Tender ID
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹68.3 LAdmitted-Finance NEAR PETROL PUMP TALLI BAGHI BHAGIRATHI PURAM TEHRI GARHWAL PIN 249131 | BHAGIRATHI PURAM | TEHRI GARHWAL | UTTARAKHAND | 249131 | L1 | Admitted-Finance |
Tender Value
₹69.8 L
EMD Value
₹1.4 L
Closing Date
20 Feb 2026, 5:30 pmClosed
AGM(PLANNING/PROCUREMENT)
THDC INDIA LIMITED, Bhagirathi Bhawan, Bhagirathipuram, Tehri, Pin-249124
Annual Operation and Maintenance work of Hydro Mechanical Equipment at Tehri HPP
2026_THDC_896323_1
THDC/TEHRI/PROC/OPEN/ 2025-26/47
Open Tender
Miscellaneous Works
Percentage
THDCIL, Bhagirathipuram, Tehri
As per Tender Document
3 documents required · 3 mandatory
₹1,770
THDC India Limited
₹1.4 L
19 Mar 2026
30 Jan 2026
21 Feb 2026
30 Jan 2026
20 Feb 2026
30 Jan 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Item No. 1 :
Yearly operation of Hydro Mechanical equipments viz. Gates, Hoists, Gantry cranes, Winch Machines etc. including shifting of All HM Equipments like gate panels, winch machines, wire rope pulleys & lifting slings etc. (except shifting of items mentioned in BOQ Sl. No. 3 to 5) to place of operation with all materials, labors etc. in all respect. (Crane & trailer/truck for shifting of gate panels, winch machines, wire rope pulleys etc. Wherever required will be provided by THDCIL on free cost) | 12 | Month | 2,65,511 | ₹31,86,132 |
| 2 | Item No. 2:
Yearly Preventive & breakdown Maintenance Work of Hydro Mechanical Equipments viz. Gates, Hoists, Gantry cranes, Winch machines etc. including embedded parts of HM equipments, Support structures & other hoisting equipments as per the Maintenance schedule/Projects requirements including labors, consumables, T&P in all respect. (Excluding Mechanical & Electrical spare parts, lubricants such as grease, gear oil, hydraulic oil, cardium compound & Rubber seals, Bolts/nuts. The Crane & trailer/truck etc. if required will be provided by THDCIL on free of cost. Electricity at the site will be provided free of cost by THDCIL. | 12 | Month | 3,05,595.43 | ₹36,67,145.16 |
| 3Item No. 3: Optional Items | |||||
| 3.1 | Loading, Unloading & Shifting of Stoplog gates of D/s of Trashracks with lifting beam from storage place to HRT intake site (EL.745.00 m) platform and back to storage place after completion of operation of Stoplog Gate (lowering & lifting) during maintenance of Trashracks (Crane & trailer/truck will be provided by THDCIL on free cost for Loading, Unloading & shifting of Gate panels). | 1 | Job | 15,472.6 | ₹15,472.6 |
| 3.2 | Operation of Stoplog gates of D/s of Trashracks i.e. lowering of Stoplog gate panels in to groove & removing the same after completion of cleaning and lowering of Trashracks assembly at HPP-1/HPP-2 | 1 | Job | 16,465.9 | ₹16,465.9 |
| 3.3 | Operation of Trashracks assembly & cleaning of Trashracks i.e. lifting of Trashracks from groove to top of HRT platform (EL.745.00 m), cleaning of Trashracks & lowering of Trashracks back in to the groove. | 1 | Job | 16,465.68 | ₹16,465.68 |
| 3.4 | Loading, Unloading & shifting of Stoplogs gates of D/s of Trashracks from one groove to another after completion of cleaning of Trashracks assembly. (Crane & trailer/truck will be provided by THDCIL on free cost for Loading, Unloading & shifting of gate panels) | 1 | Job | 3,868.7 | ₹3,868.7 |
| 4Item No. 4: Optional Items | |||||
| 4.1 | Loading, Unloading & shifting of HRT entry Stoplog gates with lifting beam from storage place to HRT intake site platform (EL. 745.00 m) and back to storage place after completion of operation of Stoplog gate (lowering & lifting) during maintenance of HPP tunnels between HRT entry gate groove & MGS gate groove. (The crane, trailer/truck will be provided by THDCIL on free of cost for Loading, Unloading & shifting of Gates/lifting beam from storage yard to site and for shifting back from site to storage yard after completion of maintenance work at HPP-1/2 or at PSP-1/2). | 1 | Job | 18,168.7 | ₹18,168.7 |
| 4.2 | Operation of HRT entry Stoplog gates i.e. lowering of Stoplog gate panels in one gate groove and removing of the same after completion of maintenance of one HPP tunnel between HRT entry gate groove & MGS gate groove. | 1 | Job | 21,953.8 | ₹21,953.8 |
stage.html
html • 0.02 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.27 MB
TenderDocument.pdf
Tender Documents • 2.13 MB
BOQ_942112.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .