| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.1 CrAccepted-AOC | ₹1.1 Cr | 1 | Accepted-AOC First lowest |
| 2 | 2₹1.1 Cr+₹3.8 L (3.48%)Rejected-AOC | ₹1.1 Cr+₹3.8 L (3.48%) | 2 | Rejected-AOC Second lowest |
| 3 | 3₹1.3 Cr+₹17.5 L (16.0%)Rejected-AOC | ₹1.3 Cr+₹17.5 L (16.0%) | 3 | Rejected-AOC Third lowest |
Tender Value
₹1.2 Cr
EMD Value
₹50,000
Closing Date
24 Jul 2020, 4:00 pmClosed
Construction Engineer K L D C Ltd Thrissur
Construction Engineer K L D C Ltd Thrissur
Construction of Regulator- 1 No.
2020_KLDC_371970_1
KLDC/ TSR/2020-21/4(6)
Open Tender
Civil Works - Others
Item Rate
545 days
Viyoor - Puzhakkal.
Please refer Tender documents.
4 documents required · 4 mandatory
₹5,600
Yes
Construction Engineer K L D C Ltd Thrissur
₹50,000
Yes
12 Jan 2021
15 Jul 2020
28 Jul 2020
15 Jul 2020
24 Jul 2020
15 Jul 2020
Amount
APPENDIX A - Construction of Regulator-1 No. :-Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
Putting up ring bund with a width of 2 mtr and height of 2.50 m, protect the sides with Ist class bamboo posts 4m long driving down 1.50 m below bed level at 60 cm c/c in 2 rows 2m apart and tied well with half split bamboo struts on both sides and screening inside with bamboo thaithals with coir yarn and inside filled with ordinary earth, cut, conveyed and consolidated with all leads and lifts and maintaining the bund leak proof till completion of the work including dismantling the bund after completion and clearing the site neatly.
Bailing out water using pump above 5 HP and Up to 10 HP-Bailing out water with engine and pump set above 5HP and up to 10HP, including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Filling with Quarry Muck Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)
Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
Providing and fixing in position pre- moulded joint filler in expansion joints.
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Colour washing such as green, blue or buff to give an even shade:New work ( two or more coats) with a base coat of white washing with lime
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
Finishing walls with water proofing cement paint of required shade:New work (Two or more coats applied @ 3.84 kg/10 sqm)
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Supplying and filling at site with contractors own earth suitable for filling brought from out side, levelling the top at site and banking in layers not exceeding 20 cm in depth, breaking clods, watering, ramming and dressing up in embankments for bunds,roads, flood banks, marginal banks and guide banks or filling up ground depressions, and as per the direction of officers at the site, etc, complete.
Providing BOUNDARY STONE .- 30*30*75 cm of hard stone 15cm chiseled dressed on all four sides including top including earthwork excavation and levelling course.
Southern Rock And Aggregate Mining Company
Abhishek Baby
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_526718.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .