| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹10.1 LAccepted-Finance | ₹10.1 L | L-1 | Accepted-Finance L-1 |
| 2 | L-2₹10.4 L+₹24,190.17 (2.39%)Rejected-Finance | ₹10.4 L+₹24,190.17 (2.39%) | L-2 | Rejected-Finance L-2 |
| 3 | L-3₹11.6 L+₹1.5 L (14.6%)Rejected-Finance | ₹11.6 L+₹1.5 L (14.6%) | L-3 | Rejected-Finance L-3 |
| 4 | L-4₹12.0 L+₹1.9 L (19.2%)Rejected-Finance | ₹12.0 L+₹1.9 L (19.2%) | L-4 | Rejected-Finance L-4 |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹12.2 L
EMD Value
₹29,000
Closing Date
1 Jun 2026, 5:00 pmClosed
GM-CIVIL
Main Administrative Building Sector-6 Noida
Village Development (P/F and Repair of Culvert Jaal in Village-Chaura) Noida
2026_NOIDA_1149813_1
60/GM/SM(WC-05)/2026-27
Open Tender
Civil Works
Fixed-rate
90 days
NOIDA
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,416
NOIDA
₹29,000
23 Jul 2026
18 May 2026
2 Jun 2026
18 May 2026
1 Jun 2026
18 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains ( not exceeding 1.5 m in width or 10 sum on plan) including dressing of sides and amming of bottum, lift upto 1.5 m, including getting out the excavated soil and disposal of surface excavated soil as directed, within lead up to 50m All kinds of soil | 13 | Cum | 144.95 | ₹1,884.35 |
| 2 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 14 | cum | 923.42 | ₹12,927.88 |
| 3 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 10 in foundation and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand) | 7 | Cum | 5,214.8 | ₹36,503.6 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering -1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) | 2 | Cum | 6,753.45 | ₹13,506.9 |
| 5 | Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of ngineer-incharge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately). | 16 | cum | 8,141.85 | ₹1,30,269.6 |
| 6 | Steel work welded in built up sections/ framed work including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. | 8,500 | KG | 92.34 | ₹7,84,890 |
| 7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars of grade Fe-500D or more. | 1,550 | Kg | 82.81 | ₹1,28,355.5 |
| 8 | Providing and laying in position ready mixed M-25 grade concrete for reinforced cement concrete work, using cement content as per approved design mix, manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying , excluding the cost of centering, shuttering finishing and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer-in-charge. (Note :- Cement content considered in this item is @ 330 kg/cum.Excess/less cement used as per design mix is payable/recoverable separately).All works upto plinth level | 10 | Cum | 7,912.32 | ₹79,123.2 |
| 9 | Centering and shuttering including strutting, propping etc. and removal of form for:Foundations, footings, bases of columns, etc. for mass concrete. | 74 | sqm | 181.64 | ₹13,441.36 |
| 10 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. | 27 | Cum | 120.55 | ₹3,254.85 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.08 MB
TD.pdf
Tender Documents • 12.91 MB
Capability.xls
Additional Documents • 0.04 MB
BOQ_2152883.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .