| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹22.5 LAccepted-AOC KORATHARA KANNADY P O PULINCUNNOO ALAPPUZHA | PULINCUNNOO | ALAPPUZHA | KERALA | 1 | Accepted-AOC first lowest | |
| 2 | 2₹24.1 L+₹1.6 L (7.20%)Rejected-AOC | 2 | Rejected-AOC Second lowest | |
| 3 | 3₹25.8 L+₹3.3 L (14.6%)Rejected-AOC | 3 | Rejected-AOC Third lowest | |
| 4 | Rejected-Technical | - | Rejected-Technical 4TH LOWEST |
Tender Value
₹25.8 L
EMD Value
₹50,000
Closing Date
28 Feb 2024, 4:00 pmClosed
Construction Engineer Alappuzha
Office of the Construction Engineer Alappuzha 28/747 Sabari Gardens Chandanakavu Alappuzha- 688011
Side protection work, Construction of culvert
2024_KLDC_659704_1
KLDC/ALP/CE/2023-24/05(5)
Open Tender
Civil Works - Others
Item Rate
540 days
Ward XIV of Mannancherry GP in Alappuzha District.
Please refer Tender documents.
5 documents required · 5 mandatory
₹2,950
Yes
₹50,000
Yes
19 Mar 2024
16 Feb 2024
2 Mar 2024
16 Feb 2024
28 Feb 2024
16 Feb 2024
Amount
App.A side protection works
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
od328720/2023_2024 : Dry rubble masonry (without concrete levelling course) with good quality blasted rubble (without bond stone), and packing to compactness to lines and level cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
7.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
APP B: Construction of Culvert (1.5 m span)
60.1.1 : RING BUND Type-I-Putting up ring bund as per approved shape 2.5m bottom width, 1m top width using empty gunny/polythene bags filled with earth placed in 2 rows at 0.6m apart and filled in between with puddle clay to form bund for an average height 2.00m including labour dismantling the bund after completion of the work etc. complete.
60.2.3 : Bailing out water using pump above 5 HP and Up to 10 HP-Bailing out water with engine and pump set above 5HP and up to 10HP, including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.16.2 : Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete (Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not exceeding 3 m
od335913/2023_2024 : Filling with quarry muck Filling up low lying and water logged areas with quarry muck, spreading in layers, levelling the top at site and consolidation by smooth wheeled roller etc complete for improving the CBR value of subgrade. Details of cost for 300 cum
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
4.1.5 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.3.2 : Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
ANIL KUMAR G
T SURESH
Subeesh S
Bidder Name
T SURESH
ANIL KUMAR G
Thomas Joseph
Subeesh S
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1021058.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .