Executive Engineer’s office, Valsad (R&B) Division,
Repairs To Taluka Court Building Staff Quarters at Dharampur Ta. Dharampur Dist- Valsad
314595
08 Of 2026-27
Open
Civil - All
Valsad
8 documents required · 8 mandatory
₹900
Executive Engineer, Valsad (R&B)Division, Valsad
₹16,000
16 Jun 2026
16 Jun 2026
16 Jun 2026
23 Jun 2026
16 Jun 2026
Sr. Description of Item Quantity Unit Rate Amount
1 Providing and fixing to wall ceiling and floor 10.0 Kg. F/Cm2 working pressure 61.00 Rmt 336.24
poluthene pipes of the following outside Dia. Low densidy, complete with special
falnge compression type fittings, wall clipsetc. including making good the wall ceiling
and floor.(G)110 mm
2 Excavation for foundation upto 1.5 m depth including sorting out and stacking of 48.00 Cu.Mt 117.08
useful materials and disposing off the excavated stuff upto 50 Meter lead.(A) Loose
3 Providing and laying cement concrete 1:3:6 (1-Cement : 3- coarse sand : 6- hand 32.00 Cu.Mt 3005.76
broken stone aggregates 40 mmnominal size) and curing complete excluding cost
of formwork in (A) Foundation and Plinth
4 Providing and fixing pre-cast Rubber Dye / steel Dye inter locking concrete block 316.00 Sq.Mt 686.90
60mm thick with grade of concrete M300 pnumatic compressed / vibrated
mechanically and as per approved design Confirming to IS 15658 : 2006 including
35 mm Sand layer for levelling and filling the joint with sand in proper line and level
as per guidlines of IRC : SP 63-2018 etc. Complete.
5 Providing and Laying homoginious Grey cement based concrete kerbing of size 30 57.00 Rmt 361.64
cm x 30 cm x 10 cm size as per detailed drawing having grade of concrete M25
grade, including necessary excavation, BBCC 1:5:10 7.5 cm as per ddetailed
drawing fixing in line and level, filling joints in CM 1:3 with smooth finished, white
washing three coats etc. complete as directed by Engineer in charge.
6 Providing laying (to level or slopes) and jointing reinforced concrete Light duty non- 75.00 Rmt 665.47
pressure pipes I.S. class NP2 of the following internal diameter with collars and butt
ends prepared for collar joints including testing of joints complete.(D) 300mm
7 Providing and laying controlled cement concrete M-250 and curing complete 35.00 Cu.Mt 5125.54
including the cost of form work but excluding the cost of reinforcement for reinforced
concrete work in Footing and Mass concrete
8 Compaction and finishing of cement concrete road by trimix M.250 process 350.00 Sq.Mt 63.63
providing extra Labour charges for the trimix vacume dewatering service process on
cement concrete road sutface by using vacuum dewatering pump floater surface
vibrator including making groves and rough finish to surface including leveling etc
9 Providing TMT Bar FE 500D reinforcement for R.C.C. work including bending, 1575.00 Kgs 76.21
binding and placing in position complete upto floor two level
10 Steel work, welded in built up sections framed work including cutting, hoisting, fixing 4298.00 Kgs 90.47
in position and applying a priming coat of read lead paint & two coat oil paint. (A)In
beams and joists, channels angles Tees, flats, with connecting plates or angle
cleats as in main and cross beams. Hip and jack rafters, purlins conneted to
common rafters and the like..
11 Providing and fixing of Ridge flashing for roof panel shall be made out of 0.5 mm 172.00 Sq.Mt 858.67
thick pre coated GI sheet . The Precoated sheet shall be of minimum 240 mpa steel
grade confirming to IS 14246:1995 and shall have zinc coating of minimum 120 gsm
as per IS:277:1992 , 5-7 microns epoxy primer on both side of the sheet and
polyester top coat 15-18 micron. The PPGI Sheet shall have plastic protective guard
film of minimum 25 microns to avoid scratches during transportation. The ridge shall
be fixed to the steel members by pop rivet or self drilling/self stitching fastners @
maximum 450 mm c/c along length of capping/flashing etc complete .
12 Wall Painting (Two coats) with weather proof acraylic emulsion paint of approved 2129.00 Sq.Mt 114.53
brand and manufacture and of required shade on exterior wall surface to give an
even shade over and including primery coat with Alkaly resistance primer of
approved brand after thoroughly brushing surface to remove all dust and remains
of loose powdered material etc. copm. for all height
Deputy Executive Engineer, Executive Engineer
Dharampur (R&B) Sub Division Valsad (R&B) Division
Dharampur Valsad
I/We am/are willing to carry out the work at ………………………………………………..% above/below (percent should be written in
figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under.
*Estimated amount *Estimated amount
Put to tender Rs…1511971.78 Put to tender Rs…1511971.78
Deduct ……. % below Rs……………… Add ……. % Avove Rs…………..….
Net Rs. ……………… Total Rs. ………….…
In words ………………….…………………… In words ………………….
*( please strike out whichever is not applicable)
An Amount of 0.00 (Rupees ) shall be recovered from the 1st RA Bill of this work towards salvage value of dismentalled /
Diversion material likely to be available from dismentalling the Dismentaling of stone flooring irrespective of the dismentalled
quantity actuallly received on site.
All works shall be carried out as public works department Handbook and other
specification of Division or as directed.
All the columns in schedule should be filled in ink or ballpen and the total of the
entries in last column should be struck by the contractor under his signature.
Rate quated include clearance of site (Prior commencement of work and at its close)
in all respects and hold good for work under all conditions,site moisture, weather etc.
The Contractor shall exhibit a board with detailed specification and details of work
as directed by the Engineer-In-Charge for which no extra payment shall be made.
The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
GST and Income tax TDS will be deducted at a source while making payments of bills
In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per
Govt. G.R.: PRC-10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in
S.O.R. therefore in R.C.C. items where there is a change as per actual mix design the cost
of difference of cement consumption have been deducted from the rate of original item at
the rate of input rate mentioned in all the tender.
To be continued on additional sheet,if found necessary.
Deputy Executive Engineer, Executive Engineer
Signature of the contractor Dharampur (R&B) Sub Division Valsad (R&B) Division
ÀùËÿëÀËßÞí çèí Dharampur Valsad
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
BOQ.pdf
SBD.pdf
SPECIFICATIONS.pdf
Download all tender documents and submit your bid