Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹3.4 L
EMD Value
₹6,800
Closing Date
16 Oct 2026, 5:00 pm5d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer
Electrical Division No.II, HPPWD, U.S. Club, Shimla-01.
Running operation of central heating plant in Block D at IGMC Shimla for the year 2026 to 27. w.e.f. 01.11.2026 to 15.03.2027
2026_PWD_143216_26
ED.II.TA.NIT.26-27-2639 dt. 10-09-2026
Open Tender
Electrical Works
Percentage
135 days
Shimla
Please refer to tender documents. Eligibility criteria is mentioned at page No. 6-7, 9-10 of GCC. Documents mentioned in eligibility criteria must be uploaded to qualify the bid.
7 documents required · 7 mandatory
₹350
₹6,800
9 Oct 2026
9 Oct 2026
17 Oct 2026
9 Oct 2026
16 Oct 2026
9 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Running and operation of Central Heating plant in Block D IGMC Shimla-171001 for period of 4.5 months w.e.f 01.11.2026 to 15.03.2027. There should be engagement of Two number Electricians/ Technicians for running and operation of Central Heating Planfrom 06AM to 06:00P.M. (Tewelve hours) Reliever should be provided for the shift management . Note:-Repetitive assignment of shifts to the same individual is strictly prohibited.Shifts should be rotated among all eligible & qualified persons as per Labour laws. | |||||
| 2Running and operation shall mean the operation of all the Electrical & Mechanical equipments forming part of the Central heating System, including Boilers,Motor-pump sets, hot water pipeline,valves, air handling unit cleaning the machinery, oiling & greasing the Motors , fans and other moving parts,fault,attending,erection of fuses minor adjustment checking of water and air pressure,filling of Gland-Dori, maintaining the day to day log-Book of Temperature & relative humidity complete in all respects as per the satisfaction of Engineer-in-Charge.The running and opration includes cleaning of all central heating units such as Fan coil Units, heat convectors etc year 2026-27 w.e.f 01.11.2026 to 15.03.2027 | |||||
| 2.01 | T.Mate(Electrical) Shift -1 (06:00 AM – 02:00 PM) | 135 | Days | 591 | ₹79,785 |
| 2.02 | Electrical-ii Shift-2 (08 AM to 04.00 PM) including reliever | 135 | Days | 667 | ₹90,045 |
| 2.03 | Electrical-ii Shift-3 (02 PM to 10.00 PM) including reliever | 135 | Days | 667 | ₹90,045 |
| 2.04 | T.Mate(Electrical) Shift-4 (10:00 PM to 06:00 AM) | 135 | Days | 591 | ₹79,785 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.20 MB
BOQ_216372.xls
BOQ • 0.33 MB
GCC.pdf
Tender Documents • 4.97 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .