Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Tender Value
₹61.4 L
EMD Value
₹62,000
Closing Date
16 Feb 2026, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Executive Engineer, R&B Division, Jamnagar
Jamjodhpur Mahiki Satapar Vansjaliya Tarsai Hanumangadh Road Km.0/0 to 35/0 (Pro. Gunitting Jacketing Grouting and Floor Protection work and Misc. work at Structure Ch.11/0 to 11/2 & Ch. 14/4 to 14/6, Dist.Jamnagar)
271002
30 of 2025-26
Open
Civil Works
Works
Jamnagar
4 documents required · 4 mandatory
₹2,400
Yes
Executive Engineer, R&B Division, Jamnagar
₹62,000
Yes
30 Jan 2026
30 Jan 2026
30 Jan 2026
16 Feb 2026
30 Jan 2026
Name of work :- Jamjodhpur Mahiki Satapar Vansjaliya Tarsai Hanumangadh road K.M. 0/0 to 35/0 (Pro. Gunitting Jacketing
Grouting and floor protection work & Misc. work at structure Ch. 11/0 to 11/2 & Ch. 14/4 to 14/6 Dist : Jamnagar.)
BILL OF QUANTITIES
(A) Percentage Rate Tender
Item Description of Item (With brief Specification and reference in book of Quantity Unit Rate in Amount
No. Specifications) Figures
1 Clearing and grubbing road land including uprooting rank vegetation grass 0.19 Hect, 28455.09
bushes, shrubs, saplings and trees girth upto 300mm, removal of stumps
of trees cut earlier and disposal of unserviceable materials © by
mechanical means in area of light jungle.
2 Excavation for foundation upto all Depth including sorting out and stacking 595.00 Cum 259.93
of useful materials and disposing off the excavated stuff upto 50Mt. Lead
Dense or Hard soil
3 Providing and filling in foundation with ordinary cement concrete M-100 130.00 Cum 3362.25
Mix and providing necessary vertical pin headers including formwork,
vibrating ramming and curing complete.
4 Providing and casting in situ ordinary cement concrete M-200 for 342.00 Cum 4218.57
approach slab including formwork curing and finishing complete.
5 Providing and casting in situ ordinary concrete M-20 Mix for 23cm. Thick 835.20 Cum 2609.84
Jacketing consisting 16mm dia. 200mm c/c vertical reinforcement 12mm
dia @ 200mm c/c horizontal reinforcement & 500mm c/c horizontal
Support bar drilled inside pier complete including drilling holes in the pier,
providing steel bars for connecting existing pier to jacketing and filling the
holes with rich mortar including shuttering scaffolding wherever necessary,
laying, vibrating curing and finishing etc. complete.
6 Providing and inserting nipples of internal diameter 15mm minimum & 194.00 No 502.98
Length 150mm minimum with approved fixing compound in drilling holes
minimum 20mm dia & depth 150mm & for grouting as per technical
specifications including subsequet cutting/removal and sealing of the hole
as necessary of nipples after completion of grouting
7 Strengthening and repairing to masonry and concrete structure of Bridges 1485.00 Kg. 794.87
pier, slab etc. by Epoxy Grouting by injecting neat Epoxy Material in ratio
1:0.50 ( 1 Resin 0.50 hardener by weight) under pressure 3 to 7 Kg/Cm.
The rate including all material, labours machinery equipments and
scaffolding upto 5Mt. Height Epoxy grout by injection through nipples
complete as per clause 2803 as per clause
8 Strengthening and repairing to masonry structure of bridges, pier, wing 1073.00 Kg. 149.48
wall slab, etc. by sealing of craks/porous concrete by injecting process
through cement grouting as per technical specifiction. The rate including
all material, labours, machinery, equipments and scaffolding upto 5Mt.
Height cement mortar grouting.
9 Repairing & covering of patches & Open steel in bridges component liks 149.00 Sqm 436.32
slab, pier, etc with epoxy mortar 1:0.5:6) Epoxy material in proportion (1
Kg. Rresin. 0.50Kg. Hardner, 6 Kg Sillica Powder)
10 Gunitting concrete surface with cement mortar applied with compressor 535.00 Sqm 775.68
after cleaning surface and spraying with epoxy complete as per technical
I/We am/are willing to carry out the work at _______________% above/below Percent
(Should be Written in Figures & Words) of the estimated rates mentioned above. Amount of my/our
Tender works out as under.
# Estimated Amount Put to Tender # Estimated amount put to Tender
Deduct __________ % below Add : _________ % Above
Deputy Executive Engineer Executive Engineer
Jamjodhpur. (R&B) Sub-Division Jamnagar (R&B) Division
Jamnagar. Jamnagar.
1 The Contractor shall exhibit a board with detailed specification and details of work as per directed by the Engineer-in-Charge
for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income Tax TDS will be deducted at a source while making payments of bills
4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.: PRC-10/2017 Cement
Consumption /16/C Date : 11/05/2017 as stated in S.O.R. therefore in R.C.C. items where there is a change as per actual nix
design the cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate
mentioned in all the tender.
5 Testing of materials shall be as per statement attached for quantity control. with specification, the materials shall be tested in
GERI for testing charges shall be paid by Executive Engineer, and of amount put to tender after deduction the cost of
materials as per Schedule-'A' shall be recovered from contractor in Running bill as per G.R. of R&B Deptt. No. TNC/1085-4-6,
6 The Contractor shall be state even "NIL" precent of no reduction as offered.
7 One percent of Contract value. for this work shall be recovered from the contract payment as " Labour cess" in terms of the
Gujarat Government Gazette extra ordinary Dated 12-12-2004 implementation of building & other construction worker's
(Regulation of Employment and condition of service Act, 1996)
8 For R.C.C. Item where there is change of grade mix or charge as per actual mix design the difference of cement consumption
shall be deducted from rate of original item at the rate of star rate mentioned in the tender.
9 GST Will be paid extra as per Govt. Emendment.
Deputy Executive Engineer Executive Engineer
Jamjodhpur. (R&B) Sub-Division Jamnagar (R&B) Division
Jamnagar. Jamnagar.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Boq.pdf
E-Tender-30.pdf
index.pdf
SBD - Annexure - Jamjodhpur Mahiki Satapar Road Km.0.0 to 35.0.pdf
SBD JAM. MAHIKI SATAPAR BRIDGE 15-1-26.pdf
SPECIFICATION JAM. MAHIKI SATAPAR BRIDGE 15-1-26.pdf
TEST SCHEDULE MAHIKI SATAPAR BRIDGE.pdf
GR-64 PAGE.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .