Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹38.6 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹39.9 L+₹1.1 L (2.76%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
Refer Docs
EMD Value
₹35,590
Closing Date
28 Dec 2020, 5:00 pmClosed
Executive Engineer, RWSS Division
Near Jarada Bunglow, Berhampur
Laying of pipelines, Construction of valve Chambers, bore well platform , boundary wall, Construction of 50 KL UGR ,providing 100 percent FHTC etc. in connection with PWS to Badachakada under Ganjam Block.
2020_RWSS_64644_7
EERWSSBAM- 16 ( B ) / 2020-21
National Competitive Bid
Civil Works - Water Works
Item Rate
180 days
PWS to Badachakada under Ganjam Block
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹35,590
Yes
5 Jun 2021
15 Dec 2020
29 Dec 2020
15 Dec 2020
28 Dec 2020
15 Dec 2020
15 Dec 2020 - 24 Dec 2020
Amount
Laying of pipe line ,Head works, Other Balance Works
Supplying all materials labour T&P design, drawing ,soil testing etc. complete in all respect for construction of Compound wall for Pump House .Laying, testing and commissioning of Rising main & Distribution system pipe line such as UPVC,HDPE,ASTM, G.I /CI pipes line etc along with required fittings & specials and construction of valve chamber, bore well platform,individual house hold connection, installation of submersible pump with motor in deep Tube well etc.as per detail scope of work & technical specification, quantity of work mention in Schedule-I in DTCN and in ( Annexure-A to C). Materials as required shall be supplied by the Contractor as per terms and condition of DTCN & all dimensions are as per Schedule-I in DTCN and as per direction of Engineer in Charge . All work shall be completed in such a manner that all house hold of entire village will get required quantity of drinking water with residual head of 7m without any likage in the entire PWS system as per direction of Engineer-in-charge.
Construction of 50000 LTR RCC UGR Supplying of all labour,T&P, material including taxes , testing ,supply of design, drawing , construction,errection,testing & commissioning etc. of RCC Under ground reservoir of 50,000 ltrs capacity cylindrical container circular dome, full raft using CC M-25 , with sand and PCC layers as per approved drawing,supplying, fitting & fixing of 100 mm dia medium grade GI pipe Tata/Jindal/Sail/Nezone make confirming to IS specification of required length from PW to UGR & UGR to rising main including in-let,out-let,over flow & washing line of UGR, and use of aluminum ladder inside the UGR,CI puddle collar,0.6 m dia CI manhole cover at dome(2 Nos.) , RCC vent with brass jally,water level indicator etc. complete as per direction of the Engineer - in- Charge. (The contractor is to approve all structural design & drawing from State Technical Agency IGIT,Saranga /CET,BBSR/VSSUT,Burla /NIT,Rourkela /IIT,BBSR at his own cost)
HIMANSHU SEKHAR PADHI
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .