Loading…
Loading…
Tender Value
₹57.4 L
EMD Value
₹1.1 L
Closing Date
16 Jun 2026, 6:00 pm2d left
Executive Engineer, Drainage Project, Vadodara Municipal Corporation
The Work of shifting the drainage line and Machine hole in front of Real Kathiyawadi Hotel at the new flyover bridge project at Sardar Estate Junction on the 40.0 meter ring road.(4th attempt)
311630
PRO No.134/2026-27
Open
Civil Works - Water Works
Vadodara
3 documents required · 3 mandatory
₹6,000
Municipal Commissioner, Municipal Corporation, Vadodara
₹1.1 L
5 Jun 2026
5 Jun 2026
5 Jun 2026
16 Jun 2026
5 Jun 2026
8 Section -7 Bill of Quantities III
9 Section -8 Securities and Other Forms
10 Section -9 Drawings IV
11 Section -10 Documents to be furnished by Bidder V
INVITATION FOR BID
NATIONAL COMPETITIVE BIDDING
1. The Vadodara Municipal Corporation invites bids for the construction of works detailed in the table. The
bidders may submit bids for any or all of the following works.
Package Name of work Approxi Bid Cost of Period of Class of
No. mate securi document completi Registration /
value of ty on Category of
works (Rs.) contractor if
The Work of shiing the 57,42,712 /- 1,14,854/ 6,000 /- 3 Months The Contractors
drainage line and Machine - (Excluding must have
hole in front of Real monsoon) registration in
appropriate class
Kathiyawadi Hotel at the new
either with VMC,
flyover bridge project at Central/State/P
Sardar Estate Juncon on the WD/M.E.S./Semi
40.0 meter ring road.(4th Government or
atempt) other such
institutions for
Note: The bidder who fills the tender on N-procure must have valid appropriate class registration. He must
have apply for the registration in VMC after issue of work order.
(B) SCHEDULE OF TENDERING: -
Sr. Schedule Time Date Place
1. Downloading of Tender - 05/06/2026 The tender document for these works
Documents available on website
https://tender.nprocure.com.
2A Submission of Tender Up to 18:00 16/06/2026 Volume-I – Volume V shall be submitted
documents (Volume-I on n-Procure Website.
,II,III,IV & V) on n-
procure Website
2B Submission of Tender Up to 18:00 17/06/2026 Volume-I to V - Technical and
Document and Prequalification Bid in hard copy
Prequalification Bid in (Including Tender Fees, EMD) in separate
Hard Copy of Volume-I sealed Envelope –A through
only, EMD, and Tender RPAD/SPEED Post Only & Hand delivery
Fees (in original) and will not be accepted. Addressed to
attested copies of all P.Q. Executive Engineer, Drainage Project,
Documents. Room No. 204, second floor, Vadodara
Municipal Corporation, Khanderao Market
Building, Rajmahal Road, Vadodara -
3. Pre- Bid Meeting 11:00 hrs. - Executive Engineer, Drainage Project,
Room No. 204, second floor, Vadodara
Municipal Corporation, Khanderao Market
Building, Rajmahal Road, Vadodara -
4. Opening of Technical Bid 18:10 hrs. 17/06/2026 In the office of Executive Engineer,
onwards Drainage Project Dept. Vadodara
Municipal Corporation, Khanderao Market
Building, Rajmahal Road,
5. Opening of Price-Bid - - The price-bid will be opened after scrutiny
of pre-qualification.
Contacting Office:
The Executive Engineer,
Drainage Project,
Room No. 204, second floor
Vadodara Municipal Corporation,
Khanderao Market Building,
Rajmahal Road, Vadodara-390
2. Prospective / Interested bidder may download the Bid Documents from website https://tender.nprocure.com
free of cost till the Time and Date as mentioned on online NIT at website https://tender.nprocure.com.
3. However, Bidder who is submitting the Bid Online will have to pay the Bid Document Fee / Tender Fee
through Demand Draft only of RBI Approved Bank payable at Vadodara and in favour of ‘Municipal
commissioner, Vadodara’’. Once the Bid is received, Bid Document / Tender Fee will not be refundable.
The Demand Draft for Bid Document / Tender fee and Bank Guarantee against Bid Security / EMD shall be
submitted in electronic format through online (by scanning) while uploading the bid, this submission shall
mean that bid document / tender fee and Bid Security / EMD has been received. Accordingly, the offer of only
those shall be opened whose Bid Document / Tender Fee and Bid Security / EMD have been received
electronically. However, for the purpose of realization of Demand Draft / Bank Guarantee bidder, shall send
the same in original through R.P.A.D/Speed Post so as to reach to Municipal commissioner, Vadodara’ as per
Penaltative action for not submitting Demand Draft / Bank Guarantee in original to Executive Engineer /
Tender Inviting Authority by bidder shall be initiated and He will be put in abeyance from filling tenders for
next 6 months in VMC.
4. Bids received online, will be opened on the time, date and place as specified in the online NIT at website
https://tender.nprocure.com in the presence of the bidders or their authorized representatives, who wish to
remain present.
If the office happens to be closed on the last day of submission in Hard copies of the bids as specified, the
Hard copies of the bids will be accepted on the next working day at the same time and venue.
5. A pre bid meeting will be held on at the office of Executive Engineer, Drainage Project Dept. Room No.
204, second floor, Vadodara Municipal Corporation, Khanderao Market Building, Rajmahal Road, Vadodara-
390 001 to clarify the issues and to answer questions on any matter that may be raised at that stage as stated in
clause 9.2 of ‘instructions to Bidders’ of the bidding documents.
6. Bid Security (EMD) is equal to 2% of Estimated Amount put to bid / tender. Bid security for the work costing
up to Rs. 1 crore shall be deposited in form of DD (demand draft) and for works costing above Rs. 1 crore
bank guarantee shall be accepted. (DD/Bank Guarantee shall be from banks as listed in D.M.O. date
11/03/2024 circular attached herewith. or as per their latest amendment. (as per list attached here with as per
7. Other Information is as under:
a) Agencies can prepare and edit their offers a number of times before the end of the tender submission date
and time. After the tender submission date and time, the bidder cannot modify / edit / withdraw their
submitted offer in any case. No written or online request in this regard shall be granted.
b) Offers in physical form will not be accepted in any case.
c) Demand Draft purchased by the other then bidder and also issued after the last date of submission of
Bids, will not be considered or accepted.
d) The cost incurred by the contractor for this offer for clarification or attending discussion, conferences or
site visits will not be reimbursed by the Employer or Engineer-in-Charge.
e) Conditional tender shall not be accepted.
f) Any changes, addition, alternation made in the prescribed form attached with tender are liable to be
g) Any change in format or conditional Bank Guarantee will not be accepted and the bidder will be
considered non-responsive.
h) All the bidders are instructed to fill in information strictly in accordance with the format given in the
checklist /qualification document / tender document.
i) It is mandatory for the bidders to supply each and every information as asked strictly in electronic format
at appropriate places only.
j) Blank / insufficient information shall be treated as nil information and shall result in disqualification.
k) Even if the bidder has been qualified in a similar or larger size of project in the past, it shall not be
deemed to be a ground / reason for not giving required information for this work / bid.
l) Information supplied for earlier projects shall not be considered while evaluation of this bid. The
Government will not ask for any other information, unless it is found absolutely necessary by the
competent authority.
m) If found necessary, the contractor will be intimated for negotiation,
n) Time allowed for completion: As per the Notice Inviting Tender. From the date of written order to
commence: This shall exclude monsoon period from 1st June to 30th Sep and festival on Holi (15 Days)
& Diwali (15 Days). It will be applicable only if it is found reasonable by the department. These days
shall be considered as non-working days.
Following documents shall be submitted in electronic format only through online by scanning and the (i) Bid
Document Fee / Tender Fee (ii) Bid Security / EMD should be sent in original to the Tender opening
authority through RPAD/Speed Post, so as to reach the Executive Engineer as per tender notice.
i) Bid Document Fee / Tender Fee
ii) Bid Security
iii) Registration certificate of appropriate class either with VMC, Central, State, PWD, MES, Govt. Semi
Govt. or such other institutions. After issue of work order; Contractor have to apply for registration in
VMC within 30 days.
v) Work Experience, if necessary…
vi) Other Documents, as required…
INSTRUCTIONS TO BIDDERS
Section 1: Instructions to Bidders
Table of Clauses
Page No. Page No.
A. D. Submission of Bids
1. Scope of Bid 9 19. Sealing & Marking of Bids
2. Source of Funds 9 20. Deadline for Submission of
3. Eligible Bidders 9 21. Late Bids
4. Qualification of the 9 22. Modification and
Bidder Withdrawal of Bids
5. One Bid per Bidder
6. Cost of Bidding 13 E. Bid Opening and Evaluation
7. Site Visit 13 23. Bid Opening
B. Bidding Documents 25. Clarification of Financial
8. Content of Bidding 14 26. Examination of Bids and
Documents Determination of
9. Clarification of Bidding 14 27. Correction of Errors
10. Amendment of Bidding 15 28. Deleted
29. Evaluation and Comparison
of Financial Bids
C. Preparation of Bids 30. Deleted
11. Language of Bid
12. Documents Comprising 16 F. Award of Contract
13. Bid Prices 16 31. Award Criteria
14. Currencies of Bid and Payment 17 32. Employer’s Right to Accept
any Bid and to Reject any or all
15. Bid Validity 17 33. Notification of Award and
Signing of Agreement
16. Bid Security 17 34. Performance Security
17. Alternative Proposals by Bidders 18 35. Advance Payment and
18. Format and Signing of Bid 18 36. Dispute Review Expert
37. Correct or Fraudulent
1. Scope of Bid
1.1 The Employer (Named in Appendix to ITB) invites bids for the Construction of works (as defined in these
documents and referred to as ‘the works”) detailed in the table given in IFB. The bidders may submit bids for
any or all of the works detailed in the table given in IFB.
1.2 The successful bidder will be expected to complete the works by the intended completion date specified in
the Contract data.
1.3 Throughout these bidding documents, the terms ‘bid’ and ‘tender’ and their derivatives (bidder/ tenderer, bid
/ tender, bidding/ tendering, etc.) are synonymous.
2. Source of Funds
2.1 The expenditure on this project will be met from the budget of VMC /Govt. of Gujarat / Govt. of India for
centrally sponsored projects.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all eligible bidders.
3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a statement that the
Bidder is neither associated, nor has been associated, directly or indirectly, with the consultant or any other
entity that has prepared the design, specifications, and other documents for the Project or being proposed as
Project Manager for the Contract. A firm that has been engaged by the Employer to provide consulting
services for the preparation or supervision of the works, and any of its affiliates, shall not be eligible to bid.
4. Qualification of the Bidder
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description
of the proposed work method and schedule, including drawings and charts, as necessary. The proposed
methodology should include a program of construction backed with equipment planning and deployment duly
supported with broad calculations and quality assurance procedures proposed to be adopted justifying their
capability of execution and completion of work as per technical specifications, within stipulated period of
4.5 QUALIFICATION CRITERIA:
(Applicable for the works which require Post Qualification)
4.5.1 Qualification will be based on meeting all the following minimum pass/fail criteria regarding the bidder’s
general and particular experience, personnel and equipment capabilities, and financial position, as demonstrated
by the bidder’s responses in the forms attached. The bidder should be registered in VMC & required class for
State and Central Government, semi government and other Corporations / Boards or such other instuons. Sub-
contractor’s experience and resources shall not be taken into account in determining the bidder’s compliance with
the qualifying criteria.
Eligible Applicants:
The tenders for this contract will be considered only from those bidders (proprietorship firms, partnerships firms,
companies, corporations) who meet requisite qualification criteria prescribed as under. Joint Ventures Shall not be
TECHNICAL CAPABILITIES
PARTICULAR EXPERIENCE
Experience of having successfully completed similar works during last 7 years ending last day of month previous to
the one in which applications are invited should be either of the following: - (Cost shall be derived at current year
price level as per appendix)
A. Three similar completed works costing not less than the amount equal to 40% of the estimated cost.
B. Two similar completed works costing not less than the amount equal to 50% of the estimated cost.
C. One similar completed work costing not less than the amount equal to 80% of the estimated cost.
Note: Definition of “similar work” means any kind of sewerage work completed (Excluding Storm
Water) in any city in India in the Govt./Semi Govt. during last 7 years. Ending last day of month
previous to the one in which tenders are invited.
In addition to this The Bidder Must have experience in execution and completion of sewerage line by
Sinking-Pushing Method / Micro tunneling Method in Min 5 Rmt length in any of Maximum Three
works Physically completed and project certificate shall be submitted having signature of Executive
Engineer or Equivalent.
Only J.V. Partner’s experience shall be considered. He should have acquired the experience of execution
or Major items of works. In case of J.V. experience weight towards experience of the project would be
given to each J.V. partner in proportion to their J.V. percentage. Necessary supporting documents to be
submitted along with tender. Sub contractor’s experience shall not be considered.
In addition to the above, the criteria regarding satisfactory performance of works, personnel,
establishment, plant, equipment etc. may be incorporated according to the requirement of the project.
4.5.2 Base year and Escalation
The base year shall be taken as Current financial year
Following enhancement factors will be used for the costs of works executed and the financial figure to a
common base value for works completed in India.
Last One (25-26)
Last Two (24-25)
Last Three (23-24)
Last Fourth (22-23)
Last Fifth (21-22)
Last Six (20-21)
Last Seven (19-20)
Applicant should indicate actual figures of costs and amount for the works executed by them without
accounting for the above-mentioned factors.
In case the financial figures and value of completed works are in foreign currency the above enhanced
multiplying factors will not be applied. Instead, the current market exchange rate (State Bank of India BC
Selling rate as on the last date of submission of the bid) will be applied for the purpose of conversion of the
amount in foreign currency into India rupees.
4.5.3 General Experience.
The Applicant shall meet with the following minimum criteria:
Average Annual financial turnover during the last 3 years, ending 31st March of the previous financial
year, should be at least 30% of the estimated cost.
Substantially completed works means those works which are at least 90 % completed as on the date of
submission (i.e. gross value of work done up to the last date of submission is 90 % or more of the original
contract price) and continuing satisfactorily. Project certificate shall be submitted having signature of
Executive Engineer or Equivalent.
For these, a certificate from the employers (3A Signed by not below the rank of Executive Engineer or
Equivalent) shall be submitted along with the application incorporating clearly the name of the work,
contract value, billing amount, date of commencement of works, satisfactory performance of the
contractor and any other relevant information.
4.5.4 Personnel Capabilities.
Availability for his work of personnel with adequate experience as required; as per Appendix.
4.5.5 Equipment Capabilities
Based on the studies carried out by the Engineer, the minimum suggested major equipment to attain the
completion of works in accordance with the prescribed construction schedule are shown in the Appendix.
The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction
planning and methodology supported with layout and necessary drawings and calculations to allow the
employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be
shown in the proposals along with the cycle time for each operation for the given production capacity to
match the requirements.
4.5.6 Financial Position
The Applicant should give undertaking that he has access to, or has available, liquid assets (aggregate of
working capital, cash in hand and uncommitted bank guarantees) and / or credit facilities amounting to Rs
17,22,814/- (Without GST).
Note: Also Bank Credit facilities Certificate of the Same Amount from the Bank Shall be Submitted for this
4.5.7 The audited balance sheets for the last five years should be submitted, which must demonstrate the
soundness of the applicant’s financial position, showing long – term profitability including an estimated
financial projection for the next three years, if necessary, the employer will make inquiries with the
applicant’s bankers.
4.5.8 Litigation History
The Applicant should provide accurate information on any litigation or arbitration resulting from contracts
completed or under execution by him over the last five years.
The tender document of any bidder who has been blacklisted by any government / semi-government body
will be outrightly rejected.
4.5.9 Disqualification
Even though the applicants meet the above criteria, they are subject to be disqualified if they have:
Made misleading or false representation in the forms, statements submitted, and / or Record of poor
performance such as abandoning the work, rescinding of contract for which the reasons are attributable to
the non – performance of the contractor; consistent history of litigation awarded against the applicant or
financial failure due to bankruptcy.
4.7 Bid Capacity
Applicants who meet the minimum qualification criteria will be qualified only if their available bid capacity at
the expected time of bidding is more than the total estimated cost of the works. The available bid capacity will
be calculated as under:
Assessed Available Bid Capacity = (A*N*2‐B), where
A = Maximum value of work executed in any one year during the last five years (updated to the price level of
the year indicated in appendix) taking into account the completed as well as works in Progress.
B = Value at current price level of the existing commitments and ongoing works to be completed during the
next (period of completion of work for which bids are invited); and
N = Number of years prescribed for completion of the works for which the bids are invited.
Bid capacity will be more applicable for works costing more than 1 crore.
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
• Made misleading or false representation in the forms, statements and Attachments the submitted in proof
the qualification requirements; and / or
• Record of poor performance such as abandoning the works, not properly completing the contract,
inordinate delay in completion, litigation history, or financial failures etc.; and/ or
• Participated in the previous bidding for the same work and had quoted unreasonably high bid prices and
could not furnish rational justification to the employer.
5. One bid per bidder
5.1 Each bidder shall submit only one bid for one package. A bidder who submits or participates in more than one
bid (other than as a subcontractor or in cases of alternatives that have been permitted or requested) will cause all
the proposals with the bidder’s participation to be disqualified.
6. Cost of Bidding
6.1 The bidder shall bear all costs associated with the preparation and submission of his Bid, and the Employer
will in no case be responsible and liable for those costs.
7.1 The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and examine the Site of work
and its surrounding and obtain all information that may be necessary for preparing the Bid and entering into a
contract for construction of the Works.
The costs of visiting the site shall be at the Bidder’s own expense.
B. BIDDING DOCUMENTS
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed below and addenda issued in accordance
with Clause 10:
Section Particulars Volume No.
- Invitation for Bids
1 Instructions to Bidders I
2 Qualification Information, and other forms
3 Conditions of Contract
4 Contract Data
5 Technical Specifications II
6 Form of Bid III
7 Bill of Quantities
8 Securities and other forms
10 Documents to be furnished by bidder V
8.2 Volumes I, II, III and IV are available online and documents to be furnished by the bidder in compliance
to section 2 will be prepared by him and furnished as Volume- V in two parts (refer clause 12).
8.3 The bidder is expected to examine carefully all instructions, conditions of contract, contract data, forms,
terms, technical specifications, bill of quantities, forms, Annexes and drawings in the Bid Document.
Failure to comply with the requirements of Bid Documents shall be at the bidder’s own risk. Pursuant to
clause 26 hereof, bids which are not substantially responsive to the requirements of the Bid Documents
shall be rejected.
9.0 Clarification Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents may notify the Employer in
writing or through E-mail at the Employer’s address indicated in the invitation to bid. The Employer will
respond to any request for clarification which he received earlier than 15 days prior to the deadline for
submission of bids. Employer’s response will be published on website including a description of the
enquiry but without identifying its source.
9.2 Pre‐bid meeting
9.2.1 The bidder or his official representative is invited to attend a pre-bid meeting which will take place
at the address, venue, time and date as indicated in the appendix.
9.2.2 The purpose of the meeting will be to clarify issues and to answer questions on any matter that may
be raised at that stage.
9.2.3 The bidder shall be required to submit any questions in writing or e-mail to reach the Employer not
later than 03 days before the meeting.
9.2.4 Minutes of the meeting, including the question raised (Without identifying the source of enquiry)
and the responses given will be published without delay on the tender website i.e.
tender.nprocure.com. Any modification of the bidding documents listed in sub-Clause 8.1 which
may become necessary as a result of the pre-bid meeting shall be made by the Employer
exclusively through the issue of an Addendum pursuant to Clause 10 and not through the minutes
of the pre-bid meeting.
9.2.5 Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
10.0 Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding documents by
issuing addenda.
10.2 Any addendum thus issued shall be part of the bidding documents. The Employer will assume no
responsibility for the same.
10.3 To give prospective bidders reasonable time in which to take an addendum into account in
preparing their bids, the Employer may, at his discretion, extend as necessary the deadline for
submission of bids, in accordance with Sub-Clause 20.2 below.
C. PREPARATION OF BIDS
11.0 Language of the Bid
11.1 All documents relating to the bid shall be in the English language.
12.0 Documents Comprising the Bid
12.1.1 The bid be submitted by the bidder as Volume V of the bid document (refer Clause 8.1) shall be
in two separate parts:
Part I shall be named “Technical Bid” and shall comprise
i) Bid Security in the form specified in Section
ii) Qualification Information and supporting documents as specified in Section
iii) Certificates, undertakings, affidavits as specified in Section
iv) Any other information pursuant to Clause 4.5 of these instructions
v) Undertaking that the bid shall remain valid for the period specified in Clause
Part I shall be named “Technical Bid” and shall comprise
i.) Form of Bid as specified in Section
ii.) Priced Bill of Quantities for items specified in Section
12.1.2 The Bidder shall submit the details / information pertaining to each part i.e. technical as well as
financial and must be submitted online only.
12.1.3 Following documents will be deemed to be part of the bid.
Section Particulars Volume No.
- Invitation for Bids
1 Instructions to Bidders I
2 Qualification Information, and other forms
3 Conditions of Contract
4 Contract Data
5 Technical Specifications II
6 Form of Bid III
7 Bill of Quantities
8 Securities and other forms
10 Documents to be furnished by bidder V
13.0 Bid Prices
13.1 The Contract shall be for the whole works as described in Sub-Clause 1.1, based on the priced Bill of
Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line-item total (both in figures and words) for all items of the
Works described in the Bill of Quantities along with total bid price 13.3 (Both in figures and words).
Items for which no rate or price is entered by the bidder will not be paid for by the Bill of Quantities.
13.3 All duties, taxes, and other levies except GST payable by the contractor under the contract, or for any
other cause shall be included in the rates, prices and total Bid Price submitted by the Bidder. (GST will
13.4 All bank guarantee / insurance policies etc., shall be deposited on amount of project cost including GST
(VMC changes shall be applicable).
13.5 The rates and prices quoted by the bidder are subject to adjustment during the performance of the
Contract in accordance with the provisions of Clause 47 of the Condition of Contract (Irrespective of the
time limit and Bid Amount)
14.0 Currencies of Bid and Payment
14.1 The unit rates and the prices quoted by the bidder shall be entirely in Indian Rupees. All payments
shall be made in Indian Rupees.
15.0 Bid Validity
15.1 Bids shall remain valid for a period of not less than 120 days after the deadline date forbid
submission specified in Clause
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may request
that the bidders may extend the period of validity for a specified period. A bidder may refuse the
request without forfeiting his bid security. A bidder agreeing to the request will not be required or
permitted to modify his bid, but will be required to extend the validity of his security for a period of
the extension, and in compliance with Clause 16 in all respects.
16.0 Bid Security
16.1 Bid Security (EMD) is equal to 2% of Estimated Amount put to bid / tender and should be rounded
off to the next thousand rupees. Bid security for the work costing up to Rs. 1 crore shall be deposited
in form of DD (demand draft) and for works costing above Rs. 1 crore bank guarantee shall be
The bid must be accompanied by the bid security as specified and shown in Table SCHEDULE OF
TENDERING Sr. No. 2(B) above. The Bid Security shall be in one of the following forms:
Demand Draft payable to Municipal Commissioner, Vadodara issued by any nationalized bank/RBI
approved bank / Scheduled bank as per the list attached in tender only. OR
An unequivocal and unconditional Bank Guarantee in the prescribed format given in this document
issued by any Nationalized Bank/RBI approved bank / Scheduled bank as per the list attached in tender
only for a validity period of 45 days (ie.120+45 = 165 days) beyond the validity of the bid. (EMD)
Exemption Certificate will not be accepted)
16.2 Bank guarantees (and other instruments having fixed validity) issued as surety for the bid shall be
valid for 45 days beyond the validity of the bid i.e. total validity of 120+45 = 165 Days
16.3 Any bid not accompanied by an acceptable Bid Security and not secured as indicated in Sub-Clauses
16.1 and 16.2 above shall be rejected by the Employer as non-responsive.
16.4 The Bid Security of unsuccessful bidders except 2nd lowest, will be returned within 28 days of the
end of the bid validity period specified in Sub-Clause
Bid Security of 2nd lowest bidder shall be released after work order is given to 1st lowest.
16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed the
Agreement and furnished the required Performance Security.
16.6 The bid Security may be forfeited
a) If the Bidder withdraws the bid after Bid opening during the period of Bid validity.
b) If the Bidder does not accept the correction of the Bid Price, if any or
c) In the case of a successful Bidders, if the Bidder fails the specified time limit to
i) Sign the Agreement; or
ii) Furnish the requirement Performance Security.
d) If found necessary, the bidder will be intimated for negotiation, He will be intimated maximum three
times within the validity period for negotiation, if contractor does not respond in time, his Bid
Security (EMD) will be forfeited and his tender will be rejected. Punitive action will be taken on such
contractors. (As per GoG R&B Dept’s Gr. No. S/22/2017/6369/D, Dt.08/06/2018)
17.0 Alternative Proposals by Bidders.
17.1 Bidders shall submit offers that fully comply with the requirements of the bidding documents, including
the conditions of contract (including mobilization advance or time for completion), basic technical design
as indicated in the drawing and specifications. Conditional offers or alternative offers will not be
considered further in the process of tender evaluation.
18. Format and Signing of Bid
18.1 The Bidder shall prepare documents comprising the bid as described in Clause 12 of these Instructions
to bidder as the “Technical Bid “and “Financial Bid” in separate parts to be uploaded.
D. SUBMISSION OF BIDS
20. Deadline for Submission of the Bids
20.1 Complete Bids must be received online by the Employer at the tender website specified above not later
than the date indicated in appendix.
20.2 The Employer may extend the deadline for submission of bids by issuing an amendment in accordance with
Clause 10, in which case all right and obligation of the Employer and the bidders previously subject to the
original deadline will then be subject to the new deadline.
22. Modification and Withdrawal of Bids
22.1 Bidders may modify or withdraw their bids online before the deadline prescribed in Clause 20 or
pursuant to Clause
22.3 No bid shall be modified or withdrawn after the deadline for submission of Bid.
22.4 Withdrawal or modification of a bid between the deadline for submission of bids and the expiration of
the original period of bid validity specified in Clause 15.1 above or as extended pursuant to Clause
may result in the forfeiture of the Bid security pursuant to Clause
E BID OPENING AND EVALUTION
23. Bid Opening
23.1 The Employer will open all the Bids received including modifications made pursuant to Clause 22, in
the presence of the Bidders or their representatives who choose to attend at time, date and the place
specified in Appendix in the manner specified in Clauses 20 and 23.3, In the event of the specified date
of Bid opening being declared a holiday for the Employer, the Bids will be opened at the appointed
time and location on the next working day.
23.3 The “Technical Bid” shall be opened. The amount, form and validity of the bid security furnished with
each bid will be announced. If the bid security furnished does not conform to the amount and validity
period as specified in the invitation for bid (ref. Column 4 and paragraph 3), and has not been furnished
in the form specified in Clause 16, the technical bid will not be opened.
23.4 i) Subject to confirmation of the bid security by the issuing Bank, the bids accompanied with
valid bid security will be taken up for evaluation with respect to the Qualification
information and other information furnished in part I of the bid pursuant to Clause 12.1.
iii) If required, the bidder will be asked in writing to clarify his Qualification Documents with
respect to any required clarification.
iv) The bidders will respond in not more than 7 days of issue of the clarification letter.
v) Immediately (usually within 3 or 4 days), on receipt of these clarification the Evaluation
Committee will finalize the list of responsive bidders whose financial bids are eligible for
23.6 At the time of opening of “Financial Bid”, the names of the bidders were found responsive in
accordance with Clause 23.4(iv) will be announced. The bids of only these bidders will be opened. The
responsive Bidders’ names, the Bid prices, the total amount of each bid, any discount and such other
responsive Bidders’ names, the Bid prices, the total amount of each bid, any discount and such other
details as the Employer may consider appropriate, will be announced by the Employer at the opening.
23.7 the time of opening of “Financial Bid”, the names of the bidders were found responsive in accordance
with Clause 23.4(iv) will be announced. The bids of only these bidders will be opened. The responsive
Bidders’ names, the Bid prices, the total amount of each bid, any discount, and such other details as the
Bidders’ names, the Bid prices, the total amount of each bid, any discount, and such other details as the
Employer may consider appropriate, will be announced by the Employer at the opening.
23.8 In case bids are invited for more than one package, the order for opening of the “Financial Bid” shall
be in order of Estimated Amount of Bids from highest to lowest.
23.9 The Employer shall prepare minutes of the Bid opening, including the information disclosed to those
present in accordance with Sub-Clause 23.6.
24.1 Information relating to the examination, clarification, evaluation, and comparison of Bids and
recommendations for the award of a contract shall not be disclosed to Bidders or any other persons not
officially concerned with such process until the award to the successful Bidder has been announced.
Any effort by Bidder to influence the Employer’s processing of Bids or award decisions may result in
the rejection of his Bid.
25. Clarification of Financial Bids
25.1 To assist in the examination, evaluation, and comparison of Bids, the Employer may, at his discretion,
ask any Bidder for clarification of his Bid, including breakdowns of unit rates. The request for
clarification and the response shall be in writing or by e- mail, but no change in the price or substances
of the Bid shall be sought, offered, or permitted except as required to confirm the correction of
arithmetic errors discovered by the Employer in the evaluation of the Bids.
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to his Bid
opening to the contract is awarded. If the Bidder wishes to bring additional information to the notice of
the Employer, it should do so in writing.
25.3 Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid comparison or
contract award decision may result in the rejection of the Bidders’ bid.
26. Examinations of Bids and Determination of Responsiveness
26.1 During the detail evaluation of "Technical Bid", the Employer will determine whether each Bid (a)
meets the eligibility criteria defined in Clause 3 and 4; (b) has been properly signed; (c) is accompanied
by the required securities and; (d) is substantially responsive to the requirements of the Bidding
document. During the detailed evaluation of the “Financial Bid”, the responsiveness of the bids will be
further determined with respect to the remaining bid conditions, i.e., priced bill of quantities, technical
specifications, and drawings.
26.2 A substantially responsive “Financial Bid” is one which confirms all the terms, conditions and
specifications of bidding documents, without material deviation or reservation. A material deviation or
reservation is one (a) which affects in any substantial way the scope, quality, or performance of the
Works; (b) which limits in any substantial way, inconsistent with the Bidding documents, the
Employer’s rights or the Bidder’s obligations under the Contract; or (c) whose rectification would affect
unfairly the competitive position of other Bidders presenting substantially responsive Bids.
26.3 If a “Financial Bid” is not substantially responsive, it will be rejected by the Employer, and may not
subsequently be made responsive by correction or withdrawal of the non-conforming deviation or
29. Evaluation and Comparison of Financial Bids
29.1 The Employer will evaluate and compare only the Bids determined to be substantially responsive in
accordance with Sub-Clause 26.2.
29.3 The Employer reserves the right to accept or reject any variation or deviation. Variation and deviations
and other factors, which are in excess of the requirements of the Bidding documents or otherwise result
in unsolicited benefits for the Employer, shall not be taken in to account in Bid evaluation.
29.4 The estimated effect of the price adjustment conditions under Clause 47 of the Conditions of Contact,
during the period of implementation of the Contract, will not be taken in to account in Bid evaluation.
29.5 If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer’s estimate of the
cost of work to be performed under the contract the Employer may require the Bidder to produce detailed
consistency of those prices with the construction methods and schedule proposed. After evaluation of the
price analyses, the Employer may require that the amount of the performance security set forth in Clause
34 be increased at the expense of the successful /bidder to a level sufficient to protect the Employer
against financial loss in the event of default of the successful Bidder under the Contract.
29.6 A bid which contains several items in the bill of Quantities which are unrealistically priced low and
which cannot be substantiated satisfactorily by the bidder may be rejected as non-responsive.
F. AWARD OF CONTRACT
31. Award Criteria
31.1 Subject to Clause 32, the Employer will award the contract to the Bidder whose Bid has been determined.
i) to be substantially responsive to the Bidding documents and who has offered the lowest evaluated
ii) to be within the available bid capacity adjusted to account for his bid price which is the lowest
evaluation in any of the packages opened earlier than the one consideration.
In no case, the contract shall be awarded to any bidder whose available bid capacity is less than the
evaluated bid price, even if the said bid is the lowest evaluated bid. The contract will in such cases be
awarded to the next lowest bidder at his evaluation bid price.
32. Employer’s Right to Accept any Bid and to Reject any or all Bids
32.1 Notwithstanding Clause 31, the Employer reserves the right to accept or reject any Bid, and to cancel
the Bidding process and reject all Bids, at any time prior to the award of contract, without thereby
incurring any liability to the affected bidder or Bidder or any obligation to inform the affected Bidder or
Bidders of the grounds for the Employer’s action.
33. Notification of Award and Signing of Agreement
33.1 The Bidder whose Bid has been accepted will be notified of the award by the Employer prior to
expiration of the Bid validity period by cable, telex or facsimile confirmed by registered letter. This
letter (hereinafter and in the condition of contract called the “Letter of Acceptance”) will state the sum
that the Employer will pay the Contractor in consideration of the execution, completion, and
maintenance of the Works by the Contractor as prescribed by the Contract (hereinafter and in the
Contract called the “Contract Price”).
33.2 The notification of award will constitute the formation of the contract, subject only to the furnishing of a
performance security in accordance with the provisions of Clause
33.3 The Agreement will incorporate all agreements between the Employer and the successful Bidder. It will
be signed by the Employer and to the successful Bidder, within 28 days following the notification of
award along with the Letter of Acceptance. Within 21 days of receipt, the successful Bidder will sign
the Agreement and deliver it to the Employer.
33.4 Upon the furnishing by the successful Bidder of the Performance Security, the Employer will promptly
notify the other Bidders that their Bids have been unsuccessful.
34. Performance Security
34.1 A) Within 15 (Fifteen) days of receipt of Letter of Acceptance, the successful Bidder shall furnish to
the Employer an Irrevocable and unconditional guarantee from a Bank in the form set forth in
Section 8 (the “Performance Security/ Security Deposit”) for
a. an amount equal to 5% (five percent) of its Contract Price (capital cost + GST) in the form of
Demand Draft / Bank Guarantee of the R.B.I. approved Nationalized Bank/Scheduled Bank as per
attached List in (DOCUMENTS TO BE FURNISHED BY BIDDER, VOLUME - V) on award of
b. 2% of its Contract value (Capital cost + GST) in the form of security deposit submitted in the form
of DD/BG or the Contractor’s EMD can be converted in the form of security deposit on award of
work + remaining 3% of its contract value (Capital cost + GST) shall be deducted from the running
bills of the work to be retained against remaining security deposit.
Failure to submit performance security within 15 days shall impose penalty at 6% per Annum for any
additional delayed days (as per VMC circular) in case of bids mentioned below, the successful Bidder,
along with the Performance Security, shall also furnish to the Authority an irrevocable and
unconditional guarantee from a Bank in the same form given at Section 8 towards an Additional
Performance Security (The “Additional Performance Security”) for an amount calculated as under:
a. If the Contract Price (Capital cost + GST) offered by the Selected Bidder is lower than 10% but
upto 20% of the Estimated Project Cost (Capital cost + GST), then the Additional Performance
Security shall be calculated @ 20% of the difference in the
i.) Estimated Project cost (Capital cost + GST) (as mentioned in Bid Document) – Minus
10% of the Estimated Project Cost (Capital cost + GST), and
ii.) Contract Price (Capital cost + GST), offered by the selected Bidder.
b. If the Contract Price (Capital cost + GST) offered by the Selected Bidder is lower than 20% of
the Estimated Project Cost (Capital cost + GST)., then the Additional Performance Security shall
be calculated @30% of the difference in the
i.) Estimated Project cost (Capital cost + GST) (as mentioned in Bid Document) – Minus
10% of the Estimated Project Cost (Capital cost + GST), and
ii.) Contract Price (Capital cost + GST), offered by the selected Bidder.
c. This Additional Performance Security shall be treated as part of the Performance Security.
B) The Performance Security shall be valid beyond 60 (Sixty) days from the stipulated date of completion of
the project and the Additional Performance Security shall be valid beyond 28 (twenty-eight) days of
Project Completion Date.
Performance Security shall become refundable/releasable within 15 days after certified project
completion date subject to Fulfillment of contractual obligation and settlement of all dues and claims.
34.2 If the performance security is provided by the successful Bidder in the form of a Bank Guarantee, it
shall be issued either (a) at the Bidder’s option, by a Nationalized/Scheduled Indian bank or (b) by a
foreign bank located in India and acceptable to the Employer. As per GoG Finance Department’s
Circular No. FD/MSM/e-file/4/2023/4020/D.M.O. Date 11/03/2024 or as per their latest amendment.
(as per list attached here with as per GOG GR).
34.3 Failure of the successful Bidder to comply with the requirement of Sub-Clause 34.1 shall constitute
sufficient grounds for cancellation of the award and forfeiture of the Bid Security
35. Advance Payment and Security
35.1 The Employer will provide an Advance payment on the Contract Price as stipulated in the Conditions
of Contract, subject to maximum amount, as stated in the Contract Data.
37. Corrupt of Fraudulent Practices
37.1 The Employer will reject a proposal if it determines that the Bidder recommended for award has
engaged in corrupt or fraudulent practices in completing for the contract in question and will declare the
firm ineligible, either indefinitely or for a stated period of time, to be awarded a contract with National
Highways Authority of India/ State PWD and any other agencies, if it at any time determines that the
firm has engaged in corrupt or fraudulent practices in completing for the contractor, or in execution.
37.2 Furthermore, Bidders shall be aware of the provision stated in Sub- Clause 59.2 of the Conditions of
APPENDIX TO ITB
Clause Reference
With respect to Section –I
1. The Name of the Employer is Executive Engineer, Drainage [ Cl.1.1]
2. The last seven years.
3. This Average Annual Financial Turnover Amount is Rs. [Cl.4.5.3 (a)]
17,22,814/- (avg annual turnover during last 3 years) (ie 30%
if estimated cost)
4. Value of Work is Rs. 93,29,558 /-
5. The cost of electric work is Rs. NA
6. The cost of water supply / sanitary works is Rs. NA
7. Liquid assets and / or availability of credit [Cl.4.5.6 ]
facilities is Rs. …………(25% of value of contract)
8. Price level of the financial year 2025-2026 (base year) [Cl. 4.5.2]
9. The pre-bid meeting will take place at Office of Execuve [Cl. 9.2.1]
Engineer, Drainage Project, Room No. 204, Second floor,
Vadodara Municipal Corporation, Khanderao Market
Building, Rajmahal Road, Vadodara - 390
10. The technical Bid will be opened at the office of the
Executive Engineer, Drainage Project on dt 17/06/2026
11. Address of the Employer: Drainage Project, Room No.
Second floor, Vadodara Municipal Corporation, Khanderao
Market Building, Rajmahal Road, Vadodara - 390
13. The bid should be submitted latest by 20/02/2026 [Cl. 20.1 & 20.2]
As stated on online NIT
14. The bid will be opened at 05/02/2026
As stated on online NIT [Cl. 23.1 ]
15. The Bank Draft in favor of Municipal Commissioner, VMC
17. Escalation factors (for the cost of works executed and [Cl.4.5.2]
financial figure to a common base value) for works
Last One (25-26)
Last Two (24-25)
Last Three (23-24)
Last Fourth (22-23)
Last Fifth (21-22)
Last Six (20-21)
Last Seven (19-20)
#LIST OF KEY PLANT & EQUIPMENT TO BE DEPLOYED ON CONTRACT WORK
[Reference CL. 4.5.5]
The contractors shall also give a list of machineries in his possession and which they propose to use on the
Sr. Plant or Machinery Location Age of Make Capacity Approximate Remark
No. Machinery Value
1 Excavator Machines -1 Nos
2 Trucks/Tipper/ Tractor -
3 Dewatering pump (5-25 hp)
4 The Theodolite & Leveling
instruments - 1 Nos
5 Hydra Machine -1 Nos
6 Welding set - 2 Nos
7 Generator - 1 Nos
8 Vibrator 60 mm & 40 mm -
9 Concrete Mixer Machine -
10 Reinforcement Cutting /
Bending Machine - 1 Nos
11 Multi-Gas Monitor - 1 Nos
List of Key Personnel to be deployed on Contract Work
(Reference Cl. 4.5.4)
The Bidder must have suitably qualified personnel, to fill the following position. The Bidder will supply
information on a prime candidate and an alternate for each position, both of whom should meet the experience
requirements specified below for work involved:
Experience in Similar Works
Position (Nos.) Total Experience in year
Construction Engineer (1) 5
Supervisor (1) 3
MINIMUM REQUIREMENT OF EQUIPMENTS: 1) Auto Level: 1 No. (With Complete Set)
Note: As per site requirements during execution of work simultaneously agency shall have to depute Site
Engineers for full time. In the Absence Rs. 1000/- per Day will be deducted from Bill for one Site Engineer.
QUALIFICATION INFORMATION
QUALIFICATION INFORMATION
The information to be filled in by the Bidder in the following pages will be used for the purpose of post
qualification as provided for in Clause 4 of the Instruction to Bidders. This information will not be
incorporated in the Contract.
1. For Individual Bidders
1.1 Constitution or legal status of Bidder
Place of registration _______________________
Principal place of business ________________________
Power of attorney of Signatory of Bid
1.2 Total value of Civil engineering construction 2025-2026
work performed in the last Seven years 2024-2025
(in Rs. Lakhs) 2023-2024
1.3 Work performed as prime contractor, work performed in the past as a nominated sub-contractor will also
be considered the sub – contract involved execution of all main items of work described in the bid
documents, provided further that all other qualification criteria are satisfied (in the same name) on works
of a similar nature over the last five years** and in current year before the submission of the bid.
Name of of Stipulated Actual Date
Project Description Contract issue reasons for
the contract period of of
Name of work No. of delay &
Employer (Rs. completion completion*
order completed
* Attach certificate(s) from the Engineer(s) in-charge
** Immediately preceding the financial year in which bids are received.
1.3.2 ONGOING WORKS
Contractor’s liability to complete ongoing works. Contractor shall submit list of ongoing work in a given
Performa (Annexure-6)
Sr. No. Name of Work Order Date of Date of Percentage of work Reason of
Work Amount work order completion completed Delay
Physical Financial
1.4 Information on Bid Capacity (works for which bids have been submitted and works which are yet to be
completed) as on the date of this bid.
(A) Existing commitments and on-going works:
Descripon Place & Contract Name & Value Spulated Value of Ancipated
of works State No. Address Contract Period of works* date of
of (Rs. Cr) Compleon remaining compleon
*Attach certificate (s) from the Engineer(s) in-charge
**Immediately preceding the financial year in which bids are received.
1.5 Availability of key items of Contractor Equipment for carrying out the works (Ref. Clause 4.5.5). The Bidder
should list all the information requested below.
Item of Requirement Availability Proposals Remarks
Equipment (from whom
No. Capacity Owned / Nos. / Age /
Leased to Capacity Condions
1.6 Qualification and experience of key personnel required for administration and execution of the contract.
Attach biographical data. Refer also to Sub Clause 9.1 of the Conditions of Contract.
Position Name Qualification Year of Year of experience in
Experience the proposed position
Project Manager
1.7 Proposed sub-contract and firms involved
Sections of the works Value of Sub - Sub – Contractor Experience in similar
Contractor (Name & Address) work
Attach copies of certificates on possession of valid license for executing water supply / sanitary work / building
electrification works.
1.8 Financial reports for the last five years: balance sheets, profit and loss statements, auditors’ reports (in case
of companies / corporations), etc. List them below and attach copies.
1.9 Evidence of access to financial resources to meet the qualification requirements: cash in hand, lines of
credit, etc. List them below and attach copied documents.
1.10 Name, address, and telephone, telex, and fax numbers of the Bidders bankers who may provide references
if contacted by the Employer.
1.11 Information on Litigation history in which the Bidder is involved.
Other Party (ies) Employer Cause of Dispute Amount Involved Remarks showing Present
1.12 Statement of compliance under the requirements of Sub Clause 3.2 of the instruction to Bidders. (Name of
Consultant engaged for project preparations is *………….)
1.13 Proposed work method and schedule. The Bidder should attach descriptions, drawings and charts as
necessary to comply with the requirements of the Bidding documents. {Refer ITB Clause 4.1}
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the requirements of Clause 4 of the
Instructions to the Bidders, if applicable.
(ii) Undertaking
* Fill the name of consultant
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR
AVAILABILITY OF CREDIT FACILITIES
(CLAUSE 4.5.6 OF ITB)
BANK CERTIFICATE
This is to certify that M/s. _______________________________________ is a reputed company with a good
financial standing.
If the contract for the work, namely ________________________________ is awarded to the above firm, we
shall be able to provide overdraft / credit facilities to the extent of Rs.__________ to meet their working
capital requirements for executing the above during the contract period.
Senior Bank Manager
Address of the Bank
1. I, the undersigned, do hereby certify that all the statements made in the required attachments are true and
2. The undersigned also hereby certifies that neither our firm M/s. _______________________ have not
abandoned any work of Government of Gujarat / Government of India / any Board or Corporation under
Government of Gujarat / Government of India nor any contract awarded to us for such works have been
rescinded, during last five years prior to the date of this bid.
3. The undersigned hereby authorize(s) and request (s) any bank, person, firm or corporation to furnish
pertinent information deemed necessary and requested by the Department to verify this statement or
regarding any (our) competence and general reputation.
4. The Undersigned understands and agrees that further qualifying information may be requested, and agrees to
furnish any such information at the request of the Department / Project implementing agency.
(Signed by an Authorized Officer of the Firm)
Title of Officer
I, the undersigned do hereby undertake that our firm M/s. ………………………………………would invest a
minimum cash up to 25% of the value of the work during implementation of the contract.
(Signed by an Authorized officer of the firm)
Title of officer
CONDITIONS OF CONTRACT
Condions of Contract
A General Page D. Cost Control
1 Definitions 37 37 Bill of Quantities
2 Interpretation 38 38 Changes in the Quantities
3 Language and Law 39 39 Variations
4 Engineer’s Decisions 39 40 Payments for Variations
5 Delegations 39 41 Cash Flow Forecasts
6 Communications 39 42 Payment Certificates
7 Sub-Contractors 39 43 Payments
8 Other Contractors 39 44 Compensations Events
9 Personnel 40 45 Tax
10 Employer’s & Contractor Risk 40 46 Currencies
11 Employers Risks 40 47 Price Adjustment
12 Contractor’s Risk 40 48 Retention
13 Insurance 40 49 Liquidated damages
14 Site Investigations Reports 41 50 Bonus
15 Queries about the Contract 41 51 Advance Payment
16 Contractors to Construct the works 41 52 Securities
17 The Works to be Completed By 41 53 Deleted
the Intended Completion Date
18 Approval by the Engineer 41 54 Cost of Repair
20 Discoveries 42 E. Finishing the Contract
21 Possession of the Site 42 55 Completion
22 Access to the Site 42 56 Taking Over
23 Instructions 42 57 Final Account
24 Disputes 42 58 Operating and Maintenance
25 Procedure for Disputes
26 Deleted 43 59 Terminations
60 Payment upon Terminations
B. Time Control 61 Property
27 Programme 44 62 Release from Performance
28 Extensions of the Intended
completion date
29 Deleted 44 F. Special Conditions of
30 Delays Ordered by The 44 63 Labour
Engineer 64 Compliance with labour
31 Management Meetings 45 65 Arbitration
32 Early Warning
C. Quality Control
33 Identifying Defects
35 Correction of Defects
36 Uncorrected Defects
CONDITIONS OF CONTRACT
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of Contract but
keep their defined meaning.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the Bid.
Compensation Events are those defined in Clause 44 hereunder
The Completion Date is the date of completion of the Works as certified by the Engineer in accordance with
The Contract is the contract between the Employer and Contractor to execute, complete and maintain the
Works till the completion of Defects Liability Period. It consists of the documents listed in Clause
The Contract data defines the documents and other information which comprise the Contract.
The Contractor is a person or corporate body whose Bid to carry out the Work has been accepted by the
The Contractor’s Bid is the completed Bidding document submitted by the Contractor to the Employer and
includes Technical and Financial Bids.
The Contract Price is the price stated in the Letter of Acceptance and thereafter as adjusted in accordance
with the provisions of the Contract.
Days are calendar days: months are calendar months.
The Defects Liability Period is the period named in the Contract Data and calculated from the Completion
The Employer is the party who will employ the Contractor to carry out the Works.
The Engineer is the person named in the Contract Data (or any other competent person appointed and notified
to the contractor to act in replacement of the Engineer) who is responsible for supervising the Contractor,
administering the Contract, certifying payments due to the Contractor, issuing and valuing the Compensations
Equipment is Contractor’s machinery and vehicles brought temporarily to the site to construct the Works.
The Initial Contract Price is the Contract Price listed in the Employer’s Letter of Acceptance.
The Intended Completion Date is the date on which it is intended that the Contractor shall complete the
Works. The Intended Completion Date is specified in the Contract Data. The Intended Completion Date may
be revised only by the Engineer by issuing an extension of time.
Materials are all supplies, including consumables, used by the contractor for incorporation in the works.
Plant is any integral part of the work which is to have mechanical, electrical, electronic or chemical or
biological functions.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the Bidding documents and are factual
interpretive reports about the surface and subsurface conditions at the site.
Specifications means the Specifications of the works included in the Contract and any modification or
addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the Contractor shall commence execution of
the works. It does not necessarily coincide with any of the Site Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with the Contractor to carry out a part of
the work in the Contract which includes work on the Site.
Temporary Works are works designed, constructed, installed and removed by the Contractor which are
needed for construction or installation of the Works.
A Variation is an instruction given by the Engineer, which varies the Works.
The Works are what the Contract requires the Contractor to construct, install, and turn over to the Employer
as defined in the Contract Data.
2. Interpretation
2.1 Interpreting these Conditions of Contract, singular also means plural, male also means female or neuter
and the other way around. Heading have no significance. Words have their normal meaning under the
language of the Contract unless specifically defined. The Engineer will provide instructions clarifying
queries about Conditions of Contract.
2.2 If sectional completion is specified in the Contract Data, references in the Conditions of Contract to the
Works, the Completion date, and Intended Completion Date apply to any Section of the Works (other
than references to the Completion Date and Intended Completion date for the whole works)
2.3 The documents forming the Contract shall be interpreted in the following order of priority
(2) Letter of Acceptance, notice to proceed with works
(3) Contractor’s Bid
(4) Contract Data
(5) Conditions of Contract including Conditions of Contract
(6) Specifications
(8) Bills of quantities and
(9) Any other document listed in the Contract Data as forming part of the Contract.
3. Language and Law
3.1 The language of the Contract and the law governing the Contract are stated in the Contract Data.
4. Engineers Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters between the
Employer and the Contractor in the role representing the Employer.
5.1 The Engineer may delegate any of his duties and responsibilities to other people after notifying the
Contractor and may cancel any delegation after notifying the Contractor.
6. Communications
6.1 Communications between parties which are referred to in the conditions are effective only when in
writing. A notice shall be effective only when it is delivered (in terms of Indian Contract Act).
7. Sub – Contracting
7.1 The Contractor may subcontract any portion of work, upto a limit specified in contract data, with the
approval of the engineer but may not assign the Contract without the approval of Employer in writing.
Subcontracting shall not alter the Contractor’s obligations. Sub-contracting of supply or specific
items of work is not allowed.
7.2 The sub-contractor must be registered in appropriate class and category for the part of work to be
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other contractors, public authorities, utilities and
the Employer between the dates given in the Schedule of other Contractor. The Contractors shall as
refer to in the Contract Data, also provide facilities and services for them as described in the Schedule.
The employer may modify the schedule of other contractors and shall notify the contractor of any such
9.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel as referred to
in the Contract Data to carry out the function stated in the Schedule or other personnel approved by the
Engineer. The Engineer will approve any proposed replacement of key personnel only if their
qualifications, abilities, and relevant experience are substantially equal to or better than those of the
personnel listed in the Schedule.
9.2 If the Engineer asks the Contractor to remove a person who is a member of the Contractor Staff or his
work force stating the reasons the Contractor shall ensure that the person leaves the Site within seven
days and has no further connection with the work in the Contract.
10. Employer’s and Contractor Risks
10.1 The Employer carries the risk which these Contract states are Employer’s risks, and the Contractor
carries the risks which these Contracts states are Contractor’s risk.
11. Employer’s Risks
11.1 The Employer is responsible for the excepted risks which are (a) in so far as they directly affect the
execution of the Works, the risks of war, hostilities, invasion, act of foreign enemies, rebellion,
revolution, insurrection or military or usurped power, civil war, riot commotion or disorder (unless
restricted to Contractor’s employees), and contamination from any nuclear fuel or nuclear waste or
radioactive toxic explosive.
12. Contractor’s Risks
12.1 All risks or loss or damages to physical property and of personal injury and death which arise during
and in consequence of the performance of the Contract other than the excepted risks are the
responsibility of the Contractor.
13.1 The Contractor shall provide, in the joint names of the Employer and the Contractor, insurance cover
from the Start date to the end of the Defects Liability Period, in the amounts and deductibles stated in
the Contract data for the following events which are due to the Contractor’s risks:
(a) Loss of or damage to the works, Plant and materials,
(b) Loss of or damage to Equipment
(c) Loss of or damages of property (expect the Works, Plant, Materials and Equipment) in
connection with the Contract; and
(d) Personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for the
Engineer’s approval before the Start Date. All such insurance shall provide for compensation to be
payable in the types and proportions of currencies required to rectify the loss or damage incurred.
13.3 Within a month of receipt of the notification of award (Letter of Intent Acceptance) from the Employer,
the successful bidder shall furnish Insurance / CAR policy to the Employer. If the Contractor fails to
submit the policy by the stipulated date, Penalty shall be imposed on the contractor as per VMC rules.
If Contractor does not provide any of the Insurance/ CAR policies and certificates required, RA bill
from the Contractor will not be processed.
13.4 Alterations to the terms of an insurance shall not be made without the approval of the Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies.
13.6 The Contractor shall insure against such liability and shall continue such insurance during the whole of the
time that any persons are employed by the contractor on the Facility Provided that, in respect of any persons
employed by any Subcontractor, the Contractor’ s obligations to insure as aforesaid under this Sub-Clause
shall be satisfied if the Subcontractor shall have insured against the liability in respect of such persons in
such manner that the Owner is indemnified under the policy, but the Contractor shall require such
Subcontractor to produce to the Owner, when required, such policy of insurance and receipt for the payment
of the current premium.
13.7 HON. SUPREME/ HIGH COURT GUIDELINES
Hon. Court guidelines must be strictly followed by Contractor for drainage work for better safety of
workmen. All the work must be carried out by using all safety equipments and measures and cleaning of
manholes must be by mechanical equipments by the contractor.
a. The contractor will be responsible to pay a compensation of minimum Rs.30 lakhs in addition to the
compensation paid by Government in the case of death of workman, while working with this work. Also,
insurance should be required for all workers.
14. Site Investigation Report
14.1 The Contractor in preparing the Bid shall rely on any site Investigation reports referred to in the
Contract Data, supplemented by any information available to the Bidder. The soil Investigation report
shall be used for reference only.
15. Queries about the Contract Data
15.1 The engineer will clarify queries on the Contract Data
16. Contractor to Construct the Works
16.1 The Contractor shall construct and install the works in accordance with the specification and Drawings.
17. The Works to be completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Works on the Start Date and shall carry out the Works
in accordance with the programme submitted by the Contractor, as updated with the approval of the
Engineer, and complete them by the Intended Completion Date.
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary works to the
Engineer, who is to approve them if they comply with the Specifications and drawings.
18.2 The Contractor shall be responsible for design of temporary works.
18.3 The Engineer’s approval shall not alter the contractor responsibility for design of the Temporary works.
18.4 The Contractor shall obtain approval of third parties to the design of the Temporary works where
18.5 All Drawings prepared by the Contractors for the execution of the temporary or permanent work are
subject to prior approval by the Engineer before their use.
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly discovered on the site is the
property of the Employer. The contractor is to notify the Engineer of such discoveries and carry out the
Engineer’s Instructions for dealing with them.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized by the Engineer access to the Site,
to any place where work in connection with the Contract is being carried out or is intended to be carried
out and to any place where materials or plants are being manufactured / fabricated / assembled for the
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining to works which comply with
the applicable laws where the site is located.
23.2 The Contractor shall permit the Employer to inspect the Contractor’s accounts and records relating to
the performance of the Contractor and to have them audited by auditors appointed by the Employer, if
so required by the Employer.
24.1 If the contractor is of the view that a decision taken by the Engineer was either outside the authority
given to the Engineer by the contract or that the decision was wrong taken, the decision shall be referred
to Municipal Commissioner (Higher Authority) within 14 days of the notification of the Engineers
decision. If the issue is not resolved, any party can refer the matter for conciliation within 15 days from
the decision given by the Municipal Commissioner.
24.2 For the work up to Rs. 100 crores or more than Rs.100 Crore if the agency is not satisfied with the
decision of the Additional City Engineer /Head of Department / City Engineer concern for the
conciliation process he shall refer to the Municipal Commissioner.
If the dispute is not resolved through the conciliation process, he may refer the dispute to Gujarat Public
works contract Dispute Arbitration Tribunal. If the contractor fails to refer a claim / dispute to the
Highter Authority within 14 days of the notification of the Engineers decision, the Contractor shall not
be entitled to any additional payment / claim if he doesn’t follow the above sequence in stipulated time
and he should not stop the work.
25. Procedure for Disputers
25.1 The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special
Conditions of Contract.
26. If the contractor breaches any condition of the agreement and executes inferior quality of work, VMC
may reduce the payment for the said work or stop all payments towards work done and forfeit deposits
and shall get remaining work done from other agency at risk and cost of the contractor. Moreover in
case of prolonged undue delay more than maximum delay penalty period, contractor shall be put in
abeyance or debarred or blacklisted and he shall be liable to liquidated losses which may require to
complete the remaining work at the risk and cost of the contractor by assigning the work to any other
B. TIME CONTROL
27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a
Programme showing the general methods, arrangements orders, and timing for all the activities in the
works alongwith monthly cash flow forecast.
27.2 An update of the Programme shall be a programme showing the actual progress achieved on each activity
and the effect of the progress achieved on the timing of the remaining work including any changes to the
sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval an updated programme at intervals no longer than
the period stated in the Contract data. If the Contractor does not submit an updated programme within this
period, the Engineer may withhold the amount stated in the Contract Data from the next payment after the
date on which the overdue programme has been submitted.
27.4 The Engineer’s approval of the programme shall not alter the Contractor’s obligations. The Contractor may
revise the programme and submit it to the Engineer again at any time. A revised programme is to show the
effect of Variations events.
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Compleion Date if a compensation Event occurs or a Variation is
issued which makes it impossible for completion to be achieved by the Intended Completion Date without
the Contractor taking steps to accelerate the remaining work and which would cause the Contractor to incur
additional cost.
28.2 The Engineer shall decide whether and by how much to extend the Intended Completion Date within
days of the Contractor asking the Engineer for a decision upon the effect of a compensation event or
Variation and submitting full supporting information. If the Contractor has failed to give early warning or
delay or has failed to cooperate in dealing with a delay, the delay by this failure shall not be considered in
assessing the new Intended Completion Date.
28.3 The Engineer shall within 14 days of receiving full justification from the contractor for extension of
Intended Completion Date refer to the Employer his decision. The Employer shall in not more than 21 days
communicate to the engineer the acceptance or otherwise of the Engineer’s decision. If the employer fails
to give his acceptance, the Engineer shall not grant the extension and the contractor may refer the matter
under Clause 24.1.
30. Delays ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or progress of any activity within the works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other to attend a management meeting. The business
of a management meeting shall be to review the plans for remaining work and to deal with matters raised in
accordance with the early warning procedure.
31.2 The Engineer shall record the business of management meetings and is to provide copies of his record to
those attending the meeting and to the Employer. The responsibility of the parties for actions to be taken is
to be decided by the Engineer either at the management meeting or after the management meeting and
stated in writing to all who attended the meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely future events or
circumstances that may adversely affect the quality of the work, increase the Contract price or delay the
execution of works. The Engineer may require the contractor to provide an estimate of the expected effect
of the future event or circumstance on the contract price and completion date. The estimate is to be
provided by the Contractor as soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and considering proposals for how the effect
of such an event or circumstance can be avoided or reduced by anyone involved in the work and in carrying
out any resulting instruction of the Engineer.
C. QUALITY CONTROL
33. Identifying Defects / Defect Liability period
33.1 Defect liability period: The contractor shall be responsible to make good and remedy at his own
expense any defect which may develop or may be noticed before the period mentioned hereunder
from the certified date of completion. The Engineer in charge shall give the contractor a notice in
writing about the defects and the contractor shall make good the same within 15 days of receipt of
the notice. In the case of failure on the part of the contractor, the Engineer- in-charge may rectify
or remove or re-execute the work at the risk & cost of the contractor. The Engineer-in-charge shall
be entitled to appropriate the whole or any part of the amount of security deposit towards the
expenses, if any, Incurred by him in rectification, removal or re-execution.
The Defects Liability period shall be as under….
a) For all works costing up to Rs. 50,000 (amount put to tender), the period shall be 3 Months
from the certified date of completion.
b) For all works costing more than Rs. 50,000 and up to Rs. 1 crore (amount put tender), the
period shall be 12 (Twelve) months from the certified date of completion or one monsoon,
whichever is later.
c) For major projects costing more than Rs. 1 crore, the period shall be 36 Months from the
certified date of completion which should include three monsoons.
d) For original building works the defect liability period will be 4 years or elapse of 4 monsoon
period following date of possession of building taken over by user agency following the
certified date of completion, whichever is later. For the purpose of deciding the monsoon
period, 30th September shall be treated as the last date.
33.2 (i) The Contractor shall be responsible for all the Defects in the Works or any part thereof, as the case may
be, during the execution of the Works and during the defects liability period.
(ii)The Defect Liability Period for the Works shall be 3 years from the Physical Completion Date.
(iii)The Performance Bank Guarantee submitted shall be refunded if no defects are noticed during the
Defect Liability Period or the Defects pointed out are removed.
(iv) Contractor shall be responsible for security (watch and ward) of the project assets/ facilities for the
period between Completion Date and commissioning.
34.1 If the engineer instructs the Contractor to carry out a test not specified in the Specification to check
whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test and
34.2 Engineer must ensure nos. of tests and types of tests to be performed as per specification. In case if it is
not done or up to the mark, by bidder 1% deduction from work done in a particular RA bill should be
34.3 Agency has to establish testing laboratory on site for the various test to be carried out in the work, for this
purpose agency shall construct a pukka laboratory building with all facility on site at location specified by
the Engineer in charge.
35. Correction of defects
35.1 The Engineer shall give notice to the Contractor of any defects before the end of the defects Liability
Period, which begins at Completion and is defined in the contract data. The Defects Liability Period shall
be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified defect within the length of
time specified by the Engineer’s notice.
36. Uncorrected Defects
36.1 If the contractor has not corrected a defect within the time specified in the Engineer’s notice, the Engineer
will assess the cost of having the Defect corrected, and the Contractor will pay this amount.
D. COST CONTROL
37. Bill Quantities
37.1 The bill of Quantities shall contain items for the construction, installation, testing and
commissioning work to be done by the Contractor.
37.2 The bill of Quantities is used to calculate the Contract price. The Contractor is paid for the
quantity of the work done at the rate in the Bill of Quantities for each item.
38. Change in the Quantities
38.1 The Engineer shall have power to make any alterations in or addition to the original specifications
drawings, designs and instructions that may appear to him to be necessary or advisable during the
progress of the work and the contractor shall be bound to carry out the work in accordance with any
instruction in this connection which may be given to him in writing signed by the Engineer and such
alteration shall not invalidate the contract and any additional work which the contractor may be directed to
do in the manner above specified as part of the work shall be carried out by the contractor on the same
conditions in all respects on which he agreed to do the main work and at the same rate as are specified in
the tender for the main work.
Except that when the quantity of any item exceeds the quantity as in the tender by more than 130%, the
contractor will be paid for the quantity in excess of 130%, at the rate entered in the SOR of the year
during which the excess in quantity is first executed.
40.1 All Variations shall be included in updated programmes produced by the Contractor.
40. Payments for Variations
40.1 If the additional or altered work includes any class of work for which no rate is specified in
this contract, then such class of work shall be carried out as under.
(i) At the rate derived from the item within the contract which is comparable to the one involving additional
or altered class of work; where there are more than one comparable item, the item of the contract which is
nearest in comparison with regard to class or classes of the work involved shall be selected and the
decision of the Superintending Engineer as to the nearest comparable item shall be final and binding on
the contractor.
(ii) If the rate cannot be derived in accordance with (i) above, such class of works shall be carried out at the
rate entered in the Schedule of Rates of the division 50 for the year in which the tender was received,
increased or decreased by the percentage by which the tender amount is more or less as compared to the
amount arrived at the rates in the “Schedule of Rates” of the Division in the year in which the tender was
received. If the Schedule of rates of the Division does not contain all the items, the percentage increase or
decrease of the tender shall be calculated considering such items which were included in the “Scheduled
Rates” of the division for the year and for materials consumed on such item the rate to be charged would be
the basic rate taken into account for fixing the rate in S.O.R. referred to above.
(iii) If it is not possible to arrive at the rate from (i) and (ii) above, such class of work shall be carried out at
the rate decided by the competent authorities on the basis of detailed rate analysis after hearing the
contractor before a Committee of two Superintending Engineers stationed at the same place or the nearest
40.2 If the additional or altered work, for which no rate is entered in the “Schedule of Rates” of the Division is
ordered to be carried out before the rate is agreed upon, then the contractor shall within seven days of the
date of receipt by him of the order to carry out the work, inform the Engineer-in-charge of the rate, which it
is his intention to charge for such class of work and if the Engineer in charge does not agree to this rates, he
shall by notice in writing be at liberty to cancel his order to carry out such class of work and arrange to carry
it out in such manner as he may consider it advisable, provided always that if the contractor shall commence
work or incur any expenditure in regard thereof before the rates shall have been determined as lastly herein
before mentioned, then in such cases he shall only be entitled to be paid in respect of the work carried out or
expenditure incurred by him prior to the date of the determination of the rate as aforesaid according to such
rate or rates as shall be fixed by the Engineer-in-charge. In the event of the dispute, the decision of the
Superintending Engineer of the Circle shall be final.
Where, however, the work is to be executed according to the designs, drawings and specifications
recommended by the contractor and accepted by the competent authority, the alternation above referred to
shall be within the scope of such designs, drawings and specifications appended to the tenders.
The time limit for the completion of the work shall be extended in the proportion that the increase in the
cost occasioned by alterations bears to the cost of the original work and the certificate of the Engineer-in-
charge as to such proportion shall be final and conclusive.
41. Cash Flow Forecasts
41.1 When the programme is updated, the contractor is to provide the engineer with an updated cash flow
42. Payment Certificates
42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the
work completed less the cumulative amount certified previously.
42.2 The Engineer shall check the Contractor’s monthly statement within 14 days and certify the
amount to be paid to the Contractor after taking in to account any credit or debit for the month in
question in respect of materials for the works in the relevant amounts and under conditions set
forth in sub-clause 32.3 of the Contract Data (secured Advance).
42.3 The value of work executed shall be determined by the Engineer.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of
Quantities completed.
42.5 The value of work executed shall include the valuation of variations and compensation events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion
of any item previously certified in any certificate in the light of later information.
43.1 Payments shall be adjusted for deductions for advance payments, retention, other recoveries in
terms of the contract and taxes at source, as applicable under the law. The Employer shall pay the
Contractor the amounts certified by the Engineer within 28 days of the date of each certificate.
43.2 Payment of GST (prevailing rates) on the amount payable under the contract to the Contractor
will be made by the Employer. Hence, it is the responsibility of the contractor to pay the GST to
the concerned Authority.
43.3 Items of the works for which no rate or price has been entered in will not be paid by the
Employer and shall be deemed covered by other rates and prices in the Contract.
45.1 The rates quoted by the Contractor must be inclusive of all taxes prevailing on due date of bid
submission except GST. However, any subsequent changes in the tax structure by Government
after due date of bid submission will be compensated (+/-) on availability or submission of actual
documentation. Contractor will have to intimate Engineer regarding changes occurred in the tax
structure after bid submission. If the contractor fails to provide such information and if any
financial obligation may arise due to change in tax structure, same will be recovered from the
45.2 GST will be paid separately on the bills. Hence, it is the responsibility of the contractor to pay
the GST to the concerned Authority.
46.1 All payment shall be made in Indian Rupees.
47. Price Adjustment
47.1 Contract price shall be adjusted for increase or decrease in rates and price of cement, steel, HR
coil, bitumin and pig iron in accordance with the following principles and procedures and as per
formula given in the contract data:
(a) The price adjustment shall apply for the work done from the start date given in the contract
data up to end of the initial intended completion date or extensions granted by the Engineer and
shall not apply to the work carried out beyond the stipulated time for reasons attributable to the
(b) The price adjustment shall be determined during each month from the formula given in the
(c) Following expressions and meanings during to the work done during each month R = Total
value of work done during the month. It would include the amount of secured advance granted, if
any, during the month less the amount of secured advance recovered, if any during the month. It
will exclude value for works executed under variations for which price adjustment will be
worked separately based on the terms mutually agreed.
47.2 To the extent that full compensation for any rise or fall in costs to the contractor is not covered
by the provisions of this or other clause in the contract, the unit rates and prices included in the
contract shall be deemed to include amounts to cover the contingency of such other rise or fall in
48.1 The Employer shall retain from each payment due to Contractor the proportion stated in the
Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the
Contractor and half when the Defects Liability Period has passed and the Engineer has certified
that all Defects notified by the Engineer to the Contractor before the end of this period have been
48.3 On completion of the whole works, the contractor may substitute retention money with an “on
demand” Bank guarantee.
In case, Contractor requests for refund of the Retention Money deducted by the
Employer under the provision of this clause, Employer shall consider the said request of the
Contractor provided that the refund hereunder shall be made in tranches of not less than 1% (One
Percent) of the Contract Price and Contractor furnishes an irrevocable and unconditional Bank
guarantee for an equal amount substantially in the format of Bank Guarantee for Performance
Guarantee enclosed with SBD and valid up to 60 day beyond the scheduled / extended Defects
Liability Period. On completion of the whole works, the contractor has however an option to
submit a fresh irrevocable and unconditional Bank Guarantee for an amount equal to 5% of the
total value of work executed substantially in the format of Bank Guarantee for Performance
Guarantee enclosed with SBD and valid up to 60 days beyond the Defect Liability Period and yet
refund the Retention Money Bank Guarantee submitted for refund of Retention Money.
49. Liquidated Damages
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the
Contract Data for each day that the Completion Date is later than the Intended Completion Date
(for the whole works or the milestone as stated in the contract data). The total amount of liquidated
(for the whole works or the milestone as stated in the contract data). The total amount of liquidated
damages shall not exceed the amount defined in the Contract Data. The Employer may deduct
liquidated damages from payment due to the Contractor. Payment of liquidated damages does not
affect the Contractor’s liabilities. Liquidated damaged shall be 0.05% of Contract Value (inc GST)
per day subject to max 10% of Contract Value (inc GST)
49.2 If the Intended Completion Date is extended after liquidated damages have been paid, the
Engineer shall correct any overpayment of liquidated damages by the Contractor by adjusting the
next payment certificate. The Contractor shall not be entitled for any interest on the over payment
calculated from the date of payment to the date of repayment.
49.3 If the contractor fails to comply with the time for completion as stipulated in the tender, then
the contractor shall pay to the employer the relevant sum stated in the Contract Data as Liquidated
damages for such default and not as penalty for everyday or part of day which shall elapse
between relevant time for completion and the date stated in the taking over certificate of the whole
of the works on the relevant section, subject to the limit stated in the contract data.
The employer may, without prejudice to any other method of recovery deduct the
amount of such damages from any monies due or to become due to the contractor. The payment or
deduction of such damages shall not relieve the contractor from his obligation to complete the
works on from any other of his obligations and liabilities under the contract.
49.4 If, before the Time for Completion of the whole of the Works or, if applicable any Section, a
Taking Over Certificate has been issued for any part of the Works or of a Section, the liquidated
damages for delay in completion of the remainder of the Works or of that Section shall, for any
period of delay after the date stated in such Taking-Over-Certificate, and in the absence of
alternative provisions in the Contract, be reduced in the proportion which the value of the part so
certified bears to the value of the whole of the Works or Section, as applicable. The provisions of
this Sub-clause shall only apply to the rate of liquidated damages and shall not affect the limit
49.5 Contractor fails to perform the work to the required standards and specifications punishment will
50.1 If the contractor achieves completion of the whole of the works prior to the intended
Completion Date prescribed in Contract Data the Employer shall pay to the contractor a sum stated
in Contract Data as bonus for every completed month but subjected to maximum amount as stated
in Contract Data; which shall elapse between the date of completion of all items of works as
stipulated in the contract, including variations ordered by the Engineer and the time prescribed in
50.2 Bonus shall be paid only to works amounting to above INR 5 crore with time limit of the works
is equal or more than 6 months. The bonus would be paid as under
% of Time Saved f Initial Contract Price entitled for
Less than 10% 0%
51. Advance Payment
51.1 The Employer shall make advance payment (not to be paid less than two installments except in special
circumstances for which the reason to be Recorded in writing) to the Contractor of the amounts stated in the
Contract Date by the date stated in the Contract Date, against provision by the Contactor of an Unconditional
Bank Guarantee in a form and by a bank acceptable to the Employer in amounts and currencies equal to be at
least 110% of the advance payment. The guarantee shall remain effective until the advance payment has been
repaid, but the amount of the guarantee shall be progressively reduced by the amounts repaid by the
Contractor. The Mobilization advance would be deemed as interest bearing advance at an interest rate of
% to be compounded, quarterly.
51.2 The Contractor is to use the advance payment only to pay for Equipment, plant and Mobilization
expenses required specifically for execution of the Works. The Contractor shall demonstrate that advance
payment has been used in this way by supplying copies of invoices or other documents to the engineer.
51.3 The advance payment shall be repaid by deduction proportionate amount from payments otherwise due
to the Contractor, following the schedule of completed percentages of the Works on a payment basis. No
account shall be taken of the advance payment or its repayment in assessing valuations of work done,
variations, price adjustments, or Liquidated damages.
52.1 The performance Security (including additional security for unbalanced bids) shall be provided
to the Employer no later than the date specified in the Letter of Acceptance and shall be issued in
an amount and form and by a bank or surety acceptable to the Employer, and denominated in
Indian Rupees. performance Security shall be valid until a date 60 days from the certified date of
completion of the project and the additional security
for unbalanced bids shall be valid until a date 28 days from the date of issue of the certificate of
completion of the work.
Performance and Additional Performance Security shall become refundable/releasable within 15 days
after project certified completion date subject to fulfillment of contractual obligation and settlement
of all dues and claims
54. Cost of Repairs.
54.1 Loss or damage to the Works or Materials to be incorporated in the Works between the Start
date and the end of Defects Correction periods shall be remedied by the Contractor at the
Contractor’s cost if the loss or damages arises from the Contractor’s acts or omissions.
E. FINISHING THE CONTRACT
55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of the works and the
Engineer will do so upon deciding that the work is completed.
56. Taking Over
56.1 The Employer shall take over the Site and the Works within seven days of the Engineer issuing a
certificate of Completion.
57. Final Account
57.1 The Contractor shall supply to the Engineer a detailed final account of the total amount that the
57.1 The Contractor shall supply to the Engineer a detailed final account of the total amount that the
Contractor considers payable as full and final settlement of all claims under the Contract for items before
the end of the Defects Liability Period. The Engineer shall issue a Defect Liability Certificate and certify
any final payment that is due to the Contractor within 56 days of receiving the Contractor's account if it is
correct and complete. If it is not, the Engineer shall issue within 56 days a schedule that states the scope of
the corrections or additions that are necessary. If the Final Account is still unsatisfactory after it has been
resubmitted, the Engineer shall decide on the amount payable to the Contractor and issue a payment
certificate, within 56 days of receiving the Contractor’s revised account.
57.2 If reversal in characteristic of tender (L1 becoming L2) on account of excesses and savings in final
account is observed, the Engineer/Employer shall be at liberty to restrict the final payment of BOQ items to
the lowest amount evaluated of the bids considering the final quantities and the rates quoted including the
rebates if any. Payment of variation items shall however be made at the rates approved by the Employer,
within 90 days from the physical completion of work. Taxes will be deducted as per government rules from
58. Operating and Maintenance Manuals
58.1 If “as built” drawings and/or operating and maintenance manuals are required, the Contractor shall supply
them by the dates stated in the Contract data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the Contract data, or
they do not receive the Engineer’s approval, the Engineer shall withhold the amount stated in the Contract
Data from payments due to the Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party causes a fundamental
breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited to the
1. The contractor stops work for 28 days when no stoppage of work is shown on the current programme
and the stoppage has not been authorized by the Engineer.
2. The Engineer instructs the Contractor to delay the progress of the Works and the instructions is not
withdrawn within 28 days;
3. The Employer or the Contractor is made bankrupt or goes into liquidation other than for a
reconstructions or amalgamation
4. A payment certified by the Engineer is not paid by the Employer to the Contractor within 56 days of the
date of the Engineer’s certificate
5. The Engineer gives Notice that failure to correct a particular Defect is a fundamental breach of Contract
and the Contractor fails to correct it within a reasonable period of time determined by the Engineer;
6. The Contractor does not maintain a security which is required;
7. The Contractor has delayed the completion of works by the number of days for which the maximum
amount of liquidated damages can be paid as defined in the Contract data; and
8. If the Contractor, in the judgment of the Employer has engaged in corrupt or fraudulent practices in
competing for or in executing the Contract.
For the purpose of this paragraph: “corrupt practice” means the offering, giving, receiving or soliciting of
anything of value to influence the action of a public official in the procurement process or in contract
execution. “Fraudulent practice” means a misrepresentation of facts in order to influence a procurement
process or the execution of a contract to the detriment of the borrower, and includes collusive practice
among Bidders (prior to or after bid submission) designed to establish bid prices at artificial non-
competitive levels and to deprive the Borrower of the benefits of free and open competition.
59.3When either party to the Contract gives notice of a breach of contract to the Engineer for a cause other
than those listed under Sub Clause 59.2 above, the Engineer shall decide whether the breach is
fundamental or not.
59.4 Notwithstanding the above, the employer may terminate the Contract for convenience.
60. Payment upon Termination
60.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the Engineer
shall issue a Certificate for the value of the work done less advance payments received up to the date of
the issue of the certificate, less other recoveries due in terms of the contract, less taxes due to deducted at
source as per applicable law and less the percentage to apply to the work not completed as indicated in the
Contract data. Additional Liquidated Damages shall not apply. If the total amount due to the Employer
Contract data. Additional Liquidated Damages shall not apply. If the total amount due to the Employer
exceeds any payment due to the Contractor the difference shall be a debt payable to the Employer.
60.2 If the Contract is terminated at the Employer’s convenience or because of a fundamental breach of
Contract by the Employer, the Engineer shall issue a certificate for the value of the work done, the cost of
balance material brought by the contractor and available at site, the reasonable cost of removal of
equipment, repatriation of the Contractor’s personnel employed solely on the works, and the Contractor’s
cost of protecting and securing the Works and less advance payment received up to the date of the
certificate, less other recoveries due in terms of the contract and less taxes due to deducted at source as
per applicable law.
61.1 All materials on the Site, Plant Equipments, Temporary Works and Works are deemed to be property of
the Employer, if the Contract is terminated because of a Contractor’s default.
62. Release From Performance
62.1 If the Contract is frustrated by the outbreak of war of by any other event entirely outside the control of
either the Employer or the Contractor the Engineer shall certify that the Contract has been frustrated. The
Contractor shall make the Site safe and stop work as quickly as possible after receiving this certificate and
shall be paid for all work carried out before receiving it and for any work carried out afterwards to which
commitment was made.
F. SPECIAL CONDITIONS OF CONTRACT
The Contractor shall, unless otherwise provided in the Contract, make his own arrangements for the
engagement of all staff and labour, local or other, and for their payment of housing, feeding and transport.
The Contractor shall, if required by the Engineer, deliver to the Engineer a return in detail, in such form
and at such intervals as the Engineer may prescribe, showing the staff and the numbers of the several classes of
labour from time to time employed by the Contractor on the site and such other information as the Engineer
64. COMPLIANCE WITH LABOUR REGULATIONS
During continuance of the contact, the Contractor and his subcontractor shall abide at all times by all
existing labour enactments and rules made thereunder, regulations, notification and bye laws of the State or
central Government or local authority and any other labour law (including rules), regulations, bye laws that
may be passed or notifications that may be issued under any labour law in future either by the State or the
Central Government or the local authority. Salient features of some of the major labour laws that are applicable
to the construction industry are given below. The Contractor shall keep the Employer indemnified in case any
action is taken against the Employer by the competent authority on account of contravention of any of the
provisions of any Act or rules made thereunder, regulations or notifications including amendments. If the
Employer is caused to pay or reimburse, such amounts as may be necessary to cause or observe, or for
observance of the provisions stipulated in the notifications/bye laws/Acts/Rules/regulations including
amendments, if any, on the part of the Contractor, the Engineer/employer shall have the right to deduct any
money due to the Contractor including his amount of performance security. The Employer/Engineer shall also
have the right to recover from the Contractor any sum required or estimated to be required for making good the
loss or damage suffered by the Employer.
The employees of the Contractor and the Sub-Contractor in no case shall be treated as the employees of the
Employer at any point to time. SALIENT FEATURES OF SOME MAJOR LABOUR AND OTHER LAWS
APPLICABLE TO ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTIONS
A) Workmen Compensation Act 1923: - The Act provides for compensation in case of injury by accident
arising out of and during the course of employment.
B) Payment of Gratuity Act. 1972: - Gratuity is payable to an employee under the Act on satisfaction of
certain conditions on separation if an employee has completed 5 years service or more on death, the rate of
15 days wages for every completed year of service. The Act is applicable to all establishments employing
10 or more employees.
C) Employees P.F. and Miscellaneous Provision Act 1952: ‐ The Act Provides for monthly contributions by
the employer plus workers @ 10% or 8.33% The benefits payable under the Act are:
1. Pension or family pension on retirement or death, as the case may be.
2. Deposit linked insurance on the death in harness of the worker.
3. Payment of P.F. accumulation on retirement/death etc.
D) Maternity Benefit Act 1951: - The Act provides for leave and some other benefits to women employees in
case of confinement or miscarriage etc.
E) Contract Labour (Regulation & Abolition) Act 1970: The Act provides for certain welfare measures to be
provided by the Contractor to contract labour and in case the Contractor fails to provide, the same are required
to be provided, by the Principal Employer by Law. The principal Employer is required to take Certificate of
Registration and the Contractor is required to take license from the designated Officer. The Act is applicable to
the establishments or Contractor of Principal Employer, if they employ 20 or more contract labour.
F) Minimum Wages Act 1948: ‐ The Employer is supposed to pay not less than the Minimum Wages fixed by
appropriate Government as per provisions of the Act, if the employment is a scheduled employment.
Construction of Building, Roads, Runways are scheduled employment.
G) Payments of wages Act 1936: ‐ It lays down as to by what date the wages are to be paid, when it will be
paid and what deductions can be made from the wages of the workers.
H) Equal remunerations Act 1979: - The Act provides for payment of equal wages for work of equal nature to
Male and Female workers and for not making discrimination against female employees in the matter of
transfer, training and promotions etc.
I) Payments of Bonus Act 1965: - The Act is applicable to all establishments employing 20 or more
employees. The Act provides for payments of annual bonus subject to a minimum of 8.33% of wages and
maximum of 20 % of wages to employees drawing Rs. 3500/- per month or less. The bonus to be paid to
employees getting Rs, 2500/- per month or above Rs. 3500/- per month shall be worked out by taking wages as
Rs. 2500/- per month only. The Act does not 61 apply to certain establishments. The newly set-up
establishments are exempted for five years in certain circumstances. Some of the State Governments have
reduced the employment size from 20 to 10 for the purpose of applicability of this Act.
J) Industrial Disputes Act 1947: - The Act lays down the machinery and procedure for resolutions of
Industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for
laying off or retrenching the employees or closing down the establishment.
K) Industrial employment (standing Orders) Act 1946: ‐ It is applicable to all establishments employing
or more workmen (employment size reduced by some of the State and Central Government to 50). The Act
provides for laying down rules governing the conditions of employment by the Employer on matters provided
in the Act and get the same certified by the designated Authority.
L) Trade Unions Act 1926: ‐ The Act lays the procedure for registration of trade unions of workmen and
employers. The Trade Unions registered under the Act have given certain immunities from civil and criminal
M) Child Labour (Prohibition & Regulation Act 1986: ‐ The Act prohibits employment of children below
years of age in certain occupations and process and provides for regulation of employment of children in all
other occupations and processes. Employment of Child labour is prohibited in Building and Construction
N) Inter – State Migrant workmen’s (Regulation of Employment & Conditions of service) Act 1979:‐ The
Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an
intermediary (who has recruited workmen in one state for employment in the establishment situated in another
state).The inter-state migrant workmen, is an establishment to which this Act becomes applicable, are required
to be provided certain facilities such as housing, medical aid, traveling expenses from home upto the
establishment and back, etc.
O) The Building and Other Construction workers (Regulation of employment and Conditions of Service)
Act 1996 and the Cess Act of 1996: ‐ All the establishments who carry on any building or other constructions
work and employ 10 or more workers are covered under this Act. All such establishments are required to pay
cess at the rate not exceeding 2% of the cost of construction as may be modified by the government. The
Employer of the establishment is required to provide safety measures at the Building or construction work and
other welfare measures, such as canteens, First Aid facilities, Ambulance, Housing accommodations for
workers near the workplace etc. The Employer to whom the Act applies has to obtain a registration certificate
from the Registering Officers appointed by the Government.
P) Factories Act 1948: ‐ The Act lays down the procedure for approval of plans before setting up a factory,
health and safety provisions, welfare provisions, working hours, annual earned leave and rendering information
regarding accidents or dangerous occurrences to designated authorities. It is applicable to premises employing
10 persons or more with aid of power or 20 or more persons without the aid of power engaged in the
manufacturing process.
Q) Royalty charges‐The contractor shall pay the royalty to the competent authority as per rule. The royalty
charges paid shall be borne by the contractor and shall not be reimbursed by the Employer.
R) Following Pollution control Acts and amendments made thereof from time to time shall be applicable.
1. Water (Preservation and control of Pollution) Act,
2. Air (Prevention and Control of Pollution Act
3. Environmental (Protection) Act
The contractor must commit to adopting Environmental management plan for best energy use, waste
management, the reduction of pollution as in EMS (Environmental Management system) ISO-14001-
65. ARBITRATION (GCC CLAUSE 24)
The procedure for arbitration will be as follows: -
65.1 If the Contractor is of the view that a decision taken by the Engineer was either outside the authority
given to the Engineer by the Contract or that the decision was wrongly taken, the decision shall be referred
to Municipal Commissioner (Higher Authority) within 14 days of the notification of the Engineer's
decision. If the issue is not resolved, any party can refer the matter for conciliation within 15 days from the
decision given by the Municipal Commissioner.
65.2 All disputes and differences of any kind whatever arising out of or in connection with the Contract or the
carrying out of the works (whether during the progress of the works or after their completion and whether
before or after the termination, abandonment or breach of the Contract) shall be first referred to and
settled by the Executive Engineer who shall state his decision in writing. Such decision may be in the
form of a Final Certificate or otherwise. If the contractor does not satisfy with the decision of the
Executive Engineer, an appeal shall be raised to the City Engineer/ Head of the Department or Additional
City Engineer as stated in the preceding Clause. But if either the Employer or the Contractor be
dissatisfied with the decision of the City Engineer / Head of the Department or Additional City Engineer
on any matter, question or dispute or any kind (except any of the expected matters) or as to the
withholding by the City Engineer / Head of the Department or Additional City Engineer of any Certificate
to which the Contractor may claim to be entitled, then and in any such case either party (the Employer or
the Contractor) may within twenty-eight days after receiving notice of such decision give a written notice
to the other party through the City Engineer / Head of the Department or Additional City Engineer
requiring that such matters in dispute is arbitrated upon. Such written notice shall specify the matters
which are in dispute or difference of which such written notice has been given and no other shall be and is
hereby referred to the Arbitration and final decision of a single Arbitrator being a Municipal
Commissioner of VMC. The final decision of Municipal Commissioner shall be binding on both the
parties (i.e. the Contractor and Head of the Department / Additional City Engineer. The decision of
Municipal Commissioner shall be in form of written order.
Clause Reference With respect To section
Item marked “N/A” do not apply to this Contract.
1. The Employers is [CL.1.1]
Name: Executive Engineer, Drainage Project, Vadodara Municipal Corporation
Address: Drainage Project, Room No. 204, Second floor, Vadodara Municipal Corporation, Khanderao
Market Building, Rajmahal Road, Vadodara - 390
Name of authorized Representative (will be intimated later)
2. The Engineer is Executive Engineer
Name of Authorized Representative: -----
3. The Defects Liability Period is 03( THREE) years from the date of completion. [CL.1.1&33]
4. The Start Date shall be 7th day from the date of issue of the Notice to proceed with the work. [CL.1.1]
5. The Intended Completion Date for the whole of the works is ………… Months after start of work.
6. The Site is located at Sardar estate CIRCLE [CL.1.1]
7. The name and identification number of the Contract is: [CL.1.1]
8. The works consist of The Work of shifting the drainage line and Machine hole in front of Real Kathiyawadi
Hotel at the new flyover bridge project at Sardar Estate Junction on the 40.0 meter ring road.
with items as per B.O.Q. The works shall, inter alia, include the following, as specified or directed.
8.1 To carry out Pre Execution and Post Execution survey of the Pressure line /proposed route by taking
levels at every 5 m longitudinally interval. (using total station and drawing of existing feature and
proposed work and on completion of execution as- built drawing shall be submitted). Necessary jungle
cutting activities like fencing removal, fencing restoration depositing to respective VMC office / store as
per EIC shall be in the scope of work and for which no payment shall be done to the contractor.
8.2 During the Pre Execution survey the contractor shall identify the locations where there are obstructions
(legal / illegal) and where constructing/laying of Pressure line will not be feasible unless these
obstructions are removed. Trial pits shall have to be taken by the contractor as per instruction of engineer
in charge. Contractors should clearly show obstructions, crossings along with all dimensional and
construction details. Wherever the proposed system is to be integrated with the existing system, the
contractor shall take the GL and IL of the connecting pipeline / channel. 3 sets of the survey drawings
including L/S and C/S (hard copy) and a editable soft copy ( in AutoCAD format/ MS office) on Pen
drive shall be submitted by the contractor.
8.3 The contractor shall establish sufficient Nos. of TBMs and PBMs at suitable locations i.e. permanent
structures like electrical poles etc, which can be used for checking the Invert Levels of the pipes/channel
during the execution. No payment shall be made for these activities by VMC.
8.4 Water and Electricity for construction and testing for all material and items involved in work shall be
arranged by the Contractor at their own cost and informed to VMC in advance.
8.5 Submitting detail drawing/ Sketch to VMC for the stretch of the pipeline and allied work laid as per the
specifications and drawings before refilling the trench for approval.
8.6 Any and all other works indicated and considered necessary for the execution of this work whether or
not specifically mentioned or called for.
8.7 Any damage to the existing structures during execution shall be repaired by the contractor and no extra
payment shall be done for the same.
8.8 Testing shall be done by collecting samples from site in Govt. approved testing laboratory & 10% of
total Quantity in M.S.U. or GERI at cost of contractor. The Contractor has to deposit the testing fee for
TPI as per rules separately.
8.9 Bore holes to be taken by contractor to derive SBC of soil without any extra cost as per requirement.
8.10 Dewatering payment shall not be paid for water (any quantum) appearing during excavation / Sinking of
shaft and during pushing work.
8.11 There is drainage line, water supply line, GAS line, CCTV, MGVCL, GETCO, OFC Cables crossing in
the proposed Gravity main alignment which is to be retained as if it is and execution of work has to be
done. No payment shall be made for these activities by VMC.
8.12 If the water table is at high level at site and soil strata is loose and collapsible. Then the contractor shall
have to consider all the factors for execution of work. Also, all the safety precautions with necessary
safety instruments must be taken at site and the contractor shall be solely responsible for any kind of
unwanted incidence happening at site.
8.13 For Extra Dewatering work other than excavation item, and during sinking & manual pushing
(including shaft work etc) the Contractor shall have to maintain records signed by the Eng. In charge of
8.14 Excavating (Dry or Wet soil, sludge) as per guidelines to acquire the design section of the Pipeline
laying. At most care shall be taken to safe guard and save all other utility services during execution. Any
problem arises due to bad workmanship of the contractor, the contractor shall be fully responsible and
he shall get the repairing done urgently, corporation may levy penalty on such misbehave.
8.15 The contractor shall be responsible for restoration of kachcha part with brick bats, wmm, wet mix, gsb,
metals, quarry waste etc according to required for approaches especially during monsoon in case of
settlement occurs without any cost.
8.16 All safety and environmental management measures.
8.17 Labor welfare and health measures and requirements.
8.18 Provision of all materials compliant with the specifications.
8.19 Provision of all skilled, semiskilled and unskilled manpower.
8.20 Preparation of working drawings, work schedules in MS Project format and getting the same approved
from PMC/ VMC before execution of the works involved.
8.21 To carry out Pre-Execution and Post Execution survey (Alignment Survey) using Total Station
equipment of the proposed route by taking levels at every 30 m interval and capturing all topographic
features. Making L-Section for the existing line & proposed line and getting the same approved from
PMC/VMC before execution of the works involved.
8.22 All excavation required for pipe laying by conventional method with compact shoring including
backfilling and road reinstatement. To safe guard the excavation for necessary shoring & strutting
related safety measures shall be done by the contractor.
8.23 No disposal / transportation of excavated earth shall be paid to the contractor for excavation / manual
pushing item. The contractor shall also have to do disposal of excavation stuff for more than 1 time in
view of any kind of existing situation of work without any cost.
8.24 The contractor shall be responsible for using bonding agent to be used for casting of concrete over
existing concrete which shall be approved by TPI/PMC/VMC and cost of this shall be borne by the
8.25 The preparation of approach road / access for the work shall have to be done by the contractor at their
own cost & no payment shall be made by VMC. The approach road / access shall have to be removed
after completion of work by the contractor at their own cost & no payment shall be done by VMC.
8.26 Providing safety rails / Solid board barricading along with installing cautionary sign boards showing
project details to be erected on site, blinkers during night, and other safety works etc. as per the
guidelines where ever required and instructed and specifications on all sides of the excavated trench and
must be maintain till the completion of the work. The contractor shall be responsible for any kind of
accident occurred due to absence/ lacking of any kind of safety measure (like safety rails / solid
barricading/cautionary sign boards etc). by the contractor at their own cost & no payment shall be done
by VMC. No work will be allowed to start without proper safety equipment’s like solid Board
Barricades, Blinkers etc., All safety Arrangements will be in scope of the contractor.
8.27 There is road parallel/ perpendicular to drain, necessary all kind of safety measures / precautions shall
be taken in view of traffic / public safety entry / exit. No payment shall be made for these activities by
8.28 Construction of machineholes.
• Brick masonry machineholes for byline connection and for open excavation.
• RCC machineholes for Main line.
8.29 Removal of the soil from the site, as per the guidelines including dewatering, diversion of flow, etc so as
to make the stretch of the excavation suitable for executing the work shall be borne by the Contractor.
8.30 All flow interconnections & byline connection including the connection from / to live sewers as directed
by TPI/PMC/VMC.
8.31 Making the connection(s) from existing work to new proposed work. Connection(s) may be wet
connection(s) or Dry connection(s). Contractor must carry out by them by taking all the safety
precaution(s) at their own cost.
8.32 All tests on raw materials and tests during ongoing works as per specifications and as directed by
TPI/PMC/VMC engaged in this work.
8.33 All other works deemed necessary for the execution of the intended work whether specifically
mentioned or called for.
8.34 No payment for road restoration for shaft will be paid to the contractor, however the contractor is
responsible to restore the damaged road at their own cost for the portion of shaft Construction.
8.35 The Contractor has to make all the necessary arrangement(s) for crossing proposed drainage gravity line
to existing drainage gravity line at same level. The Contractor to submit the method statement like
dummy work, dewatering arrangement(s) and connection work before starting the work.
8.36 The contractor shall be responsible for carrying out shaft construction in any nos. irrespective of
distance as per requirement of site. Between two shaft should be maintain at 30 – 35 mtr (center to
center) as per site situation the distance between two shafts in rare case will be permitted by PMC &
VMC as per requirement.
8.37 Any kind of dewatering (including manually pushing / shaft related bore / bore work) will not be paid
during the manually pushing work and during and after construction of shaft / shaft.
8.38 No plugging / dummy will be paid for stopping flow in existing UPVC / SWD / Stoneware / Channel
for such dummies only respective activity item (i.e., sand / earth fill back / masonry / plaster etc.) will
be paid for relative items. Dummy item will be paid only if will be done in submerged condition.
8.39 No Job connection (wet / dry connection new line with old existing line) shall be paid for DI / CI water
pipe line / Drainage line shifting / laying work separately.
8.40 No payment shall be made for breaking or cutting the existing old drainage pipe during manually
8.41 Half rate shall be paid for pakka dummy / plugging provide to drainage line / machinholes incase of non
performance of breaking of such pakka dummy / plugging.
8.42 Refilling of the excavated trench after laying of the line in the proper manner, consolidating and
restoring the road before compaction. Refilling must be done layer wise with proper compaction.
8.43 Firm bed should be provided to the pipe line with the Murrum/sand/rubble where ever required for
which no payment shall be made to the contractor and instructed as per the specifications to achieve the
required slope. Realignment / shifting of the existing utilities (except electricity and telephone) falling in
line of excavation alignment.
8.44 Providing and supplying ISI standard RCC pipes of socket spigot type with rubber-ring joint only shall
be allowed, with in factory Testing in presence of Third-party Inspection Agency. Laying of the pipe
line shall be in the required slope and alignment as instructed in drawing and engineer-in-charge.
8.45 Brickwork Machine hole shall be constructed as per the type design provided by the department.
8.46 Providing safety rails as per the guidelines where ever required and instructed and as per specifications
on side of the excavation for protection and safety.
8.47 Reinstatement of the facilities like road, water supply lines, sewer lines, etc., damaged during
executions as per the guidelines of engineering in charge.
8.48 Ensuring the safety (up to handover of work) of the worker and citizens at the work site during
execution and during monsoon when the work is stopped as per the guidelines of the Engineering in
8.49 Irrespective of any other clause in the tender, the Contractor shall use Ready Mixed Concrete (RMC) for
major concrete works as per instruction of engineer in charge, with minimum cement content specified
in the tender. RMC shall be used of approved make only.
8.50 set of soft copy and 5 set of hard copies of AS-BUILT drawings (showing approved) in a size
acceptable by VMC / PMC / TPI shall be submitted by the contractor to all the agencies (VMC, PMC,
TPI). Final bill shall be cleared only after the submission of As- built drawings.
8.51 Until and unless required and asked for by the Engineer in charge, night work shall not be permitted.
8.52 Works done without informing any/all of the three (VMC, PMC, TPI) and without their presence shall
not be considered valid. Photographs shall be submitted by the contractor fortnightly to monitor the
progress of work.
8.53 The contractor will be responsible to pay a compensation of minimum Rs.30 lakhs in addition to the
compensation paid by Government in the case of death of workman, while working with the sewer
work. Also insurance should be required for all workers.
8.54 No Machinehole Connection will be paid in new constructed Machinehole Old Existing Machinehole
Connections will be paid to contractors.
8.55 Before excavation inform to all agencies like MGVCL, Broadband companies, etc. by using “CBUD”
(Call Before You Dig) application. If any cable damaged by contractor, then repaired it by own cost.
8.56 The work of RCC shaft wall must be done upto Road or GL. In addition to this "9thickness brick
masonry min 0.50 mtr in height from top of RCC shaft wall must be done at site before starting of
Jacking work. After construction of MH the brick wall and RCC shaft wall in @ 1.5to 2.0mtr height
from top must be dismantled before refilling work andno extra payment shall be done for the same.
8.57 Penalty / deduction for not providing Barricades around pit opening in case of trench length both sides
as per site conditions Rs.200 per Rmt of barricades for single side per day, length will be calculated for
both the sides of trench and all shaft/Excavated pit/ Machine holes shall be considered.
8.58 Photographs soft copy as well as hard copy mentioning locations etc. shall be submitted by the
contractor along with all R.A bills & Final bill & fortnightly to monitor the progress of work.
8.59 Design of shaft is in the scope of contractor and shall get it approved by PMC/VMC prior to execution.
8.60 All jacking and receiving RCC shafts for Manual Pushing by well sinking method including backfilling
and road reinstatement, etc.
8.61 Provision of all equipment such as MTBM, CCTV sewer inspection systems, temporary works like
shoring, sheet piles, caisson systems etc. Establishment of MTBM along the pipeline route.
1. The Bidder shall collect all the relevant data about the sites (soil conditions etc.), required for assessing the
work and submitting his Technical and Financial bid.
2. The Preliminary Layout of the work is attached with the Tender. The Network shown in the drawing is
preliminary and can change during the execution. The quantity shown in the tender is preliminary and shall be
finalized after the Pre-Execution survey by the contractor.
3. The size, levels and quantities shown in the Design Sheets are preliminary and can change during execution
(after the pre-execution survey by the Contractor)
4. Existing Utilities: VMC is not having any ready data on the existing utilities likely to meet during the
excavation and laying of pipelines / construction of channel. The shifting of Telephone / Electric Pole shall be
arranged by VMC.
5. VMC has also appointed third-party inspection of the project. Any tests recommended by Consultant or TPI
during the execution of this contract shall be conducted by the contractor in the laboratory acceptable to VMC
/TPI without any extra cost to VMC. The charges of testing and inspection charges (TPI) of any material or of
any type shall be borne by the contractor.
6. The Contractor must Construct R.C.C. Shafts for pushing work as per actual site condition and requirement
(such as change of alignment, distance, etc.) without any other cost.
7. The Contractor must have to do pushing work by Dismantling/Removing of existing R.C.C. drainage gravity
line as per actual site condition.
8. Mode of measurement for pushing work Qty will be measured from Inner side of Machine holes for pushing
9. Any obstruction appeared during manual pushing work such as concrete, concrete block, any type of pipes
(concrete, DI, CI, etc.) shall have to be demolished/broker/removed by the contractor for which no extra
payment shall be paid to the contractor.
(A) Other Items
Any Other Items as required to fulfill all contractual obligations as per the Bid documents. [CL.1.1]
10 . The following documents also form part of the Contract.
11. The law which applies to the Contract is the law of Union of India [CL.3.1]
12. The language of the Contract documents is English [CL.3.1]
13. Limit of subcontracting 25% of the Initial Contract Price [CL.7.1]
18. DELETED [CL.8]
15. The Schedule of Key Personnel As per Annex – II to Section I
16. The minimum insurance cover for physical property, injury and death is Rs. 5 lakhs per occurrence with
the number of occurrences limited to four. After each occurrence, the contractor will pay an additional
premium necessary to make insurance valid for four occurrences always [CL13]
Hon. Court guidelines must be strictly followed by Contractor for drainage work for better safety of
workmen. All the work must be carried out by using all safety equipments and measures and cleaning of
manholes must be by mechanical equipments by the contractor.
The contractor will be responsible to pay a compensation of minimum Rs.30 lakhs in addition to the
compensation paid by Government in the case of death of workman, while working with this work. Also
insurance should be required for all workers.
17. Site Investigation report [CL.14]
19. The period for submission of programme for approval of the engineer shall be 21 days from the issue of
Letter of Acceptance. [CL. 27.1]
20. The period between program updates will be 30 days. [CL.27.3]
23. The currency of the Contract is Indian Rupees [CL. 46]
24. PRICE VARIATION FOR CEMENT, STEEL, PIG IRON, HR COIL & BITUMEN
The amount payable to the contractor for the work done shall be adjusted for increase-decrease in
the rate of Cement, Steel,Pig Iron, HR Coil & Bitumen as under
Price variation for Cement, steel, Pig Iron, HR Coil & Bitumen brought by the contractor.
The star rates of Cement, Steel, Pig Iron, HR Coil & Bitumen to be brought by the contractor shall be
considered at site as per RBI indices of April
Cement (OPC) Rs.325.27/- per bag of 50 Kg.
Pig Iron WPI index 131.60.
HR Coil WPI index 127.00.
TMT steel (FE-500) Rs._62350/- per MT
CRS Fe-500 Rs. 67480/- per MT
Bitumen Rs._56831/- per MT
(The above star rates shall be linked with Reserve Ban of India price index for steel and cement for the
month in which the Tender Documents shall be invited- july 2025).
The fluctuations in rates of steel-reinforcement, cement, HR Coil, Pig Iron & Bitumen shall be adjusted
in the bills payable to the contractors as under:
A= Amount payable or recoverable
B= Star rate of steel-reinforcement / cement / HR Coil / Pig Iron / Bitumen
CI= The (quarterly) average corresponding index for steel-reinforcement, cement, HR Coil, Pig Iron &
Bitumen for the quarter under consideration (as published monthly bulletin of Reserve bank of India)
C0= Price index of steel-reinforcement / cement / HR Coil / Pig Iron / Bitumen for the month in which
the tender documents are invited published in monthly bulletin of Reserved Bank of India.
D= Quantity of steel-reinforcement, cement, HR Coil, Pig Iron & Bitumen actually brought by the
contractor on site of work and consumed in the work during the quarter duly supported with bill as
recorded in cement consumption register or MB (for steel).
• No ceiling for escalation for difference of steel and cement will be applicable.
• This clause shall be operative from the date issue of work order and up to the expiry of original and
extended time limit.
• This formula shall be used individually for cement and steel for calculating adjustment.
• The steel-reinforcement, cement, HR Coil, Pig Iron & Bitumen brought by the contractor on site of
work shall be used only after the same is tested at the cost of contractor or after production of steel
certificate by manufacture as desired by the authority.
• If such materials are not found as per the IS specification, the same shall be removed by the contractor
for which no claim shall be entertained.
This Clause is Only for D.I Type pipe Procurement.
(a) Price Variation Clause will be applicable based on Office of the Economic advisory under Ministry of
Commerce and Industry, Govt. of India, are publishing Wholesale price Index (WPI) for Pig Iron the
Governing material for Manufacture of D.I Pipe. Formula for this tender based on WPI Index as
published by Ministry of Commerce and Industry Govt. of India is as Follow:
(b) Price Variation Formula (PVF) for Supply of materials:
The F.O.R rates quoted by the supplier shall be subject to price variation as per following price
Variation Formula:
VD =Increase or Decrease in the F.O.R Rate of D.I Pipes, in rupees/ meter, to be dispatched from
manufacturers works, during the calendar month, under consideration, due to change in WPI for Foundry
grade Pig Iron.
R =Base F.O.R Rate (Rs/ m) of DI Pipes as per Tender.
D0= The Confirmed monthly Wholesale Price Index (WPI) for pig Iron, of the month in which the online
tender is submitted and as published by office of Economic – Advisor, Ministry of Commerce and
industry on Their website www.eaindustry.nic.in
D1=The Latest available monthly provisional wholesale Price Index (WPI) for Pig iron at the time which
DI pipes are dispatched from manufactures’ works and as published by office of economics advisor,
Ministry of commerce and Industry on their www.eaindustry.nic.in
Transportation charges once quoted shall remain fixed throughout the completion of the entire contract,
no variation will be allowed.
Bidder shall invariably submit a break up of the rates i.e. Basic Rates, Excise Duty/ GST,
Transportation Charges (including Loading, Insurance, Transportation, unloading and Stacking),
E.P.D.M Rubber Gasket etc. shall be furnished on per Rmt. Basis on separate sheet final rate per Rmt.
Arrived here, shall, be mentioned in Schedule – “B” for Calculating final Amount.
25. The proportion of payments retained (retention money) shall be 6% {CL. 48}
from each bill subject to a maximum of 5% of final contract price.
26. Amount of Liquidated damages for For Whole of work {CL.49} delay in
completion of works (1/2000)th of the Initial contract
price, rounded off to the nearest
Thousand, per day.
27. Maximum limit of liquidated damages 10 percent of the Inial {CL. 49}
For delay in completion work Contract Price rounded off to the nearest
28. Amount of Bonus for early completion Amount of bonus for early completion of
work shall be given as per CL.50 of Section-3
29. Maximum limit of bonus for early 5 percent of the Contract {CL. 50}
Completion of work Price
30. The amount of the advance payment are: {CL. 51 & 52}
#Nature of Advances (FOR WORK>5 CRORE) Amount (Rs.) Conditions to Be fulfilled
i Mobilization 5% of the contract Price On submission of unconditional Bank
Guarantee. The contractor may furnish two
bank guarantees of 2.5 % of each valid for
the full period of repayment. (Bank
Guarantee shall be with GST)
Mobilization advance applicable to works costing more than 5 crores.
31. Repayment of advance payment for mobilization {CL. 51.3}
The payment to be made to the Contractor against mobilization advance will be considered as Advance and,
in the format, given by VMC. The advance shall be recovered from the Contractors 2nd, 3rd and 4th running
Bills. The bank Guarantee shall be discharged after recovery of 100% of advance paid to the Contractor.
BG format enclosed as per Section-8.
33. The securities shall be for the following minimum amounts equivalent {CL. 52}
As a percentage of the Contract Price: Performance Security for 5 percent of contract price plus Rs.
…………….. (to be decided after evaluation of the bid) as additional security in terms of ITB
The standard form of Performance security acceptable to the Employer shall be an unconditional Bank
Guarantee of the type as presented in Section 8 of the Bidding Documents.
34. The Schedule of Operating and maintenance Manuals…. N/A. {CLs. 58}
35. The date by which “as– built” drawings (in scale as directed) in 5 sets in soft copy in pen drive as per VMC
format (AutoCAD) with geotagging (latitude & longitude) and 5 sets in hard copy {CL. 58} are required
within 28 days of the issue of certificate of completion of the whole or section of the work, as the case may
36. The amount to be withheld for failing to supply “as built” drawings {CL. 58} by the Date required is Rs
37. The following events shall also be fundamentals breach of contract: {CL.59.2} “The Contractor has
contravened Sub- clause 7.1 and Clause 9 of GCC”
38. The percentage to apply the value of the work not completed representing {Cl 60} the Employer’s
additional cost for completing the Works shall be 20 per cent.
TECHNICAL SPECIFICATION
GENERAL INSTRUCTIONS FOR WORK
DEFINITION OF TERMS: -
In the Contract documents as hereinafter defined the following words & expression shall have the meanings hereby
assigned to them except where the context otherwise requires: -
1. “The Owner or Employer”, means the Municipal Commissioner Vadodara Municipal Corporation, Vadodara
which may abbreviated as “VMC” and includes the Owner’s or Municipal Commissioner, VMC’s authorized
representatives or successors.
2. The abbreviation VMC wherever used in contract shall mean Vadodara Municipal Corporation and term shall be
used to in place of authorized person or persons who will be operating this contract as VMC’s representative and
will include namely Municipal Commissioner, Additional City Engineer and Executive Engineer or their
authorized representatives.
3. The “City Engineer/ Additional City Engineer/ Head of Department”, shall means the City Engineer/ Additional
City Engineer/ Head of Department related to respective department of Vadodara Municipal Corporation and shall
include those who are expressly authorized by him to act on his behalf and who is heading Drainage Department.
4. The “Executive Engineer”, shall means the Executive Engineer of Vadodara Municipal Corporation, who is in
charge of the project and shall include those who are expressly authorized him to act for and on his behalf.
5. The “Engineer in charge”, shall means the Deputy Executive Engineer of Vadodara Municipal Corporation, who
is in charge of the project and shall include those who are expressly authorized him to act for and on his behalf.
6. “The Contractor”, means the person or persons, firm or Company whose tender has been accepted by the Owner
and include the Contractor’s legal representatives, his successor and permitted assignees.
7. The term “Work or Works” of the contract shall mean all of the various classes of works to be executed in
accordance with the contract, whether temporary or permanent, and include all labour and material, machinery,
instruments, construction equipment, plant, plant operation and maintenance, all tools and all other items required
for the completion of the construction. It shall also mean the place of working, where the context so includes.
8. “Contract”, shall mean the Agreement between the VMC and the contractor for the execution of works including
therein all contract documents like Condition of Contract, Specification, Drawings, Prices Bill, Schedule of
quantities, Schedule of rates and prices (if any), work order and all tender.
9. The “Contract Price”, means the sum named in the Tender subject to such additional there to or deduction there
from as may be under the provisions hereinafter the contained.
10. “Construction Plant”, means all machinery, tools, appliances or thing of whatsoever nature required for the
execution, completion or maintenance of the works or temporary works (as hereinafter defined) but does not
include materials or other things form or forming part to the permanent work.
11. “Temporary Works”, means all temporary works of every kind required in or about the execution, completion or
maintenance of the works. The cost of such work associated with tender is included.
12. “Drawings”, means the drawings referred to in the Specification and any modification such drawings approved in
writing by the Head of the Department/Additional City Engineer / Executive Engineer, Consultant and such other
drawings, diagrams, or sketches as may from time to time be furnished or approved in writing by the Head of the
Department/Additional City Engineer / Executive Engineer.
13. “Site”, means the land and other places on under in or through which the permanent works are to be executed or
carried out & any other land or places provided by the Owner for purpose of the contract.
14. Words importing the singular number only also include the plural and vice versa where the context requires.
15. ” Contract Documents”, means collectively the Tender documents, Designs, Drawings, Specifications agreed
variations if any, contract such other documents constituting the Tender and acceptances thereof.
16. “The Specification”, shall mean the various technical specifications attached and referred to in the Tender
documents. It shall also include the latest edition of relevant Indian Standard Specification published before
entering into contract. Further in absence of any specific reference in I.S.S. the standards and specifications of
P.W.D.H.B. or GWSSB as the case may be will be followed as per the consent of Additional City Engineer.
17. The “Tender”, means the tender submitted by the contractor for acceptances by the Owner.
18. The “Alternation Order”, means the order given in writing by the Engineer-in-charge to effect to or deleting
from and alternations in the works.
19. The “Completion Certificates”, shall mean the certificate to be issued by the Additional City Engineer, when the
works have been completed to his satisfaction.
Clause - 1: Security Deposit and Performance Guarantee:
Refer clause 15 of ITB
Refer clause 34 of ITB
Clause 2: Liquidated Damages for Delay
Refer clause 49 of Conditions of contract
Clause 3: Default by Contractor
If the Contractor shall neglect or fail to proceed with work with due diligence or if he violates any of the
provision of the contract, the Engineer-in-Charge shall give the Contractor a notice identifying deficiencies in
performance and demanding corrective action. Such notice shall clearly state that it is given under the
provision of this clause. After services of such notice, the Contractor shall not remove any plant, equipment
and materials from the site. The VMC shall have lien on all such plant, equipment and material from date of
such notice till said deficiencies have been corrected as mentioned in the said notice.
If the Contractor fails to take satisfactory corrective action within ten days after receipt of such notice, the
Engineer - in - charge on behalf of VMC shall terminate the contract in whole. In case, the entire contract is
terminated, the amount of security deposit and performance bond if any together with value of the work done
but not paid for, shall stand forfeited to the VMC. The plants, equipment and materials held under this clause
shall then be at the disposal of the VMC to recover the amount equivalent to the liquidated damages and
registration of the contractor shall be kept in abeyance for three years from the date as fixed in all such cases.
The Engineer-in-Charge, if necessary, shall direct that a part or whole of such plant equipment and materials
be removed from the site within a stipulated period. If the contractor fails to do so the Engineer-in-Charge
shall cause them or any part of them to sold holding the net proceeds of such sale to the credit of the
contractor. After settlement of accounts, the lien by the VMC of the Contractor’s remaining plants, equipment
and balances of materials shall be released. Termination of contract in whole shall be an adequate authority for
the Engineer-in-Charge to demand discharge of the obligations from the guarantors of the security for the
Clause 4: Action when the progress of any particular portion of the work is unsatisfactory
If the progress of any particular portion of the work is unsatisfactory the Engineer-in-Charge shall,
notwithstanding that the general progress of the work is satisfactory, in accordance with the conditions
mentioned in Clause 2, be entitled to take action under Clause 3 after giving the Contractor 10 days’ notice in
writing, and the Contractor will have no claim for compensation for any loss sustained by him owing to such
Clause 5: Contractor remains liable to pay compensation if action not taken under Clauses 2, 3 &
In any case in which any of the powers conferred upon the Engineer-in-Charge by Clause 2, 3 & 4 hereof shall
have become exercisable and the same shall not have been exercised, the non-exercise thereof shall not
constitute a waiver of any of the conditions hereof and such power shall notwithstanding be exercisable in any
future case of default by the Contractor under any clause or clauses before he is declared liable to pay
compensation amounting to the whole of his security deposit and the liability of the Contractor for past and
future compensation shall remain unaffected. In the event of the Engineer-in-Charge taking action under
Clause 2,3 and 4, he may, if he so desired, take possession of all or any tools, plants, materials and stores, in or
upon work or the site thereof or belonging to the Contractor or procured by him and intended to be used for the
execution of the work or any part thereof, paying or allowing for the same in account at the contract rates or in
the case of contract rates not being applicable at current market rates to be certified by the Engineer In Charge
whose certificates thereof shall be final.
In the alternative the Engineer-in-Charge, may after giving a notice in writing to the Contractor or his clerk, or
the works Foreman or other authorized agent require him to remove such tools, plant, materials or stores from
premises within a time to be specified in such a notice and in the event of the Contractor failing to comply
with any such requisition the Engineer-in-Charge may remove them at the Contractor’s expenses or sell them
by auction to private sale at the risk and cost of the Contractor in all respects and the certificate of the
Engineer-in-Charge as to the expense of any such removal and the amount and the proceeds and expense of
any such sale shall be final and conclusive against the Contractor.
Clause 6: Extension of time limit / non-working days For the Work
Refer Section 3 part -B Clause 28 of ITB
Clause 7: Final Certificate (Read in Conjunction With Section 3 Part D Clause 42 of ITB)
On completion of the work, the Contractor shall have to submit completion certificate from PMC as well as
TPI. Then after he shall be furnished with a certificate by the Engineer In- Charge (hereinafter called the
Engineer-In-Charge, VMC) of such completion but no such certificate shall be given nor shall the work be
considered to be completed until the Contractor shall have removed from the premises on which the work shall
have been executed all scaffolding, surplus materials and rubbish, and shall have cleaned off the dirt from all
wood work, Steel works, walls, floor or other parts of any building, in or upon which the work has been
executed or of which he may have had possession for the purpose of executing the work, nor until the works
shall have been measured by the Engineer-In-Charge, VMC or where the measurements have been taken by
his subordinates until they have received the approval of the Engineer-In-Charge, VMC, the said
measurements being binding and conclusive against the Contractor. If the Contractor shall fail to comply with
the requirements of this clause as to removal of scaffolding, surplus materials and rubbish and cleaning off dirt
on or before the date fixed for the completion of the work, remove such scaffolding, surplus materials and
rubbish and dispose off the same as he thinks fit and clean off such dirt as aforesaid and the Contractor shall
forthwith pay the amount of all expenses so incurred but shall have no claim in respect of any such scaffolding
or surplus material as aforesaid except for any sum actually realized by the sale thereof.
Clause 8: Payments on intermediate bill to be regarded as advance
No payment shall be made for any work of estimated cost less than Rupees One Crore except for initial period
till after the whole of the said work shall have been completed and a certificate of completion given. But in the
case of works estimated to cost more than rupees One Crore, the Contractor shall, on submitting a monthly bill
therefore be entitled to receive payment proportionate to the part of the work then approved and passed by the
Engineer-In- Charge, VMC, whose certificate of such approval and passing of the sum so payable shall be
final and conclusive against the Contractor. All such intermediate payments shall be regarded as payments by
way of advance against the final payments only and not as payments for work actually done and completed
and shall not preclude the Engineer-In-Charge, VMC from requiring bad, unsound, imperfect or unskilled
work to be removed or taken away and reconstructed, or re-erected, nor shall any such payment be considered,
as an admission of the due performance of the contract or any part thereof in any respect, or the accruing of
any claim nor shall it conclude, determine, or effect in any way the powers of the Engineer-In- Charge, VMC
as to the final settlement and adjustment of the accounts or otherwise or in any otherwise or in any other way
vary or affect the contract. The final bill shall be submitted by the Contractor within three months of the date
fixed for the completion of the work, otherwise the Engineer-In-Charge, VMC’s certificate of the
measurements and of the total amount payable for the work shall be final and binding on all parties.
measurements and of the total amount payable for the work shall be final and binding on all parties.
Clause 9: Deleted.
Clause 10: Bills to be submitted monthly (Read in Conjunction With Section 3 Part D Clause 42 of ITB)
A bill shall be submitted by the Contractor each month on or before the date fixed by the Engineer-In-Charge,
VMC for all works executed in the previous month and the Engineer-In-Charge, VMC shall take or cause to be
taken the requisite measurement for the purpose of having the same verified and the claim, so far as it is
admissible, shall be adjusted, if possible, within ten days from the presentation of the bill. If the Contractor
does not submit the bill within the time fixed as aforesaid, the Engineer-In-Charge, VMC may depute a
subordinate to measure up the said work in the presence of the Contractor or his duly authorized agent whose
countersignature to the measurement list shall be sufficient warrant and the Engineer-In-Charge, VMC may
prepare a bill from such a list which shall be binding on the Contractor in all respects.
Clause 11: Bills to be on printed forms
The Contractor shall submit all bill on the printed forms to be had on application from the office of the
Engineer-In-Charge, VMC. The charges to be made in the bills shall always be entered at the rates specified in
the tender or in the case of any extra work ordered in pursuance of those conditions and not mentioned or
provided for in the tender, at the rates hereinafter provided for such work.
Clause 12: Drawings, designs, instructions of the Engineer-In-Charge, VMC and specifications, order of
precedence in case of discrepancies.
The Contractor shall execute the whole and every part of the work in the most substantial and workman like
manner and both as regards materials and in other respects in strict accordance with specifications. The
Contractor shall also conform exactly, fully and faithfully to the design, drawings and instructions in writing
relating to the work signed by the Engineer-In-Charge, VMC and lodged in his office and to which the
Contractor shall be entitled to have an access for the purpose of inspection at such office or on the site of the
work during office hours.
Where the instructions referred to above are not contained in separate letters addressed to the contractor the
same shall be recorded in the work-order book, which shall be maintained and kept on the site of the work.
The contractor shall be required to sign such entries in the work- order book in token of having noted the
instructions. However, if the contractor fails to sign the work-order book for any reason whatsoever, the entry
of the instructions in the work-order book shall be deemed to be the due notice to him of the said instructions.
The work- order book shall be open for inspections to the contractor on the site of the work during office
hours. The various documents foregoing the contract are essential parts of the contract and a requirement
occurring in one is a binding as through in all. They are intended to be mutually explanatory and
complementary and to describe and provide for a complete work. In the event of any discrepancy in the several
documents forming the contract or in any one document, the following order of precedents should apply.
Dimension and quantities: (1) Drawings (2) Item of BOQ (price bid) (3) Specification and drawings, figured
dimensions, unless obviously incorrect, will be followed in preference to scaled dimensions.
Description: (1) Item of BOQ (price bid) (2) Drawings (3) Specifications. In the case of defective description
or ambiguity, the Engineer-In-Charge, VMC shall be entitled to make corrections and interpretations as
necessary to fulfill the plans and specifications.
Clause 13: Excess over tender Quantities, Extra items and Variations
Refer Section 3 Part D Clause 38 of ITB
Clause 14: No claim to any payment or compensation for alteration in or restriction of work
If at any time after the execution of the contract documents, the Engineer-In-Charge, VMC shall for any
reason whatsoever, require the whole or any part of the work, as specified in the tender, to be stopped for any
period or shall not require the whole or part of the work to be carried out at all or to be carried out by the
Contractor, he shall give notice in writing of the fact to the Contractor who shall thereupon suspend or stop the
work totally or partially, as the case may be. In any such case, except as provided hereunder the Contractor
shall have no claim to any payment or compensation whatsoever on account of any profit or advantage which
he might have derived from the execution of the work in full but which he did not so derive in consequence of
the full amount of the work not having been carried out, or on account of any loss that he may be put to on
account of materials purchased or agreed to be purchased or for unemployment of labour recruited by him. He
shall not have also any claim for compensation by reason of any alterations having been made in the original
specifications, drawings, designs and instructions, which may involve any curtailment of the work, as
originally contemplated. Where, however, the Contractor will be entitled for compensation for loss, if any on
the date of notice, the purchased materials or for the contract executed for the materials to be purchased for
such work. Such compensation will be paid for only actual loss for materials, if such materials so purchased or
agreed to purchase is of required quantity/quality and was purchased/contracted to be purchased for the same
work. But no compensation shall be granted to the Contractor on material for which advance has been given to
the Contractor by VMC. The amount of loss for such claim will be decided by Engineer- In-Charge, VMC,
whose decision shall be final. If the Contractor suffers any loss on account of his having to pay labour charges
during the period during which the stoppage of work has been ordered under this clause, the Contractor shall,
on application, be entitled to such compensation on account of labour charges as the Engineer- In-Charge,
VMC, whose decision shall be final, may consider reasonable. Provided the Contractor shall not be entitled to
any compensation on account of labour charges, if in the opinion of the Engineer-In-Charge, VMC, the labour
could have been employed by the Contractor elsewhere for the whole or part of the period during which the
stoppage of work has been ordered as aforesaid.
Clause 15: Time limit for unforeseen claims
Under no circumstances whatever shall the Contractor be entitled to any compensation from VMC on any
account unless the Contractor shall have submitted a claim in writing to the Engineer-In-Charge within one
month of the cause of such a claim occurring.
Clause 16: Action and compensation in case of bad work (Read in Conjunction with Section 3 Part C
Clause 35 and 36 of ITB)
If, at any time before the security deposit is refunded to the Contractor, it shall appear to the Engineer-In-
Charge, VMC or his subordinate in charge of the work, that any work has been executed with unsound,
imperfect or unskillful workmanship or with materials of inferior quality or that any materials or articles
provided by him for the execution of the work are unsound, or of a quality inferior to that contracted for, or are
otherwise not in accordance with the contract, it shall be lawful for the Engineer-In- Charge, VMC to intimate
this fact in writing to the Contractor and then notwithstanding the fact that the work, materials or articles
complained of may have been inadvertently passed, certified and paid for, the Contractor shall be bound
forthwith to rectify or remove and reconstruct the work so specified in whole or in part, as the case may
require, or if so required, shall remove the materials or articles so specified and provide other proper suitable
materials or articles at this own charge and cost and in the event of his failing to do so within a period to be
specified by the Engineer-In-Charge, VMC in the written intimation aforesaid, the contractor shall be liable to
pay compensation at the rate of one percent on the amount of the estimate for every day nor exceeding ten
days, during which the failure so continues and in the case of any such failure as aforesaid the Engineer-In-
Charge, VMC may rectify or remove and re- execute the work or remove and replace the materials or articles
complained of as the case may be at the risk and expense in all respect of the Contractor should the Engineer-
In- Charge, VMC consider that any such inferior work or materials as described above may be accepted or
made use of it shall be within his discretion to accept the same at such reduced rates as he may fix, therefore.
However, the contractor shall be responsible for the normal maintenance of the work till the final bill of the
work is prepared by the Departmental Officer.
Clause 17: Deleted
Clause 18: Works to be open to inspection, Contractor or responsible agent to be present
All works under or in course of execution or executed in pursuance of the contract shall at all times, be open to
the inspection and supervision of the Engineer-In-Charge, VMC and his subordinates and the Contractor shall
at all times during the usual working hours, and at all his subordinate to visit the works shall have been given
to the Contractor, either himself be present to receive orders and instructions, or have a responsible agent duly
accredited in writing present for the purpose. Orders given to the Contractor’s duly authorized agent shall be
considered to have the same force and effect as if they had been given to the Contractor himself/herself.
The contractor shall also supply without charge the requisite number of persons with the means and materials
necessary for the purpose of setting out works, and counting, weighing and assisting in the measurement or
examination at any time of the work or materials, failing this the same may be provided by the Executive
Engineer at the expense of the contractor and the expense may be deducted from any money due to the
contractor under the contract or from his Security Deposit. The contractor shall provide all necessary fencing
and lights required to protect the public from accident and shall also be bound to bear the expense of defence
of every suit, action or other legal proceedings, at law, that may be brought by any person for injury sustained
owing to neglect of the above precautions, and to pay any damages and costs which may be awarded in any
such suit, action or proceedings to any such persons or which may be with the consent of the contractor be
paid in compromising any claim by any such person.
Clause 18A: Employment of a qualified site Engineer by the Contractor.
The contractor shall employ full-time technically qualified staff during the execution of this work as specified
in this tender. The Engineers so employed for the Government work must have sufficient experience to handle
the work independently. Such an Engineer shall have to stay at the site of work and he shall not be entrusted
with other duty except this work. In case the contractor or partner of the contractor firm is a Civil Graduate
Engineer, Employment of the separate Engineer will not be necessary provided that the Engineer partner
himself attends the execution of work on the site.
At least 1 No. of Construction Engineer (Diploma In Civil Engg.) shall be deputed for full time. In the
Absence Rs. 1000/- per Day will be deducted from Bill. (not only for engineer for all staff)
Clause 19: Notice to be given before work is covered up
The Contractor shall give not less than five days’ notice in writing to the Engineer-In- Charge, VMC or his
subordinate in charge of the work before covering up or otherwise placing beyond the reach of measurement
any work in order that the same may be measured and correct dimensions thereof taken before the same is so
covered up or placed beyond the reach of measurement and shall not cover up or place beyond the reach of
measurement without the consent in writing of the Engineer-In-Charge, VMC of his subordinate-in- charge of
the work and if any work shall be covered up or placed beyond the reach of measurement without such notice
having been given or consent obtained the same shall be uncovered at the Contractor’s expense and in default
thereof no payment or allowance shall be made for such work or for the materials with which the same was
Clause 20: Contractor liable for damage and for imperfections for months after Payment of RA or
completion certificate
If the Contractor or his workmen, or servant shall break, deface, injure or destroy any part of a building in
which they may be working or any building, road, fence, enclosure or grass land or cultivated ground
continuous to the premises on which the work or any part thereof is being executed or if any damage shall be
done to the work from any cause whatever while it is in progress or if any imperfections become apparent in it
within one year from the grant of a certificate of completion, final or otherwise, by the Engineer-In-Charge,
VMC, the Contractor shall make good the same at his own expenses or in default, the Engineer-In-Charge,
VMC may cause the same to be made good by other workmen, and deduct the expenses (of which the
certificate of the Engineer- In-Charge, VMC shall be final) from any sums that may then be due or may
thereafter become due to the Contractor or from his security deposit or the proceeds of sale thereof or as
sufficient portion thereof.
Clause 20A: Force majeure
Any delays in or failure of the performance of either part hereto shall not constitute default hereunder or give
rise to any claims for damages, if any to the extent such delays or failure of performance is caused by
occurrences such as acts of God or the public enemy appropriation or confiscation of facilities by Government
authorities act of war, rebellion or subterfuge or fire, flood, explosion, riots or illegal strikers. The contractor
shall keep records of the circumstances referred to above and bring these to the notice of Purchaser/Client in
writing immediately on such occurrences.
Clause 21: Contractor to supply plant ladders scaffoldings, etc. and is liable for damage arising from
non- provision of lights, fencing etc.
The Contractor shall supply at his own cost all materials, (except such special material, if any, as may, in
accordance with the contact be supplied from the VMC Store) plant, tools, appliances, implements, ladders,
cordage, tackle, scaffolding, shoring, strutting and any temporary works which may be required for the proper
execution of the work, whether in the original, altered or sustained form and whether included in the
specifications, or other documents forming part of the contract or referred to in these conditions or not and
which may be necessary for the purpose of satisfying or complying with requirements of the Engineer-In-
Charge, VMC as to any matter or to which under these conditions he is entitled to be satisfied, or which he is
entitled to required together with carriage therefore to and from the work. The Contractor shall also supply
without charges the requisite number of persons with the means and materials necessary for the purpose of
setting out works and counting, weighting and assisting in the measurement or examination at any time and
from time to time of the work or the materials. Failing this, the same may be provided by the Engineer- In-
Charge, VMC at the expense of the Contractor and the expenses may be deducted from any money due to the
Contractor under the contract or from this security deposit or the proceeds of sale thereof or of a sufficient
portion thereof. The Contractor shall provide all necessary fencing and light required to protect the public from
accident and shall also be bound to bear the expenses of defence of every suit, action or other legal
proceedings, at law that may be brought by any person for injury sustained owing to neglect of the above
precautions and to pay any damage and costs which may be awarded in any such suit, action or proceeding to
any such person, or which may, with the consent of the Contractor be paid in compromising any claim by any
such persons. Further,
The contractor to indemnify the VMC
The VMC shall not be liable for or in respect of any damages or compensation payable by law in respect or in
consequence of any accident of injury to any workman or other person in the employment of the contractor or
his any sub-contractor or any other outside person/persons and contractor shall indemnify the VMC against
such damages and compensation and against all claims, demands, proceedings, costs, charges, expenses
whatsoever in respect thereof or in relation thereto.
Payments of Claims and Damages
VMC have to pay any money in respect of such claims or demands as aforesaid the amount so paid and the
costs incurred by the VMC shall be charged to and paid by the contractor and the contractor shall not be at
liberty to dispute or question the right of the VMC to make such payments notwithstanding the same may have
been made without his consent or authority or in law or otherwise to the contrary.
The contractor shall provide suitable scaffolds, and working platforms, gangways and stairways and shall
comply with the following regulations in connection therewith:
a) Suitable scaffolds shall be provided for workmen for all work that cannot be safely done from ladder or by
b) A scaffold shall not be constructed, taken down or substantially altered except:
1. A scaffold shall not be constructed, taken down or substantially altered except:
2. As far as possible by competent workers possessing adequate experience in this kind of work.
c) All scaffolds and appliances connected therewith and all ladders shall: -
1. Be of adequate strength having regard to the loads and strains to which they will be subjected,
2. Be maintained in proper condition.
d) Scaffolds shall be so constructed that no part thereof can be displaced in consequence of normal use.
e) Scaffolds shall not be overloaded and so far as practicable the load shall be evenly distributed.
f) Before installing the lifting gear on scaffolds special precautions shall be taken to ensure the strength
stability of the scaffolds.
g) A competent person shall periodically inspect scaffolds.
h) Before allowing a scaffold to be used by his workmen, the Contractor shall, whether the scaffold
has been erected by his workmen or not, take steps to ensure that it complies fully with regulations
herein specified.
i) Working platforms, gangways and stairways shall: -
1. Be so constructed that no part thereof can sag unduly or unequally.
2. Be so constructed and maintained having regard to the prevailing conditions as to reduce as far as
practicable risks of persons tripping or slipping and
3. Be kept free from any unnecessary obstruction
j) In this case of working platforms, gangways, working places, and stairway at a height exceeding
3.25 meters (To be specified).
1. Every working platform and every gangway shall be closely boarded unless other adequate
measures are taken to ensure safety. Every working platform and gangway shall have adequate
2. Every working platform, gangway, working place and stairway shall be suitably fenced.
k) Every opening in the floor of a building or in a working platform shall, except for the time and to
the extent required to allow the access of person or the transport or shifting or materials be
provided with suitable means to prevent the fall of persons or materials.
l) When persons are employed on a roof where there is a danger of falling from a height exceeding
3.25 meters (to be prescribed) suitable precaution shall be taken to prevent the fall of persons on
m) Suitable precautions shall be taken to prevent persons being struck by articles which might fall
from scaffolds or other working places.
n) Safe means of access shall be provided to all working platforms and other working places.
Contractor shall comply with the following regulation as regards the Hoisting Appliances to be used by him:
a) Hoisting machines and tackle including their attachment anchorage and support shall:
1. Every working platform and every gangway shall be closely boarded unless other adequate
measures are taken to ensure safety. Every working platform and gangway shall have adequate
2. Every working platform, gangway, working place and stairway shall be suitably fenced.
b) Every rope used in hoisting or lowering materials or as a means of suspension shall be of suitable
quality and adequate strength and free from patent defect.
c) Hoisting machines and tackle shall be examined and adequately tested after erection on the site
and before use and be re-examined in position at intervals to be prescribed by Engineer- In-
d) Every chain, ring, hook, shackle, swivel and pulley block used in hoisting of lowering, materials
or as a means of suspension shall be periodically examined.
e) Every crane driver or hoisting appliance-operator shall be properly qualified.
f) No persons who are below the age of 14 years shall be in control of any hoisting machine,
including any scaffold nor shall give signals to the operator.
g) In the case of every hoisting machine and of every chain, ring, hook, shackle, swivel and pulley
block used in hoisting or lowering or as a means of suspension, the safe working load shall be
ascertained by adequate means.
h) Every hoisting machine and all gear referred to in the proceeding regulation shall be plainly
marked with the safe working load.
i) In the case of a hoisting machine having a variable safe working load, each safe working load and
the conditions under which it is applicable, shall be clearly indicated.
j) No part of any hoisting machine or of any gear referred to in regulation `g’ above shall be loaded
beyond the safe working load except for the purpose of testing.
k) Motors, gearing, transmissions, electric wiring and other dangerous parts of hoisting appliance
shall be provided with sufficient safeguards.
l) Hoisting appliances shall be provided with such means as will reduce to a minimum the risk of the
accidental descent of the load.
m) Adequate precaution shall be taken to reduce to a minimum the risk of any part of a suspended
load becoming accidentally displaced.
Clause 22: Measures for prevention of fire
The Contractor shall not set fire to any standing jungle, trees, bush wood or grass without a written
permit from the Engineer-in-Charge. When such permit is given, and also in all cases when
destroying, cut or dug up trees, bush wood, grass, etc., by fire the contractor shall take necessary
measures to prevent such fire spreading to or otherwise damaging surrounding property. The
Contractor shall make this own arrangement for drinking water for the labour employed by him/her.
Clause 23: Liability of contractor for any damage done in or outside work area
Compensation for all damages done intentionally or unintentionally by Contractor’s labours, whether
in or beyond the limits of VMC property, including any damage caused by the spreading of fire
mentioned in clause 22, shall be estimated by the Engineer-In-Charge, VMC, subject to the decision
of the Engineer-in-Charge, on appeal, shall be final and the Contractor shall be bound to pay the
amount of the assessed compensation on demand failing which the same will be recovered from the
Contractor as damages in the manner prescribed in Clause 1 or deducted by the Engineer-In-Charge,
VMC from any sums that may be due to or become due from VMC to the Contractor under this
contract or otherwise.
The Contractor shall bear the expense of defending any action or other legal proceedings that may be
brought by any person for injury sustained by him owing to neglect of precautions to prevent the
spread of fire and he shall also pay any damage and cost that may be awarded by the court in
Clause 24: deleted
Clause 25: Work on Sunday/Holiday
No work shall be done on a Sunday/Holiday without the sanction in writing of the Engineer-In-
Clause 26: Work not to be sublet. The contract may rescind and security deposit forfeited for
subletting it. (Read in Conjunction with Point 13 of Contract Data).
The contract shall not be assigned or sublet without the written approval of the Engineer-In- Charge,
VMC. And if the Contractor shall assign or sublet his contract, or attempt to do so or become
insolvent or commence any proceedings to get himself adjudicated as an insolvent or make any
compromise with his creditors or attempt to do so, the Engineer-In-Charge, VMC may, by notices in
writing rescind the contract. Also if any bribe, gratuity, gift, loan, perquisite, reward or advantage,
pecuniary or otherwise, shall either directly or indirectly be given, promised or offered by the
Contractor, or any of the servants or agents to any public officer or person in the employ of VMC in
any way relating to his office or employment, or if any such officer or person shall become in any
way directly interested in the contract , the Engineer-In-Charge, VMC may thereupon, by notice in
writing, rescind the contract.
In the event of a contract being rescinded, the security deposit of the Contractor shall thereupon stand
forfeited and be absolutely at the disposal of VMC and the same consequences shall ensure as if the
contract had been rescinded under Clause 3 hereof and in addition the Contractor shall not be entitled
to recover or be paid for any work therefore actually performed under the contract. VMC will ask to
contractor to provide the Invoices of Purchase materials for checking.
Clause 27: Sum payable by way of compensation to be considered as reasonable compensation
without reference to actual loss.
All sums payable by a Contractor by way of compensation under any of these conditions shall be
considered as a reasonable compensation to be applied to the use of VMC without reference to the
actual loss or damage sustained and whether any damage has or not been sustained.
Clause 28: Changes in the constitution of firm to be notified
In the case of a tender by partners, any change, in the constitution of a firm shall be forthwith notified
by the Contractor to the Engineer-In-Charge, VMC for his information.
Clause 29: Works to be under direction of Engineer-in-Charge
All works to be under the contract shall be executed under the direction and subject to the approval in
all respects of the Engineer-in-Charge of the VMC who shall be entitled to direct at what point or
points and in what manner are to be commenced and from time to time carried on.
Clause 30: Settlement of Dispute Arbitration
(Refer Clause 24.3-part A of Section 3 of ITB)
Clause 31: Decision of Engineer-In-Charge, VMC to be final (Read in Conjunction with Section
3 Part A Clause 4 of ITB)
Except where otherwise specified in the contract and subject to the powers delegated to him/her by
VMC, the code, rules then in force the decision of the Engineer-In-Charge, VMC shall be final,
conclusive and binding but subject to arbitration, if the contractor is not satisfied with the meaning of
the specifications, designs, drawings, and instructions herein before mentioned and as to the quality
or workmanship, or materials used on the work or as to any other question, claim, right, matter or
thing whatsoever, in any way arising out of or relating to the contract, designs, drawings,
specifications, estimates, instructions, orders of these conditions or otherwise concerning the works
or the execution of failure to execute the same, whether arising during the completion or
abandonment thereof.
Clause 32: Access to the Site
The contractor shall arrange to construct, maintain and afterwards remove and reinstate any
temporary access required for and in connection with execution of the works. Reinstatement shall
include restoring the area of the access route to at least the degree of safety, stability, drainage and
appearance that existed before the Contractor entered the site.
Clause 33: Lump sum in estimates (If Applicable)
When the estimate on which a tender is made include Lump sum in respect of parts of the work, the
Contractor shall be entitled to payment in respect of the items of work involved or the part of the
work in question at the same rates as are payable under this contract for such items or if the part of
the work in question is not in the opinion of the Engineer-In-Charge, VMC capable of measurement,
the Engineer-In- Charge, VMC may, at his discretion, pay the Lump sum amount entered in the
estimate and the certificate in writing of the Engineer-In-Charge, VMC shall be final and conclusive
against the Contractor with regard to any sum or sums payable to him under the provisions of this
Clause 34: Deleted
Clause 35: Deleted
Clause 36: Deleted
Clause 37: Royalties
The contractor shall pay the royalty to the competent authority/local body as per rules and shall
produce “No Due Certificate” from the Royalty Inspector having jurisdiction over the work site area,
to the Engineer-In- Charge, VMC before claiming refund of Security Deposit. The royalty charges
paid shall not be refunded to the Contractor.
Clause 38: Compensation under the Workmen’s Compensation Act (Read in Conjunction with
Section 3 Part F Clause 64 of ITB)
The Contractor shall be responsible for and shall pay any compensation to his workmen payable
under the Workmen’s Compensation Act, 1923 (VIII of 1923), (hereinafter called the said Act) for
injuries caused to the workmen. If such compensation is paid by VMC as principal under sub-section
(1) of section 12 of the said Act on behalf of the Contractor, it shall be recoverable by VMC from the
contractor under sub-section (2) of the said section. Such compensation shall be recovered in the
manner laid down in Clause 1 above.
In every case in which by virtue of the provisions sub-section (1) of Section 12, of the Employee’s
Compensation Act, 1923, Employer is obliged to pay compensation to a workman employed by the
Contractor, in execution of the Works, Employer will recover from the Contractor the amount of the
compensation so paid; and, without prejudice to the rights of the Employer under sub-section (2) of
Section 12, of the said Act, Employer shall be at liberty to recover such amount or any part thereof by
deducting it from the Security Deposit or from any sum due to the Contractor whether under this
Contract or otherwise. Employer shall not be bound to contest any claim made against it under sub-
section (1) Section 12, of the said Act, except on the written request of the Contractor and upon his
giving to Employer full security for all costs for which Employer might become liable In
Consequence of contesting such claim.
Clause 39: Liability of the Contractor in case of accidents
The contractor shall be responsible for and shall pay the expenses of providing medical aid to public
or to any workmen who may suffer a bodily injury as a result of an accident. If such expenses are
incurred by Government, the same shall be recoverable from the Contractor forthwith and be
deducted, without prejudice to any other remedy of Government, from any amount due or that may
become due to the Contractor. For any accident due to this work, Agency is fully responsible in all
Clause 39A: Medical Aid to Workmen
The contractor shall be responsible for and shall pay the expenses of providing medical aid to any
workmen who may suffer a bodily injury as a result of an accident. If VMC incurs such expenses, the
same shall be recoverable from the Contractor forthwith and be deducted, without prejudice to any
other remedy of VMC, from any amount due or that may become due to the Contractor.
Clause 39B: Safety and First Aid
The Contractor shall provide all necessary personal safety equipment and first aid apparatus available
for the use of the persons employed on the site and shall maintain them in the same condition suitable
for immediate use at any time and shall comply with the following regulations in connection
1. The workers shall be required to use the equipment so provided by the Contractor and the
Contractor shall take adequate steps to ensure proper use of the equipment by those concerned.
2. When work is carried on in proximity to any place where there is a risk of drowning, all necessary
equipment shall be provided and kept ready for use and all necessary steps shall be taken for the
prompt rescue of any person in danger.
3. Adequate provision shall be made for prompt first aid treatment of all injuries likely to be
sustained during the course of the work.
Clause 40: Claim for quantities of work entered in the tender or estimate
Quantities shown in the tender are approximate and no claim shall be entertained for quantities of
work executed being either more or less than those entered in the tender or estimate.
Clause 41: Deleted
Clause 42: Claim for compensation for delay in starting the work
No compensation shall be allowed for any delay caused in the starting of the work on account of
acquisition of land or in the case of clearance works on account of any delay in according to sanction
Clause 43: Claim for compensation for delay in the execution of work
No compensation shall be allowed for any delay in execution of the work on account of water
standing in borrows pits or compartments. The rates are inclusive of hard or cracked soil, excavation
in mud, sub-soil water or water standing in borrows pits and no claim for an extra rate shall be
entertained unless otherwise expressly specified.
Clause 44: Entering upon or commencing any portion of work
The Contractor shall not enter upon or commence any portion of work except with written authority
and instructions of the Engineer-In-Charge, VMC or of his subordinate in charge of the work failing
such authority the Contractor shall have no claim to ask for measurements of or payment for work.
Clause 45: DELETED
Clause 46: Method of payment (Read in Conjunction with Section 3 Part D Clause 43 of ITB)
Payment of Contractors shall be made by cheque / through ECS drawn on Bank within the division
convenient to VMC. The contractor shall intimate in writing about details of account as & when
Any sum of money due and payable to the Contractor (including the security deposit returnable to the
under this Contract shall be appropriated by the VMC and shall be set off against any claim of the
contractor with the VMC for the payment of a sum of money arising out of or under any other
contract made by the Contractor with the VMC. When no such amount of the purpose of the recovery
from the Contractor against any claim of the VMC is available, such a recovery shall be made from
the Contractor as arrears of land revenue.
Clause 47: Acceptance of conditions compulsory before tendering for work
Any Contractor who does not accept these conditions shall not be allowed to tender for works.
Clause 48: Employment of Scarcity Labour
If Government declares a state of scarcity or famine to exist in any village situated within
kilometres of the work, the piece worker/contractor shall employ upon such parts of the work as are
suitable for unskilled labour, any persons certified to him by the Engineer-in-Charge, or by any
person to whom the Engineer-in-Charge may have delegated this duty in writing to be in need or
relief and shall be bound to pay such persons wages not below the minimum which VMC may have
fixed in this behalf. Any disputes, which may arise in connection with the implementation of this
clause, shall be decided by the Engineer-In-Charge VMC whose decision shall be final and binding
on the piece worker/Contractor.
Clause 49: Prices quoted by the Contractor
Refer clause 12 of IFB
Clause 50: Rates inclusive of all Taxes
Refer clause 45 of part D of section 3of IFB
Clause 51: Deleted
Clause 52: Fair Wages
Refer Section 3 Part F Clause 64 of ITB
Clause 53: Shed for Materials
The Contractor will have to construct shed for storing materials with locking arrangements. The
materials will be taken for use in the presence of the departmental persons. No material will be
allowed to be removed from the site of work.
Clause 54: List of Machinery
The Contractor shall also give a list of machinery (Annexure-08) in his possession and which he
proposes to use on the work.
Clause 55: Deleted
Clause 56: Deleted
Clause 57: Deleted
Clause 58: Pure and wholesome water for labourers
The Contractor shall provide an adequate supply of pure and wholesome water for the use of
labourers. This provision shall be at the rate of not less than 10 gallons per head; no provision need
be made where there is a suitable nallah, river or well within 250 metres of the camp.
a) The Contractor shall construct trench or semi-permanent latrines for the use of the labourers; such
latrines shall be on the scale of not less than 5 per 100 persons in the camp, separate latrines shall
be provided for system.
b) The Contractor shall build a sufficient number of huts on a suitable plot of land for the use of the
labourers according to the following specification:
1. Huts of bamboo and grass may be constructed.
2. A good site shall be selected. High ground, removed from jungle but well provided with trees, shall be
chosen wherever it is available. The neighbourhood of tank, jungle, and grasses avoided. Camps should
not be established close to large cutting or cuttings of earthwork.
3. The lines of huts shall have open spaces of at least 4 meters between rows. When a good natural site
cannot be procured, particular attention should be given to the drainage.
4. There should be no overcrowding. Floor space at the rates of 30 square feet per head shall be provided.
Care should be taken to see that the huts are kept clean and in good order.
c) The Contractor shall construct a sufficient number of bathing places, every unit of 20 persons being
provided with a separate bathing place. Such bathing places should be suitably screened, and separate place
provided for men and women. Washing places should also be provided for the purpose of washing clothes.
Every unit of 30 persons shall have at least one washing place.
d) The Contractor shall make efficient arrangements for draining away the sullage water as well as water from
the bathing and washing places and shall dispose off this waste water in such a way as not to cause
e) The Contractor shall engage medical officer with a traveling dispensary for a camp containing 500 or more
persons if there is no other private dispensary situated within 8 kilometers from the camp.
f) The Contractor shall provide the necessary staff for effecting the satisfactory conservancy and cleanliness of
the camp to the satisfaction of the VMC Officers. At least one sweeper per 200 persons should be engaged.
g) The Engineer-In-Charge VMC shall be consulted before opening a labour camp and his instructions on
matters, such as, the water supply, sanitary convenience, the camp site, accommodation and food supply shall
be followed by the Contractor.
1. The authorities in charge of the colonies should get the labourers inoculated against Cholera, and
Plague at the time of recruitment if they are not inoculated or vaccinated within 6 months prior to
and date of recruitment.
2. When in any labour camp there is an outbreak of an epidemic disease or is threatened with such an
outbreak the authorities in charge of the labour camps should ensure that all the inmates of the labour-
colonies are inoculated or vaccinated, as the case may be depending on the disease, within 72 hours after
3. The authorities, in charge of the labour colony should arrange to communicate by telegram
regarding the outbreak of the epidemic diseases, on the very day of the outbreak to the Engineer-
4. When the authorities, in charge of the labour colony suspect or have reason to believe that any inmate of
the labour colony is suffering from the infections or contagious disease, they shall forthwith arrange for the
segregation of such persons in isolated huts to be specifically provided for the purpose and also for their
5. As regional malaria epidemic outbreaks are likely to occur in such project areas, the authorities in
charge of Health Office of the VMC and also arrange to institute all necessary anti-malaria
measures as may be advised by the Health Officer.
The authorities in charge of the colonies should also arrange to carry out any other measures that may
be recommended by the officials of the Health Department necessary to prevent or control the spread
Clause 59: No distinction between Harijans and other workers
The contractor shall not show any distinction between Harijan and other class of labourers/workers
employed to carry out the VMC work.
Clause 60: Fencing and Lighting
The contractor shall, unless, otherwise specified, be responsible for the proper fencing, lighting,
grading and taking of the necessary safety measures for all works comprised in the same may be
rendered necessary by reasons of the work for the accommodation of workmen, for passengers or
other traffic and of owners and of and occupiers of adjacent property and the public and shall remain
responsible for any accidents that may occur on account of his failure to take proper and timely
precautions. All the arrangements made for fencing and lighting shall be maintained by the
Contractor throughout the currency of the contract till the physical taking over the work by
Clause 61: Liabilities for accidents to person
Refer Section 3 Part F Clause 64 of ITB
Clause 62: Reports regarding labour
The Contractor shall submit the following reports to the Engineer-In-Charge, VMC:
A daily report in the form as may be prescribed of the strength of labour both skilled and unskilled
employed by him on the work(s). The Contractor shall increase or decrease the strength, both skilled
and unskilled, if directed by the Engineer-In-Charge, VMC. The submission of such report shall not,
however, relieve the Contractor of the responsibilities and duties regarding progress or any other
obligation under the Contract. A classified weekly return in the prescribed form of the number of
persons employed on the works during the preceding week. A weekly medical report in the report in
the prescribed form showing the health of the Contractor’s camp, the number of persons ill or
incapacitated and the nature of their illness. A report of any accident which may have occurred, to be
sent within 24 hours of the occurrence. Such other reports as may be prescribed.
Clause 63: Treasure trowel
In the event of discovery by the Contractor or his employees, during the progress of work of any
gold, silver, oil or other minerals of any description and precious stones, treasures, coils, antiquities,
relic fossils or other articles or value of interest whether geological, archaeological or any other such
treasure & other things shall be deemed to be absolute property of the Government and the
Contractor shall duly preserve the same to the satisfaction of the Engineer- In-Charge, VMC, from
time to time, and deliver the same to such persons as the Engineer- In- Charge, VMC may appoint.
The Contractor shall take all reasonable precautions to prevent his workmen or any other person from
removing or damaging any such articles or things, immediately after the discovery there of and
before removal acquaint Engineer-In-Charge, VMC with such discovery and carry out these orders
for the disposal of the same.
Clause 64: Indemnity
The Contractor shall indemnify the Government against all actions, suits claims and demands
through or made against the department in respect of work of this contract and against any loss or
damage to Department in consequence of any action or suit being brought against the Contractor for
anything done or omitted to be done in execution of the work of this contract.
Clause 65: Insurance taxes and duties Insurance:
Refer Section 3 Part A Clause 13 of ITB
Clause 66: Cement Register
A register in the prescribed form showing day-to-day receipt, consumption and balance of cement on
site of work will be maintained by the Department, which shall invariably be signed daily by the
Contractor or his authorized representative in token of its correctness.
Clause 67: Deleted
Clause 68: License for contract labour
Before starting the work, the Contractor will have to obtain the license from the District Assistant
Labour Commissioner under the Contract Labour (Regulation and Abolition) Act 1970 and contract
number of labourers to be employed on the work and will have to supply two true copies of the said
license to the Deputy Executive Engineer before the work is started.
Clause 69: Liability of the Contractor in case of Fraud, Dishonest and Fraudulent concealment.
Certificate of payment issued by Architect/Owner during the progress of the works or after their
completion shall not relieve the Contractor from his liability under all or any of the clause(s) in this
contract. In case of fraud, dishonesty or fraudulent concealment relating to the works or material or to
any matter dealt in with the certificate and in case of defects and insufficiencies in the works or
material which any reasonable examination would not have disclosed the certificate issued by
Architect/Owner shall not be considered as a conclusive evidence that any work and material to
which it relates or in accordance with the contracted and such a certificate shall be considered to have
been obtained by the contractor by fraud or misrepresentation and it shall be liable to the cancelled or
Clause 70: DELETED
Clause 70A: DELETED
Clause 71: Forfeiture/Termination
Refer Section 3 Part E Clause 59 of ITB
Clause 71 A: Valuation at date of forfeiture
The owner shall as soon as may be practicable after his entry consequent upon the expulsion of the
Contractor fix and determine expert or by or after reference to the parties or after such investigations
or inquiries as he may think fit to take or institute and shall certify what amount ( if any) which had at
the time of such entry and expulsion become reasonably due to the Contractor in respect of work then
actually done by him under the contract including the value of any unused or partially used materials,
any constructional plant and any temporary works which are taken over by owner under his exclusive
Clause 71 B: Payment after Forfeiture
Refer Section 3 Part E Clause 60 of ITB
Clause 72: If the Contractor dies
Without prejudice to any of the rights or remedies under this contract, if the Contractor dies owner
shall have option of terminating the contract without any compensation to the Contractor.
Clause 73: Insolvency and breach of contract
The VMC may at any time, by notice in writing, summarily terminate the contract without
compensation to the contractor in any of the following events:
1. If the contractor, a firm or any partner thereof, shall be at the time adjusted insolvent or shall have
a receiving order for administration of his estate made against him or shall take any proceedings
for composition under any Insolvency Act for the time being in force to make any conveyance or
assignment of his assets or enter into any arrangement or composition with his creditors or
suspend of payment if the firm is dissolved under the partnership Act.
2. If the contractor being a company is wound up voluntarily by the order of a court or receiver,
liquidator or Manager on behalf of the debenture holders is appointed or circumstances shall have
arisen which entitled the court or Debenture holders to appoint a receiver liquidator or Manager.
3. If the contractor commits any breach of the contract not herein specifically provided any right of
action or remedy which shall have occurred or shall occur thereafter and provided also the
contractors be liable to pay the VMC for any extra expenditure he is thereby put to and the
contractor shall under no circumstances be entitled to any gain in repurchase.
Clause 74: Action when whole of Security Deposit is forfeited.
In any case in which under any clause of this contract, the contractor shall have rendered himself
liable to pay compensation amounting to the whole of his Security Deposit (Whether paid in one sum
or deducted by installment) or in the case of abandonment of the work owing to serious illness or
death of the contractor or any other cause, the City Engineer/ Additional City Engineer/ Head of
Department, on behalf of VMC shall have power to adopt any of the following courses as man,
deemed best suited to the interest of VMC.
1. To rescind the contract (of which recession notice in writing to the contractor under the hand of
the executive Engineer shall be conclusive evidence) and in that case, the Security deposit of the
contractor shall stand forfeited and be absolutely at the disposal of the VMC.
2. To employ labour paid by the VMC and to supply materials to carry out the work, or any part of
the works, debiting the contractor with the cost of the labour and price of materials as to the
correctness of which cost and price the certificate of the City Engineer/Additional City
Engineer/Executive Engineer shall be final and conclusive against Contractor and crediting him
with the value of the work done, in all respect in the manner and at the same rate as if it had been
carried out by the contractor under the terms of this contract and in that case the certificates of the
Executive Engineer as to the value of the work done shall be final and conclusive against the
3. To order that the work of the contractor be measured up and to take such part thereof as shall be
unexecuted out of his hands, and to give it to another contractor to complete, in which case, any
expenses which may be incurred in excess of the sum which would have been executed by him (as
to the amount of which expenses the certificate in writing of the City Engineer/Additional City
Engineer/Executive Engineer shall be final and conclusive) shall be borne and paid by the original
contractor and shall be deducted from any money due to him by the VMC under the contractor or
otherwise or from his security deposit or the proceeds of sale thereof, of a sufficient part thereof.
In the event of any of the above courses being adopted by the City Engineer the contractor shall
have no claim to compensation for any loss sustained by him by reason of his having purchased,
or prepared any materials, or entered into any engagements, or made any advances on account of
or with a view to execution of the work or the performance of the contract. And in case of the
contract shall be rescinded under the provision aforesaid, the contractor shall not be entitled to
recover or be paid any sum, for any work therefore actually performed by him under this contract
unless and until the Executive Engineer shall have certified in writing the performance of such
work and the amount payable to him in respect thereof and he shall only be entitled to be paid the
amount so certified.
Clause 75: DELETED
Clause 76: Alterations in Specifications and Designs not to be invalidate contracts. Rates for
works not entered or schedule rate.
The City Engineer/ Additional City Engineer/ Head of Department/ Executive Engineer shall have
power to make any alteration in or addition to the original specifications, drawings and instructions
that may appear to him to be necessary or advisable during the progress of the work and the
contractor shall be bound to carry out the work in accordance with any instruction in this connection
which may be given to him in writing signed by the City Engineer / Additional City Engineer /
Executive Engineer and such alteration shall not invalidate contract. Any additional work which the
contractor may be directed to do in the manner above specified as part of the work shall be carried
out by the contractor on the same conditions in all respect on which he agreed to do the main work,
and at the same rates as are specified in the tender for the main work. And if the additional and
altered in the tender for the work, and if the additional and altered work includes any class of works
for which no rate is specified in this contract, then such class of works shall be carried out at the rates
entered in the Scheduled Rates or at the calculated rates whichever are lower. If the additional or
altered work for which no rate is entered in the Schedule of Rates in ordered to be carried out before
the rates are agreed upon then contractors shall within seven days of the date of receipt by him of the
order to carry out the work, inform the Executive Engineer of the rate which he is intending to charge
for such class of work, and to arrange to carry out in such manner as he may consider advisable
provided always that if the contractor shall commence work or incurred any expenditure in regard
there to before the rates shall have been determined as lastly here in before mentioned then in such
cases, he shall only be entitled to be paid in respect of the work carried out or expenditure incurred
by him prior to such date of the determination of the rate as aforesaid according to such rates as shall
be fixed by the Executive Engineer, in the event of a dispute, the decision of the Additional City
Engineer will be final. Where however, the work is to be executed according the designs, drawings
and specifications recommended by the contractor and accepted by VMC, the alteration above
referred shall be within the scope of such design, drawings and specifications appended to the tender.
The time limit for completion of works shall be extended in the proportion that the increase in cost
occasioned by alterations or additions bears to the cost of the original contract work, and the
certificate of the Executive Engineer as such proportion shall be conclusive.
Clause 77: Execution of Works.
All works to be executed under the direction and subject to the approval in all respect of Engineer-in-
charge or Executive Engineer for the time being, who shall be entitled to direct at what point or
points and in what manner they are to be commenced and from time to time carried on.
Clause 78: Action where no specifications are available.
In the case of work for which there is no such specification, work shall be carried out in accordance
with the GWSSB / P.W.D. or I.S.I. specification / relevant specifications published by state or central
Government, and in the event of there being no P.W.D. or I.S.I. specifications the work shall be
carried out in all respects in accordance with the instructions and requirements of the Executive
Clause 79: DELETED
Clause 80: Removal of Workmen
The VMC shall be at liability to object & require the Contractor to remove forth with from the works
any person employed by the contractor in or about the execution or maintenance of the works who in
the opinion of the VMC misconducts himself or is in completed or negligent in the proper
performance of his duties or whose employment is otherwise considered by the Executive Engineer
to be undesirable & such person shall be replaced by the contractor without delay by a competent
substitute approved by VMC.
Clause 81: Jurisdiction.
The contractor shall be governed and be constituted according to laws in India. The Contractor will
submit to the jurisdiction of the courts situated at Vadodara for the purpose of disputes, actions and
proceedings arising out the contract and the courts at Site location only will have the jurisdiction to
hear and decide disputes, actions and proceedings.
Clause 82: Programme of Work
Refer Section 3 Part B Clause 27 of ITB
Clause 83: Progress
The Contractor shall regularly review his programme in the light of the progress actually achieved
and shall submit for approval updated PERT/CPM Network and bar charts at intervals to be agreed
with the Engineer’s Representative. If progress falls behind that needed to ensure timely completion
of the various parts of the works, the Contractor shall submit proposals for improving his methods
and pace of working to the satisfaction of Engineer’s Representative and shall carry out such
measures as are needed to ensure that the works are completed on time.
Clause 84: TIME FOR COMPLETION
The Contractor shall commence the works on site when ordered by the Engineer and shall proceed
with the same with due expedition and without delay except as may be expressly sanctioned or
ordered by the Engineer or be wholly beyond the Contractor’s control.
Clause 85: CERTIFICATES OF COMPLETION
If the Engineer issues a Certificate of Completion for a part of the Works pursuant to Clause 7, the
Contractor shall as far as practicably finish all outstanding work on that part of the works during the
relevant Defects Liability Period. No Certificates of Completion shall relieve the Contractor or any of
his obligations in connection with other Contractors whose work is carried out after the issue of such
Clause 86: PATENTS, RIGHTS AND ROYALTIES
The Contractor shall save harmless and indemnify the Municipal Commissioner VMC and of VMC
and VMC from and against all claims and proceedings for or on account of infringement of any
patents, rights, design, trade mark or name or other protected rights in respect of any Constructional
plant, machine, work or material use for or in connection with the works or temporary works or any
of them and from and against all claims, demands, proceedings, damages, costs, charges and
expenses whatsoever in respect thereof or in relation thereto. Except where otherwise specified, the
Contractor shall pay all tonnage and other royalties, rent and other payment or compensation if any
for getting stone, sand, gravel, clay or other materials required for the works or temporary works or
Clause 87: THE SITE
1. Tenderer must visit the work site and see for himself/herself the site, pipeline route and ground
conditions in all respects including availability of labour (skilled and unskilled), approaches,
obstructions, drains, availability of water, electricity, materials and all other matter affecting the
work before submitting the tender.
2. The submission of the tender by Tenderer implies that he has visited the work site, read the entire
tender document and has made himself aware of the scope of specification of work to be
performed and of the conditions and rates at which materials will be issued to him/her and local
conditions and other factors which have a bearing on the execution of work.
3. Owner will not, therefore, after acceptance of the tender, pay any extra charges for any reason
whatsoever in case Contractor finds later on to have misjudged the site and other conditions.
Clause 88: ACCESS TO THE SITE
The Contractor shall arrange to construct, maintain and afterwards remove and reinstate any
temporary access required for an in connection with the execution of the works. Reinstatement shall
include restoring the area of the access route to at least the degree of safety, stability, drainage and
appearance that existed before the Contractor entered the site.
Clause 89: SETTING OUT THE WORKS
1. The Contractor shall be responsible for the true and proper setting out of the works in relation to
original points, lines and levels of reference given by the Engineer in writing or shown on the
Drawings and for correctness, subject as above mentioned in the position, levels, dimensions and
alignment of all parts of the works and for the provision of all necessary instruments, appliances
and labour in connection therewith.
2. The checking of any setting out of any line or level by the Engineer’s Representative shall not in
any way relieve the Contractor of his responsibility for the correctness thereof.
Clause 90: TEMPORARY WORKS
A reasonable time before he intends to commence construction of any temporary works, the
Contractor shall submit full particulars including drawings of the same for the approval of the
Engineer’s Representative. Submission to an approval by the Engineer’s Representative of any such
particulars shall not relieve the Contractor of any of his responsibilities under the Contract.
Clause 91: AMENITIES TO BE PRESERVED
The Contractor shall cause the least possible interference with the existing amenities, whether natural
or man-made. No tree shall be felled without permission of the Engineer’s Representative and
clearance of the site shall generally be kept to the minimum necessary for the Works and Temporary
Works. Temporary Works shall be sited so as to minimize the number of trees to be felled.
Clause 92: WORKS TO BE KEPT CLEAR OF WATER
1. The Contractor shall keep the works well drained until the Engineer certifies that the whole of the
works is substantially complete and shall ensure that so far as is practicable, all work is carried out
in the dry. Excavated areas shall be kept well drained and free from standing water.
2. The Contractor shall construct, operate and maintain all temporary dams, water courses and other
works of all kinds including pumping and well-point dewatering that may be necessary to exclude
water from the Works while they are in progress and till they are handed over to the VMC. This
refers mainly to surface water they may enter into the excavated construction work. No separate
payment will be made for such dewatering works/measures. Unit rates quoted by Contractor will
be deemed to have covered expenses for such dewatering works/measures. Such temporary works
shall not be removed without the approval of the Engineer’s Representative.
3. Notwithstanding any approval by the Engineer’s Representative of the Contractor’s arrangements
for the exclusion of water, the Contractor shall be responsible for the sufficiency thereof and for
keeping the Works safe at all times, particularly during any floods and for making good at his own
expense any damage to the Works including any that may be attributable to floods. Any loss of
production or additional costs of any kind that may result from floods shall be at the Contractor’s
Clause 93: DISCHARGE OF WATER INTO EXISTING WATER COURSES
The Contractor shall make provision for the safe discharge or disposal from the Works and
Temporary Works of all water and waste products howsoever arising and the methods of disposal
shall be to the satisfaction of the Engineer’s Representative and of any Authority or person having an
interest in any land or watercourse or in which waste may be so discharged.
Clause 94: PREVENTIVE MEASURES OF POLLUTION
The Contractor shall ensure that at all times during the construction of the Works all-reasonable
precautions are taken to the satisfaction of the Engineer’s Representative to prevent pollution of the
Site and of the environment. In particular, the Contractor shall prevent pollution arising from the
disposal or spillage of sewage, diesel fuel, oil, liquid mud, or from the disturbance of natural dust,
aggregate dust or cement dust.
Clause 95: EFFECTS OF WEATHER
1. The Contractor shall ensure that no damage occurs to the works during construction by arranging
adequate protection for excavation or building work against the effects of drought, sunshine, wind
or rainfall (including erosion and flooding). No work shall be performed when in the opinion of
the Engineer’s Representative such work is liable to be injuriously affected by the weather.
2. The Contractor shall have no claim against the VMC on account of loss alleged to have been
sustained directly or indirectly by reason of the Engineer’s Representative declining to permit such
work to start or continue, or ordering any work damaged by the weather to be made good or
removed and re-executed.
Clause 96: SITE TO BE KEPT TIDY
The Contractor shall keep the Site and all working areas in a tidy and workmanlike condition and free
from rubbish and waste materials. Any temporary works, constructional plant, materials or other
things which for the time being are not required for use by the Contractor may with the consent of the
Engineer’s Representative be removed from the site but otherwise shall be dispersed about the Site in
an orderly fashion and shall be properly and securely stored thereon.
Clause 97: SAFETY MEASURES AND SERVICES
1. The Contractor shall be responsible for the safety of all workmen and other persons entering or in
the Works and shall take all measures necessary to ensure their safety to the approval of the
Engineer’s Representative. such measures shall include the following:
a) Provision of proper safety and emergency regulations, fire, gas and electric shock precautions,
stretches and first-aid box together with rescue facilities generally for each place of working;
b) Provision of efficient safety helmets for all personnel including the Engineer’s Representative
and each of his staff and any authorized visitors to site;
c) Safe control of water including provision of ample standby generating and pumping plant.
d) Provision and maintenance of suitable lighting to provide adequate illumination of Works
with appropriate spares and standby equipment;
e) Provision and maintenance of safe, sound mechanical equipment, each item of plant having an
up- to- date testing certificates;
f) Provision and maintenance of safe, sound ropes, slings, pulleys and other lifting tackle, each
appliance having an up-to-date testing certificate where appropriate;
g) Provision of notices 1.25m x 1.5 m size written in bold letters in English, Gujarati and Hindi
to be erected on existing footpaths and at points of access likely to be used by the public,
which shall warn the public of the existence of the Works. These notices shall be in addition
to any statutory requirements demanded of the Contractor.
h) Provision of safety rails (wherever instructed by Engineer-in-Charge).
2. The Contractor shall submit for the approval of the Engineer’s Representative detailed proposals
under (a), distribute copies in English or in their languages as appropriate to all his employees and to
the Engineer’s Representative.
3. The Contractor shall ensure that all his employees are fully conversant with the regulation,
emergency and rescue procedures etc. and the Contractor shall enforce the rule that any employee
committing a serious breach of such a regulation shall be instantly dismissed and shall not be re-
4. Contractor shall provide and maintain at his own expenses all lights, guards, fencing and necessary
watchmen when and where necessary or as required by Owner/Engineer for the protection of the
works or for the safety and convenience of those employed on the works and the public. Contractor
shall also provide at his cost traffic barricades, men for diverting and controlling traffic, necessary
signboards for diversion of traffic. In the event of failure on the part of Contractor, Owner may with
or without notice to Contractor put up a fence or improve a fence already put up or provide and/or
improve the lighting or adopt such other measures as he may deem necessary, and all the cost of such
work and procedures as may be adopted by Owner/Engineer shall be borne by Contractor.
Maintenance of adequate warning and general lighting at nights at place of work is essential.
5. Contractor shall take the necessary permission and clearance of all the authorities like department of
Roads, Traffic, Water Supply and Drainage; Electricity Board, Telephone Company, etc. wherever
necessary and observe the regulations regarding the execution of work in congested areas, heavy
traffic areas, etc.
Clause 98: CLAIMS FOR DAMAGE TO PERSONS OR PROPERTY (Read in Conjunction with
Section 3 Part A Clause 13 of ITB)
1. Any claim received by the VMC or the Engineer’s Representative in respect of matters in which the
Contractor is required under the Contact to indemnify the VMC will be passed to the Contractor who
shall likewise inform the VMC and an Engineer’s Representative of any such claim which is
submitted directly to him by a claimant. The Contractor shall do everything necessary, including
notifying the insurers of claims received, to ensure that all claims are settled properly and
expeditiously and shall Keep the VMC and the Engineer’s Representative informed as to the progress
made towards settlement, failing which the VMC shall be entitled to make direct payment to
claimants of all outstanding amounts due to them in the VMC’s opinion and without prejudice to any
other method of recovery to deduct by way of offset the amounts so paid from any sums due or which
become due from the VMC to the Contractor.
2. If the Contractor receives a claim, which he considers to be in respect of matters in which he is
indemnified by the VMC under the Contract, he shall immediately pass such claims to the VMC.
3. Contractor will be solely responsible for any loss to life or limbs of workmen or the public arising out
of inadequate protective and/or safety measures taken by Contractor and irrespective of whether or
not Engineer has ordered Contractor to take protective and safety measures.
4. The contractor will be responsible to pay a compensation of minimum ₹30 Lakhs in addition to the
compensation paid by State government in the death of workman, while working with the drainage
Clause 99: ASSISTANCE OF THE ENGINEER’S STAFF
1. The Contractor shall provide all necessary assistance to the Engineer’s Representative and his staff in
carrying out their duties of checking the setting out, inspecting and measuring the work. The
Contractor shall provide chairs, staff men, office attendants and labourers as may be needed from
time to time by the Engineer’s Representative.
2. The Contractor shall provide for the Engineer’s Representative and his staff such protective clothing,
safety helmets and rubber boots of suitable sizes as may reasonably be required by them. These
articles shall remain the property of the Contractor. No separate payment shall be made on this
Clause 100: PUBLICITY NOTICE BOARD
The Contractor shall provide, maintain and remove at the end of the Defects Liability Period a publicity
notice board constructed according to the requirements of the VMC without any cost.
Clause 101: CLEARING SITE ON COMPLETION
1. On completion of the Works, the Contractor shall clear away and remove from the Site all
Constructional Plant, surplus materials, rubbish, Temporary Works of every kind and leave the whole
of the Site and the Works clean and in a workmanlike condition to the satisfaction of the Engineer.
2. The Contractor shall comply with the above requirements before the start of the Defects Liability
Period and by the end of that period shall clear, regarded terrace, level topsoil and grass all his
working areas as instructed by the Engineer’s Representative. No separate payment shall be made on
Clause 102: PRODUCTION OF VOUCHERS, ETC.
The Contractor shall when required by the Engineer produce all quotations, invoices, vouchers and
accounts or receipts in connection with expenditure in respect of provisional sums.
1. The Contractor shall furnish to the Engineer’s Representative such receipts or other vouchers as may
be necessary to provide the amounts paid and before ordering materials shall submit to the Engineer
quotations for the same for his approval.
Clause 103: DAYWORK
In respect of all work executed on a day work basis, the Contractor shall during the continuance of such
work deliver each day to the Engineer’s Representative an exact list in duplicate of the names,
occupations and time of all workmen employed on such work and a statement also in duplicate showing
the description and quantity of all materials and plant used thereon or therefore (other than plant which
is included in the percentage addition in accordance with the Schedule herein above referred to). One
copy of each list and statement will it corrects or when agreed to, be signed by the Engineer’s
Representative and returned to the Contractor. At the end of each month, the Contractor shall deliver to
the Engineer’s Representative a priced statement of the labour, materials and plant (except as aforesaid)
used and the Contractor shall not be entitled to any payment unless such lists and statements have been
fully and punctually rendered. Provided always that is the Engineer shall consider that for any reason the
sending of such list of statement by the Contractor in accordance with the foregoing provision was
impracticable, he shall nevertheless be entitled to authorize payment for such work either as day’s work
(on being satisfied as to the time employed and plant and materials used on such work), or at such value
therefore as shall in his opinion be fair and reasonable.
Clause 104: CLAIMS
The Contractor shall send to the Engineer’s Representative once in every month an account giving
particulars (as full and detailed as possible) of all claims for any additional expense to which the
Contractor may consider himself/herself entitled and of all extra or additional work ordered by the
Engineer which he has executed during the preceding month and no claim for payment for any such
work will be considered which has not been included in such particulars. Provided always that the
Engineer shall be entitled to authorize payment to be made for any such work notwithstanding the
Contractor’s failure to comply with this condition if the Contractor has at the earliest practicable
opportunity notified the Engineer that he intends to make a claim for such work.
Clause 105: ENGINEER’S REPRESENTATIVE
Where reference in the Specification is made to the Engineer, the powers as described shall be deemed
to be delegated to the Engineer’s Representative.
Clause 106: SUBSIDENCE OF ROAD
If any subsidence takes place in the filling of road or any part of the work whatsoever during defects
liability period from the completion of the contracted work, Contractor shall make good the same at his
own cost, or Owner/Engineer may without notice to Contractor make good the same in any and with any
material that he may think proper and at the expense of Contractor. Owner/Engineer may also if he
anticipates the occurrence of any subsidence, employ watchmen to look after the same unless it has been
set right. The expenses of such watchmen shall be charged to Contractor.
Clause 107: PAYMENT OF ITEMS ON LUMPSUM BASIS
Items to be paid on “Lump sum” basis shall be paid only after these items are accepted by Engineer as
Clause 108: DISPUTES
Any legal dispute with the Contractor(s) will be settled within the area subject to Vadodara jurisdiction.
Clause 109: MATERIAL TESTING: (Read in Conjunction with Section 3 Part C Clause 34 of
Necessary material testing shall be carried out by the contractor at VMC approved laboratory at his own
cost as directed by Engineer-in-charge of VMC as well as PMC/TPI.
Clause 110: DRAWING SUBMISSION
Refer point 35 and 36 of contract data
Clause 111: INTERPRETATION OF DOCUMENTS
In this Contract, unless the context otherwise requires:
1. References to any legislation or any provision thereof shall include amendment or re- enactment or
consolidation of such legislation or any provision thereof so far as such amendment or re-enactment
or consolidation applies or is capable of applying to any transaction entered into hereunder;
2. References to laws of India or Indian law or regulation having the force of law shall include the laws,
acts, ordinances, rules, regulations, bye laws or notifications which have the force of law in the
territory of India and as from time to time may be amended, modified, supplemented, extended or
3. References to a “person” and words denoting a natural person shall be construed as a reference to any
individual, firm, company, corporation, society, trust, government, state or agency of a state or any
association or partnership (whether or not having separate legal personality) of two or more of the
above and shall include successors and assigns;
4. The table of contents, headings or sub-headings in this Contract are for convenience of reference only
and shall not be used in, and shall not affect, the construction or interpretation of this Contract.
5. The words “include” and “including” are to be construed without limitation and shall be deemed to
be followed by “without limitation” or “but not limited to “whether or not they are followed by such
6. References to “construction” or “building” include, unless the context otherwise requires, survey and
investigation, design, developing, engineering, procurement, supply of Plant, Materials, Equipment,
labour, delivery, transportation, installation, processing, fabrication, testing, commissioning and
maintenance of the project (water/ waste water, networks, treatment and storage as applicable)
including removing of Defects, if any, and other activities incidental to the construction and
“construct” or “build” shall be construed accordingly;
7. References to “development” include, unless the context otherwise requires, construction,
renovation, augmentation, up-gradation and other activities incidental thereto, and “develop” shall
be construed accordingly;
8. Any reference to any period of time shall mean a reference to that according to Indian Standard
9. Any reference to day shall mean a reference to a calendar day as per the Gregorian calendar;
10. References to a “business day” shall be construed as a reference to a day (other than Sundays and
other holidays for Employer) on which banks in [Vadodara] are generally open for business;
11. Any reference to month shall mean a reference to a calendar month as per the Gregorian calendar;
12. References to any date, period or project milestone shall mean and include such date, period or
project milestone as may be extended pursuant to this Contract;
13. Any reference to any period commencing “from” a specified day or date and “till” or “until” a
specified day or date shall include both such days or dates; provided that if the last day any period
computed under this Contract is not a business day, then the period shall run until the end of the
next business day;
14. The words importing singular shall include plural and vice versa;
15. References to any gender shall include the other and the neutral gender;
16. “lakh” means a hundred thousand (100,000) and “crore” means ten million (10,000,000);
17. “indebtedness” shall be construed so as to include any obligation (whether incurred as principal or
surety) for the payment or repayment of money, whether present or future, actual or contingent;
18. References to the “winding-up”, “dissolution”, “insolvency”, or “reorganization” of a company or
corporation shall be construed so as to include any equivalent or analogous proceedings under the
jurisdiction of law in which such company or corporation is incorporated or any jurisdiction in
which such company or corporation carries on business including the seeking of liquidation,
winding-up, reorganization, dissolution, arrangement, protection or relief of debtors;
19. Save and except as otherwise provided in this Contract, any reference, at any time, to any
agreement, deed, instrument, license or document of any description shall be construed as reference
to that agreement, deed, instrument, license or other document as amended, varied, supplemented,
modified or suspended at the time of such reference; provided that this sub Clause shall not operate
so as to increase liabilities or obligations of the Employer hereunder or pursuant hereto in any
manner whatsoever;
20. Any agreement, consent, approval, authorization, notice, communication, information or report
required under or pursuant to this Contract from or by any Parties or the Engineer-in-Charge shall
be valid and effective only if it is in writing under the hand of a duly authorized representative of
such Parties or the Engineer in- Charge, as the case may be, in this behalf and not otherwise;
21. The Schedules and Recitals to this Contract form an integral part of this Contract and will be in full
force and effect as though they were expressly set out in the body of this on tract;
22. References to Recitals, Articles, Clauses, Sub-Clauses or Schedules in this Contract shall, except
where the context otherwise requires, mean references to Recitals, Articles, Clauses, Sub-Clauses
and Schedules of or to this Contract, and references to a Paragraph shall, subject to any contrary
indication, be construed as a reference to a Paragraph of this Contract or of the Schedule in which
such reference appears; and
23. The damages payable by either Parties to the other of them, as set forth in this Contract, whether on
are mutually agreed genuine pre- estimated loss and damage likely to be suffered and incurred by
the Parties entitled to receive the same and are not by way of penalty (the “Damages”)
24. Time shall be of the essence in the performance of the Parties’ respective obligations. If any time
period specified herein is extended, such extended time shall also be of the essence.
Clause 112: Contractor & Contractor’s obligations and its representatives
1. A Contractor may be an individual, firm, company, corporation, whether incorporated or not, who
enters into the Contract with the Employer, and shall include his heirs, his executors, administrators,
successors, legal representatives, as the case may be.
2. Contractor’s representative shall mean a person in supervisory capacity who shall be so declared by
the Contractor and who shall be authorized under a duly executed power of attorney to comply with
the instructions and to receive materials issued by the Engineer-in Charge to the Contractor for
Works. He shall be capable of taking responsibility for proper execution of Contract.
Clause 113: Removal of worker or subcontractor by Employer
The appointment of key personnel and subcontractor for the Contract shall be authenticated by the
Employer. The Engineer-in-Charge may require the Contractor to dismiss or remove from the Site any
person or persons or sub- Contractor who is found to be incompetent or indulging in misconduct and the
Contractor shall forthwith comply with such requirements within 21 days of such notice from the
Engineer-in-Charge. Such person(s) shall not be employed again at Site without the written permission
of the Engineer-in-Charge and the person(s) so removed shall be replaced as soon as possible by
competent substitutes. The decision of Engineer-in-Charge shall be final and binding.
Clause 114: Unauthorized occupancy at the construction site
It shall be the responsibility of the Contractor to see that the Site is not occupied by any unauthorized
person during construction, and that Site is handed over to the Engineer-in- Charge with vacant
possession of complete building or site, as applicable and free from all encumbrances.
Provided that where such construction site is occupied illegally, and notwithstanding that the Works on
the Site is executed by the Contractor, the Engineer-in-Charge shall have the option to refuse to accept
the said site in that condition. Any delay in acceptance on this account will be treated very seriously, and
the Contractor shall be liable to pay compensation for delays. Provided further that for such delay a levy
up to maximum of 5% of Contract Price may be imposed by the Engineer-in-Charge whose decision
shall be final both with regard to the justification and quantum of levy and shall be binding on the
Provided further that the Engineer-in-Charge may require through a written notice removal of any illegal
occupation of Site that comes into his/her knowledge at any time during the execution of the Contract.
Clause 115: Site office
The Contractor shall on his own arrange for space for site office at his cost. Contractor shall also be
responsible to arrange a store for proper storage of material in a weather proof environment as required
for a particular kind of material.
Clause 116: Excavated materials
The Contractor shall not sell or otherwise dispose off, or remove, except for the purpose of this
Contract, sand, stone, clay, ballast, earth, rock or any other substance or materials, which may be
obtained from any excavation made for the purpose of the Works, or any building or produce existing at
the Site at the time of delivery of possession thereof. All such substances, materials, buildings and
produce, shall be the property of the Employer;
provided that the Contractor may with the permission of the Engineer-in-Charge use the same for the
purpose of Works either free of cost or on payment of cost, as provided for under the Special Conditions
of the Contract or in the absence of such conditions, as per mutually accepted terms and conditions.
Clause 117: Care of work
Subject to the insurance obligations of the Parties, the Contractor shall bear full risk in and take full
responsibility for the care of the Works and Materials, goods and equipment for incorporation therein
from the Commencement Date until the Completion Certificate is issued, except and to the extent that
any loss of or damage to the same shall arise out of any default or neglect of the Employer.
Clause 118: Employment of foreign nationals
The Contractor acknowledges, agrees and undertakes that employment of foreign personnel by the
Contractor and/or its Sub-Contractors and their Sub-contractors shall be subject to grant of requisite
regulatory permits and approvals including employment/residential visas and work permits, if any
required, and the obligation to apply for and obtain the same shall and will always be of the Contractor.
Notwithstanding anything to the contrary contained in this Contract, refusal of or inability to obtain any
such permits and approvals by the Contractor or any of its Sub- Contractors or their sub-Contractors
shall not in any manner excuse the Contractor from the performance and discharge of its obligations and
liabilities under this Contract.
Clause 119: Deleted
Clause 120: Reporting, Inspection & Quality
(Refer Section 3 Part C of ITB)
Clause 121: Deleted
Clause 122: Material & Workmanship
1. Materials to be supplied by Contractor
1.1 The Contractor shall, at his own expense, provide all materials, required for the Works other than those,
which are stipulated, to be supplied by the Employer.
1.2 The Contractor shall, at his own expense and without delay; supply to the Engineer-in- Charge samples of
materials to be used on the Works and shall get these approved in advance. All such materials to be provided
by the Contractor shall be in conformity with the specifications laid down or referred to in the Contract. The
Contractor shall, if requested by the Engineer-in-Charge furnish proof, to the satisfaction of the Engineer-in-
Charge that the materials so comply. The Engineer-in-Charge shall within 30 (thirty) days of supply of
samples, intimate the Contractor in writing whether samples are approved by him or not. If samples are not
approved, the Contractor shall forthwith arrange to supply to the Engineer-in-Charge for his approval fresh
samples complying with the specifications laid down in the Contract. When materials are required to be tested
in accordance with specifications, approval of the Engineer-in-Charge / PMC / TPI agency shall be issued
after the test results are received.
1.3 The Contractor shall, at his risk and cost, make all arrangements and shall provide all facilities as the
Engineer-in-Charge / PMC / TPI agency may require for collecting, and preparing the required number of
samples for such tests at such time and to such place or places as may be directed by the Engineer-in-Charge /
PMC / TPI agency and bear all charges and cost of testing unless specifically provided for otherwise
elsewhere in the Contract or specifications. The Engineer-in-Charge or his authorized representative shall at
all times have access to the works and to all workshops and places where work is being prepared or from
where materials, manufactured articles or machinery are being obtained for the Works and the Contractor
shall afford every facility and every assistance in obtaining the right to such access.
1.4 The Engineer-in-Charge / PMC / TPI agency shall have full powers to require the removal from the premises
of all materials which in his opinion are not in accordance with the specifications and in case of default the
Engineer-in-Charge / PMC / TPI agency shall be at liberty to employ at the expense of the Contractor, other
persons to remove the same without being answerable or accountable for any loss or damage that may happen
or arise to such materials. The Engineer-in-Charge / PMC / TPI agency shall also have require other proper
materials to be substituted thereof and in case of default the Engineer-in- Charge / PMC / TPI agency may
cause the same to be supplied and all costs which may attend such removal and substitution shall be borne by
the Contractor.
1.5 Leveling instrument/ survey equipment
The Contractor shall always make available and accurate leveling instrument with updated calibration
certificate at the Site. Necessary levels shall be given by the Contractor or his authorized site engineer and the
same will be checked by the site staff of the Employer / PMC / TPI agency.
Clause 123: Suspension of Work
1.1 The Contractor shall within 3 days of receipt of the order in writing of the Engineer-in- Charge,
(whose decision shall be final and binding on the Contractor) suspend the progress of the work or
any part thereof for such time and in such manner as the Engineer- in-Charge may consider
necessary so as not to cause any damage the work already done or endanger the safety in general
thereof for any of the following reasons:
a) On account of any default on the part of the Contractor or;
b) For proper execution of the Works or part thereof for reasons other than the default of the
c) For safety of the Works, public and or public property; or
d) To avoid hindrance to other works; or
e) As communicated by Engineer-in-Charge for any other reason.
The Contractor shall, during such suspension, properly protect and secure the Works to the extent
necessary and carry out the instructions given in that behalf by the Engineer-In- charge.
1.2 In the event of the Contractor treating the suspension as an abandonment of the Contract by
Employer, the Contractor shall have no claim to payment of any compensation on account of any
profit or advantage which he might have derived from the execution of the Works in full but which
he could not derive in consequence of the abandonment.
Clause 124: Non-Political Event
A Non-Political Event shall mean one or more of the following acts or events:
i) Act of God, epidemic, extremely adverse weather conditions, lightning, earthquake, landslide,
cyclone, flood, volcanic eruption, chemical or radioactive contamination or ionising radiation, fire or
explosion (to the extent of contamination or radiation or fire or explosion originating from a source
external to the Site);
ii) Strikes or boycotts (other than those involving the Contractor, Sub contractors or their respective
employees / representatives, or attributable to any act or omission of any of them) interrupting
supplies and services to the Site for a continuous period of 24 (twenty-four) hours and an aggregate
period exceeding 7 (seven) days in an Accounting Year.
iii)Any failure or delay of a Sub-contractor/Contractor but only to the extent caused by another Non-
Political Event and which does not result in any offsetting compensation being payable to the
Employer by or on behalf of such Contractor.
iv) Any judgement or order of any court of competent jurisdiction or statutory authority made against the
Contractor in any proceedings for reasons other than (i) failure of the Contractor to comply with any
Applicable Law or Applicable Permit, or (ii) on account of breach of any Applicable Law or
Applicable Permit or of any contract, or (iii) enforcement of this Contract, or exercise of any of its
rights under this Contract by the Employer.
v) The discovery of geological conditions, toxic contamination or archaeological remains on the Site
that could not reasonably have been expected to be discovered through a site inspection; or
vi) Any event or circumstances of a nature analogous to any of the foregoing.
Clause 125: Indirect Political Event
An Indirect Political Event shall mean one or more of the following acts or events:
i) an act of war (whether declared or undeclared), invasion, armed conflict or act of foreign enemy,
blockade, embargo, riot, insurrection, terrorist or military action, civil commotion or politically
motivated sabotage;
ii) industry-wide or State-wide strikes or industrial action for a continuous period of 24 (twenty four)
hours and exceeding an aggregate period of 7 (seven) days in an Accounting Year;
iii)any civil commotion, boycott or political agitation which prevents construction of the Works by the
Contractor for an aggregate period exceeding 7 (seven) days in an Accounting Year;
iv) Any failure or delay of a Contractor to the extent caused by any Indirect Political Event and which
does not result in any offsetting compensation being payable to the Employer by or on behalf of such
v) Any Indirect Political Event that causes a Non-Political Event; or
vi) Any event or circumstances of a nature analogous to any of the foregoing.
Clause 126: Political Event
A Political Event shall mean one or more of the following acts or events by or on account of any
Government Instrumentality:
i) Change in Law, only if consequences thereof cannot be dealt with under and in accordance with the
ii) Compulsory acquisition in national interest or expropriation of any project assets or rights of the
Contractor or of the Sub-Contractors;
iii)Unlawful or unauthorized or without jurisdiction revocation of, or refusal to renew or grant without
valid cause, any clearance, license, permit, authorization, no objection certificate, consent, approval
or exemption required by the Contractor or any of the Sub-contractors to perform their respective
obligations under this Contract; provided that such delay, modification, denial, refusal or revocation
did not result from the Contractor’s or any sub contractor’s inability or failure to comply with any
condition relating to grant, maintenance or renewal of such clearance, license, authorization, no
objection certificate, exemption, consent, approval or permit;
iv) Any failure or delay of a Contractor but only to the extent caused by another Political Event and
v) result in any offsetting compensation being payable to the Employer by or on behalf of such
vi) Any event or circumstance of a nature analogous to any of the foregoing.
Clause 127: Notice of Occurrence
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
0. Front Page (Vol-I).pdf
5.3. Safety Provisions.pdf
5.4 General Specifications.pdf
5.5 ITEM WISE SPECIFICATIONS.pdf
6.00 FORM OF BID.pdf
7. ANNEXURE.pdf
1.0 sbd tender.pdf
Download all tender documents and submit your bid