Tender Value
₹9.7 Cr
EMD Value
₹19.5 L
Closing Date
8 Oct 2026, 3:00 pm
CE BDA
CE Office BDA Bareilly
Greater Bareilly Aawasiya Yojana ke Sector-11 mein aantrik vikas karya ke antargat sewer line, water line, RCC drain, electric trench, park, boundary wall tatha sadak nirman karya.
2026_BDAUP_1184722_1
T-26/2026/03
Open Tender
Civil Works
Percentage
365 days
Bareilly
Please refer Tender documents.
2 documents required · 2 mandatory
₹15,000
Vice Chairman, Bareilly Development Authority
₹19.5 L
11 Sept 2026
11 Sept 2026
9 Oct 2026
11 Sept 2026
8 Oct 2026
11 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in filling in ordinary soil including leveling dressing and ramming and also including cartage 4.00 Km distance Including loading unloading cost of earth royalty etc. all complete as per direction of E/I Excluding royality
PWD SOR ITEM No. 253+ cartage+ cost of earth etc | 74,873.68 | Cum | 290.7 | ₹2,17,65,778.78 |
| 2 | Extra for machnical compection of Earth including of levelling, dressing, watering & compacting the soil to achieve 95% proctor density etc. all complete (S.I. 253a).
PWD SOR ITEM NO. 253a | 74,873.68 | Cum | 155 | ₹1,16,05,420.4 |
| 3 | Construction of granular sub base (G.S.B.) by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, compete at per clause 401.
(Analysis Rate) | 658.35 | Cum | 4,133.1 | ₹27,21,026.39 |
| 4 | Providing laying, spreading and compacting graded stone aggregate to wet mix macadam (WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material to site laying in uniform layers with paver finisher in sub base/ base course on well prepared surface and compcting with vibratory roller to achieve the desired density. complete in all respect. as per MORTH specification 406.
(Analysis Rate) | 495.6 | Cum | 4,155 | ₹20,59,218 |
| 5 | Providing and applying bitumen emulsion tack coat with butumenus grade VG-10 over prepare surface of granuler base(primer coat) including cleaning of road sruface sand spreading tack coat @ 0.50 Kg/ sqm using machanical means as per morth (Morth 502)
(Analyis Rate) | 9,912 | Sqm | 59.4 | ₹5,88,772.8 |
| 6 | First layer of DBM 50mm thick Providing and laying dense graded bitumenous concrete(DBM) with (VG-30) 100-120 TPH batch type HMP prooducing an average output of 75 tonnes per hour using brushed aggregates of spcified gading premixed with bitumenous binder @ 4.0 % to 4.50% by weight of total mix and filler transpored to site laid over a previous prepared surface with paver finisher to the required grade level and alingment and rolled as per clause 501.6 and 501.7 to achieve the desire compaction all complete as per morth specification morth-504
(analysis rate) | 495.6 | Cum | 13,096 | ₹64,90,377.6 |
| 7 | Providing and applying bitumen emulsion tack coatwith butumenus grade VG-10 over bituminious surface of including cleaning of road sruface sand spreading tack coat @ 0.20 Kg/ sqm using machanical means as per morth (Morth 503) (Analysis Rate) | 9,912 | Sqm | 17.4 | ₹1,72,468.8 |
| 8 | Providing and laying bitumenous concrete (BC) 25 mm thick with (VG-30) 100-120 TPH batch type HMP prooducing an average output of 75 tonnes per hour using brushed aggregates of spcified gading premixed with bitumenous binder 60/70 grade @ 5.0 % of mix & filler transpored the hot mix to site laying with a hydrostatic paver finisher with sensor control to the required grade level and alingment and rolling with smooth wheeled vibratory and tendom rollers as per MORTH specification clause no. 509 complete in all respcet.
Analysis Rate | 743.4 | Sqm | 15,998 | ₹1,18,92,913.2 |
| 9 | Providing and applying 2.5mm thick road marking strips (retro reflective of specified shade/colour using hot themoplastic material by fully/semi automatic paint applicator machine fitted with profile shoe glass beads dispenser, propane tank heater and profile shoe heater, driven by experienced operator on road surface including cost of material, labour, T&P cleaning the road surface of all dirt, seals, oil grease and foreign material etc. complete as per direction of Engineer In charge and accordance with applicable specifications.
DSR-16.62 (2023) | 241.35 | Sqm | 565.5 | ₹1,36,483.43 |
| 10 | Provding and fixing Glow studs(Cats Eye) af size 100x 20m made of heavy duty body shall be moulded ASA (Acrylic styrene Acryloetrite ) or HIP (High impact polystyrene ) of ABS having electronically welded micro- prismatic lens with abrasion resistant coating as approved by Engineer in charge. The glow stud shall support a load of 13635 Kg tested in accrodance with ASTM D4280. The slope of retro- reflective surface shall be 35(+/-5) degress to base. The reflective panels of both sides with at least 12 cm of reflective area up each side. The luminationce intensity should be as per the specification and shall be tested as described in ASTM I:809 as recommended in BS :873 part 4 :1973. Teh studs shall be fixed to the Road surface using the adhesive conforming to IS as per procedure recommended by the manufacturer complet and as per direction of engineer - in - charge
D.S.R. ITEM NO. 16.50 | 145 | Nos | 156 | ₹22,620 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.60 MB
Tenderdoument.pdf
Tender Documents • 8.07 MB
BOQ_2228904.xls
BOQ • 0.47 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .