Resurfacing & Strengthening Sadhali Pandharva Road Km. 0/0 to 1/80 Sec: 1/150 to 1/80 (VR) Ta.Jetpur Pavi Dist. Chhotaudepur Under BUJ (2025-26)
289249
14 of 2025-26
Open
Civil Works - Roads
Works
Chhotaudepur
₹2,400
Executive Engineer, Panchayat (R&B) Division, Chhotaudepur
₹55,000
23 Mar 2026
23 Mar 2026
23 Mar 2026
1 Apr 2026
23 Mar 2026
Name Of Work :- Resurfacing & Strengthing Sadhali Pandharva Road Km. 0/0 to 1/80 Sec: 1/150 to
1/80 (VR) Ta.Jetpur Pavi Dist. Chhotaudepur Under BUJ (2025-26)
Sr No. Clause no Page
1 Principle Approval Date and - - :- GSR-20254-Job No.19-D-2 Dtd.
Amount (Attach letter) 15/09/2025
2 Administrative Approval Date and - - :- BUJ (2025-26)
Amount (Attach letter )
Sr. No. 8 60.00 Lacs
3 Technical Approval Date and - - :-
Amount (Attach letter)
3.1 Resurfacing & Strengthing Sadhali Pandharva Ts. For Rs.6472000.00 By E.E.Panchyat ,R &
Road Km. 0/0 to 1/80 Sec: 1/150 to 1/80 (VR) B Chhotaudepur Div , as per Sr No.69 Pg
Ta.Jetpur Pavi No. 10 Dtd.20/03/2026
5 DTP amount IFB 4 :-
6 Tender Fee Rs. - - :- 2400.00 Rs
(As per GR- PRCH-102000-IB-
7 Earnest Money Deposit (Bid IFB 4 :-
Security-1% of DTP amount) Rs. point 6
8 Time Limit (Months) Section 3 41 :- 04 (Four) months including Monsoon
9 Annual Financial Turnover Section 1 cl. 9 :-
Amount Rs. 4.5.3(a)
10 Defect Liability Period (In Section 3 46 :-
Months & includes no. of cl. 33.1 ( C ) 12 Months (including 1 monsoons)
11 Free Maintenance Guarantee Period Section 3 46 :-
(for Road & Bridge Construction) cl. 33.2 (b) 4 Years
12 Registration/Category - - :- Class “B” with Special Cat.-III for
required Road & Above
13 Site Possession Date Section 3 42 :- 1st day of Work order#
14 Period between Program Section 3 44 :- 30 days
Update (Days) cl.
15 Amount to be withheld for late Section 3 44 :- 1.00 Lakh
submission of Program cl.
16 Milestone: - Section 3 53 :- % of work Days
(A) Milestone 1 - - :- 25% 30 Days
(B) Milestone 2 - - :- 50% 60 Days
(C) Milestone 3 - - :- 75% 90 Days
(D) Milestone 4 - - :- 100% 120 Days
#In case of LA/FRA is in progress give likely date.
17 Price Adjustment Components Section 4 66 :- % Input
cl. 24 index/price*
(A) Labour, PL Section 4 66 :- PL= 24.20 Lo=
(B) Cement, PC Section 4 66 :- PC= 27.80 Co=
(C) Steel, PS Section 4 67 :- PS= 14.03 So=
(D) Bitumen, Pb Section 4 67 :- Pb= 0.00 Bo=
(E) POL, Pf Section 4 68 :- Pf= 3.82 Fo=
(F) Plant and Machinery Spares Pp Section 4 68 :- Pp= 16.13 Po=
(G) Other Materials, Pm Section 4 69 :- Pm= 14.02 Mo=
18 Amount to be withheld for Section 3 56 :-
failing to supply “as built” cl.
19 Percentage Rate Contract Section 7 78 :-
(upto INR 50 Cr. )/ Item Rate
Percentage Rate
Contract (above INR 50 Cr.)
*Input index/price for each component on 28 days preceding the date of opening of technical bid shall be
This is to certify that the contract document prepared for the work
Resurfacing & Strengthing Sadhali Pandharva Road Km. 0/0 to 1/80 Sec: 1/150 to 1/80
(VR) Ta.Jetpur Pavi Dist. Chhotaudepur Under BUJ (2025-26)
is based on the Standard Bidding Document Procurement of Civil Works published
by R&B department letter No. RBD/0346/10/2023 dated 12/10/2023.
No further modification and alteration in this standard format has been made by this office.
Deputy Executive Engineer Executive Engineer
Panchayat (R & B) Sub Division Panchayat (R&B) Division
Jetpur Pavi Chhotaudepur
Name Of Work :- Resurfacing & Strengthing Sadhali Pandharva Road Km. 0/0 to 1/80 Sec: 1/150 to 1/80
(VR) Ta.Jetpur Pavi Dist. Chhotaudepur Under BUJ (2025-26)
Taluka :Jetpur Pavi District : Chhotaudepur
INDEX OF SPECIFICATION
Applicable Separate Road
Tender Specification booklet attached
Discription of item as per schedule "B" of the tender.
Item No reference
Item No. Pg No.
1 Earthwork for embankment including breaking clods, dressing with all lead and lift and Attached Separetely
including watering rolling and consolidation of subgrade in layers at O.M.C. to required
dry density including filling the depression which occur during the process using power
roller 8T to 10T.(C) From Borrow area within 1.0KM. lead
2 Providing and laying Controlled cement concrete M-250 For a concrete pavement Attached Separetely
made by Trimix system and mixed with heavy duty floor hardner at the rate of
Kg./Sq.M. including curing etc. complete over prepared sub base including providing
and fixing centering of MS channels of required thickness as per required level slope,
Grade and thickness of concrete road including leveling of placed concrete with
surface vibrators finishing surface with power floater and trowel light brooming on the
surface including providing construction joint of 10 mm x 25 mm by using concrete
cutter machine etc. complete as directed. The Payment Of this Item Shall be Made on
Core Cutter testing results.
3 Citizen' s information Board- Providing and fixing of typical information board as per Attached Separetely
instruction. Two MS plates of 1.6 mm thick, of 900 mm x 750mm size fixed at top &
bottom duly welded with MS angles of 25 x 25 x 5 mm thick M.S plate shall be
welded by two vertical M.S flats & four horizontal M.S flates 5 mm thick to 75 mm x
75 mm of 12 SWG square tubes posts duly embedded in cement concrete M-15 grade
blocks of 600mm x 600mm x 750 mm, below ground level. Painting New letters &
figure of any shade with ready mixed synthetic enample paint of superior quality in
required shade and colour, All sections of framed posts and steel tube will be painted
with primer and two coats of epoxy paints as per detailed drawing
4 Excavation for foundation upto 1.5M. depth including sorting out and stacking of Attached Separetely
useful materials and disposing of the excavated stuff upto 50 meter lead.(A) Loose of
5 Providing and filling in foundation with ordinary Cement concrete M-100 mix and Attached Separetely
providing necessary vertical pin headers including formwork, vibrating, ramming and
curing complete.
6 Providing and casting in situ ordinary cement concrete M-150 mix and providing Attached Separetely
necessary pin headers including shuttering, scaffolding, laying, vibrating, curing and
finishing complete without V-Groves. (A) Height from 0.0 M. to 5.0 M.
7 Supplying and fixing reinforced concrete heavy duty non-pressure pipes with collars for Attached Separetely
culverts including setting and joining the pipes in C.M. 1:2 watering and laying (To
level of slops of I.S. 458 / 1971 Class NP4 of following internal diameter. (iv) 900 mm
8 Supplying and fixing reinforced concrete heavy duty non-pressure pipes with collars for Attached Separetely
culverts including setting and joining the pipes in C.M. 1:2 watering and laying (To
level of slops of I.S. 458 / 1971 Class NP4 of following internal diameter. (vi) 1200 mm
9 Providing ISI Mark TMT bar Fe-500D reinforcement for RCC Work including bendinf, Attached Separetely
binding and placing in position complete as per detailed drawinngs for Solid slab,
Abutment cap, dirt wall & Pier cap & Also for the (For Temperature Reinforcement of
Abutment, Return & Pier)
10 Providing and casting in situ Controlled Cement concrete M-250 for R.C.C. solid Attached Separetely
slab including centering, scaffolding curing and finishing complete.
11 Providing and casting in situ Controlled Cement concrete M-250 for average 75 mm Attached Separetely
thick wearing coat laid as directed including tamping ,vibrating, finishing, curing and
filling in joints with bitumen complete.
Applicable Separate Road
Tender Specification booklet attached
Discription of item as per schedule "B" of the tender.
Item No reference
Item No. Pg No.
Deputy Executive Engineer Executive Engineer
Panchayat ( R & B) Sub Division Panchayat ( R & B) Division
Jetpur Pavi Chhotaudepur
Name Of Work :- Resurfacing & Strengthing Sadhali Pandharva Road Km. 0/0 to 1/80 Sec: 1/150 to
1/80 (VR) Ta.Jetpur Pavi Dist. Chhotaudepur Under BUJ (2025-26)
1 All works shall be carried out as per latest MORTH Specification Booklet and other specification
of Division as directed.
2 All Rates quoted include clearance of site (prior commencement of work and at its close) in all
respects and hold good for work under all conditions, site moisture, weather etc.
3 The contractor shall exhibit a board as per Government Circular No. Vernacular TNC/1090/24/S
dated 05.03.2011 with details specifications and details of works and amount involved at site at
his own cost as directed by Engineer-in-charge.
4 Testing of material shall be done as per statement attached with specification. The material should
be tested in GERI or Private laboratory approved by Govt. of Gujarat. Bill for testing charges
should be paid by Executive Engineer and computed after deducting the cost of materials to be
supplied by the Govt. and shall be recovered from the contractor's running bill as per Govt., R&B
Department No. TNC-1085/(4)/C dtd 20-12-91.
5 1.00 % of Construction cost shall be deducted form Bill. Amount of Contract as per the Building
and other Construction worker's welfare cess Act - 1996 (Labour & Employment Department
Letter No. CWA - 2004 - 1831 - M (3). Dt. 9-12-05, Notification of Labour & Employment
Department Dtd. 03-01-05 and Labour & Employment Department letter No. CWA / 2004-841-
6 In all R.C.C. items in rate analysis, standard cement consumption has been taken as per Govt. GR,
PRC-10/2017/Cement Consumption/16/C, Dtd. 11/05/2017 as stated in SOR therefore in RCC
items where there is a change as per actual mix design the cost of difference of cement
consumption shall be deducted from the rate of original item at the rate of input rate mentioned in
7 Bidders are advised to visit the site & make himself / themself aware of the scope & specification
of the work to be done & of conditions and other factors bearing on the execution of the work
before on line submission of his / their bids. Once the bid is finalized, under no circumstances
arguments for crust deficiency / additional / altered works will be heard until & unless Engineer
in charge deem so. Engineer in charge shall have right to reject & decision of Engineer in charge
shall be final & binding.
8 If found necessary, contractor will be intimated for negotiation. He will be intimated maximum
three times within validity period for negotiation. If contractor does not respond in time, his
earnest money will be forfeited and his tender will be rejected. Paneltative action will be taken on
such contractor.
Name Of Work :- Resurfacing & Strengthing Sadhali Pandharva Road Km. 0/0 to 1/80 Sec: 1/150 to 1/80 (VR) Ta.Jetpur Pavi Dist.
Chhotaudepur Under BUJ (2025-26)
Taluka :Jetpur Pavi District : Chhotaudepur
SCHEDULE FOR TESTING OF MATERIALS
For ensuring quality control and workmanship, various tests prescribed below for materials shall be taken at periodical intervals as stipulated below.
The material should be tested in GERI or Private laboratory approved by Govt. of Gujarat. Bill for testing charges should be paid Govt.
Item No. as Brief Description of materials to be Qty. of Unit Prescription of test which Frequency @ which test shall be Total Nos of
per tested. Materials shall be carried out carried out test to be
Schedule 'B' taken
1 45 to 90 MC.Metal Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
2 40 to 63 M.C.Metal 0.00 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
3 25 to 40 M.C.Metal 0.00 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
4 Kapchi 20 mm Nominal 773.00 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
5 Grit (6 mm) 0.00 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
6 Grit as Key aggregate (12 mm) 0.00 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
97.1.Sch B Resf. Sadhali Pandharva Road Ta. Jetpur Pavi.xls
Item No. as Brief Description of materials to be Qty. of Unit Prescription of test which Frequency @ which test shall be Total Nos of
per tested. Materials shall be carried out carried out test to be
Schedule 'B' taken
7 Supplying of Quarryspall 0.00 Cum *Gradation,CBR One test per work
8 Supplying of Sand/ 388.00 Cum *Silt Content,F.M One test per work
9 Stonedust 0.00 Cum *Gradation One test per work
10 Sel;ected Soil for Embankment 293.00 Cum P.I ,CBR,MDB
11 Rubble 0.00 Cum *Density & Los Angeles abrasion As per IRC:SP:116-2018
12 Asphalt (VG-30) 0.00 M.T. Viscosity Test Tanker test in Geri Lab. Only
as per I.S. 1206 Up to 10
Above 50 one per Tanker
Ductility Test As per I.S.
Specification Gravity test As per I.S.
Softening point test As per I.S.
Quality of binder test 3 test per 2 tankers on plant site.
13 Tack Coat *Binder Temperature for applicationIrregular close in intervals
*Rate of spread of Binder. 2 test per Day.
14 Carpet & Seal Coat. Mix Grading One Test on Individual
Temperature of binder in Boilor Constituents and mixed aggregates from the
aggregates in the dryer and mix dryer for each 100 tonnes of mix subject to
at the time of laying and rolling. minimum of Two tests per plant per day.
( Binder content vide 45/MD. One Test for each 100 tones of mix
2172) subjects to minimum of two per Day.
Rate of Spreaded mix materials. Regular control through checks on layer
15 Cement (OPC) 288.800 M.T. *Consistency,Soundness 1 test @ 50.0 M.T. 100 T 2 tests,
*Setting time,Finessness Test 200 T 3 tests, 300 T 4 tests, 500 T 5 tests,
*Compressive Strength. 800 T 6 tests, 1300 T 7 tests & 8 testd for
large consingment.
97.1.Sch B Resf. Sadhali Pandharva Road Ta. Jetpur Pavi.xls
Item No. as Brief Description of materials to be Qty. of Unit Prescription of test which Frequency @ which test shall be Total Nos of
per tested. Materials shall be carried out carried out test to be
Schedule 'B' taken
16 Steel (TMT) 12.84 M.T. *Tensile, (TMT) As per Manual of Quality Control
Yield 1 test/40 tonnes / per category
17 C.C.Cube Test 1:2:4 *Compressive Strength. 1 to 5 cmt - 1 No
M250 424.10 51 to above - 4 +1 additional sample
for each 50 cu.mt. Or part there of.
18 Retro Reflective Sheeting for the signage 1.00 Nos. as per Test schedule attached GR SOR/1018/715/Part file/C-1 Dtd.4/6/19
19 Road studs / Cat Eyes 0.00 Nos. as per Test schedule attached GR SOR/1018/715/Part file/C-1 Dtd.4/6/19
20 Hot Applied Thermoplast Road Marking 0.00 Sqmt as per Test schedule attached GR SOR/1018/715/Part file/C-1 Dtd.4/6/19
Note (1):- In case of excess in quantity. Further more test shall be carried out as per required frequency.
Note (2):- Apart from above listed materials for carrying out various tests during Road / Structure
Construction Works , if any other than above mentioned material/s are to be used during road /
structure construction work then it must be tested as per prevailing criteria of Govt. of Gujarat (R &
B Deptt.) and necessary tests should be carried out as per prevailing norms.
Signature of Contractor. Deputy Executive Engineer Executive Engineer
Panchayat (R & B) Sub Division Panchayat (R & B) Division
Jetpur Pavi Chhotaudepur
97.1.Sch B Resf. Sadhali Pandharva Road Ta. Jetpur Pavi.xls
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
97.2 SBD Resf. Sadhali Pandharva Road Jetpur Pavi Ta..pdf
Bill of Quantities.pdf
Schedule B.pdf
97.3.Speci. Resf. Sadhali Pandharva Road Jetpur Pavi Ta..pdf
Scan Drawing Sadhali Pandharva Road.pdf
GR_to_be_attached_with_DTP_SBD_with_Index (1).pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .