Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹28.4 L
EMD Value
₹29,000
Closing Date
23 Nov 2026, 12:05 pmDue today
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer (R & B) Division, Bharuch
Renovation of Compound Wall at District Court Bharuch
364118
22 Of 2026-27
Open
Civil Works - Others
Works
Bharuch
1 document required · 1 mandatory
₹1,500
Executive Engineer, Bharuch (R&B) Division, Bharuch
₹29,000
7 Nov 2026
7 Nov 2026
7 Nov 2026
23 Nov 2026
7 Nov 2026
90 days
No figures
1 Demolition of Brick work and stone masonry including 84.00 Cum 536.09
stacking of serviceable materilas and disposal of
unserviceable materials with all lead and lift. (ii) In
Cement Mortar.
2 Demolition including stacking of serviceable materilas 31.07 Cum 1030.81
and disposal of unserviceable materials with all lead and
lift. (i) R.C.C. work
3 Excavation for foundation upto 1.5 m depth including 108.00 Cum 117.08
sorting out and stacking of useful materials and
disposing off the excavated stuff upto 50 Meter lead. (A)
Loose or soft soil
4 Boring holes 3.5 m deep in ordinary soil (for cast in situ 98.00 Each 1486.14
piles) and getting out the soil and disposal of the surplus
excavated soil as directed within a lead of 50 Meter for
following diameter of pipes. (iii) 300 mm
5 Extra for under reaming inside the bore Holes for under 98.00 Each 632.44
reamed piles of following Diameter. (iii) 300 mm
6 Providing and laying cement concrete 1:3:6 (1-Cement: 3- 11.97 Cum 2965.76
coarse sand: 6- hand broken stone aggregates
mmnominal size) and curing complete excluding cost of
formwork in (A) Foundation and Plinth
7 Providing and laying cement concrete 1:2:4 (1-Cement: 2- 23.94 Cum 3481.28
Coarse sand: 4- graded stone aggregates 20 mm nominal
size) and curing complete excluding cost of formwork in
(A) Foundation and Plinth
8 Providing and laying cement concrete work 1:2:4 (1- 23.38 Cum 3835.96
Cement: 2- Coarse sand: 4-graded stone aggregates
mm nominal size) and curing complete excluding cost of
formwork and reinforcement for reinforced concrete
work in (D) Columns, Pillars posts and struts upto floor
two level.
9 Providing and laying cement concrete work 1:2:4 (1- 24.24 Cum 3746.12
Cement: 2-Coarse sand: 4-graded stone aggregates
mm nominal size) and curing complete excluding cost of
formwork and reinforcement for reinforced concrete
work in (A) Foundations, footings, Base or columns and
Mass concrete
Item Rate In
Description of Item Quantity Unit Amount
No figures
10 Brick work using common burnt clay building bricks 138.76 Cum 4021.02
having crushing strength not less than 35 kg./Sq.Cm. in
foundation and plinth in Cement Mortar 1:6 (1-Cement: 6-
fine sand) (B) Conventional
11 Providing and laying cement concrete 1:3:6 (1-Cement: 3- 11.97 Cum 3816.45
Coarse sand: 6-crushed stone aggregates 20 mm nominal
size) and curing complete including cost of formwork in
(A) Wall Caps/Coping
12 Providing 20mm thick cement plaster in single coat on 1490.00 Sqm 213.16
single. or half brick walls for interior plastering upto
floor two level and finished even and smooth in (ii)
Cement mortar 1:4 (1-cement :4-sand)
13 Providing TM T. bar reinforcement of Fe-500 D for 10645.00 Kg 76.21
R.C.C.work including bending binding and placing in
position complete up to All floor Level.
14 Finishing wall with weather proof exterior emulsion 1490.00 Sqm 114.53
paint on wall surface (two coats) to give an required
shape even shade after thoroughly brushing the surface
to remove all dirt, and remains of loose powdered
materials.etc complete
15 Providing formwork of ordinary timber planking so as to 399.00 Sqm 197.25
give a rough finish including centering shuttering
strutting and propping etc. height of propping and
centering below supporting floor to ceiling not exceeding
4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (H) (1) Sides and
soffits of Beams Beam Haunchings cantilevers Girders
Bressumers and Lintels not exceeding 1 M. in Depth.
16 Providing formwork of ordinary timber planking so as to 312.00 Sqm 303.84
give a rough finish including centering shuttering
strutting and propping etc. height of propping and
centering below supporting floor to ceiling not exceeding
4 M. and removal of the same for in situ reinforced
concrete and plain concrete work in. (G) Columns
PillarsPosts and struts. (1) Square Rectangular Polygonal
17 Providing and fixing "Y" shape concertina razor coil roll 266.00 Rmt 621.15
fencing 10 mm c/c with 50 x 50 x 5 angle for "Y" and 35 x
35 x 5 angle for bottom and sides as shown in drawing &
G.I. barbed roll fencing 10 cm C.C. spray and oil painting
Total Rs.
I/We am/are willing to carry out the work at………………….% above/below percent(Should be written in figures and
words) of the estimated rate mentioned above. Amount of my /our
Tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
Item Rate In
Description of Item Quantity Unit Amount
No figures
In words In words
1 The Credit Value of Dismentalled Materials of Amount Rs. 17217.00 shall be recovered from the 1st Running
Bill of the Contractor.
2 The Contractor shall exhibit a board with detailed specification and details of work as directed by the
Engineer-In-Charge for which no extra payment shall be made.
3 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
4 Income tax TDS will be deducted at a source while making payments of bills
5 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.: PRC-
10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in S.O.R. therefore in R.C.C. items where
there is a change as per actual mix design the cost of difference of cement consumption have been deducted
from the rate of original item at the rate of input rate mentioned in all the tender.
Deputy Executive Engineer Executive Engineer
City (R&B) Sub Division Bharuch ( R & B ) Division
Bharuch Bharuch
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
GRs - Circulars - 1.pdf
GRs - Circulars - 2.pdf
INDEX-GRs.pdf
SBD.pdf
BOQ.pdf
Specification.pdf
4 Building-Specification Booklet (2 side).pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .