| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹67.5 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹75.3 L+₹7.8 L (11.5%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹77.1 L+₹9.7 L (14.3%)Rejected-AOC | L3 | Rejected-AOC L3 | |
| 4 | L4₹78.3 L+₹10.8 L (16.0%)Rejected-AOC | L4 | Rejected-AOC L4 | |
| 5 | L5₹79.2 L+₹11.7 L (17.3%)Rejected-AOC | L5 | Rejected-AOC L5 |
Tender Value
Refer Docs
EMD Value
₹50,000
Closing Date
7 Mar 2023, 4:00 pmClosed
EE Roads DVn MVPA
PWD Roads Division Muvattupuzha
The provisions included in this estimate are Pot hole filling using 36mm aggregates Levelling course using 36mm and 12mm aggregates 20 mm thick close graded chipping carpet Shoulder strengthening using PCC 1 3 6 and M20 grade concrete
2023_PWD_561614_1
PWD/RB/TR/15612/2022_5_1_1/1
Open Tender
Civil Works - Roads
Item Rate
364 days
Erakulam
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
₹50,000
Yes
11 May 2023
25 Feb 2023
10 Mar 2023
25 Feb 2023
7 Mar 2023
25 Feb 2023
Amount
Reactive Maintenance(Initial Rectification Work)
55.4:Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.
55.8.a:Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface.
55.7.a:Providing bitumen leveling coarse between 40mm and 150mm with 36mm deptl metal by spreading the metal to line and levels and rolling until the compacted coarse aggregate has a firm surface and applying hot bitumen with pressure sprayer at the rate of 20 Kg per M3 metal including all cost of bitumen conveyance heating mixing spreading in appropriate locations to proper levels compacting with power roler and other sundry stores.
55.2:Supplying and stacking 12mm hard blue granite broken stone in standard heaps for measurement(IRC 3.2.1.a)
55.6.a:Providing pre mix bitumen leveling coarse having thickness between 20mm and 40mm with 12mm deptl metal by spreading the metal to line and levels and rolling until the compacted coarse aggregate has a firm surface and applying hot bitumen (vg 30) with pressure sprayer at the rate of 48 Kg per M3 metal including all cost of bitumen conveyance heating mixing spreading in appropriate locations to proper levels compacting with power roler and other sundry stores.
5.2.a:Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.
OD110078/2022-2023:OD129035/2021-2022 Providing , laying and rolling of close graded premix carpet (CGPC) of 20 mm thickness composed of 11.2 mm to 0.09 mm (MoRTH M -041) aggregates premixed using viscosity grade bitumen (VG 30@22 kg of bitumen per 10 sqm (MoRTH 5.7.1 Type A) to required line, grade and level on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel static, roller of 80-100 kN capacity, finished to required level and grades. By Manual means.
OD243446/2022-2023:Providing and fixing RC work board with non reflectorized vinyl sign with 1 year warranty manufactured vinyl printed sheeting fixed over aluminium sheeting 2mm thick/ aluminium composite material 4mm thick with area not exceeding 0.9 sqm, with suitable back supporting frame of MS angle 40x40x6 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete with min size 45cmX45cmX60cm, 60 cm below ground level including painting all exposed surface with 2 coats of epoxy paint over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc
Pre monsoon works
2.3.2.A:Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness In area of light jungle - By Mechanical Means
2.1.2:Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. Girth from 600 mm to 900 mm
3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
OD110079/2022-2023:Filling up potholes with bituminous ready mix compound (25 kg bag) and compacting by ramming to get a compact surface after applying bituminous priming coat measured seperately including cost of material, laying charges, transportation to site etc. complete rate is arrived for a bag of 25 kg
OD110080/2022-2023:Engaging labour for cleaning existing drain and existing chocked culverts
Proactive / preventive maintenance
3.13.1.B:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. Ordinary soil - Mechanical Means - (Depth upto 3 m)
12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
12.8.1.C:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br> RCC Grade M20 - Using Concrete Mixer - (Without formwork) <br>
OD110076/2022-2023:Conducting and reporting routine inspections for the entire length of the project road at frequently of 7 days through out the agreement period of contract as directed by the departmental officers at site
OD110077/2022-2023:Filling up potholes with bituminous ready mix compound (25 kg bag) and compacting by ramming to get a compact surface after applying bituminous priming coat measured seperately including cost of material, laying charges, transportation to site etc. complete rate is arrived for a bag of 25 kg
Emergency Works
OD110081/2022-2023:Labour engaged for cleaning of choked culverts , drain and placing of precast slabs
OD110082/2022-2023:Hire charges of JCB for clearing water stagnation, deposited sols from road portion etc
OD110083/2022-2023:Hire charges for Tipper for removing the materials to the dumping place
Eldho Varghese
VARGHESEKUTTY M K
MOHANAN.N.V
OUSEPH P P
Bidder Name
MOHANAN.N.V
N A SUBAIR
VARGHESEKUTTY M K
Eldho Varghese
OUSEPH P P
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_827433.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .