Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹47.7 LAccepted-Finance NEAR SHIV SHAKTI DHARAM KANTA SHIV PURAM FULSUNGA RUDRAPUR U S NAGAR UTTARAKHAND | UDAM SINGH NAGAR | UTTARAKHAND | 244712 | ₹47.7 L | L-1 | Accepted-Finance Accepted as per committee approval |
| 2 | L-2₹48.2 LRejected-Finance COURT ROAD UTTARKASHI | ₹48.2 L | L-2 | Rejected-Finance Due to higher rate |
| 3 | L-3₹49.3 LRejected-Finance WARD NO 01 PUNJABI COLONY GADARPUR U S NAGAR | LUDHIANA | PUNJAB | 141001 | ₹49.3 L | L-3 | Rejected-Finance Due to higher rate |
| Sl No | Description | Qty | Unit | SHIV ELECTRICALS H2 | PERFECT ELECTRICALS AND ENGINEERS H3 | HIMALAYA BUILDCON H1 |
|---|---|---|---|---|---|---|
| 1.00Annexure-A (LABOUR CHARGES) | ||||||
| 1.01 | Earthing of support with M.S. Earth rod of 2.5 meter long by hammaring of M.S. Rod to proper depth and connecting the earth electrode with the help of G.I. wire as per construction manual. | 5 | Nos. | 398 ₹1,990 | 396 ₹1,980 Lowest | 400 ₹2,000 |
| 1.02 | Excavation of earth for stay pit of size 0.6x0.6x1.2 mtr in all types of soil including proper dressing of sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as directed complete work | 30 | CBM | 230 ₹6,900 | 225 ₹6,750 Lowest | 235 ₹7,050 |
| 1.03 | Fixing, tightening and nozzling of stay with pole and stay rod on required tension as per drawing/manual in LT line | 30 | Nos. | 446 ₹13,380 | 445 ₹13,350 Lowest | 450 ₹13,500 |
| 1.04 | Grouting of Stay in size 0.6x0.6x0.3 in CC ratio 1:4:8 (1 cement : 4 graded stone 20mm nominal size : 8 coarse sand ) block including cost of Cement, sand and stone ballast back filling of soil and boulders in pit and ramming and proper alignment, leveling as per RESSPO Manual. | 3.24 | CBM | 5,495 ₹17,803.8 | 5,491 ₹17,790.84 Lowest | 5,500 ₹17,820 |
| 1.05 | Excavation of earth for pole pit of size 0.9x0.6x1/6 of full length of pole for erection of pole in all types of soil including proper dressing of sides and ramming of bottom including etting out the excavated soil and disposal of surplus excavated soil as directed complete work | 35 | CBM | 238 ₹8,330 | 236 ₹8,260 Lowest | 240 ₹8,400 |
| 1.06 | Erection of PCC single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual. | 35 | Nos. | 1,295 ₹45,325 | 1,293 ₹45,255 Lowest | 1,300 ₹45,500 |
| 1.07 | Erection of SP-33 single support pole in proper level and alignment along with fixing of all accessories like top channel & clamps as per RESPO manual. | 5 | Nos. | 1,048 ₹5,240 | 1,041 ₹5,205 Lowest | 1,050 ₹5,250 |
| 1.08 | Grouting of pole in size 0.45x0.45x1/9 of the support in CC ration 1:4:8(1 cement:4 graded stone20 mm niminal size: 8 coarse sand) block including cost of cement, sand and stone ballast back filling of soil and boulders in pit and ramming and proper alignment, levelling as per RESPO cnstruction manual. | 1.01 | CBM | 5,125 ₹5,186.5 | 5,120 ₹5,181.44 Lowest | 5,150 ₹5,211.8 |
| 1.09 | Muffing of poles size 0.45x0.60 cm radius with 1:3:6(1 cement:3 coarse sand :graded stone 10 mm nominal size) block size 45 cm height from ground level including cost of cement,stone and sand etc. | 5 | Nos. | 598 ₹2,990 | 594 ₹2,970 Lowest | 600 ₹3,000 |
Tender Value
Refer Docs
EMD Value
₹98,000
Closing Date
21 Jul 2026, 12:00 pmClosed
Superintending Engineer
Electricity Distribution Circle, Rudrapur
Replacement of bare conductor by AB Cable in 11 KV Town-II Feeder at Gas Agency Road and Pant Colony Kichha emanating from 33/11 KV S/s Kichha under EDD, Kichha
2026_UPCL3_97241_1
EDC(USN)23/2026-27
Open Tender
Electrical Works
Item Rate
90 days
Kichha
Pl. refer tender documents
4 documents required · 4 mandatory
₹2,360
EE ETD Rudrapur
₹98,000
24 Aug 2026
4 Jul 2026
22 Jul 2026
4 Jul 2026
21 Jul 2026
4 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Annexure-A (LABOUR CHARGES) | |||||
| 1.01 | Earthing of support with M.S. Earth rod of 2.5 meter long by hammaring of M.S. Rod to proper depth and connecting the earth electrode with the help of G.I. wire as per construction manual. | 5 | Nos. | - | - |
| 1.02 | Excavation of earth for stay pit of size 0.6x0.6x1.2 mtr in all types of soil including proper dressing of sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as directed complete work | 30 | CBM | - | - |
| 1.03 | Fixing, tightening and nozzling of stay with pole and stay rod on required tension as per drawing/manual in LT line | 30 | Nos. | - | - |
| 1.04 | Grouting of Stay in size 0.6x0.6x0.3 in CC ratio 1:4:8 (1 cement : 4 graded stone 20mm nominal size : 8 coarse sand ) block including cost of Cement, sand and stone ballast back filling of soil and boulders in pit and ramming and proper alignment, leveling as per RESSPO Manual. | 3.24 | CBM | - | - |
| 1.05 | Excavation of earth for pole pit of size 0.9x0.6x1/6 of full length of pole for erection of pole in all types of soil including proper dressing of sides and ramming of bottom including etting out the excavated soil and disposal of surplus excavated soil as directed complete work | 35 | CBM | - | - |
| 1.06 | Erection of PCC single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual. | 35 | Nos. | - | - |
| 1.07 | Erection of SP-33 single support pole in proper level and alignment along with fixing of all accessories like top channel & clamps as per RESPO manual. | 5 | Nos. | - | - |
| 1.08 | Grouting of pole in size 0.45x0.45x1/9 of the support in CC ration 1:4:8(1 cement:4 graded stone20 mm niminal size: 8 coarse sand) block including cost of cement, sand and stone ballast back filling of soil and boulders in pit and ramming and proper alignment, levelling as per RESPO cnstruction manual. | - | CBM | - | - |
| 1.09 | Muffing of poles size 0.45x0.60 cm radius with 1:3:6(1 cement:3 coarse sand :graded stone 10 mm nominal size) block size 45 cm height from ground level including cost of cement,stone and sand etc. | 5 | Nos. | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.82 MB
TN232627TenderdocumentABCGasagency.pdf
Tender Documents • 1.48 MB
TechnicalSpecification1232627.pdf
Additional Documents • 0.64 MB
TechnicalSpecification2232627.pdf
Additional Documents • 2.89 MB
FormAandB.pdf
Other Document • 0.67 MB
GeneralInnstruction232627.pdf
Other Document • 0.76 MB
BOQ_114854.xls
BOQ • 0.41 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].