Loading…
Loading…
Tender Value
₹10.6 L
EMD Value
₹21,140
Closing Date
25 Jun 2026, 6:00 pm
ADPC SMSA KOTA
ADPC SMSA KOTA
STRENGTHENING OF EXISTING SCHOOL GSSS MORAK STATION DISTT-KOTA, BLOCK-KHAIRABAD
2026_RCSCE_568236_2
NITNO-03/2026-27-SMSA KOTA
Open Tender
Civil Works
180 days
KOTA
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
Yes
1000 ADPC SMSA KOTA
₹21,140
Yes
16 Jun 2026
16 Jun 2026
29 Jun 2026
16 Jun 2026
25 Jun 2026
16 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils | 80.59 | cum | 178 | ₹14,345.02 | BI01010001010000000000000515BI0100001113 |
| 2 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). | 10.8 | cum | 3,302 | ₹35,661.6 | - |
| 3 | Random Rubble stone masonry for with hard stone in foundation and plinth in Cement Sand mortar above 30 CM thick wall in:Cement Mortar 1:6 ( 1-Cement : 6-Sand). | 28.95 | cum | 2,838 | ₹82,160.1 | - |
| 4 | Brick masonry with F.P.S. bricks of class designation 75 in foundation and plinth with bricks Cement mortar 1 : 6 (1 cement : 6 coarse sand) | 1.16 | cum | 4,263 | ₹4,945.08 | - |
| 5 | Centering and Shuttering with plywood or steel sheets including strutting, propping bracing both ways and removal of formwork for foundation , footings, strap beam, raft , bases of columns etc. | 22.65 | sqm | 157 | ₹3,555.45 | - |
| 6 | Providing and laying in position specified grade of cement concrete for all RCC structural elements upto plinth level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( if required) excluding the cost of centering, shuttering and reinforcement. M20 grade Nominal Mix / Design Mix | 8.9 | cum | 4,934 | ₹43,912.6 | - |
| 7 | Centering and Shuttering with plywood or steel sheets including strutting, propping bracing both ways and removal of formwork for foundation , footings, strap beam, raft , bases of columns etc. Columns, pillars, posts and struts etc. | 43.9 | sqm | 375 | ₹16,462.5 | - |
| 8 | Providing and laying in position specified grade of cement concrete for all RCC structural elements upto plinth level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( if required) excluding the cost of centering, shuttering and reinforcement.
M20 grade Nominal Mix / Design Mix | 3.03 | cum | 4,934 | ₹14,950.02 | - |
| 9 | Providing and laying in position specified grade of cement concrete for RCC structural elements upto floor five level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers (if required ) excluding the cost of centering, shuttering and reinforcement for Walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc.M20 grade Nominal Mix / Design Mix | 4.06 | cum | 5,609 | ₹22,772.54 | - |
| 10 | Filling available excavated earth (excluding rock) in trenches, plinth side of foundation etc. in layers not exceeding 20 cm. in depth, consolidating each deposited layer by ramming and watering including lead up to 50 meter and with all lift. Supply & Stacking good soil of earth at site complete including loading unloading & Transportation etc. | 31.2 | cum | 304 | ₹9,484.8 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 9.45 MB
Tendernotice_2.pdf
PDF • 8.64 MB
Tendernotice_3.pdf
PDF • 1.60 MB
BOQ_1010871.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid