| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹45.1 LAdmitted-Fee/PreQual/Technical/Finance | ₹45.1 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹47.0 L+₹1.9 L (4.19%)Admitted-Fee/PreQual/Technical/Finance | ₹47.0 L+₹1.9 L (4.19%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 3 | L3₹47.7 L+₹2.6 L (5.75%)Admitted-Fee/PreQual/Technical/Finance | ₹47.7 L+₹2.6 L (5.75%) | L3 | Admitted-Fee/PreQual/Technical/Finance |
| 4 | L4₹50.4 L+₹5.3 L (11.8%)Admitted-Fee/PreQual/Technical/Finance | ₹50.4 L+₹5.3 L (11.8%) | L4 | Admitted-Fee/PreQual/Technical/Finance |
| 5 | L5₹51.6 L+₹6.5 L (14.4%)Admitted-Fee/PreQual/Technical/Finance | ₹51.6 L+₹6.5 L (14.4%) | L5 | Admitted-Fee/PreQual/Technical/Finance |
| Sl No | Description | Qty | Unit | M/S TRILOK SINGH NEGI CONTRACTOR L6 | RAJPAL SINGH CONTRACTOR L4 | kundan singh L7 | rajesh kamra contractor L5 | ARORA CONSTRUCTION L1 | ANWAR ALI L3 | Hemant Kumar Contractor L2 |
|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Earth work in excavation by mechanical means (Hydraulic Excavator)/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.in all kinds of soil. | 44.64 | cum | 2 ₹89.28 Lowest | 174.26 ₹7,778.97 | 220 ₹9,820.8 | 200 ₹8,928 | 170 ₹7,588.8 | 200 ₹8,928 | - |
| 2.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - -All work upto plinth level in 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). | 2.48 | cum | 5,200 ₹12,896 | 5,751.88 ₹14,264.66 | 5,772 ₹14,314.56 | 4,500 ₹11,160 | 4,213 ₹10,448.24 Lowest | 5,200 ₹12,896 | 4,323.89 ₹10,723.25 |
| 3.00 | Providing and laying in position cement concrete of 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | 0.27 | cum | 6,000 ₹1,620 | 5,274.58 ₹1,424.14 | 6,675 ₹1,802.25 | 6,676.69 ₹1,802.71 | 4,873 ₹1,315.71 Lowest | 5,000 ₹1,350 | 5,000.84 ₹1,350.23 |
| 4.00 | Brick work with F.P.S. bricks of class designation 75 in foundation and plinth inCement mortar 1:4 (1 cement : 4 coarse sand) | 8.51 | cum | 5,800 ₹49,358 | 4,774.98 ₹40,635.08 | 6,043 ₹51,425.93 | 5,000 ₹42,550 | 4,800 ₹40,848 | 5,100 ₹43,401 | 4,527.17 ₹38,526.22 Lowest |
| 5.00 | Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth level upto floor V level in all shapes and sizes in Cement mortar 1:6 (1 cement : 6 coarse sand) | 91.83 | cum | 7,000 ₹6,42,810 | 6,840 ₹6,28,117.2 | 7,715 ₹7,08,468.45 | 5,700 ₹5,23,431 Lowest | 6,000 ₹5,50,980 | 6,500 ₹5,96,895 | 5,779.96 ₹5,30,773.73 |
| 6.00 | Half brick masonry with F.P.S. bricks of class designation 75 in superstructure abov plinth level upto floor V level inCement mortar 1:4 (1 cement :4 coarse sand) | 42.15 | Sqm | 900 ₹37,935 | 752.37 ₹31,712.4 | 951 ₹40,084.65 | 952.37 ₹40,142.4 | 700 ₹29,505 Lowest | 700 ₹29,505 Lowest | 713.33 ₹30,066.86 |
| 7.00 | Extra for providing and placing in position 2 Nos. 6mm dia. M.S. bars at every third course of half brick masonry (with F.P.S. bricks). | 42.15 | Sqm | 85 ₹3,582.75 | 70.15 ₹2,956.82 | 87 ₹3,667.05 | 88.81 ₹3,743.34 | 70 ₹2,950.5 | 50 ₹2,107.5 Lowest | 66.52 ₹2,803.82 |
| 8.00 | Providing and laying in position specified grade of reinforced cement concrete1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) | 7.4 | cum | 7,500 ₹55,500 | 6,056.05 ₹44,814.77 | 7,664 ₹56,713.6 | 7,665.89 ₹56,727.59 | 6,000 ₹44,400 | 5,800 ₹42,920 | 5,741.75 ₹42,488.95 Lowest |
| 9.00 | Reinforced cement concrete work in walls (any thickness), includingReinforced cement concrete work in walls (any thickness), includingattached pilasters, buttresses, plinth and string courses, fillets, columns,pillars, piers, abutments, posts and struts etc. up to floor five level,excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate20 mm nominal size) | 7.16 | cum | 9,000 ₹64,440 | 7,265.95 ₹52,024.2 | 9,176 ₹65,700.16 | 9,197.41 ₹65,853.46 | 6,714 ₹48,072.24 | 6,500 ₹46,540 Lowest | 6,888.86 ₹49,324.24 |
| 10.00 | Reinforced cement concrete work in Beam,suspended floor roof having slop up to 15 degree landing balcony shelf chajjas lintels band plain windoe cills staircase & sprial stair case etc. up to floor five level,excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate20 mm nominal size) | 83.8 | cum | 9,600 ₹8,04,480 | 7,702.83 ₹6,45,497.15 | 9,749 ₹8,16,966.2 | 7,000 ₹5,86,600 | 6,800 ₹5,69,840 Lowest | 7,200 ₹6,03,360 | 7,303.06 ₹6,11,996.43 |
Tender Value
Refer Docs
EMD Value
₹1.3 L
Closing Date
7 May 2026, 5:00 pmClosed
EXECUTIVE ENGINEER, RWD, U.S.NAGAR
RURAL WORKS DEPARTMENT, VIKAS BHAWAN, RUDRAPUR
Construction work of non-residential building of Commandant, District Training Centre Udham Singh Nagar office on the first floor of District Commandant, Home Guards, office Udham Singh Nagar.
2026_RES_94584_1
90/EE/RWD/ETENDER/dt20-04-2026
Open Tender
Civil Works - Buildings
Item Rate
240 days
Rudrapur
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,720
Head 0515008000100 and Gst no 05AAAGG2254F1ZW
₹1.3 L
12 May 2026
23 Apr 2026
8 May 2026
23 Apr 2026
7 May 2026
23 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic Excavator)/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.in all kinds of soil. | - | cum | - | - |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - -All work upto plinth level in 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). | - | cum | - | - |
| 3 | Providing and laying in position cement concrete of 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | - | cum | - | - |
| 4 | Brick work with F.P.S. bricks of class designation 75 in foundation and plinth inCement mortar 1:4 (1 cement : 4 coarse sand) | - | cum | - | - |
| 5 | Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth level upto floor V level in all shapes and sizes in Cement mortar 1:6 (1 cement : 6 coarse sand) | - | cum | - | - |
| 6 | Half brick masonry with F.P.S. bricks of class designation 75 in superstructure abov plinth level upto floor V level inCement mortar 1:4 (1 cement :4 coarse sand) | - | Sqm | - | - |
| 7 | Extra for providing and placing in position 2 Nos. 6mm dia. M.S. bars at every third course of half brick masonry (with F.P.S. bricks). | - | Sqm | - | - |
| 8 | Providing and laying in position specified grade of reinforced cement concrete1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) | - | cum | - | - |
| 9 | Reinforced cement concrete work in walls (any thickness), includingReinforced cement concrete work in walls (any thickness), includingattached pilasters, buttresses, plinth and string courses, fillets, columns,pillars, piers, abutments, posts and struts etc. up to floor five level,excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate20 mm nominal size) | - | cum | - | - |
| 10 | Reinforced cement concrete work in Beam,suspended floor roof having slop up to 15 degree landing balcony shelf chajjas lintels band plain windoe cills staircase & sprial stair case etc. up to floor five level,excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate20 mm nominal size) | - | cum | - | - |
stage.html
html • 0.03 MB
finance_111920.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.74 MB
BOQ_111920.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .