall be tamped
lightly but firmly. When blasting is done with dynamite and other high explosive dynamite
cartridges shall be prepared by inserting the square cut ends of fuse into the detonator, and
finished with dippers at the open ends. The detonator should be gently pushed into the
premier leaving one third of the copper exposed outside. The primer shall be housed into the
explosive. Bore holes shall be of such size that the cartridges can be easily passed down. The
primer shall be cleared of all debris and explosive inserted. The space for about 20 cms.
above the charge shall then be gently filled with dry clay pressed home and rest of the
tamping is firmed with any convenient materials gently packed with a wooden cover.
At a time, not more than 20 such charges shall be prepared and fired. The man in charge
shall blow a whistle in a recognised manner for cautioning the people. All the people shall
then be required to move to safe distances. The charges shall be lighted by the man in charge
only. The man-in-charge shall count the number of explosions. He shall satisfy himself that
the charges have been exploded before allowing the workman to go to the work site.
The contractor shall be fully responsible to strictly follow the prevailing rules and procedures
regarding blasting procedures.
In case of a misfire the following procedure shall be observed :
Sufficient time shall be allowed to account for the delayed blast. The man in charge shall
inspect all the charges and determine the missed charge.
If it is the blasting powder charge, it shall be completely flooded with water. A new hole shall
be drilled at about 45 cm. from the old and fired. This should blast the old charge. Should it
not blast the old charge. Should it not blast the old charge, the procedure shall be repeated
till the old charge is blasted.
In case of charge of gelatin, dynamite etc. the man in charge shall gently remove the tamping
and the primer with detonator. A fresh detonator and primer shall then be used to blast the
charge. Alternatively the hole may then be drilled 15 cm. away and parallel to it. This hole
shall then be charged fired when the misfired hole should explode at the same time. The man
in charge shall report to the office at once all cases of misfire, the cause of the same and
what steps were taken in connection therewith.
If a misfire has been found to be due to defective detonator or dynamite, the whole quantity
in the box from which defective article was taken must be sent to the authority as directed for
inspection to ascertain whether all the remaining materials in the box are also defective or
1.4. Accidents :
The contractor shall be solely responsible for any accident during the entire procedure of
handling explosive and blasting and shall pay necessary compensation to persons affected or
damage t lands or properly etc., due to the blasting without extra claims on the department.
A careful and day-to day account of explosives shall be maintained by the contractor in an
approved manner and shall be open to inspection of the Engineer-in-charge at all times.
Surprise visit may also be paid by the Engineer-in-charge to the storage and in case of any
unaccountable shortage or unsatisfactory accounting, the contractor shall be liable to be
penalised by forfeiture of part or whole of his Security Deposit or by cancellation of tender in
which case be shall not be entitled for any compensation.
1.6. Disposal of Excavated materials :
No materials excavated from foundation trenches of whatever kind they may be, are to be
placed even temporarily nearer than1.5m. of distance prescribed by the Engineer from the
outer edges of excavation. All materials excavated shall remain the property of Government.
Rate for excavation includes sorting out of useful materials and stacking them separately as
directed within the specified lead. Materials suitable and useful for back filling or other use
shall be stacked in convenient places but not in such a way as to obstruct free movement of
men, animals and vehicles or encroach upon the area required for constructional purpose. The
site shall be left clean of all debris on completion.
Disposal of excavated materials is subject to the following :
Unsuitable materials obtained from clearing site and excavation shall be disposed off within a
lead of 50 meters as directed. useful materials obtained from clearing site and excavation
shall be stacked within a lead of 50 M. beyond the building area as directed. Materials suitable
for back filling shall be stacked at convenient places within a lead of 50 M. from the structure
for reuse. Useful stones from rock excavation shall be stacked neatly within a lead of 50 M.
and will be allowed to be used by the contractor on payment at rates laid down in the contract
or if not so aid down, at schedule of rates of the Division or at a mutually agreed rates if
there are no such rates in the Schedule of rates.
If surplus materials are required to be conveyed beyond 50 M. conveyance will be paid for
under a separate item.
1.7. Mode of measurement and payment :
The work shall be measured for the work limited to the dimensions shown on drawings or
directed, Excavation to dimensions in excess of the above will not be measured or paid for
and if so ordered by the Engineer the contractor shall have to fill up the excess depth with
cement concrete specified for foundation without extra payment.
Driving of sounding bards, drill holes to explore the nature of substratum upto a total length
of meter distributed in 2 or 3 places in each foundation if necessary, will be considered
incidental work and eill not be paid for separately.
Removal of slips and blows in the foundation trenches will not be measured or paid for.
If it is necessary in the opinion of the Engineer-in-charge to carry foundation below the levels
shown on the plants the excavation for the first 1.5 M. of additional depth will be included in
the quantity for the particular classification and will be paid for as extra work at rate to be
decided under the general conditions of contract unless the contractor unless the contractor is
willing to accept payment as tendered rates.
The rate shall be for a unit of one cubic meter.
Dismantling the following including loading, unloading and disposal of
unserviceable material for all lead or as directed by Engineer-In-Charge and
stacking the serviceable material and backfilling the resulting trenches and pits
complete. Dismantling tiled or stone floors laid in mortar including stacking of
serviceable material and disposal of uservicalble material with all lead and lifts.
The relevant specifications of item no 20.1 (I) shall be followed except the dismantling of tiled or
stone floors laid on mortars shall be done Dismantling implies carefully taking up or down or these
are fixed by nail screws bolts etc. the shall be taken out with proper tools
Mode of measurement & Payment :
The supporting materials such as joints beams if any etc. shall be measured separately the relevant
specification of item no 20.1 (I) shall be followed. The rate shall include stacking the
unserviceable materials as directed will lead and lift.
The rate shall be for a unit of one sq. meatier
Conveyance charge of earth,lime,murrum, building rubbish,manual garbage,sludge
,excavated rock,fly ash, aggregate of any kind etc. comp. up to 5 Km. lead
All the surplus earth etc. shall be carried away immediately from the site of work to a
place within 5km. distance or as directed and ordered by the Engineer, so as not to cause any
inconvenience to the public traffic finding which in view of public safety and traffic
convenience. The corporation shall carry out the work by any other agency at the contractor’s
risk and cost. If the instructions are not completed within 7 days from the date of order to
cart the surplus materials and clear the site, the said work shall be carried out by the
Municipal Corporation at the risk and cost of the contractor and no claim or dispute shall be
entertained in this respect.
If the filling in trenches after settlement of the earth filling in trenches is to be done
and the same shall be carried out by the contractor without asking any extra rate. The
contractor shall have to cart the surplus earth after the trenches we will watered and refilled
with the sand. The rate of carting including carting of brickbats, metal, rubble vegetable and
garbage, if necessary to clear the road surface.
The rate shall be for a unit of one cubic meter.
Repairing damaged M.H. incl. removing damaged brick and repairing by masonry in C.M. 1:5
and plaster in C.M. 1:3 and fixing C.I. steps and M.H. and carting the same as directed.
(A) up to 0.15 mt. (@ Two Coarse)
(B) up to 0.35mt. (@ Four Coarse)
This is item pertaining to leveling MH cover. Existing manhole should be remove
property and carefully from its original level also exi. Asphalt should be removed and stacked
the excavated asphalt here by also removed top brick masonary layer as dire. So as to get
proper bonded between old masonary; and new masonary with a good quality of brick one to
there layer masonary in properly 1:5 incl. and plaster in C.M. 1:3 and fixing C.I. steps curing
etc. comp. Also provided and fixing old manhole with seat in c.c. prop 1:2:4. This MH should
be properly leveled and with road level etc. comp.
Mode of measurement shall be on No. basis.
Repairing damaged I.C./ Raising removing damaged brick work and repairing by
brick masonry in C.M. 1:5 and plaster in C.M. 1:3 and fixing C.I. steps and existing
chamber sheet cover, removing the debris from chamber and carting the same as
This is item pertaining to leveling I.C./C.P. cover. Existing Catchpit/Chamber should be
remove property and carefully from its original level also exi. Asphalt should be removed and
stacked the excavated asphalt here by also removed top brick masonary layer as dire. So as
to get proper bonded between old masonary; and new masonary with a good quality of brick
one to there layer masonary in properly 1:5 incl. and plaster in C.M. 1:3 and fixing C.I. steps
curing etc. comp. Also provided and fixing old manhole with seat in c.c. prop 1:2:4. This
IC/CP should be properly leveled and with road level etc. comp.
Mode of measurement shall be on No. basis.
Supplying and fixing of 300 mm-L x 150 mm-B x 380 mm-H Kerb block for Footpath
in M-20 grade using 20 mm nominal size black trap aggregate of Sevaliya/Timba or
equivalent quality for pre-cast blocks, reasonably exposed finish/ formwork
mould with well equipped with vibratory system for kerb stones of approved design
including curing, etc. complete, including the cost of formwork etc. complete. The
rate shall also include necessary cutting of asphalt, fixing the Kerb stones in line
and level on 5 cm thick sand bedding with necessary equipments and materials. The
rate shall also include the flush pointing in CM (1:3) for all joints of the kerbstones.
Filling of zari alone the sides of the kerb stone fixed with Bituminous concrete
mixed in proper position as directed by Engineer in change to form a portable
mixture. In any case Gravel or such type of materials shall not be allowed for
production. a) Laying on 5 cm thick Sand Bedding
Trenches of specified width and depth shall first be made along the edges of the
wearing course of the road or along the line of pave block flooring to receive the restraint
blocks. The bed of the trenches shall be compacted manually with steel rammers to a firm
and even surface and then stones shall be set in P.C.C.
The edge restraint blocks shall be laid with their length running parallet to the paving
edge, true in line and gradient. The joints of blocks shall be not more than 10 mm and filled
with the CM 1:3 ( 1 cement : 3 fine sand ) which shall be cured for 7 days.
Finishing The edges shall be restored and all surplus earth including rubbish etc.
disposed off as directed by the Engineer-in Charge.
Measurements Length of the finished work shall be measured in running metre along
the edge of the paving correct to a cm.
Rate The rate shall include the cost of the materials and labour including stone of
specified material involved in all the operation described above. The rate shall be for a unit of
one meter basis.
Providing and Laying of Rubber Moulded Paver Block Grey/Coloured 60 mm thick, M-35 Grade
of any size ; shape (Usually Uni-Paver Blocks) using black trap good quality aggragate of
mm nominal size for footpath, parking areas, service lanes and other areas as
mentioned in the drawing / instruction of engineer in charge. Cost includes formworks using
rubber mould, Rate providing and laying paver blocks as per required grading and
specification. The paver block shall be mechanically compacted. The work of paving blocks
shall be executed in line and level by skill mason of flooring work only. It should be laid in
such a way that the no cutting of the paver block to be necessary. if cutting of paver block
necessary then it should be cut by machine only and carting. The finished surface of the paver
block shall have resonably good, plain finished. Paver blocks shall be compacted and shall be
relaid if necessary. Gravel or such type of materials shall not be allowed for production.
Laying on 5cms thick sand beddding.
Scope of work :
Excavation and compaction up to 30 cm in height . for footpath paving in all sorts of soil
murrum including sorting outs and stacking of useful materials stuff up to 50 mt. lead from
excavated place and same well be carting. Up to 5 km.
The scope of work includes manufacturing, supplying and laying of precast paver blocks at
various Retail outlets. The work includes :
Verification of the existing site condition and advising our project in charge to lay suitable
base course if required. Contractors are required to satisfy themselves with quality of sub
grade, sub-base course before the paver blocks are laid and suggest strengthening if
Clearing the site by removing all obstacles such as stones, debris etc. for laying of paver
Manufacturing of paver blocks in your plant as per requirements in technical specification
Supplying of paver blocks at site, including handling at both ends.
Laying of paver blocks at site as per requirement in technical specification, within shortest
possible time. The site being existing operating Retail Outlets, care should be taken to ensure
that the operation is not closed. The job of laying may required to be carried out during night
Testing of paver blocks through reputed Govt./Non Govt. Test house and submission of test
results as per requirements in Technical Specifications. HPCL reserves the right to carryout
test at random. Cost for such tests to be borne by party.
The contractor shall guarantee that all material and components designed, fabricated,
supplied and laid by him shall be free from any type of defect due to faulty material and/or
workmanship/erection for a period of One year from the date of completion of work at
individual sites. However, the contractor fro two years shall render free maintenance.
TECHNICAL SPECIFICATIONS :
I) Paver Block Manufacturing Facilities :
The Paver Block shall be made in factory with following minimum facilities :
1.1 Concrete Block making Machines :
The machine should be capable of producing high quality Paver Blocks by obtaining
high level of compaction by application of hydraulic compaction and also by high
intensity vibration to the moulds. The machine should have automatic control panel for
uniformity in strength.
1.2 Concrete Batching & Mixing Plant : (Not essential)
The concrete Mix Design should be followed for each batch of materials. The concrete
ingredient should be mixed in concrete Batching & Mixing plant with minimum capacity
of 30 cum/hour. The plant should equipped with automatic control panel for
maintaining water cement ratio from batch to batch to obtain concrete of uniform
quality and strength. The plant should be equipped with adequate mechanism for
mechanized loading of raw materials into mixer and conveyor belt for transportation of
concrete from mixer to concrete block making machine to maintain quality of wet
1.3. Curing:- The factory should have well designed curing area to ensure adequate
curing of paver blocks.
Laboratory (Desirable but not essential) :
The factory should have the following:
Compression testing machine of adequate capacity.
Other tools and equipment for testing raw materials and paver blocks.
(1).Systematic record of test results of various paver blocks manufactured in the
(2).Concrete Mix Design for various grade of concrete used for making of paver
II) SPECIFICATIONS FOR COLOURED PAVER BLOCKS :
Coloured concrete paver blocks shall be manufactured as per attached specifications
using approved colour Pigment of “BAYER” Make “BAYFERROX IRONOXIDE PIGMENTS” with
minimum colour pigment of 3% by weight of cement. The colour shade shall be “RED” as
selected by HPCL before commencement of the work. White cement shall be used for colored
pavers to obtain the desired colour shade. The job also includes providing 50 mm thick sand
bedding to match the shade of the paver block.
The colour of the paver block shall be guaranteed against fading of colour for period of
12 months from the date of laying of the same at site.
All other technical specifications & Procedure for testing, laying & sampling of coloured
pavers will be as per attachment.
III) PAVERS BLOCK CHARACTERISTICS :
The concrete pavers should have perpendicularities after release from the mould and the
same should be retained until the laying.
The surface should be reasonably smoothe and of anti skid and anti glare type.
The paver should have uniform chamfers to facilitate easy drainage surface run off.
The pavers should have uniform interlocking space of 2mm to 3mm to ensure compacted
sand filling after vibration on the paver Surface.
The concrete mix design should be followed for each batch of materials separately and
automatic batching plant is to be used to achieve uniformity in strength and quality.
The pavers shall be manufactured in single layer only.
Skilled labour should be employed for laying blocks to ensure line and level of laying, desired
shape of the surface and adequate compaction of the sand in the joints.
The pavers shall be of cement gray colour without any pigment & for coloured pavers refer
“specifications for coloured pavers.”
The pavers are to be skirted all round with kerbing using solid concrete blocks of size 150mm
X 250mm X 380mm. The kerbing should be embedded for 100mm depth. The concrete used
for kerbing shall be cured properly for 7 days minimum.
IV) Paver Block Dimensions :
Thickness 60mm or 80mm
Shape Uniregular (Uniform Shape with no Hollow
Chamfer 4mm to 6mm along top edges
Colour Natural cement grey colour without use of
For coloured pavers refer “specifications
for coloured pavers”
Dimensional Tolerance (+/-) 2mm for length & width,
(+/-) 3mm for Height (Thickness)
V) Testing of Paver Blocks :
SR. Average Values
NO. (Average of Minimum
Five Samples/Site)
1. Compressive Strength Min. 45 N/Sqmm for 80mm
thick OR Min. 30 N/Sqmm for
2. Flexural Strength Minimum 4.5 N/Sqmm
3. Abrasion Resistance Maximum
4. Water Absorption Maximum 5.80%
5. Minimum Cement Contact 380 Kg/Cum (Not Essential)
* Sampling and Testing procedure as per enclosed specifications
SAMPLING AND TESTING PROCEDURES FOR PAVER BLOCKS.
INTERNAL – Average of minimum 3 samples per 5000 Blocks.
Essential – Minimum 2 Blocks per 10000 bocks. Average of minimum 8 blocks per site.
1. Sampling For Testing
Sampling for testing of paver blocks shall be done in accordance with Appendix-A.
Compressive Strength
Testing for compressive strength shall be undertaken in accordance with Appendix-B.
The average compressive strength of the bocks tested shall be 40 N/Sqmm.
Abrasion Resistance
Testing for abrasion shall be in accordance with IS 1237 (Specifications for Cement
Concrete Floor Tiles) – Appendix C.
Flexural Strength
Testing for flexural shall be n accordance with IS 1237 (Specifications for Cement
Concrete Floor Tiles) – Appendix D.
Water Absorption
Testing for water absorption shall be in accordance with IS 2185:1979 : Part I
(Specifications for Concrete Masonry Units) – Appendix E.
Sampling of Paver blocks.
1. Method of sampling :
Before laying paver blocks, each designated section comprising not more than
blocks, shall be divided into ten approximately equal groups. Three blocks shall be drawn
from each group.
Marking and identification :
All samples shall be clearly marked at the time of sampling in such a way that the
designated section of part thereof, and the consignment represented by the sample, are
clearly defined.
The sample shall be dispatched to the approved test laboratory taking precaution to
avoid damage to the paving in transit. Protect the paving from damage and contamination
until they have been tested. The testing shall be carried as soon as possible, after the sample
has been taken. As soon as practicable after sampling. The samples shall be stored in water
at 20 degree C 5 degree C for 24 hours prior to testing.
Providing and laying cement concrete 1:4:8 (1- Cement : 4 - Coarse aggregate : 8-Hand broken stone
aggregates 40 mm nominal size) and curing complete excluding formwork in (A) Foundation and
Before starting the concrete the bed of the foundations trenches shall be cleared of all loose
materials and watered and rammed as directed .
The proportion of cement, sand and coarse aggregate shall be one part of cement, 4 parts of
sand, 8 parts of stone aggregates and shall so measured by volume.
The concrete shall be mixed in a mechanical mixer at the site of work. Hand mixing may
however be allowed for smaller quantity of work if approved by the Engineer-incharge. When
hand mixing is permitted by the Engineer-in-charge incase of breakdown of machinery’s and
in the interest of the work. it shall be carried out on a water tight platform and care shall be
taken to ensure that mixing is continued until the mass is uniform in colour and consistency.
However in such cases 10% more cement than otherwise required shall have to be used
without any extra cost. The mixing in mechanical mixer shall be done for a period 1 to
minutes. The quantity of water shall be sufficient to produce a dense concrete of required
workability for the purpose.
The concrete shall be handled from the place of mixing to the final position in not more than
15 minutes by the method as directed and shall be placed into its final position, compacted
and finished within 30 minutes of mixing with water i.e. before the setting commences.
The concrete shall be laid in layers of 15 cms. to 20 cms.
The concrete shall be rammed with heavy iron rammers and rapidly to get the required
compaction and to allow all the interstriees to be filled with mortar.
After the final set, the concrete shall be kept continuously wet, if required by pounding for a
period of not less than 7 days from the date of placement
The concrete shall be measured for its length breadth and depth, limiting dimensions to those
specified on plan or as directed.
The rate shall be for a unit of one cubic meter.
Providing and laying cement concrete 1:3:6 (1- Cement : 3- Coarse sand :
6- Hand broken stone aggregates 40mm nominal size) and curing
complete.SOR 23-24 IT NO :05005A
Before starting the concrete the bed of the foundations trenches shall be cleared of all loose
materials and watered and rammed as directed. The proportion of cement, sand and hand
broken stone aggregates shall be one part of cement, 5 parts of coarse sand, 10 parts of hand
broken stone aggregates and shall so measured by volume. The concrete shall be mixed in a
mechanical mixer at the site of work. Hand mixing may however be allowed for smaller
quantity of work if approved by the Engineer-incharge. When hand mixing is permitted by the
Engineer-in charge in case of breakdown of machinery’s and in the interest of the work. it
shall be carried out on a water tight platform and care shall be taken to ensure that mixing is
continued until the mass is uniform in colour and consistency. The quantity of water shall be
sufficient to produce a dense concrete of required workability for the purpose. The concrete
shall be handled from the place of mixing to the final position in not more than 15 minutes by
the method as directed and shall be placed into its final position, compacted and finished
within 30 minutes of mixing with water i.e. before the setting commences. The concrete shall
be laid in layers of 15 cms. to 20 cms. The concrete shall be rammed with heavy iron
rammers and rapidly to get the required compaction and to allow all the gaps to be filled with
mortar. After the final set, the concrete shall be kept continuously wet, if required by
pounding for a period of not less than 7 days from the date of placement The concrete shall
be measured for its length breadth and depth, limiting dimensions to those specified on plan
or as directed.
Mode of measurements shall be on CMT basis
Providing F.R.C. MH seat cover incl. carting to the work site etc. comp.
F.R.C. Extra Heavy Duty (EHD-35) Manhole Covers & Frames Cover :
728mm ø & 100 mm thick circular cover, 35.00 MT load design, 100x2mm
MS flat allround, 16mm ø plain round bar for lifting the cover & should be
fitted with plastic cups. Frame: 560 mm ø clear opening, outer size-
888x888x175 mm. On the upper periphery of frame 25 x 3 mm wide MS flat
should be well embed in concrete to protect the edges of frame. FRC E.H.D.-35
manhole cover & frame described as above.
FRC heavy duty cover size 730 mm. & 90 mm thick circular Cover
20 M.T. design load and frame size 560 mm clear opening size 890 x 890 x
FRC medium duty cover size 670 mm dia & 70 mm thick 10 M.T. load design
and frame size 560 mm clear opening outer size
FRC medium duty Chamber seat cover (FRC) cover 706 x 556 x
mm rectangular cover frame size 600 x 450 mm clear opening outer size 816 x
FRC light duty Chamber seat cover (FRC) cover with rectangular frame (LD-
2.5) Cover & Frame - 600 x 450mm clear opening,
F.R.C. Extra Heavy Duty (EHD-35) Manhole Covers &Frames Cover : 728mm ø &
mm thick circular cover,35.00 MT load design, 100x2mm MS flat allround, 16mm ø plain
round bar for lifting the cover & should be fitted withplastic cups. Frame : 560 mm ø clear
opening, outer size-888x888x175 mm. On the upper periphery of frame 25 x 3mm wide MS
flat should be well embed in concrete toprotect the edges of frame. FRC E.H.D.-35 manhole
cover & frame described as above The measurement shall be for a unit of one sq. metre.
The measurement shall be for a unit of Number basis.
Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform
layers in sub- base / base course on well prepared surface and compacting with
vibratory roller to achieve the desired density as per Codal Provision.
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam
specification including premixing the Material with water at OMC in mechanical mix plant
carriage of mixed Material by tipper to site, laying in uniform layers in sub- base / base
course on well prepared surface and compacting with vibratory roller to achieve the desired
density as per Codal Provision.
(A) Production & Supply of WMM
(B) Laying of WMM
Mode of measurements shall be on CMT basis
Providing and laying in position Ready Mixed M-200 grade concrete for reinforced
cement conctere work, using cement content as per approved Design Mix
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for a lead up to 10 kms having continuous agitated mixer,
manufactured as per mix design of specified grade for reinforced cement concrete
work including pumping of R.M.C. from transit mixer to site of laying, excluding the
cost of centering shuttering finishing and reinforcement including cost of
admixtures in recommended proportions as per IS: 9103 to accelerate/retard
setting of concrete, improve workability without impairing strength and durability
as per direction of the Engineer - in - charge. Without Fly Ash (Min. cement level as
per latest IS 456 shall be maintained)
Providing and laying in position Ready Mixed M-200 grade concrete for reinforced cement
conctere work, using cement content as per approved Design Mix manufactured in fully
automatic batching plant and transported to site of work in transit mixer for a lead up to
kms having continuous agitated mixer, manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of R.M.C. from transit mixer to site of
laying, excluding the cost of centering shuttering finishing and reinforcement including cost of
admixtures in recommended proportions as per IS: 9103 to accelerate/retard setting of
concrete, improve workability without impairing strength and durability as per direction of the
Engineer - in - charge. Without Fly Ash (Min
cement level as per latest IS 456 shall be maintained)
Mode of Measurement shall be paid by CMT. Basis
Providing formwork of ordinary timber planking so as to give a rough finish
including centering shuttering strutting and propping etc. Height of propping and
centering below supporting floor to ceiling not exceeding 4 M. and removal of the
same for in situ reinforced concrete and plain concrete work in. (A) Foundations
Footings Bases of Columns etc.and Mass concrete
Providing formwork of ordinary timber planking so as to give a rough finish including
centering shuttering strutting and propping etc. Height of propping and centering below
supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (A) Foundations Footings Bases of Columns etc.and Mass
Mode of Measurement shall be paid by Smt
Providing TMT Bar FE500D reinforcement for R.C.C. Work including
bending,binding and placing in position complete upto floor two level.
Providing TMT Bar FE500D reinforcement for R.C.C. Work including bending,binding and
placing in position complete upto floor two level.
As per M.O.R.T & H. latest Specifiaction& IS CODE.
Mode of Measurement shall be paid by kg.
P/A Tremix with dewartering machine and floater machine on constructed CC
work for finishing the surface as per requirement. The rate including all
machinaries, labor, loading, unloading, ransportaion etc complete as per direction
given by engineer in charge.
P/A Tremix with dewartering machine and floater machine on constructed CC work for
finishing the surface as per requirement. The rate including all
machinaries, labor, loading, unloading, ransportaion etc complete as per direction given by
engineer in charge.
Mode of Measurement shall be paid by Smt
Making 15 mm. Groove in RCC work on road & filling it with polysulfied selant
& finished ot good incl. all labour charges etc. comp.as directed.
Making 15 mm. Groove in RCC work on road & filling it with polysulfied selant & finished ot
good incl. all labour charges etc. comp.as directed.
Mode of Measurement shall be paid by Rmt
Extra Rate Over Item of Excavation of Earth for excavation of asphalt
pavement / RCC of thickness up to 0.20 meter including demolishing the asphalt
carpet, metal,s oiling/cutting Reinforcement etc.comp. with stacking the material as
Extra Rate Over Item of Excavation of Earth for excavation of asphalt pavement / RCC of
thickness up to 0.20 meter including demolishing the asphalt carpet, metal,s oiling/cutting
Reinforcement etc.comp. with stacking the material as directed.
Mode of Measurement shall be paid by Smt
Supplying Pneumatic Breaker Machine for RCC Slab or Asphalt Demolishing
Work on site by using Operator, fuel, power Supply etc. Complete as Directed
Supplying Pneumatic Breaker Machine for RCC Slab or Asphalt Demolishing Work on
site by using Operator, fuel, power Supply etc. Complete as Directed
Mode of Measurement shall be paid by Hour Basis
Contractor’s Signature Add. Cit y Engi neer
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Tender No. 64.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .