| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.1 LAccepted-AOC 2ND FLOOR CPW VII 128 FAHAD SHOPPING CENTRE KATHIRVEKKUM THARA CHERUKUNNU P O KANNUR KERALA PIN 670301 | KANNUR | KANNUR | KERALA | 670301 | ₹6.1 L | L1 | Accepted-AOC Lowest rate 1 percentage below with GST |
| 2 | L2₹6.8 LRejected-AOC | ₹6.8 L | L2 | Rejected-AOC Second lowest 32 percentage above without GST |
| 3 | L3₹6.9 LRejected-Finance | ₹6.9 L | L3 | Rejected-Finance Highest rate quoted.Above 11.9 percentage including GST |
Updated dates
Tender Value
₹5.2 L
EMD Value
₹13,000
Closing Date
18 Mar 2026, 2:00 pmClosed
Assistant Executive Engineer
Transmission sub division,Kanhangad,110kV Substation compound,Mavungal
Providing 3 Nos of additional 11kV feeder outlets at 110kV Substation, Cheruvathur
2026_KSEB_840048_1
11/AEE/TSD/KHD/25-26/24.2.26
Open Tender
Electrical Works
60 days
110kV Substation, Cheruvathur compound
Please refer Tender documents.
6 documents required · 6 mandatory
₹1,298
₹13,000
4 Jun 2026
25 Feb 2026
23 Mar 2026
25 Feb 2026
18 Mar 2026
25 Feb 2026
25 Feb 2026 - 18 Mar 2026
Fitting and erecting one HT Double Pole Structure using A type pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing).
Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials.
Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle).
Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges.
Welding charge for welding on iron parts using arc welding as per standards .
Providing interconnection between equipments using ACSR Moose/ Kundah/ wolf Single conductor at both ends with compressed/ bolted ends including uncoiling and cutting of conductor as per the direction of departmental officers.
Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
Brick work with common burnt clay F.P.S (non modular) bricks of class designation 7.5 in foundation and plinth in:Cement mortar 1:4
12 mm cement plaster of mix:1:6 (1 cement : 6 fine sand).
Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Supplying and stacking hard blue granite broken stone 40 mm at site
Supplying and stacking hard blue granite broken stone 6 mm at site
Spreading of 6 mm size broken stone
Spreading of broken stone 40 mm size
Additional rate for excavation of Pit for A type pole in Hard Laterite.
Unpacking at the place of storage and transporting 11KV indoor VCB/SF6 switchgear panel and its accessories to the place of erection and erecting after fixing foundation bolts by chipping concrete wherever necessary, tightening, keeping lines and levels taking all safety precautions including erection of potential transformers as per the direction of departmental officers.
Interconnection of panels and 11KV bus bars after opening covers, earthing, inter panel wiring, etc. and making ready for commissioning of breaker as per the direction of the departmental officers.
Loading one set 11KV indoor VCB panel with truck from the place of its storage to department lorry using required lifting device, without causing any damage to equipment & its parts
Unloading one set 11KV indoor VCB panel with its truck from department lorry to substation site by using required lifting device, without causing any damage to equipment parts and lift the same to a pace for safe storage.
Loading 3x300 sq. mm XLPE cable from its place of storage to department lorry and properly without causing any damage to its insulation and make ready for transporting as per the direction of department officers.
Unloading 3x300 sq. mm XLPE cable from department lorry to substation site and stacking properly without causing any damage to its insulation as per the direction of department officers.
Laying of departmentally supplied GI strip/Copper strip of suitable size including cleaning and neatly bending of strips ,cutting, removing of metal/earth in the yard and burying earth strip to the required depth re-doing the yard metalling as per the direction of the departmental officers.
Welding one end of the bended GI strip of size 50x6mm with the riser of the already laid earth mat, welding 150mm in length, 6mm thick on both sides & end of the strip & other end of the strip with yard structure at 2 points 50mm apart each welding points having 50mm length and 6mm thick on both sides & end of the strip including the charges for connecting the strip with structure using bolted joints as per the directions of the department officers. Charges includes hire charges of DC arc welding set, current charges, cost of low hydrogen content DC arc welding electrodes(No.E7018) cost of anti corrosive paint etc. complete.
Doing outdoor/indoor cable termination of 3x300 mm2 11KV XLPE cable very carefully observing directions of manufactures and departmental staff including crimping of socket
Laying 3 x 300 sq mm XLPE cables in trench including drawing through pipes wherever necessary.
Mounting one 3x300 mm2 XLPE outdoor cable termination of structures very carefully without causing any damage to the drilling holes wherever necessary as directed by the departmental officers
Mounting one 3x300 mm2 XLPE indoor cable termination of structures very carefully without causing any damage to the drilling holes wherever necessary as directed by the departmental officers
Erection of 1 No. 11KV LA (station type ) /11KV Post insulator on the already erected structure after opening of crates at the place of storage leading to site carefully, keeping lines and levels as per the direction of the departmental officers
Erection of one set 11KV Isolator / AB switch (station class) on the already erected structure including opening crates and conveyance of all accessories from the place of storage to the place of erection to lines and levels including erection of mechanism box checking operation and aligning properly as per the direction of departmental officers.
Drilling holes in yard structure
Cutting of steel angle in yard structure erection
Removing the concrete cover slab and placing it over the cable trenches after the cable work.
Welding overlapping joints of 50x6mm GI strip with 50mm long, 6mm thick welding on all three sides after doing 2 Nos. bolted joints at the centre as specified after cleaning the surface. Charges includes hire charges of DC arc welding set, current charges, cost of low hydrogen content DC arc welding electrodes( No.E7018) cost of anti corrosive paint etc. complete.
Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling.
Additional rate for excavation of one Earth Pit (2.5m depth) in Hard Laterite.
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.28 MB
BOQ_1415892.xls
BOQ • 0.38 MB
tenderconditionscheruvathur.pdf
Tender Documents • 0.62 MB
BidderDetails.pdf
Other Document • 0.30 MB
Download all tender documents and submit your bid