| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.8 LAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹7.8 L+₹7,278.63 (0.94%)Admitted-Finance | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | KUMARAN RAVI L1 | M R SURESH L2 |
|---|---|---|---|---|---|
| 1.00 | Earthwork excavation and depositing on bank with an initial lead of 10m and lift of 2m in the following classification of soils as directed by TWAD Board officers. Hard stiff clay, block cotton, hard red earth shales, murram, ordinary gravel, stoney earth and earth mixed with small size boulders for foundation SS 20B | 23.12 | cum | 263 ₹6,080.56 Lowest | 350 ₹8,092 |
| 2.00 | Second depth 2.00 m - Below | 0.58 | cum | 408.16 ₹235.92 Lowest | 450 ₹260.1 |
| 3.00 | Sand filling for foundation with clear river sand including cost of sand watering, ramming and consolidation etc complete. | 1.16 | cum | 1,967.8 ₹2,274.78 Lowest | 2,000 ₹2,312 |
| 4.00 | Cement concrete 1:4:8 (one cement four sand and eight aggregates) using 40mm HBGS for levelling course for foundation including the cost of mixing concrete, ramming, curing etc., complete. | 1.73 | cum | 5,774.16 ₹10,012.39 Lowest | 5,774.16 ₹10,012.39 Lowest |
| 5.00 | Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete and as directed by TWAD Board officers. | 3.6 | sqm | 1,095 ₹3,942 Lowest | 1,095 ₹3,942 Lowest |
| 6.00 | Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete. | 0.98 | MT | 91,982 ₹89,866.41 Lowest | 91,982.5 ₹89,866.9 |
| 7.00 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete | 2 | cum | 9,691.14 ₹19,382.28 Lowest | 9,691.14 ₹19,382.28 Lowest |
| 8.00 | Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete. | 6 | Sqm | 1,314 ₹7,884 Lowest | 1,400 ₹8,400 |
| 9.00 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete. | 0.45 | cum | 9,691.14 ₹4,361.01 Lowest | 9,691.14 ₹4,361.01 Lowest |
| 10.00 | Earthwork excavation and depositing on bank with an initial lead of 10m and lift of 2m in the following classification of soils as directed by TWAD Board officers. Hard stiff clay, block cotton, hard red earth shales, murram, ordinary gravel, stoney earth and earth mixed with small size boulders for foundation SS 20B | 0.15 | cum | 263.78 ₹39.57 Lowest | 280 ₹42 |
Tender Value
Refer Docs
EMD Value
₹9,000
Closing Date
9 Sept 2025, 4:00 pmClosed
The Block Development Officer
The Block Development Officer PU Thottiyam
Construction of New OHT 10000 Litr at Palanigoundanur in Murungai Pt.
2025_RDTN_598592_2
A5/1228/2025
Open Tender
Civil Works - Others
Item Rate
120 days
PU Thottiyam
Work Experience
5 documents required · 5 mandatory
₹0
₹9,000
Yes
10 Sept 2025
30 Aug 2025
10 Sept 2025
30 Aug 2025
9 Sept 2025
30 Aug 2025
Amount
Earthwork excavation and depositing on bank with an initial lead of 10m and lift of 2m in the following classification of soils as directed by TWAD Board officers. Hard stiff clay, block cotton, hard red earth shales, murram, ordinary gravel, stoney earth and earth mixed with small size boulders for foundation SS 20B
Second depth 2.00 m - Below
Sand filling for foundation with clear river sand including cost of sand watering, ramming and consolidation etc complete.
Cement concrete 1:4:8 (one cement four sand and eight aggregates) using 40mm HBGS for levelling course for foundation including the cost of mixing concrete, ramming, curing etc., complete.
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete and as directed by TWAD Board officers.
Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete.
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
Earthwork excavation and depositing on bank with an initial lead of 10m and lift of 2m in the following classification of soils as directed by TWAD Board officers. Hard stiff clay, block cotton, hard red earth shales, murram, ordinary gravel, stoney earth and earth mixed with small size boulders for foundation SS 20B
Cement concrete 1:4:8 (one cement four sand and eight aggregates) using 40mm HBGS for levelling course for foundation including the cost of mixing concrete, ramming, curing etc., complete as directed by TWAD Board officers.
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.
Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
Refilling the foundation with excavated earth including watering and consolidation etc., complete.
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.
Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Sq.Col.Cent. Rate (2.90 - 3.30)
Sq.Col.Cent. Rate (3.30 - 4.30)
Sq.Col.Cent. Rate (4.30 - 5.30)
Sq.Col.Cent. Rate (5.30 - 5.50)
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
RCC Rate (4.50 - 5.50)
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.
Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Sq.Col.Cent. Rate (5.75 - 6.30)
Sq.Col.Cent. Rate (6.30 - 7.30)
Sq.Col.Cent. Rate (7.30 - 8.30)
Sq.Col.Cent. Rate (8.30 - 8.35)
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.
Centering Rate (8.70 - 8.70)
Curv. Surface Cent. Rate (0.00 - 3.30)
Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.
Curv. Surface. Cent. Rate (0.00-3.30)
Curv. Surface. Cent. Rate (0.00-3.30)
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
RCC Rate (9.00-11.45)
Supplying and erecting steel centering for sides and soffits I including necessary supports' and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.
Curverd Sur. Cent. Rate (0.00 -3.30)
Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete
RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc., complete.
Providing PVC ventilating arrangements mosquito proof nylon net with 110 mm PVC pipes and cowl etc., complete.,
Providing manhole cover of size 0.60 m X 0.60 m in CI and 5O x 5O x 6mm MS angle fixed along edges etc., complete.,
Providing and fixing of RCC inner access ladder in RCC 1:1.5:3 (one cement, one and half sane! and three aggregates) using 20mm HBG stone for OHT including cost of reinforcement, placing grill in position, centering shuttering charges, mixing concrete curing etc., to required height and clear width of 4Scm consisting of two Nos. of ve~ical post of 10cm x lScm and step slab of 25mm x 25mm etc., complete.
FabricatFabrication, supply, delivery and fixing of outside MS ladder of 45cm wide made out Fabrication, supply, delivery and fixing of outside MS ladder of 45cm wide made out of 50x50x6mm MS angle for sides and steps in 16mm MS plain rods fixed at 30cm centre to centre welded, jointed etc., providing with suitable side supports, clamps, and locking arrangements provided with one coat of red oxide paint for providing access to roof top of OHT of suitable inclined length, including bottom anchorage and transportation etc., complete.,
Providing cut stone slab in CM 1:3 etc., complete.,(.45x.45x.15)
Exterior Emulsion Paint two coats with approved exterior emulsion paint over one coat of priming coat over cement plastered exposed surface of the Reservoir including cleaning, preparing the surface and curing etc., complete.
65mm dia GI pipes for inlet connection
65mm dia GI pipes for over flow and RWH
65mm dia GI pipes for delivery pipe.
50mm dia GI pipes for scour pipe.
90mm dia PVC Threaded coupler
65mm dia PVC Threaded coupler
65mm dia GI Tee
65mm dia 90 Deg. Bend
65mm dia GI Bend (Short)
65mm dia GI Coupler
65mm dia GI Union
65mm dia GI Elbow
50mm dia GI Union
50mm dia GI Elbow
65mm dia GI Tee
65 X 50mm dia GI Reducer
75 X 63mm dia PVC Reducer
65mm dia GM Gate Valve
50mm dia GM Gate Valve
EPL Work, Pumping & Delivery (Sub Estimate)
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
M R SURESH (BID ID -1452487)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .