| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹22.1 LAccepted-AOC COURT ROAD UTTARKASHI | 1 | Accepted-AOC Qualified and accepted as ranked L1 bidder | |
| 2 | 2₹22.5 L+₹34,525 (1.56%)Rejected-AOC JHAWAREDI POST KARBARI IDBI BANK COMPLEX SHIMLA ROAD DEHRADUN | 2 | Rejected-AOC qualified but rejected as ranked L2 bidder | |
| 3 | 3₹22.5 L+₹34,980 (1.58%)Rejected-AOC 221 VIJAY PARK EXTENSION LANE NO 11 DEHRADUN | DEHRADUN | UTTARAKHAND | 248001 | 3 | Rejected-AOC Qualified but rejected as ranked L3 bidder |
Tender Value
₹30.5 L
EMD Value
₹61,100
Closing Date
15 Sept 2020, 4:00 pmClosed
EE(EM-I), Lakhwar project
Lakhwar-Vyasi Bhawan, Dakpathar, Dehradun
repairing overhauling of lakhwar feeder no 3 with installation of covered conductor in densely populated areas near line jeevan garh Dakpathar
2020_UJVN_25704_1
04/EE(EM-I)/LP/2020-21
Open Tender
Electrical Works
Item Rate
90 days
Dakpathar
Contained in tender document
2 documents required · 2 mandatory
₹2,360
DGM(Civil), Vyasi Project, Dakpathar
₹61,100
29 Sept 2020
25 Aug 2020
18 Sept 2020
25 Aug 2020
15 Sept 2020
25 Aug 2020
25 Aug 2020 - 14 Sept 2020
Amount
Supply Part:
ST Pole 11.0 mtr. long SP-55 for 33 KV Line
33 KV polymer pin insulator with pin and acceceries (90 KN)
33KV polymer tension pin insulator with oval eye end fitting (90 KN)
Earthing (MS Earthing Rod 2.5 Mtr Long)
Bolts & Nut off size
Barbed wire
All Aluminium Alloy Stranded Covered Conductors for 33 kV, 7/4.26 mm (99 sq.mm)
Tension Assembly/Anchoring Clamp
Insulated Cable Ties
Insulation Piercing Connector for “Bare to Covered interconnection”
Mid SpanTension Joints (TJ) for Aluminium Alloy Stranded Covered Conductors (99 sq.mm)
GI Stay wire of 7/4 mm (8 SWG)
Side arm channel (100 mm X 50 mm X 6 mm) pole top bracket for single 33 KV over headline conductor complete with 50 mm X 6 mm M.S. flat iron clamps, bolts and nuts including drilling holes for insulator pins,bolts and nuts etc and painting with primer and finish paint as required. (as per sample)
Supplying of channel iron 100 mm X 50 mm X 6 mm (9.56 kg per metre), pole top bracket for single 33 KV over head line conductor complete with 50 mm X 6 mm M.S. flat iron clamps, bolts and nuts including drilling holes for insulator pins,bolts and nuts etc and painting with primer and finish paint as required.
Danger Plate
Aluminimum Paint
Red Oxide Primer
Work Part:
Dismantling of pole embedded in brick ballast foundation etc. as required.
Erection of steel tubular or rail pole strut in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size ) foundation including excavation and refilling and secured with holding clamps, bolts, nuts, etc. as required for proper completion of work
Erection of pole top, angle iron/ channel iron, on steel tubular pole for 33 KV as required,120KN polymeric pin insulator ,earthing clamp,insulation Piercing Connector for “Bare to Covered interconnection” ,danger plate,insulator clamp,PG clamp, barbed wire,Insulation Piercing Connector,Tension Assembly earthing ,painting of poles etc including T&P and labour charges for completion of work
Erection of ACSR covered conductor including binding etc.
Laying, stringing, sagging of 3 phase Dog conductor hoisting of disc insulator and jumpering complete in all respect for proper copletion of work
Reallignment of Disc insulator 120KN,disc fitting on already existed poles including T&P and labour charges for completion of work (per pole)
Lopping / chopping/cutting of tree, plants ,creepers& vines & clear the right of way near & under of the line up to minimum eight feet distance from the line & pole structure including the cost of T&P, transportation &Labour charges etc , for proper completion of work (length of 33 kv line 29 km approx.)
Replacing of damaged /broken /puncher disc/ pin insulator fitting/clamp etc,as required including labour, transportation charges &T&P for proper completion of work.
Dismantling of over head lines comprising of copper/ aluminium over head conductor, G.I. wire, cross arms, insulators etc. as required
Shifting of one phase conductor on top cannel:-Dismantling of 3phase conductor & top channel with accessories & marking hole with drill machine for testing fitting /pin insulator in new top channel &again erection the top channel on pole structure &fixing all accessories& resagging 3phase dog conductor with shifting the phase on top parallel to other two phase including with earth wire as required including labour, transportation, T&P charges etc for proper completion of work
Erection of stay set complete (galvanised) in cement concrete1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size ) foundation including excavation and refilling etc. as required for proper completion of work
Erection of new earth wire,:-Erection laying stringing &sagging of new earth wire 7/16 SWG and binding on each pole properly including dismantling &wrapped old rusted& damage earth wire dismantled &well wrapped earth wire would be escorted at store DKP including labour, transportationcharges&T&P for proper completion of work
Testing and Comissioning of 33KV Line including the cost of T&P, transportation &Labour charges etc, for proper completion of work
M/s Shashi Enterprises
national engineers and associates
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .