| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹94.1 LAdmitted-Finance | -36.97% | ₹94.1 L | L1 | Admitted-Finance |
| 2 | L2₹1.1 Cr+₹16.5 L (17.6%)Admitted-Finance | -25.89% | ₹1.1 Cr+₹16.5 L (17.6%) | L2 | Admitted-Finance |
Tender Value
₹1.5 Cr
EMD Value
₹3.0 L
Closing Date
10 Aug 2026, 12:00 pmClosed
commissioner
MUNICIPAL CORPORATION KOTA
nagar nigam kota area vidhansabha south various palace CC road construction damar road construction orher construction and maintenance work 6 nit 20
2026_DLB_581776_6
NNK/XEN/CIVIL/2026/330-341 nit 20
Open Tender
Civil Works
Percentage
180 days
kota
Please refer Tender documents.
2 documents required · 2 mandatory
₹3,500
commissioner
₹3.0 L
Yes
13 Aug 2026
4 Aug 2026
10 Aug 2026
4 Aug 2026
10 Aug 2026
4 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1WORK NAME | |||||
| 1.01 | Dismantling of existing structures like culverts, bridges, retaining walls, CC road and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 50 metres as directed by Engineer. Cement Concrete Grade M-15 and above and PCC blocks | 630 | Cum | 678 | ₹4,27,140 |
| 1.02 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level. In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. Depth upto 1.5 m | 1,132 | Cum | 229.5 | ₹2,59,794 |
| 1.03 | Carriage of Materials by mechanical transport including loading, unloading and stacking :: Earth, 5Km | 1,409.6 | Cum | 254.76 | ₹3,59,109.7 |
| 1.04 | Providing and laying lean cement concrete 1:4:8 in Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid manually, compacting with surface vibrator, finishing and curing complete as per clause 601, 112 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. | 1,132 | Cum | 3,030 | ₹34,29,960 |
| 1.05 | Providing and laying un-reinforced, dowel jointed, plain cement concrete mix in pavement over a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS: 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades complete as per drawing and as per clause 602, 112 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. PCC M-30 | 1,080 | Cum | 6,740 | ₹72,79,200 |
| 1.06 | Cleaning and removal of earth, silt, sludge, kankar, boulder, building material and garbage in existing nallah/drains including construction of bypass arrangement to bypass water with 1.5m lift from ground level and lead upto 50 m including foul & saturated condition where pumping out or bailing out of water is required, including shoring, shuttering where required and dewatering. Making access for disposal and dressing disposal side as per the directed of the Engineer. For Depth upto 1.50 m | 32.1 | Cum | 406 | ₹13,032.6 |
| 1.07 | Providing, laying, spreading (with paver finisher only) and
compacting wet mix macadam (WMM) base course comprising of graded stone aggregate and granular material conforming to MORT&H specifications (Table 400-II) in layers of equal compacted thickness each consolidated, including pre-mixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tippers to site, laying in uniform layers in base course on a well prepared sub-base/ base course and compacting with power vibratory-roller to achieve the desired density complete as per MoRT&H specification clause - 406 including all material, labour, machinery, lighting, guarding and maintenance of diversion. | 33.75 | Cum | 1,775 | ₹59,906.25 |
| 1.08 | Providing and applying tack coat on the prepared surface with bitumen emulsion as per IS: 8887 and approved quality @ 0.2 kg/sqm with the help of spray set fitted on bitumen Container (boiler) after cleaning the surface with brooms or soft brushes and finally dusting with old gunny bags and compressed air to receive bituminous treatment complete as per clause 502 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. | 4,120 | Sqm | 12 | ₹49,440 |
| 1.09 | Providing and laying 50-75 mm compacted thick design mix (approved by Engineer) Dense Bituminous Macadam on prepared surface with specified graded crushed aggregates as per Table 500-9, 500-10 with bitumen binder set (including Cost of anti-strippingcompound Minimum 1% in Lime/Cement as per design wherever required) for base/ binder course including loading of material with F.E. loader, heating and mixing of stone aggregate, filler and bitumen in computerised hot mix plant, transporting the mixed material by tippers to paver and laying with paver finisher fitted with electronic sensor control as per clause 504.3.5 to the required level and grade, compacting by power rollers and vibratory rollers or 150 to 250 KN pneumatic tyred roller with TP = 0.7 Mpa to achieve the desired density (approximately 2.3 tonne/cum) complete as per clause 507 of MoRT&H specification but excluding primer/tack coat, including all material, labour, machinery, lighting, guarding and maintenance of diversion. Grade-II with Bitumen VG-grade 30 @ 4.50 %, lime filler @ 2% (percent by weight of total mix) | 206 | Cum | 7,860 | ₹16,19,160 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.36 MB
006.pdf
Tender Documents • 9.72 MB
BOQ_1033732.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .