| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.5 LAccepted-AOC | ₹6.5 L | L1 | Accepted-AOC Reduced the quoted rate by 1 percentage on negotiation. |
| 2 | L2₹6.9 L+₹39,247.19 (6.06%)Rejected-AOC | ₹6.9 L+₹39,247.19 (6.06%) | L2 | Rejected-AOC 5 percentage above estimate rate |
| 3 | L3₹7.1 L+₹58,870.79 (9.09%)Rejected-AOC | ₹7.1 L+₹58,870.79 (9.09%) | L3 | Rejected-AOC 8 percentage above estimate rate |
Tender Value
₹6.5 L
EMD Value
₹16,500
Closing Date
6 May 2026, 4:00 pmClosed
Assistant Executive Engineer
Office of the Assistant Executive Engineer, Electrical Sub Division, Chithirapuram- 685565
LT reconductoring work under Valiya Mullakanam DTR under Electrical Section, Rajakkad.
2026_KSEB_848558_1
02/2026-27/AEE/ESD/CPM
Open Tender
Electrical Works
Percentage
120 days
Rajakkad
Please refer Tender documents.
6 documents required · 6 mandatory
₹1,652
₹16,500
6 Jun 2026
18 Apr 2026
13 May 2026
18 Apr 2026
6 May 2026
18 Apr 2026
18 Apr 2026 - 6 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. | - | Trip | - | - |
| 2.01 | Labour charges for loading LT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). | - | No | - | - |
| 3.01 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. | - | km | - | - |
| 4.01 | Erecting one LT PSC Pole in position including digging & back filling pit in ordinary soil. | - | No | - | - |
| 5.01 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. | - | No | - | - |
| 6.01 | Providing Stay for LT poles including digging & back filling pit in ordinary soil. | - | No | - | - |
| 7.01 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. | - | No | - | - |
| 8.01 | Installing One No. 4 way Satellite Connector of size Main :16 to 95, Tap:4 to 35 Sq.mm to the LT AB cable of Standard size | - | E | - | - |
| 9.01 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. | - | No | - | - |
| 10.01 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. | - | No | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1434066.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.17 MB
BOQ_1434066.xls
BOQ • 0.32 MB
Generalconditionsofcontract.pdf
Tender Documents • 1.13 MB
NIT.pdf
Tender Documents • 0.15 MB
GeneraletenderCondition.pdf
Additional Documents • 0.68 MB
GSTRegistrationQuestionnaire.pdf
Additional Documents • 0.02 MB
SpecialConditions.pdf
Other Document • 0.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .