| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹100.2 CrAccepted-AOC | ₹100.2 Cr | L1 | Accepted-AOC L1 Bidder |
| 2 | L2₹117.8 CrRejected-AOC | ₹117.8 Cr | L2 | Rejected-AOC L2 Bidder |
| 3 | L2₹136.1 CrRejected-AOC | ₹136.1 Cr | L2 | Rejected-AOC L3 Bidder |
| 4 | Rejected-Technical | - | - | Rejected-Technical Technically Not Accepted |
Tender Value
Refer Docs
EMD Value
₹1.7 Cr
Closing Date
7 Oct 2022, 1:00 pmClosed
Director (Systems / Operations)
Admin Building (Chennai Metro Rail Limited)
Design, Manufacture, Supply, Installation, Testing and Commissioning of Platform Screen Doors for CMRL Phase II _Corridor 4
2022_CMMDB_689376_1
CMRL/PH_II/SYS/C4_ASA10/2022
Global Tenders
Miscellaneous Works
2245 days
Chennai
Please refer Tender documents.
10 documents required · 10 mandatory
₹40,000
CMRL BANK ACCOUNT
₹1.7 Cr
Admin Building (Chennai Metro Rail Limited)
6 May 2023
17 May 2022
7 Oct 2022
17 May 2022
7 Oct 2022
15 Sept 2022
17 May 2022 - 7 Jun 2022
8 Jun 2022
Indian Rupees
Foreign Currency 1
Foreign Currency 2
Description of Work / Item(s)
Training, Operation & Maintenance Manual and Maintenance Assistance
Cost for instructor week for imparting training to Employer’s Technical Personnel, in Chennai
Cost for instructor week for imparting training to Employer’s Technical Personnel, in Chennai
Cost for instructor week for imparting training to Employer’s Technical Personnel, in Chennai
Cost for instructor week for imparting training to Employer’s Technical Personnel, in off-shore locations
Cost for instructor week for imparting training to Employer’s Technical Personnel, in off-shore locations
Cost for instructor week for imparting training to Employer’s Technical Personnel, in off-shore locations
Cost for instructor week for Imparting training to Employer’s operating personnel, in Chennai
Cost for instructor week for Imparting training to Employer’s operating personnel, in Chennai
Cost for instructor week for Imparting training to Employer’s operating personnel, in Chennai
Delivery & commissioning of Computer based training systems at Chennai, as stipulated in Part 2 Employer’s requirement.
Delivery & commissioning of Computer based training systems at Chennai, as stipulated in Part 2 – Employer’s requirement.
Delivery & commissioning of Computer based training systems at Chennai, as stipulated in Part 2 – Employer’s requirement.
Operating & Maintenance Manuals (Draft as well as Final, in required copies)
Operating & Maintenance Manuals (Draft as well as Final, in required copies)
Operating & Maintenance Manuals (Draft as well as Final, in required copies)
Cost for deputing Supervisory experts in various sub-systems of Signaling for on-the-job training, supervise maintenance & trouble-shooting, as per Employer’s requirements
Cost for deputing Supervisory experts in various sub-systems of Signaling for on-the-job training, supervise maintenance & trouble-shooting, as per Employer’s requirements
Cost for deputing Supervisory experts in various sub-systems of Signaling for on-the-job training, supervise maintenance & trouble-shooting, as per Employer’s requirements
Description of Work / Item(s)
Contract Spares, Special tools, Testing Equipments, Measuring Instruments and Furniture
Contract Spares as per final list of Spares on completion of detailed design (with Notice of No objection from the Engineer)
Contract Spares as per final list of Spares on completion of detailed design (with Notice of No objection from the Engineer)
Contract Spares as per final list of Spares on completion of detailed design (with Notice of No objection from the Engineer)
Contract Tools, Testing Equipments & Measuring instruments as per final list of Tools, Testing Equipments and measuring instruments, on completion of detailed design (with Notice of No objection from the Engineer)
Contract Tools, Testing Equipments & Measuring instruments as per final list of Tools, Testing Equipments and measuring instruments, on completion of detailed design (with Notice of No objection from the Engineer)
Contract Tools, Testing Equipments & Measuring instruments as per final list of Tools, Testing Equipments and measuring instruments, on completion of detailed design (with Notice of No objection from the Engineer)
Furniture for various Control & Equipment Rooms, as per Employer’s requirements
Furniture for various Control & Equipment Rooms, as per Employer’s requirements
Furniture for various Control & Equipment Rooms, as per Employer’s requirements
Fangda Innotech Co. Ltd.
ST Engineering Electronics Ltd
ST Engineering Electronics Ltd
Zhuzhou CRRC Times Electric Co., Ltd.
Zhuzhou CRRC Times Electric Co., Ltd.
Fangda Innotech Co. Ltd.
US Dollar
European Euro
US Dollar
US Dollar
European Euro
US Dollar
US Dollar
European Euro
US Dollar
US Dollar
European Euro
US Dollar
US Dollar
European Euro
US Dollar
US Dollar
European Euro
US Dollar
US Dollar
European Euro
US Dollar
European Euro
US Dollar
US Dollar
European Euro
US Dollar
US Dollar
European Euro
US Dollar
European Euro
US Dollar
European Euro
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid