Tender Value
₹1.6 Cr
EMD Value
₹1.6 L
Closing Date
18 Apr 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
Executive Engineer, Surendranagar Irrigation Division, Surendranagar
Repairing And Restoration of Bucket of Limbdi Bhogavo-2 (Vadod) Irrigation scheme for the year-2026-27.
290469
20 of 2025-26
Open
Civil Works - Water Works
Surendranagar
6 documents required · 5 mandatory · 1 optional
₹3,600
Yes
Executive Engineer, Surendranagar Irrigation Division, Surendranagar
₹1.6 L
Yes
27 Mar 2026
27 Mar 2026
27 Mar 2026
18 Apr 2026
27 Mar 2026
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
SURENDRANAGAR IRRIGATION DIVISION - SURENDRANAGAR
Name of Work : Repairing And Restoration of Bucket of Limbdi Bhogavo-2(Vadod) Irrigation scheme for the year-2026-27.
Memorandum showing Items of Woks to be carried out
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
estimated but In Figures In words according to
may be more or estimated
less quantities
1 3889.00 Dewatering for earthen dam and allied works, foundation areas, pits, trenches etc incl cost of pumping machineries, 27.00 Rupees Twenty Seven HP-hrs
pipe line, labours diesel/electricity/DG set, etc complete. Only
2 371.45 Earth work in embankment from borrow pits in all sort of soil and soft murrum or other suitable strata as directed 165.20 Rupees One Hundred Cum
incl breaking clods and dressing to the design section with lead upto 5 km. and all lift incl.site clearance etc comp. and Sixty Five Only
For all canal capacity & Without rolling and watering.
3 1866.44 Desilting of dam bucket including depositing the same as directed with all lift and lead etc complete. 295.83 Rupees Two Hundred Cum
Ninety Five and Eighty
Three paisa Only
4 773.19 Dismantling stone/brick masonry & stacking of useful and unuseful material from the dismantled materials as 616.00 Rupees Six Hundred Cum
directed etc. complete. and Sixteen Only
(a) In Cement Mortar
5 135.50 Dismantling C.C. foundation or flooring sorting & stacking useful and unuseful material in lead upto 200mt as 828.00 Rupees Eight Hundred Cum
directed etc. complete. and Twenty Eight Only
6 1087.30 Preparing of spillway, piers and allied work incl. removal of loose weathered material incl. hard rock by wedging, 8.90 Rupees Eight and Sqmt
chiseling with all labours, tools and materials for cleaning the existing reinforcement or surfaces with sand blasting, Ninety paisa Only
compressed air and water jetting as required etc complete.
7 1216.00 Drilling for 35 mm or specified diameter Holes by mechanical rotary (diamond bits) drilling tools for consolidation 812.47 Rupees Eight Hundred Rmt
& curtain grouting in earthen dam C.O.T. in all sorts of rock formation and for fixing anchor bars of specified Twelve and Fourty
diameter with epoxy grout complete.(excluding cost of bars) Seven paisa Only
8 15.999 Providing,cutting,bending,binding and fixing in position as per drawing.TMT BAR, reinforcement for R.C.C. works 76574.00 Rupees Seventy six M.T.
and anchor bars incl cost of black annealed 16 to 18 BWG M.S.. Wire etc.complete with all lead and lift. (b) Fe-500 Thousand Five Hundred
Seventy Four Only
9 1087.30 Epoxy bonding of new concrete Or mortar to old surface in structure with proper application of coat of resin and 260.83 Rupees Two Hundred Sqmt
hardener in proportion of 2:1 by weight confirming to IS-9197 to give proper bond between old surface new Sixty and Eighty Three
concrete Or mortar etc complete paisa Only
10 1819.48 Prov. and Laying in position Controlled cement concrete using cement, sand and crushed aggregate by mass and 5267.00 Rupees Five Thousand Cum
machine mix for R.C.C/CC work including necessary formworks centering scaffolding compaction by mechanical Two Hundred Sixty
vibrator,curing as directed with all lead & lift etc complete Excluding the cost of reinforcement. For Skin conc. Seven Only
friction blocks, st.basin
C) Concrete grade M-25 and MSA-20 mm
11 1047.20 Providing and filling Asphalt of the approved make and sand in the expansion and contraction joints in the C.C. 68.03 Rupees Sixty Eight and Rmt
lining including clearing the joints with air water jet. Three Only
12 924.92 Providing epoxy plaster 6 to 8mm min.thickness incl filling of all pot-holes /ditches with epoxy mortar 2483.00 Rupees Two Thousand Sqmt
upto req. depth by using resin:hardner:aggregates confirming to IS-9162 in proportion 0.7:0.3:6.5,by Four Hundred Eighty
weight on exposed damaged old and rough surface of spillway/canal strs with proper application of Three Only
necessary primer coat of resin and hardener in proportion of 2:1 by weight confirming to IS-9197 to give
proper bond between old surface and epoxy plaster incl necessary cleaning, cheeping of old surface incl
scaffolding, tools bars for the job with labour incl all lead and lift etc complete in all condition dry and
13 40.60 Removing of existing corrosion of reinforcement and applying primer coat and applying two anti corrosive paint on 97.29 Rupees Ninety Seven Rmt
reinforcement including all labour work etc. complete. and Twenty Nine Only
In Words Rs. (One Crore Fifty Seven Lacs Sixty Eight Thousand Three Hundred Eleven Rupees And Fourty One Paisa Only)
I/We am/are willing to carry out the work at % above/ below present (should be written in figures and words)
of the estimated rates mentioned above. An amount of my/our tender works out as under:
* Estimated Amount * Estimated Amount
Put to tender Rs_____________________________ Put to tender Rs_________________
In Words (Rs. ) In Words Rs.( )
(Pease strike out whichever is not applicable)
Note-1: The Contractor shall exhibit a board with brief details of work as directed by the Engineer-In-Charge for which no extra payment shall bemade.
Note-2: Thel abour cess will be deducted as per prevailing rules i.e. 1% of the work done.
Note-3: GST and Incometax TDS will be deducted at a source while making payments of bills
Note-4: In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R. NO.: MIS102010/17/K1 Dated:30/07/2018 as stated in S.O.R. therefore in R.C.C. items where there is a change as per actual mix
design the cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of Contractor. Surendranagar Irrigation Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
01- TITLE PAGE.pdf
02- E- Tender Notice.pdf
03- Invitation for Bid P 1 to 6.pdf
04- SECTION-1 Instruction to Bidders P 7 to 27.pdf
05- SECTION-2 Qualification Information P 28 to 35.pdf
06- SECTION-3 Conditions of Constract P 36 to 64.pdf
07- SECTION-4 Contract Data P 65 to 74.pdf
08 SECTION-5 to 10 Annexure P 75 to 96.pdf
09- Annexure-1 Sec-5 tech spec p 97 to 189.pdf
10- BOQ.pdf
Download all tender documents and submit your bid