GEMC-511687722248598
Awarded to LIVE LINE ELECTRONICS
₹34.0 L
Products
| Product | Brand / Model | HSN | Quantity | Unit Price | Amount |
|---|---|---|---|---|---|
| Float Cum Boost Charger Main Supply as per Technical Specification | LIVE LINE / DCPS | 85044030 | 2 Nos | 221,822 | 443,644 |
| Battery Fuse Box Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 2 Nos | 5,203 | 10,406 |
| DISCHARGE RESISTOR Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 1 Nos | 52,038 | 52,038 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 247 | 1,482 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 520 | 3,120 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 1 LOT | 7,434 | 7,434 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 4 LOT | 5,575 | 22,300 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 SET | 7,434 | 7,434 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 SET | 892 | 892 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 3 SET | 1,238 | 3,714 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 3 SET | 2,725 | 8,175 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 SET | 26,019 | 26,019 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 SET | 446 | 446 |
| Float Cum Boost Charger Main Supply as per Technical Specification | LIVE LINE / DCPS | 85044030 | 4 Nos | 221,822 | 887,288 |
| Battery Fuse Box Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 4 Nos | 5,203 | 20,812 |
| DISCHARGE RESISTOR Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 2 Nos | 52,038 | 104,076 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 247 | 1,482 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 520 | 3,120 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 2 LOT | 7,434 | 14,868 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 8 LOT | 5,575 | 44,600 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 SET | 7,434 | 7,434 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 SET | 892 | 892 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 3 SET | 1,238 | 3,714 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 3 SET | 2,725 | 8,175 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 SET | 26,019 | 26,019 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 SET | 446 | 446 |
| Float Cum Boost Charger Main Supply as per Technical Specification | LIVE LINE / DCPS | 85044030 | 2 Nos | 221,822 | 443,644 |
| Battery Fuse Box Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 2 Nos | 5,203 | 10,406 |
| DISCHARGE RESISTOR Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 1 Nos | 52,038 | 52,038 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 247 | 1,482 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 520 | 3,120 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 1 LOT | 7,434 | 7,434 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 4 LOT | 5,575 | 22,300 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 LOT | 7,434 | 7,434 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 LOT | 892 | 892 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 3 LOT | 1,238 | 3,714 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 3 LOT | 2,725 | 8,175 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 LOT | 26,019 | 26,019 |
| Mandatory spares as per Technical Specification | LIVE LINE / NA | 8504 | 1 LOT | 446 | 446 |
| Float Cum Boost Charger Main Supply as per Technical Specification | LIVE LINE / DCPS | 85044030 | 2 Nos | 221,822 | 443,644 |
| Battery Fuse Box Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 2 Nos | 5,203 | 10,406 |
| DISCHARGE RESISTOR Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 1 Nos | 52,038 | 52,038 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 257 | 1,542 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 520 | 3,120 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 1 LOT | 7,434 | 7,434 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 4 LOT | 5,575 | 22,300 |
| Float Cum Boost Charger Main Supply as per Technical Specification | LIVE LINE / DCPS | 85044030 | 2 Nos | 221,822 | 443,644 |
| Battery Fuse Box Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 2 Nos | 5,203 | 10,406 |
| DISCHARGE RESISTOR Main Supply as per Technical Specification | LIVE LINE / NA | 8504 | 1 Nos | 52,038 | 52,038 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 247 | 1,482 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 520 | 3,120 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 148 | 888 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| Erection and commissioning SPARES FOR FLOAT CUM BOOST CHARGER | LIVE LINE / NA | 8504 | 6 Nos | 74 | 444 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 1 LOT | 7,434 | 7,434 |
| COST OF SUPERVISION OF Erection and Commissioning | LIVE LINE / NA | 9987 | 4 LOT | 5,575 | 22,300 |