| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.3 LAccepted-AOC | L1 | Accepted-AOC lowest bidder | |
| 2 | L2₹10.4 L+₹3,883 (0.38%)Accepted-AOC | L2 | Accepted-AOC not lowest bidder | |
| 3 | L3₹10.4 L+₹7,746.23 (0.75%)Accepted-AOC | L3 | Accepted-AOC not lowest bidder | |
| 4 | L4₹10.5 L+₹12,235.74 (1.18%)Accepted-AOC | L4 | Accepted-AOC not lowest bidder | |
| 5 | L5₹10.5 L+₹19,166.45 (1.85%)Accepted-AOC | L5 | Accepted-AOC not lowest bidder |
Tender Value
₹12.7 L
EMD Value
₹31,769
Closing Date
4 Nov 2023, 3:30 pmClosed
Assistant executive engineer
Assistant executive engineer,MI Subdivision, Mulanthuruthy
GENERAL-Annual Maintenance for the year 2023-2024-Kakkad and Kakkad Tail End L I Scheme-General Civil Work
2023_Irrig_617776_1
13/AEE/MIMLTY/2023-24
Open Tender
Civil Works - Others
Item Rate
240 days
KAKKAD, PIRAVOM
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
Yes
₹31,769
Yes
23 Nov 2023
31 Oct 2023
6 Nov 2023
31 Oct 2023
4 Nov 2023
31 Oct 2023
Amount
KAKKAD & KAKKAD TAIL END LI SCHEME
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
10.26.3:Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approves steel primer.G.I. pipes
OD19509/2023-2024:Engaging Man Coolie for clearing blocks in canal and syphon, cleaning suction pit and canal premises during the entire periods of water distribution etc complete as per the direction of departmental officers at site
KAKKAD TAIL END PUMP HOUSE
15.7.4:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.1.5:Solid block masonry using pre cast solid blocks ( Factory made) of size 30x20x20cm or nearest available size confirming to IS 2185 Part I of 1979 for super structure up to floor two level thickness 20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete
13.4.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 coarse sand)
13.60.1:Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade:Two or more coats on new work
Shaji Varghese
ROY M.T
Saju C S
va george
Jomin Benny
Bidder Name
Shaji Varghese
va george
Saju C S
ROY M.T
INNAMMA PAULOSE
Jomin Benny
stage.html
html • 0.06 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_926830.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .