Loading…
Loading…
Tender ID
Tender Value
₹1.2 Cr
EMD Value
₹79,000
Closing Date
12 May 2026, 5:30 pmClosed
Chief General Manager (Thermal)
Surat Lignite Power Plant - 4X125 MW-Biennial Rate Contract for Housekeeping services for Colony & School area at Village: Nani Naroli for two years of contract period 2026-28
294740
SLPP/Civil/Colony/Housekeeping/2026
Open
HouseKeeping Services
Fixed-rate
Surat
₹2,950
Gujarat Industries Power Company Limited.
₹79,000
22 Apr 2026
22 Apr 2026
22 Apr 2026
12 May 2026
22 Apr 2026
Any error in description or quantity or omission in the contract document shall not
vitiate the contract or release the contractor from executing the work comprised in
the contract according to scope of works, magnitude of the works, requirement of
materials, equipment, tools & tackles, labour, etc. Contractor has to complete the
work in accordance with the contract documents irrespective of any defects,
omissions or errors that may be found in the contract documents.
BIDDER shall inspect the site, examine and obtain all information required and
satisfy himself/herself regarding matters such as access to site, communication,
transport, working condition including constraint of work place, confined area,
quantum of dusting, importance of work, round the clock working conditions, safety
requirements, right of way, high flood level in River, flow of water during
monsoon/dry season in the River/Nallah, the type and number of tools/tackles,
housekeeping materials, equipment and facilities required for the satisfactory
completion of work, the estimated quantity/frequency of various items of the work,
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
the availability of local labour, availability & rates of materials, local working
conditions, uncertainties of weather, obstructions &d hindrances that may arise, etc
which may affect the work or cost thereof, before submission of his/her Bid.
Ignorance of site conditions shall not be accepted by the GIPCL as basis for
any claim for compensation. The submission of a Bid by the BIDDER will be
construed as evidence that such an examination was made. Any later claims /
disputes in regard to rates quoted shall not be entertained or considered by the
The rates quoted by BIDDER shall be based on his/her own knowledge and
judgment of the conditions & hazards involved and shall not be based on any
representations of the Engineer of GIPCL.
5. ELIGIBILITY CRITERIA
The following criteria will be adopted for qualifying the Bidders for consideration of
the Bid for the further proceeding.
5.1 Bidder should possess minimum Three years of experience during last five
years in similar nature of jobs (like Housekeeping, Hospitality, Material handling
through deploying manpower) in Power Plant, Process Industries, Corporations,
Corporate, Institutes, Residential Colony, Hospitals, Shopping malls, commercial
and/or residential complex and should enclose proof of the same. Bidder shall
submit necessary evidence for the same like self-attested copies of work orders
along with work completion certificates from clients. The work completion certificate
shall comprise of order value and executed value. Bidders should have executed
the work directly. The work executed as a sub-contractor or subletting agency shall
not be taken in to consideration.
Note: For evaluation of the bid the executed value mentioned in the work
completion certificate will be considered.
5.2 Bidder should produce evidence of having successfully completed similar works (as
per above clause no. 5.1) during last five years ending last day of the month
previous to the one in which tender is invited, satisfactory progress of ongoing works
etc… secured from clients along with self-attested copies of documentary evidence
preferably photo copies of work experience. The experience should be either of the
a. One similar completed/executed work each costing not less than Rs.
b. Two similar completed/executed work each costing not less than Rs.
c. Three similar completed/executed work each costing not less than Rs.
Note: For evaluation of the bid the executed value mentioned in the work
completion/work in progress certificate will be considered.
Bidder should specifically mention fulfilling of above criteria in his offer along with
details of work orders & work completion certificates issued by clients.
5.3 Tender fee: The tender fee of Rs. 2,950/- (Rupees Two Thousand Nine Hundred
and Fifty only), including applicable GST (nonrefundable) shall be submitted
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
through RTGS or through online payment as per details provided in clause no.
herein under. Demand Draft will not be accepted for Tender Fee.
5.4 EMD: The EMD of Rs. 79,000/- (Rupees Seventy Nine thousand only), shall be
accompanied in the form of DD/RTGS/online or irrevocable Bank Guarantee given
by Bank as described in subsequent clause no.
5.5 Bidder should have separate Employees Provident Fund code number towards
registration of firm with RPF commissioner.
5.6 Attested copies of relevant documents duly signed & seal on each & every page
shall be submitted. The above documents will be analyzed and after satisfaction,
the Price Bid will be open. GIPCL may verify the documents, experience certificates
issued by concern authority. After opening of technical Bid, if any required attested
documents found missing in the Technical Bid submitted by the Bidder, the tender
inviting authority may inform to that Bidder only once by E-mail to submit the missing
required documents within stipulated time limit. If Bidder/Bidders fail to submit within
stipulated time, their Bid will be declared technically disqualified and no further
correspondence will be entertained.
5.7 Bidder should have minimum average annual turnover of Rs. 15.68 Lakh
during last three financial years (average of financial years of 2022-23, 2023-24
& 2024-25). Bidder shall furnish annual audited financial statement duly certified by
Chartered Accountant for the last three financial years to demonstrate the financial
healthiness of the company. The Balance sheet must be in the name of the
company. Any type of MOU for this purpose will not be entertained.
Note: In case, the annual turnover is less than the statutory guideline which does
not require audit, the bidder shall submit the turnover certificate from Chartered
5.8 The Bidder has to submit INCOME TAX Permanent Account Number (PAN) & GST
registration number. Copies of the same shall be submitted.
5.9 The net worth of the bidder should be positive as evidenced from audited accounts
of last financial year (2024-25), audited (or where, as per extant laws of the land,
audit is not applicable, certified) by a qualified Chartered Accountant who should be
a member of the Institute of Chartered Accountants of India.
5.10 In case Bidder is Consortium/Joint deed of under taking of company, the above
requirements/credential of consortium leader/bidder shall be considered unless
otherwise specifically mentioned in the tender.
5.11 If Bidder or its Partner(s) or Director(s) is /are/was Black Listed / Deregistered /
Stopped or banned from dealing in the past by any Govt, of Gujarat Undertakings /
Depts. / Authorities and Govt. of Gujarat supported companies / undertakings /
organizations, Bid of that party may be liable to be rejected. Bidder agrees and
undertakes to accept decision of GIPCL in this regard as final and binding on the
Bidder without any demur and that no further correspondence shall be done in this
regard at any stage. Bidder shall have to submit “Declaration for Contractual
Litigations” as amended in Annexure / Form attached.
5.12 Bidder shall have to submit the “Declaration-cum-Undertaking for Compliance of
Safety Laws and Regulations” as amended in Annexure / Form attached.
• If any Major Violation of any safety law(s) / Rule(s) is / are found during the
preceding Three (3) years, Bid of that party will be liable to be rejected. Bidder
agrees and undertakes to accept decision of GIPCL in this regard as final and
binding on the Bidder without any demur and that no further correspondence
shall be done in this regard at any stage.
• If any of the details submitted in the prescribed Annexure / Form to the Bid
is/are found to be false, incorrect at any time in future, then the Contract
awarded to that Bidder / Contractor shall be liable to be terminated forthwith
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
without any notice / correspondence and Bidder agrees and undertakes to
accept decision of GIPCL in this regards as final and binding on the Bidder
without any demur and that no further correspondence shall be done in this
regard at any stage. Further, Performance / Security Deposit will also be
liable to be forfeited. Any dues to GIPCL from the Bidder / Contractor shall
be recovered from the pending bills or any other dues payable to the Bidder
/ Contractor, if any or otherwise through any other recourse available under
The Bidder shall submit all the evidences, documents, attested copies of work
orders & work completion certificates etc… as a proof with EMD &Tender Fee
and also provide the requisite details online for meeting the prequalification
requirements. GIPCL will verify the experience, performance, capability &
strength of Bidders, independently for executing the job. GIPCL may visit the
site & consult the owner of the industry/property where similar job is executed
by the Bidder. GIPCL reserves the right to accept/cancel/reject any/all Bids
without assigning any reason thereof. The tenders of qualified Bidder/Bidders
shall only be considered for further evaluation.
Site Visit is mandatory prior to submission of bid to understand the scope of work,
working conditions, site conditions, equipments, tools & tackles, labor deployment,
associated risk, surrounding etc.
6. LANGUAGE OF BID
The Bid prepared by the Bidder, and all correspondence and documents relating to
the Bid exchanged by the Bidder and the Company, shall be written in the English
language. Any printed literature furnished by the Bidder, written in another language
shall be accompanied by an English translation for the purpose of interpretation of
7. EARNEST MONEY DEPOSIT (EMD) AND TENDER FEE
7.1 An EMD of Rs. 79,000/- (Rupees Seventy Nine thousand only and
Nonrefundable Tender fee Rs.2,950/- (Rupees Two Thousand Nine
Hundred fifty only), inclusive of applicable GST shall accompany with Bid
shall accompany with Bid. Tender fee shall be submitted through RTGS /
online mode of payment only.
7.2 The EMD shall be submitted in the form of DD/irrevocable Bank Guarantee
in favor of Gujarat Industries Power Company Limited from all Nationalized
Banks or Axis Bank, ICICI Bank, HDFC Bank, Kotak Mahindra Bank,
IndusInd Bank, Federal Bank, Bandhan Bank, IDBI Bank and Karur Vysya
Bank as per Performa of BG enclosed with this tender document under
Section-F (Annexure-C).
Bank for EMD DD Payable at :
1. Bank of Baroda Mosali, Dist: Surat
2. State Bank of India Nani Naroli, Branch Code:
3. Any Nationalized banks Surat
Alternatively, The EMD & Tender Fee may also be submitted through
RTGS/NEFT/online mode of payment by the bidders as per the details given
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
1. BANK NAME:- State Bank of India
2. BRANCH:- Nani Naroli
3. IFSC CODE:- SBIN0013423
4. BENEFICIARY NAME: Gujarat Industries Power Company Limited
EMD & Tender fee may also be submitted through online payment
gateway of company’s website:www.gipcl.com (online payment form)
as per detail provided in ANNEXURE- I of Section-F herein under.
7.3 In case EMD is paid in the form of BG, the same shall be valid for a period
of 180 days after the due date for submission of the bid
7.4 The EMD of the successful bidder will be returned after payment of Security
Deposit by successful bidder and after award of LOI/Work Order.
Alternatively EMD will be converted in SD and successful bidder shall submit
SD or performance bank guarantee for balance amount.
7.5 The earnest money deposit paid in the form of demand draft will be refunded
to the unsuccessful BIDDER as soon as the tender is finalized and awarded
of LOI/Work Order.
7.6 Any bid not accompanied with EMD and Tender fee will be rejected. Detail
of Tender fee & EMD paid by RTGS/online payment should be submitted as
per. Clause 7.9.EMD in physical form,to be submitted directly to GIPCL as
per clause 7.9.
7.7 No interest shall be payable on EMD.
7.8 The EMD will be forfeited if the BIDDER (i) withdraws his tender after
acceptance or (ii) withdraws his tender before the validity date of the tender.
7.9 SCHEDULE OF EMD & TENDER FEES AND OTHER SUPPORTING
Details/receipts of EMD & Tender fee paid Address for Submission:
by RTGS/online or EMD in physical form Chief General Manager (Thermal)
by way of DD/BG (as applicable) with GUJARAT INDUSTRIES POWER CO. LTD.,
other documents duly signed to be (Surat Lignite Power Plant)
submitted in physical form in sealed cover Village: Nani Naroli, Taluka: Mangrol,
as per details mentioned in NIT. Bid District: Surat. PIN: 394 112, Gujarat.
No. shall be mentioned at the top of Phone : 02629-261063
cover/envelope EMAIL: [email protected]
8. SUBMISSION OF BIDS
A: MODE OF SUBMISSION
The bids shall be submitted online through website: https://tender.nprocure.com or
https://gipcltender.nprocure.com within the dates specified in the NIT along with the
details of tender fees, EMD in two parts as under:
(a) Pre-qualification and Techno-commercial Bid without price.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Note: Tender fee RTGS details and EMD shall be submitted in physical
form as per NIT.
(a) Pre-qualification and Techno-commercial Bid without price:
The tender document duly signed in all pages without price bid along with techno-
commercial deviations, if any, shall accompany the bid. The following Information
shall be provided in the techno commercial bid:
1. Qualification and experience of site in charge.
2. Schedule of deviation (Annexure-E in Section-F) Technical as well as
commercial, if any.
3. Qualification & experience of Supervisors/Engineers.
The following supporting documents shall also be submitted along with EMD &
Tender Fee in physical form:
1. The tender documents duly signed in all pages without price bid along with
techno-commercial deviations, if any.
2. Proof of experience meeting the minimum eligibility criteria
3. Performance certificate issued by clients.
4. Previous work order copies.
5. Details of present work order (if any)
6. Turn over for the last three years, audited annual accounts/financial
statements i.e. profit and loss account and balance sheet duly certified by a
practicing CA will be required.
7. P.F. Number and Allotment Letter.
9. GST registration number/certificate copy.
10. Declaration-cum-Undertaking for Compliance of Safety Laws & Regulations
and Contractual Disputes / Litigations as per Performa Annexure-F under
11. Bidder should submit duly filled Annexure-G provided under Section-F of
Tender document
12. E-Reverse Auction User ID on website: https://e-auction.nprocure.com
1. Percentage Rate Price Bid shall be submitted only in soft form through e-
Note: Estimate includes cost of all labour & manpower (including prevailing
minimum wage rate as well as specific additional adhoc allowance),
supervisors/site-in-charge, uniform charges, housekeeping &
sanitization materials, insurance, equipments, vehicles, consumables,
fuel, tools & tackles, maintenance, spares, transportation,
mobilization-demobilization, loading-unloading, Safety, Legal &
Statutory compliance, all taxes & duties (including GST) etc...
Total Estimated SoR Amount is including GST by considering present
2. Bidder’s % offer will be on Total Estimated Amount (including GST) and in
Invoice/Bill, GST shall be mentioned separately as per extant GST Laws at
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
actual as per prevailing rates as declared by Central Government on
submission of documentary evidence.
3. Bidder shall have to quote the rates in the form of %age. i.e. “At
Estimated Value OR _____%age below the estimated value
OR______%age above the estimated value”.
4. The quantities shown in the SoR (Section-E) are approximate for the contract
period and may vary as per job requirement.
5. The Bidder shall fill the Bid documents with utmost care in consonance with
the instructions contained in the Bid documents.
6. Rates will remain firm throughout the contract period and any extension
thereof. There will not be any escalation/compensation to the contractor
against any revision and/or change in rate of materials, fuels, MWR (Minimum
Wage Rates), etc… whatsoever.
B: METHOD OF TENDERING/SIGNATURE ON BIDS
(i) The Bid must contain the postal address like name, residence and place of
business of the person or persons submitting the Bid and must be signed and
sealed by the Bidder with his usual signature. The name of all persons signing
the documents shall also be typed or printed below the signature on each page.
(ii) Bid by a joint venture/partnership firm must be furnished with full names of all
partners and be signed with the partnership name, followed by the signature
and designation of one of the authorized partners or other authorised
representative(s). A certified copy of the power of attorney authorizing such
partner or representative shall also be submitted.
(iii) Bids by a Corporation/Company must be signed with the legal name of the
Corporation/Company i.e by the President/Managing Director/Secretary or
other person or persons authorised to Bid on behalf of such
Corporation/Company. A certified copy of the board resolution/power of
attorney authorizing such partner or representative shall also be submitted.
(iv) The Bidder's name stated on the proposal shall be the exact legal name of the
(v) Erasures or other changes in the Bid Documents shall be initialed by the person
signing the Bid.
(vi) Bids not conforming to the above requirements of signing shall be disqualified.
9. MODIFICATION AND WITHDRAWAL OF BIDS
a. The Bidder may modify or withdraw the bid prior to the deadline prescribed for
submission of bids.
b. No Bid shall be modified subsequent to the deadline for submission of Bids.
c. No Bid shall be withdrawn in the interval between the deadline for submission
of Bids and the expiration of the period of bid validity.
10. POLICY FOR BIDS UNDER CONSIDERATION
a. Bid shall be deemed to be under consideration immediately after opening of the
bid and till official intimation of award/rejection made by the Company to the
b. While the Bids are under consideration, Bidders and / or their representative or
other interested parties are advised to refrain from contacting by any means,
the Company. The Engineer, if necessary, will obtain clarifications on the Bids
by requesting for such information from any or all the Bidders, in writing as may
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
be necessary. The Bidder will not be permitted to change the price or substance
of the Bid after the Bid has been opened.
11. EFFECT AND VALIDITY OF THE BID
a. The Bid should be kept valid for acceptance for a period of one hundred and
eighty (180) calendar days from the last date of submission of Bids.
b. The submission of any Bid along with the required documents and specifications
shall constitute an agreement that the Bidder shall have no cause of action or
claim, against the Company for rejection of his Bid.
c. The Company shall always be at liberty to reject or accept any Bid or Bids at his
sole discretion and any action will not be called into question and the Bidder
shall have no claim in that regard against the GIPCL.
12. OPENING OF BIDS
12.1 The GIPCL will open the pre-qualification/Technical Bid/price Bid, as the case
may be, in presence of Bidder's representatives whenever such a procedure
has been specified. Otherwise the tender will be opened by the authorized
officers of GIPCL.
12.2 Preliminary Examination:
12.2.1 The Company will examine the Bids for any computational errors, for sureties
furnished by bidder, for authentication of documents submitted and
completeness of the Bids.
12.2.2 Arithmetical errors will be rectified on the following basis:
(a) If there is a discrepancy between the unit price and the total price that is
obtained by multiplying the unit price and quantity, the unit price shall
prevail and the total price will be corrected & will be binding to the bidders
(b) If there is a discrepancy between the Total Bid Amount and the sum of
total prices, the sum of total prices shall prevail and the Total Bid Amount
will be corrected & will be binding to the bidders.
13. EVALUATION & COMPARISON OF BIDS
13.1 GIPCL shall evaluate the Bids received and accepted by it to ascertain the
lowest evaluated Bid in conformity with the specifications of the tender
13.2 The Technical Bids will be examined for minor matters regarding qualification
of bids. Subsequent to correspondence with the respective bidders, the
decision of Tender Committee will be final.
13.3 All responses to requests for clarifications shall be in writing and shall be
presented to the Company through e-mail or in a sealed envelope on or
before the given date requested by the Company. If the Technical
clarifications sought by the Company do not reach the Company on or before
due date, the Bid will be rejected.
13.4 The comparison of all the Bids shall be carried out with reference to the scope
of work as per the technical specification. Any deviation/omission shall be
evaluated at highest quoted price of the deviation/omission quoted by any of
the Bidder. In case a separate price (for omission) is not given by any other
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Bidder, a reasonable price of the same shall be taken & the same shall be
binding to the Bidders.
13.5 The commercial deviation, if any, shall be loaded to bring all the Bids at par.
The loading shall be carried out at an interest rate of 2% above PLR of SBI.
13.6 A Bid to be substantially responsive shall be one which on evaluation
confirms to all the terms, conditions and specifications of the Bid documents
without any material deviation or reservation.
13.7 For the above referred purpose, a ‘material deviation’ shall be one which:
(a) Which affects in any substantial way the scope, quality or performance of
the contract, or
(b) Which limits in any substantial way and in a manner inconsistent with the
Bid documents, GIPCL’s right or the Bidder’s obligations, under the
(c) Whose rectification would affect unfairly the competitive position of other
Bidders presenting substantially responsive Bids.
14. RIGHT OF REJECTION OF TENDERS
14.1 GIPCL reserves the right to accept or reject any Bid or to cancel the Bidding
process and reject all Bids at any time prior to award of contract, without
thereby incurring any liability to the affected Bidder or Bidders or any
obligation to inform the affected Bidder or Bidders regarding the same.
14.2 Any Tender without EMD and Tender fee will be treated as non responsive
and shall be rejected at the outset & no further correspondence shall be
entertained regarding this.
14.3 GIPCL reserves the right to debar any Bidder from participation in future Bids
if such Bidder has quoted an abnormally low rate in the Bid document/price
15. AWARD OF CONTRACT
15.1 GIPCL will award the contract to that bidder whose quotation has been
determined to be substantially responsive and evaluated as the lowest
quotation in conformity with the requirements of the specifications and
documents contained herein, provided further that the bidder is determined
and evaluated to be qualified to perform the contract satisfactorily.
15.2 The successful bidder shall be intimated of his selection through the Letter of
Intent or Letter of Award/ Work Order which shall be sent to him through e-
mail, courier, fax or registered mail.
15.3 GIPCL reserves the right to cancel/short close the contract during the contract
period without assigning any reason.
16. CONTRACT PERIOD
16.1 The contract will be for a period of 02 years from the date of actual
commencement of operation of the contract as stated in the Special
Conditions of Contract (‘Contract Period’).
16.2 GIPCL reserves the right to extend the Contract Period up to 3 (Three) months
at the same rates, terms and conditions without any price escalation and
entering into any new contract.
16.3 The said Contract Period can be extended if mutually agreed upon by both
the parties up to one year and in such a case a revised work order shall be
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
issued at the same rates, terms & condition or at negotiated rates acceptable
by both parties i.e. the Company & the Contractor.
16.4 GIPCL reserve the right to short close the contract any time by giving one
month notice period without assigning any reason whatsoever.
17. ASSIGNMENT AND SUB-LETTING
The Contractor shall not directly or indirectly assign or sub-let total/any part of the
contract to any other party or agency.
18. CONTRACTOR’S OBLIGATIONS
A: DEPLOYMENT & RESPONSIBILITY OF MANPOWER
(i) The Contractor shall deploy suitably qualified and sufficient manpower for
timely & satisfactorily execution of the works under the contract.
(ii) The Contractor shall deploy sufficient skilled, Semi-skilled and Un-skilled
manpower separately to properly complete the job in given/scheduled time.
(iii) The Contractor shall depute its own workmen/labor with proper identification to
enter the colony premises after ensuring that the jobs are scheduled.
(iv) At the time of deploying manpower, the Contractor shall strictly comply all the
applicable labor laws/Acts norms including but not restricted to the age of the
workers, women workers and shall also ensure that a police verification and
security check for all the workmen/labor engaged at the GIPCL site is done and
necessary documents regarding the same shall be submitted to the GIPCL’s
authorized representative/officer-in-charge. Any default in complying with the
same or any misrepresentation regarding compliance of the same shall compel
GIPCL to initiate appropriate civil or criminal proceedings regarding the same.
(v) The Contractor shall also comply with the safety requirements and provide his
workmen/labor with safety equipment like safety helmets, gum shoes/safety
shoes, uniform (minimum 03 pairs for ARC/AMC) and other necessary PPEs
for properly undertaking the operations involved under this contract. Following
are also to be issued:
a) Safety shoes (standard approved ISI make)
b) Safety helmet (standard approved ISI make in yellow colour only)
c) Hand gloves like electrical hand gloves / cotton hand gloves / Chemical hand
gloves (if required).
(vi) Contractor shall nominate /authorize senior experienced person in writing as
Site-In-Charge cum site supervisor to co-ordinate with concern GIPCL
engineers and who shall bear overall responsibility for performance of the
contract. Such person shall remain always available at site. Contractor has to
submit the authority letter and documentary proof for the same.
(vii) The supervisor shall co-ordinate with GIPCL’s Engineer-In-Charge for daily
entrusted job. Supervisor have to maintain daily records dully signed for the
works carried out and duly certified by concern Engineer-In-Charge. The
Contractor in co-ordination with the Engineer-In-Charge shall ensure the
availability of adequate manpower to carry out the job satisfactorily on a daily
basis. As per the instruction of Engineer-In-Charge they have to allot the work
and execute the same in specified time limit.
(viii) During execution of the works, one or more jobs may be required to be done
simultaneously and the Contractor shall mobilize additional resources
(ix) During emergency or similar situations the Contractor shall be required to
mobilize resources as per need within the period of 04 hours as directed by
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
GIPCL. If the contractor fails to mobilize sufficient manpower to complete the
job in time, GIPCL will execute the job through other agency at the risk and cost
of the contractor with 10% supervision charges & the same will be recovered
from the Contractor’s bill.
Important Note: Whenever any of the Unit at SLPP remains under outage due
to any reason and require emergency work, the contractor shall mobilize
sufficient work force at site within a period of twelve hours from the time of
intimation to the site-in-charge or via mail to your office
(x) During working in high risk area, the workman must wear a suitable safety
apron, safety belt, safety hand gloves and goggles. It is the
contractor’s/contractor’s supervisor’s responsibility to ensure it without fail.
(xi) During unit overhauling, the contractor has to enhance the site manpower as
per the requirement to ensure the timely completion of work (During
overhauling period quantum of work increases substantially). For this,
enhanced work shall be completed by deploying additional manpower with
separate supervisor. Payment will be made on item rate basis only. The work
during the overhauling period is to be carried out round the clock. Contractor
should mobilize sufficient number of manpower and execute the work in all
shifts with independent manpower. Contractor should not continue the same
manpower for more than 12 hours
B: TOOLS & TACKLES:
(i) All tools and tackles required to execute the contract are in the scope of the
contractor. The contractor should ensure that tools and tackles are in healthy &
working condition. All consumable items would be in the scope of the
Note: If work is suffered due to want of sufficient manpower, tools
& tackles, vehicles, equipments and/or required consumables then
25% of the total job cost will be levied as a penalty for each and
every instance.
(ii) For proper execution of the work as per the scope, the contractor is required to
maintain sufficient quantity of tools & tackles with tractors & hydraulic trolleys
in good working condition at site as per day to day work load and emergency
situations to complete the work in stipulated time.
(iii) In case of any emergency arising during night hours the contractor should be
in a position to mobilize the manpower immediately within minimum time.
(iv) Arrangement for lighting at the work spot has to be made by the contractor. He
has to arrange all lighting equipment such as power cable, hand lamps. The
contractor has to take prior approval for taking electrical power supply. The
contractor should keep hand lamps of 24Volt for confined space and sufficient
quantity of 240 Volt and halogen lamp for other area ensuring safety at work
(v) Pin sockets of IS standards should be used for all connections. For any accident
take place & any damage to the equipment and/or injury to human due to
carelessness in loose connection, contractors will be held responsible & liable
for any recovery/actions.
(vi) Contractor shall be allowed and encouraged to use mechanized equipment for
19. CLARIFICATION OF BIDDING DOCUMENTS
If any Bidder requires any further information or clarification in the Bidding
Documents, may notify the Company before one week of last date of submission
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
of online Bid, in writing or by E-mail at the GIPCL’s mailing address
[email protected] as indicated in the ‘Invitation to Bids’. The GIPCL’s response
(including an explanation of the query) will be sent in writing or by E-mail to all
prospective Bidders who have received the Bidding Documents.
20. TIME SCHEDULE
The basic considerations and the essence of the ‘Contract’ shall be the strict
adherence to the time schedule for performing the specified ‘Works’.
21. UNDERSTANDING AND CLARIFICATION ON DOCUMENTS AND
The Bidder is required to carefully examine the specifications and documents, all
the conditions and matters work wise & cost wise. If any Bidder finds any
discrepancies or omissions in the specifications and documents or is in doubt for
any meaning of any part, he shall request in writing for an interpretation/ clarification
to the GIPCL or during site visit.
All such interpretations and clarifications shall form a part of the Bid documents.
All the payments against the work order shall be in Indian currency and payable
through cheque only. However, RTGS system of online payment is also in operation
and will be applicable based on submission of required documents.
23. POINTS TO BE CONSIDERED DURING QUOTING ONLINE PRICE BID
a. The schedule of rates shall be read in conjunction with Instructions to Bidders,
General conditions of contract, Special conditions of contract and Technical
specifications.
b. The quantities given in the schedule of rates are estimated and will be made as per
actual work carried out as per the rates of work order.
c. The method of measurement of completed work for payment shall be in accordance
with the method of measurement specified in the Special Conditions of Contract.
d. No separate amount shall be payable for use of auxiliary equipment incidental to or
in day to day operation in the course of fulfillment of contractual obligation of the
Note: Interested bidders are requested to submit the online tender at least
two days in advance from the due date set for online submission of bid in
order to avoid non participation of e-tender due to probable technical problem
in e-tender system.
The quantities specified are estimated and for tendering purpose only. Payment
will be made, based on actual work done as certified by Engineer-in-charge of
Quantities of individual items may be revised during the course of contract period
based on site requirement. Contractor shall not be entitled for any compensation on
ground of such alteration in scope of work. GIPCL reserves the right to operate or
increase/decrease quantities in each item or omit any item included in Schedule of
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Quantity at his discretion. Contractor shall have no claim, whatsoever, on grounds
of loss of anticipated profit etc. on account of the same.
After commencement of the work, GIPCL, for any reason may not require to be
carried out the whole/part of the work as specified in the tender, the ENGINEER-in-
charge shall inform the fact for thereof to the CONTRACTOR and contractor shall
have no claim for any payment or compensation whatsoever on account of any
profit or advantage which he might have derived from the execution of the work in
full but which he did not derive in consequence of the full amount of the work not
having been carried out nor shall he have any claim for compensation by reason of
any change having been made in the original specifications and instructions which
shall involve any curtailment of the work as originally contemplated.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
INSTRUCTIONS TO BIDDERS FOR ONLINE TENDERING & E-
REVERSE AUCTION
SR. DESCRIPTION
1. Tender documents are available only in electronic format and same can be
downloaded from the website: https://tender.nprocure.com or
https://gipcltender.nprocure.com and It can also be viewed from Company’s
website www.gipcl.com
2. Price bid should be submitted online through the website
https://tender.nprocure.com or https://gipcltender.nprocure.com only. No
physical submission of price bid will be entertained as it should be furnished
3. Bidders who wish to participate in online tenders will have to procure / should
have legally valid Digital Certificate (Class III) as per Information Technology
Act-2000, using which they can sign their electronic bids. Bidders can
procure the same from any of the license certifying Authority of India or can
contact (n)code solutions- a division of GNFC Limited, who are licensed
Certifying Authority by Government of India
4. All bids should be digitally signed. The bidders are required to contact at the
below mentioned address for detailed training on on-line tendering and also
for requirement.
(n) Code Solutions - A division of GNFC Ltd.
403, GNFC Info tower, S.G Road,
Bodakdev, Ahmedabad – 380054 (Gujarat, India).
E-mail: [email protected], website: https://tender.nprocure.com
Interested bidders are requested to submit the online tender at least two days in
advance from the due date set for online submission of bid in order to avoid non-
participation in case of any technical issues (website and/or network) at last
E-REVERSE AUCTION:
i. GIPCL reserves the right to conduct E-Reverse auction through (n) Procure platform.
ii. E-Reverse auction shall be conducted amongst (a) the lowest 50% eligible bidders
(rounded to the next higher whole number) from the total bids received OR (b) Minimum
three (03) lowest bidders, whichever is higher, shall be invited for participation in e-
Reverse Auction through n-procure platform.
iii. Opening Price (including GST), Decrement value and duration for the e-Reverse Auction
shall be informed to the qualified bidders before start of e-Reverse Auction.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
iv. After e-Reverse Auction process, L1 bidder shall be decided on Lowest Total Contract
Price (including GST).
v. To participate in e-Reverse Auction, Bidders have to create e-Auction USER ID on
website: https://e-auction.nprocure.com that the bidder shall be allowed to participate
the e-Reverse Auction.
vi. In case of any further information regarding online bidding or if a Bidder needs any
assistance in accessing/ submission of online bid/ clarification or if training is required
for participating in online e-reverse bidding, then the Bidder can contact the following
office for assistance or training:
(n) Procure Cell, (n) code solutions-A division of GNFC Ltd.,
403, GNFC Info tower, S.G. Road,
Bodakdev Ahmedabad – 380054 (Gujarat)
Fax: 079-26857321 / 40007533, Email: [email protected]
Bidder may visit https://tender.nprocure.com for information regarding e-tendering
registration process.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
GENERAL CONDITIONS OF CONTRACT
1. CONTRACT SECURITY DEPOSIT/ PERFORMANCE BANK GUARANTEE
As a Contract Security, the successful Bidder, to whom the work is awarded, shall
be required to furnish a Performance Bank Guarantee (PBG)/Contract security
deposit in favour of Gujarat Industries Power Company Limited for guarantee
amount at ten percent (10%) of the “Annual Contract Price” Price” (excluding GST)
from all Nationalized Banks or Axis Bank, ICICI Bank, HDFC Bank, Kotak Mahindra
Bank, IndusInd Bank, Federal Bank, Bandhan Bank, IDBI Bank and Karur Vysya
Bank in the format attached in SECTION-F, and it shall guarantee the faithful
performance of the 'Contract' in accordance with the terms and conditions specified
in these documents and specifications. Contract security deposit shall be submitted
strictly within twenty-one days from the date of LoI or work order, whichever is
earlier. The PBG/ Security Deposit shall be valid up to retention period of 04 (four)
months after the contract completion/expiry date. The Contract security/Guarantee
amount shall be payable to the Company in Bidder's home currency without any
condition whatsoever. GIPCL reserves the right to forfeit Performance Bank
Guarantee (PBG)/Contract security deposit.
The Performance Bank Guarantee (initial security deposit) will be returned to the
Vendor/Contractor without any interest at the end of the ‘Guarantee Period' after
completion of contract and on fulfilling contractual obligations throughout the
retention period. However, any delay in submission of initial SD will result in
equivalent late release of entire SD after guarantee period.
Bid security/EMD should be refunded to the successful bidder on receipt of
Performance Security.
2. RECOVERY CLAUSE
(i) In case of any damage of equipment/machinery due to negligence of contractor
or any other reasons attributed to contractor the decision of Engineer-In-
Charge regarding the amount of recovery shall be final and binding subject to
a maximum of 10% of contract value. Recovery will be affected from the
monthly bills and/or retention money/security deposit.
(ii) If the contractor fails to execute the work as per directions of Engineer (I/c)
within the time frame given in work order and as per day to day instructions by
Engineer-in-charge, GIPCL shall get the work done by third party at the risk &
cost of the contractor with 15% additional overhead charges of GIPCL.
3. DEDUCTIONS FROM CONTRACT PRICE
All costs, charges or expenses that GIPCL may have paid, for which, under the
contract the contractor is liable, shall be recovered by the GIPCL. The contractor
shall pay all such claims within 15 days of claim, failing which the same shall be
deducted from the bills of contractor.
4. TERMINATION OF CONTRACT BY GIPCL
Contractor shall be responsible to complete the jobs within agreed time schedule.
Contractor shall mobilize required resources within 04 hrs to meet the emergency
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
requirements and in case contractor fails to complete the emergency jobs related
to colony area, GIPCL will engage third party and will recover expenses from
contractor’s R.A. bills, Security Deposit and / or whatsoever for expenses incurred
to complete the job along with additional 10% overhead charges plus applicable
GST as per extant GST Laws.
In case if contractor’s services are not found satisfactory with respect to timely
mobilization to meet emergency requirements, time bound activities, workmanship
& safety (OHSAS policy of GIPCL) then GIPCL has right to terminate the contract
at any time by giving 15 days advance notice without assigning any reason and will
make the alternate arrangement at the risk & cost of contractor.
GIPCL may terminate the contract after due recoveries of pending jobs/damages
after giving 15 days advance notice to the contractor if any of the following events
i. Contractor is adjudged as insolvent.
ii. Contractor has abandoned the contract.
iii. Contractor fails to proceed with the work with due diligence as per
requirements of the contract.
iv. Contractor has neglected or failed persistently to observe or perform any of
the acts, matters or things, which as per the contract are to be observed and
performed by the contractor.
v. Contractor repetitively violating the safety norms for more than three
vi. Any major contradiction of applicable labour laws.
vii. Any major deviations from contractual terms and conditions including quality
viii. GIPCL reserves the right to terminate the contract without giving any reason
whatsoever and forfeit the PBG
5. FAILURE & TERMINATION
If the CONTRACTOR after receipt of written notice from the GIPCL/ ENGINEER
requiring compliance, with such further drawings and / or the GIPCL /ENGINEER
instructions fails within seven days to comply with the same, the GIPCL /ENGINEER
may employ and pay other agencies to execute any such work whatsoever as may
be necessary to give effect thereto and all costs incurred in connection therewith
shall be recoverable from the CONTRACTOR by the GIPCL on a certificate by the
GIPCL/ENGINEER as a debt or may be deducted by him from any money due or
to become due to the CONTRACTOR.
If the contractor fails to execute the work or fails to mobilize the resources and
equipments as per directions of GIPCL / ENGINEER within the time frame given
and/or violating the GIPCL’s safety rules & regulations, ENGINEER/ GIPCL shall
get the work done by third party at the risk & cost of the CONTRACTOR with
additional 15% overhead charges of GIPCL and all costs incurred in connection
therewith shall be recoverable from the CONTRACTOR by the GIPCL /ENGINEER
as a debt or may be deducted by him from any money due or to become due to the
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
6. SETTLEMENT OF DISPUTES
a. Any disputes or difference of opinion between parties arising out of the contract
to the extent possible shall be settled amicably between the parties. If amicable
settlement cannot be reached all the disputed issues shall be resolved through
arbitration before a Sole Arbitrator appointed by Managing Director, GIPCL
according to the provisions of The Arbitration & Conciliation Act-1996, as
amended from time to time. The place of arbitration shall be at Vadodara/ Surat
or any other place within state of Gujarat.
b. Work under the contract shall be continued by the contractor during arbitration
proceedings unless GIPCL shall order suspension thereof or any part thereof in
writing or unless the matter in such work cannot possibly be continued unless
the decision of the Arbitration proceedings is obtained.
7. INTERPRETATION OF CLAUSE
In case of disputes as regards interpretation of any of the clauses or specification,
the decision of Chief General Manager (Thermal) - GIPCL will be final and binding
on the contractor.
8. EMPLOYEE’S COMPENSATION INSURANCE
Contractor shall take all risk Insurance Policy to cover all his workmen/employees,
staff applicable under the Employee Compensation Act 1923 or any amendment
thereof as also insurance cover for third party liability. The contractor shall keep the
GIPCL indemnified from all liabilities arising out of his action in pursuance of this
contract. The E. C. Policy should be obtained from Surat Jurisdiction and shall be
assigned to GIPCL. EC policy should cover the specified contract period.
Contractor shall also obtain additional off-duty coverage insurance policy for all his
9. STATUTORY REQUIREMENTS
a. COMPLIANCE OF LABOUR LAWS
The contractor shall at his own cost comply with the provision of labor laws, rules,
orders and notifications whether central or state or local as applicable to him or to
this contract from time to time. These Acts/Rules include without limitation of the
1. Contractor shall be solely responsible and shall fully comply with all the provisions
of all the labor laws applicable such as but not limited to the Minimum Wages Act,
1948, Contract Labor (Regulation & Abolition) Act 1970, Factories Act,
Industrial Dispute Act 1947, Workmen Compensation Act 1923, Interstate Migrant
Workmen Act 1979, Equal Remuneration Act with Rules, Order and Notifications
issued/made there under from time to time.
2 All other Acts, Rules/Bye-Laws, Orders, Notifications etc. present of future applicable
to the contractor from time to time for performing the contract job.
2.1 The Contractor shall provide and be responsible for payment of Wages,
Salaries, Bonus, Social charges, Insurance, Food, Accommodation,
Transport, Medical and Canteen facilities and other statutory privileges and
facilities to his personnel as per law/rules/regulations and orders of the
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Central Government, State Government, Local Authorities or other
authorities as are in force from time to time. All employees of the Contractor
shall be employee of the Contractor.
2.2 The contractor shall have a valid license obtained from Licensing Authority
under the Contract Labor (Regulation & Abolition) Act-1970 at the time of
execution of the contract covering all his employees working at
Colony/SLPP site and furnish the same failing which GIPCL may terminate
the contract at its sole discretion.
2.3 The Contractor shall at the time of execution of the contract have a EPF
Code Number obtained from the Authorities concerned under the
Employees Provident & Miscellaneous Provisions Act, 1972 and remit
contributions in respect of the employees employed by him at Colony/SLPP
Site to the P.F office concerned every month failing which GIPCL will recover
from the outstanding payment to the contractor from GIPCL.PF code of
Gujarat region should be taken.
2.4. The Contractor shall maintain all records/registers required to be maintained
by him under various labor laws mentioned above and produce the same
before the Statutory Authorities whenever required.
2.5 The Contractor shall also submit periodical reports / returns to the various
statutory authorities such as the Contract Labour (Regulation & Abolition)
Act-1970, Employees Provident Fund Act etc. Under intimation to HR&
2.6 The Contractor shall not pay less than the Minimum Wages notified by the
Government from time to time to his employees of corresponding
2.7. The Contractor shall be responsible for payment of overtime wages to his
workmen, if any, in case they are required to work beyond the prescribed
hours under law as per applicable rates.
2.8 The contractor shall take Workmen Compensation Insurance Policy for all
his employees working at Colony/SLPP. The contractor shall indemnify the
company against any liability due to any work injury or accident to any of its
2.9 The Contractor shall in the event any of his workmen / employee sustains
any injury or disablement due to an accident arising out of and in the course
of his employment, provide necessary medical treatment and pay
compensation as applicable, required under the Workmen’s Compensation
2.10 If any of the persons engaged by the Contractor misbehave with any of the
officials or the Company or commit any misconduct with regard to the
property of the Company or suffer from any serious communicable disease,
the Contractor shall replace them immediately.
2.11 The Contractor shall not engage / employ persons below the age of
years. Employment of women shall be strictly according to applicable laws.
2.12 GIPCL will have right to deduct and disburse the claims of the individual /
parties being a principal employer on any account whatsoever in relation to
their employment with the contractor. The Security deposit will be released
to the contractor at the end of the contractual tenure subject to an
undertaking by the contractor that in the event any of his workmen or the
heirs of workmen puts up a claim for recovery of money due to him from the
contractor before the appropriate authority under the I.D.Act 1947 or under
any other labor laws or for compensation under the Workmen’s
Compensation Act, 1923 and the appropriate authority has given a direction
for making payment the contractor will meet the same or indemnify GIPCL
if in the event GIPCL pays it as Principal Employer.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
2.13 The contractor shall make payment of wages to his employees on fixed date
within the period specified under the applicable Law, in presence of
representative of the company. He will submit a true copy of wage sheet,
attendance register and P.F. remitted challans on monthly basis to HR&A
dept. for verification and record.
2.14 The Contractor shall provide Safety items / kits to his employees such as
safety shoes, goggles, ear plugs, hand gloves, safety belts etc., if any,
required under the law.
2.15 The contractor shall conduct pre-induction and periodic medical checkup of
his workmen as per applicable laws.
2.16 The contractor shall be solely responsible for any accident caused to his
workers and should adhere to all rules / regulations as per labor laws of
Government and other statutory laws as applicable.
2.17 The contractor should register himself under the Contract Labor Act,
Employee Compensation Act and PF Act (Code no. to be mentioned) and
submit the copy of registration certificate and should possess the same from
the date of commencement of work, failing which the contract is liable to be
cancelled. The E.C. Policy copy should be submitted to the GIPCL before
commencement of the work and Labor License should be obtained within
one week from the date of issue of form-V. Contractor should apply for Form-
V immediately after receipt of LOI. A copy of Labour License shall be
submitted to GIPCL, HR & A Department.
2.18 Contractor shall have to insure his workmen /supervisors etc. under Group
Insurance scheme.
2.19 The Contractor shall be responsible for compliance of all statutory rules,
regulation, act enforced from time framed by the government such as
Factory Act, Employee Compensation Act, payment of ‘Wages Act’,
Minimum Wages Act’, Provident Fund Act, All Labor Laws Act in respect of
employees engaged by him for the work and shall have to maintain
necessary records. In case any amount becomes due to be payable by him
to his employees or to the Government under the above rules, regulation,
Acts, GIPCL reserves the right to recover the same from the running bill of
2.20 Documentary evidence of deposit of PF paid shall have to be produced by
the contractor along with the next bill.
2.21 Records as per the provisions of various statutory Acts will have to be
maintained by the contractor and submitted as and when required.
2.22 All employees of contractor should maintain due discipline and respect local
sentiments. GIPCL reserves the right to direct the contractor to remove any
such person who does not comply with it.
2.23 The list is indicative in nature and not an exhaustive one. Any
amendment/alteration/Notifications or addition to the existing Law or a new
statute shall automatically and immediately become applicable.
2.24 Annual Health Check Up: - As per statutory requirement, Contractor has to
inform workmen deployed at site for annual health check up as per schedule
prepared by HR&A department
b. LEGAL ASPECTS
1. Contractor shall maintain all register required under the Labour Laws and make
the payment as per the Minimum Wages Act to the workers employed by him.
2. Contractor shall obtain requisite license to carry out this contract under the
provisions of Contract Labour Act, 1970 and maintain necessary records and
registers under the said Act.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
3. Contractor shall submit a copy of each of the registration certificates with respect
to Employees Provident Fund and Employee Compensation Act within one week
time, from the date of award of this contract.
4. Contractor’s employees, agent or sub-agent shall not smoke or light anything
within the premises of the GIPCL and carry match box / lighter or any other
explosive and /or inflammable material inside the plant.
5. Contractor shall abide by all the statutory rules and regulations like Labour Laws
6. Contractor shall issue an appointment order to each casual labourer stating
therein the nature of job to be performed by him and fix time for which the
concerned labourers are likely to be deployed. Contractor shall also issue a
temporary identity card specifying the period for which the labourer has been
7. Contractor is fully liable for the persons engaged by him for above work; however,
GIPCL reserves the right to deduct any amount legally justified towards any
liability not fulfilled.
8. Contractor shall indemnify GIPCL from any liabilities arising out of the
employment of the manpower.
9. If the contractor fails to complete the allocated job within specified time frame,
GIPCL shall get the work done by third party at the risk and cost of contractor.
10. PAYMENT OF WAGES
Contractor has to make payment on or before 7th of every month through bank.
Contractor shall be responsible for compliance of all statutory rules, regulation, act
enforced from time framed by the government such as Factory Act, Employee
Compensation Act, payment of ‘Wages Act’, Minimum Wages Act’, Provident Fund
Act, Payment of Bonus Act, Labor Law Act, maternity benefit act in respect of
employees engaged by him for the work and shall have to maintain necessary
records. In case any amount becomes due to be payable by him to his employees
or to the Government under the above rules, regulation, Acts.
In case any amount becomes due to be payable by him/her to his employees or to
the Government under the above rules, regulation, Acts, GIPCL reserves the right
to recover the same from the running bill of the contract.
11. ACCIDENT TO WORKMEN
Contractor shall be fully responsible for injury or death of any of your or third-party
workmen due to any act omission / indiscretion on your part while undertaking the
work and contractor shall fully abide by the statutory requirements of the employee's
compensation act. GIPCL shall not be liable for any compensation due to accident,
death or injury to any of contractor’s workmen or any third party due to negligence,
act or omission on your part.
General area lighting will be provided by GIPCL. However, work area specific
lighting should be arranged by contractor.
13. NIGHT/SUNDAY/HOLIDAY SHIFT
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
The contractor shall depute qualified and adequate resources in night
shift/Sunday/holidays for any emergency job, which may come up at
night/Sunday/holiday.
14. SAFETY ASPECT
Contractor shall observe all the safety and security rules and regulation of the
GIPCL which are at present in force and which may come into force during the
pendency of the contract. Any violation of any rules and regulations will entail
immediate termination of the contract.
When contractor moves his lifting tools and tackles to the plant area, required test
certificates as per the Factory Act 1948 and the state factories rules has to be
submitted to safety dept. Safety dept. will check the certificates and if found okay,
then only materials will be allowed to enter inside the plant. Material inward gate
pass will be made only after certification from Safety dept. Security dept. will inform
to Safety dept., as & when such tools and tackles brought at the gate for making
entry in the maintenance site.
The contractor has to submit the list of required safety gears along with safety
equipments available with him to safety Dept. Safety dept. will check for quantity
and quality of the safety gears and then allowed permission of work. Poor quality
material will not be allowed to take inside the Plant. If quantity of required safety
equipments is not satisfactory, contractor will not be allowed to carry out the work
using such safety gears inside the Plant for the work.
15 GENERAL SAFETY CLAUSES
1. The Contractor shall observe and comply, with regard to his workmen working at the
SLPP site, the safety norms as per the safety operating standards.
2. The Contractor shall ensure that his workmen are informed and trained regarding the
safety standards to be adopted while operating within the SLPP Plant & Mines
premises and the Contractor shall brief them regarding the same and use of the
Personal Protective Equipment (‘PPE’).
3. The Contractor shall issue safety shoes and safety helmet of IS standard to all his
workmen immediately on execution of the work and the contractor shall ensure that
his workmen wear the protective equipments at all times during the work operation.
Following brand of the safety shoes and helmet shall be issued to contract workmen.
Contractor shall issue safety shoes every year.
Sr.No Model Company Specifications
01. Tough Hat, HP-TH Sure Safety
02. V-Gard MSA IS : 2925 – 1984, ANSI /
ISEA Z89.1-2009
03. PN 521 - Shelmet Karam
Sr No. Model Company Specifications
01. SSTEELE (Strom) – Double
Acme Fabrik plast Co.
02. TRIMAX(Adjacent) – Double
Acme Fabrik plast Co.
03. Worktoes Warren Worktoes - Warren Plus
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
4. Other safety gears like ear plug, dust mask, hand gloves, safety goggles, gum boots,
full body safety uniform and belts, safety net etc. shall be issued and used as per
the job requirements. Safety helmet shall be of YELLOW COLOUR ONLY.
Contractor will procure safety shoes & safety helmet from a reputed company with
at least 12 months’ guarantee and shall produce the guarantee certificate and IS
standard certificate to the safety department. Contractor should purchase safety
shoes of reputed brands. Safety shoes will be issued every year. IS certificate and
guarantee certificate must be obtained from the vendor and submitted to the Safety
department. Safety shoes should be heat, water, oil and chemical resistant, having
an anti-slippery sole of 15298- 2002 make
5. It is the duty of contractor to ensure that his workmen are wearing required PPEs as
per work requirement. Contractor should ensure that their workers are wearing
Safety helmet, safety shoes, dust mask, goggles, ear plug etc. at all times when
they are at work throughout the contract period. The contractor has to maintain the
PPE issue registers with signature of workmen.
6. Contractor will reissue these PPEs in case of damage or misplacement of the same.
Replacement shall be made immediately.
7. The contractor shall be responsible for providing first aid or emergency medical help
and treatment to his workmen in the event of any accident or injury.
8. If it is observed that contractor is not issuing required PPEs timely and that of
required quality, GIPCL will issue the required PPEs to contract workers and back
charge the same with 25% overhead charges of GIPCL, plus applicable GST as per
extant GST Laws.
9. All lifting tools and tackles shall be duly certified by competent person in conformity
with the statutory requirements and certificate in form no. 10 as per rule 60 of
Gujarat Factories Rules, 1963 and section 29 of the Factories Act, 1948 shall be
submitted every year before using such tools and tackles. In case of purchase of
new lifting tools and tackles, form no. 10 as per the said rules shall be submitted
before they are taken into use. All lifting tools and tackles shall be of reputed make
having International manufacturing standard and shall be maintained in proper and
workable condition.
10. The Contractor shall nominate one Safety Officer with required qualification for
supervising the daily job/ shutdown jobs for observing and maintaining the safety
aspects at site. He is solely responsible for any safety measures during
maintenance work. He has to ensure that all the workmen working at site are
equipped with essential PPE’s and proper safety arrangement is made at the SLPP
11. After mobilization of any tools & tackles to site, which includes chain pulley blocks,
D-shackles, wire ropes, winch machines, Mobile crane, Hydra etc. shall be offered
for inspection with all above statutory test certificate before using at site for any
work. They should use all tools and tackles only after certification by GIPCL
representative/safety officer.
12. When working at height, working on ceiling or roof covered with fragile materials,
full body harness safety belt, ladders and crawling boards, fall arrester. shall be
used to prevent accident. Further, during working on height, contractor should
arrange proper scaffolding of still pipes, safety net, full body safety belt, fall arrestor
system etc. Advice and instructions of engineer in charge/ safety in charge shall be
strictly complied with in this regard. All necessary safety precautions shall be taken
by the contractor to prevent accident and personnel injuries while working on height.
13. Flash back arrestors made of reputed manufacturer shall be provided on cutting
torch, on DA cylinders and on O2 cylinder. Cylinder caps also required for handling
the cylinders at the work at height area. Gas cylinders shall be transferred through
gas cylinder trolley only with cylinder cap and stored up right (vertical) position only.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
All gas cylinders shall be hydro tested / certified as per gas cylinder rules 2004. Gas
cylinders shall be stored, handled as per gas cylinder rules
14. All vehicles shall be operated by licensed drivers only. All vehicles’ PUC to be tested
as per Government approved RTO guidelines. All Vehicles must be parked in
Parking space designated by GIPCL. If any vehicle is found inside the plant
premises other than the parking area such vehicles shall be handed over to Security
dept. and their entry shall be cancelled for movement inside the plant premises with
immediate effect.
15. All electrical equipment shall be in good condition and free from any defect. Electrical
tools & equipments i.e. welding machine, grinding and drill machine etc. may be
checked by the electrical engineer of the contractors regularly, every six month at
least and report to be submitted to concerned HOD and safety depts.
16. During hot work, contractor will use fire curtains like asbestos sheets or fire blankets
to prevent falling and spreading of sparks and hot material on and around the work
area. Contractor will procure and use such items. ELCB / RCCB shall be provided
with rating of 9-30 milli amperes on welding machine and all portable power tools.
17. The contractor shall fill – up Incident notification form (S-I), Incident Investigation
form (S-II) and near miss report within time limit as specified in forms, if any
accident, Incident, near miss occurred while working at SLPP site.
18. Major AMC / ARC contractor (Where the man power strength is more than 50 and
above) should appoint / nominate one qualified safety officer and he shall be
responsible for addressing all the safety related aspects of execution of contract
jobs and he will in close coordination with safety officer of SLPP and attend all safety
related meeting such as safety committee, on job safety training etc. Where the
contractual man power is less than 50, the site in charge of the contractor will act
as a safety officer and he will perform all the duties of safety officer as mentioned
19. No loose connection / joints allowed in electrical cables during performance of any
20. Safety shoes to be issued to female employees also.
21. All the vehicles shall be fit as per RTO guidelines and valid fitness certificate is
required as per RTO guidelines.
22. The Contractor’s nominated safety officer shall be imparted regular on-job safety
training like tool-box talk etc. and submit a record of such training in safety dept,
respective dept and HR&A dept.
23. The Contractor shall comply all the new requirements related with safety as
informed by the HOD / Safety department from time to time.
24. Penalty to be imposed for Violation of safety norms is proposed as follows:-
The Contractor & Contract workmen shall strictly adhere to Safety standards /
Guidelines as per practices. The list provided below is an indicative list to explain
the principles behind safety practice. If the contract workmen fail to comply with
safety standards as per category A, B & C below, penalty shall be levied on the
contractor as per the table mentioned below:
Category Classification Examples / Cases Penalty
A PPEs Working without helmet, Rs.100 /- per instant.
Related shoes, safety belt, gloves etc.
B WI Related Failure to adhere to HSE
guidelines/plans, careless
attitude in material
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Machine being used with • Rs.500 /- per
damaged machine guard, instant.
unsafe electrical work -
workout plug top/improper
electrical joints/cables lying • After three
on ground, electrical incidences,
equipment working without Per incidence
proper earthing, machine Rs.2500/-
being used without
machine guard, Welding
machine without ELCB / • Continuous
RCCB of proper rating, Gas unsafe acts
cylinder without test will disqualify
certificate, Cylinder cap, the contractor
NRV / Flash back arrester, from further
Cylinder trolley etc. participation
Unsafe working practices at in tender of
height more than 3 meters GIPCL-SLPP.
Working without permit or
non-compliance with permit
conditions like hot work,
height work etc. as
applicable, lifting tools and
tackles being used without
third party inspection
certificates in form no. 9/10
as per Factory Act –
C Unsafe Breach of safe practices by Suspend the entry
Practices a particular person gate pass for one
repeatedly for three times. week.
After two suspensions
his gate pass will be
Penalty so levied against the contractors and company employees will be used during the
observation of National Safety Day.
The contractor, workmen following good safety practices in their work area
continuously will be rewarded / honored on National safety day.
15.1 GENERAL ELECTRICAL SAFETY RULES & REGULATIONS
Electrical safety
a. All the electrical apparatus including welding machine (either 3-phase or single
phase) should be provided with Earth Leakage Circuit Breaker
(ELCB/RCCB/RCBO) of 30mA rating.
b. Bidder/Contractor should ensure periodic checking of ELCB provided in their
electrical apparatus.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
c. Bidder/Contractor should ensure that there should not be any joint in the power
supply cable of any machine. All cables should be in good condition with no bare
insulation or frayed wires
d. Any power supply switchboard/extension boards brought by Bidder/Contractor
should have ELCB of 30mA rating and it should have sockets along with 3-pin plug.
e. Any type of cable brought by Bidder/Contractor should not have any joint and should
be of sufficient capacity for the respective job.
f. Bidder/Contractor to bring their own 24V rating portable hand lamps along with
cable of (apparatus should be having 230V / 24V transformer) for the temporary
lighting arrangement required at site for the respective jobs.
g. Bidder/Contractor should bring sufficient quantity no. of temporary light fixtures
(230V or 24 V as per requirement of job/contract), extension boards, cables to draw
supply from nearest power point.
h. Hand-held and portable machines shall be equipped with a built-in switch to switch
off power in case of emergency
i. Bidder/Contractor to ensure healthiness of their electrical equipment whenever
brought to GIPCL site and get them tested / verified by GIPCL Electrical Department
representatives before start using.
j. Bidder/Contractor to ensure - All portable electric apparatus shall be regularly
examined, tested and maintained to ensure that the apparatus and leads are in
k. Only three-core cable shall be used for single phase operated tools with the third
core connected to earth.
l. Ensure that all metallic portable appliances are provided with 3 pin plug and socket
connections with third pin be connected to the ground terminal where ever possible.
Also, the metal work of the apparatus is effectively earthed.
m. All cables and connections should be sound and of adequate capacity and properly
insulated while using any welding machine and other power connections.
n. The earthing arrangements should be properly made with earthing clamps or a
bolted terminal while using any welding machine
o. Electric holders when not in use, should be placed on an insulated hook or the
holders should be fully insulated while using any welding machine
p. Whenever the welder stops or leaves work for any appreciable time, the power
supply to welding machine shall be effectively disconnected while using any welding
q. GIPCL will provide either single phase OR 3-phase 3 wire power supply from the
nearby point at job site. Bidder/Contractor to supply the required cable between
GIPCL power supply point to equipment brought by Bidder/Contractor for the
specified job. Further, if Bidder’s/Contractor’s equipment requires 3-ph 4 wire
supply then they should derive 3-ph 4 wire supply from GIPCL 3-ph 3 wire supply
system by incorporating sufficient capacity transformer. Like for hydro jet cleaning
system, mixer machine, induction heating machine, SR machine etc., GIPCL will
provide 3-ph 3 wire power supply.
r. Cable between welding machine to GIPCL power supply point should have cable
TOP plug towards GIPCL power supply point of Make BALS having rating as
Contractors not following above electrical safety points at any point of time are liable to
penalty and their machine/ apparatus shall be seized by GIPCL.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
16. REJECTION OF WORK
If, as a result of inspection, examination or testing, the GIPCL’s
Representative/Engineer decides that any materials, work or workmanship is
defective or otherwise not in accordance with the Contract, the GIPCL/Engineer/
GIPCL’s Representative may reject such plant, materials, work or workmanship and
shall notify the CONTRACTOR promptly, stating his reasons. The CONTRACTOR
shall then promptly make good the defect and ensure that the rejected item
complies with the Contract. If Contractor failed to rectify the rejected work or
workmanship, GIPCL/Engineer reserves the right to deduct or withhold amount
against rejected work or Workmanship. CONTRACTOR shall not entitle for any
claim or release of hold payment until rectify the defect up to satisfactory of GIPCL.
If Contractor failed to rectify any such defective work or workmanship, GIPCL
reserve the right to rectify at risk and cost of the CONTRACTOR and deducted by
the GIPCL from any amount due, or to become due, to the CONTRACTOR’s dues.
If the GIPCL/Engineer/GIPCL’s Representative requires such materials, work or
workmanship to be retested, the tests shall be repeated under the same terms and
conditions. If such rejection and retesting cause the GIPCL additional costs for the
traveling and lodging costs of GIPCL/Engineer’s personal for attending the retest,
such costs shall be recoverable from the CONTRACTOR by the GIPCL and may
be deducted by the GIPCL from any amount due, or to become due, to the
17. GENERAL TERMS AND CONDITIONS:
a. All tools & tackles, labours, equipments, materials (except free issue cement,
reinforcement steel and as specifically mentioned in item nomenclature) as per
contractor’s scope, etc… to execute the contract are in the scope of the
contractor. The contractor should ensure that tools & equipments are in healthy
b. The decision of the Engineer-in-charge shall be final and binding on the
contractor for defining the terms and condition included in this contract.
c. If the work is not found satisfactory, Engineer-in-charge reserves the right to
take suitable action.
d. Contractor shall depute full time site experienced supervisor They shall co-
ordinate with GIPCL engineer and shall bear overall responsibility of contract
including joint measurement, billing etc. Such person shall function from site
office of contractor at SLPP.
e. Contractor shall also nominate one safety supervisor (if required) at site and
shall submit nomination of safety supervisor in writing before commencement
of contract. Safety supervisor shall arrange small safety talk on every day
morning or whenever required with all workers working under this contract. He
shall coordinate with concern department’s Engineer-in-charge on daily basis
and report daily observations, tool-box talk records etc. The work shall not be
allowed without deploying safety supervisor and a penalty equal to Rs. 1,000/-
per day absent of safety supervisor shall be levied from Contractor.
f. Contractor shall strictly follow the existing work permit system of the GIPCL as
applicable and any future revisions.
g. The contractor has to take EC insurance policy for their workmen. The
contractor has to submit labour license and PF account number to the Engineer-
in-charge before start the work.
h. The contractor has to do the job timely. GIPCL shall not compromise in delay.
In case of delay of work without any valid reason, the GIPCL reserves the rights
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
to carry out the work by deploying other agencies at the risk & cost of contractor
with additional 10% overhead charges.
i. Contractor shall mobilize the resources as per need within the period of four
hours. If the contractor fails to mobilize sufficient resources to complete the job
in time, GIPCL will execute the job through other agency at the risk and cost of
the contractor with additional 10% overhead charges.
j. Contractor should mobilize all resources for efficient & smooth execution of
contract within seven days from the date of issue of Letter of Intent/Work Order.
k. The prices / item rates quoted shall remain firm till completion of the contract
and any agreed extensions thereafter and shall not be subject to any escalation,
idle charges for labour, machinery, overhead expenses etc… due to any reason
whatsoever. No price escalation / idle charges shall be entertained due to delay
in work on unavailability of work front, non-issue of work permit, holding of work
permit for any reason, unavailability of contractor’s supervisor, unavailability of
contractor’s safety supervisor, violation of safety rules, unsafe act by any of
contractor’s worker, negligence & ignorance of safety & quality instructions of
GIPCL Engineer-in-charge or any other reason whatsoever.
l. Contractor must fulfill all the safety regulations and to take safety measures to
avoid hazards. Contractor shall arrange all standard adequate healthy safety
PPEs like but not limited to approved quality safety shoes & safety helmets,
standard dust masks, safety goggles, etc… as required and shall use
exclusively under this contract for all the time during working at specified
locations failing which, the Engineer-in-charge may hold the work and will take
necessary action including penalty as decided. If the contractor repeatedly
violates safety rules/regulations (more than three successive incidents),
Engineer-in-charge may take necessary action against the contractor, including
appropriate financial penalty (Maximum of Rs. 1,000/- per incident per man-day
and as per clause no. 15) and/or termination of contract.
m. One or more jobs may be required to be done simultaneously and contractor
shall mobilize additional resources accordingly.
n. Timely completion of all jobs and works shall be the essence of this Contract.
Contractor should closely monitor each activity and complete the jobs as per the
time given by and under the supervision of the Engineer-In-charge and shall
ensure that sufficient manpower is deployed for the same.
o. The contractor has to complete the works as per the planning schedule and their
respective supervisor has to interact with Engineer In Charge for PTW (Permit
to work), work instruction, Return of permit whichever is required as applicable.
p. The contractor has to submit daily reports showing work carried out with details
of available manpower, tractors etc.
q. Any job other than the listed jobs in work order shall be executed by the
contractor on instruction from GIPCL and payment shall be made to the
contractor on respective item rate only.
r. The Government of India has enacted the Micro, Small and Medium Enterprises
Development Act, 2006 (the “Act”) and the Act has come into force from October
2, 2006. The Bidder shall confirm whether your organization is registered under
the Micro, Small and Medium Enterprises Development Act, 2006. If your
organization is registered under the Act, please specify the category i.e., Micro
Enterprise, Small Enterprise or Medium Enterprise under which it is registered
and kindly attach a copy of your registration certificate.
s. The Bidder shall provide details of registration along with copy of the registration
certificate issued by the District Industries Centre/Department of Industries, etc
of the respective State Government. It is to be noted that large scale industries
and trading firms have been excluded from the purview of the Act.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
t. GIPCL is an ISO 9001, ISO 14001, OHSAS 18001 & ISO 50001:2011 (EnMS)
certified company, and GIPCL gives extreme importance to maintain these
global standards. Contractor shall be required to observe these standards while
working with GIPCL. Contractor should ensure that his workmen/labour work in
accordance with them.
18. CONTRACTOR’S SUPERVISION
The contractor shall, during the whole time the work is in progress, employ a
qualified experienced site-in-charge of the works with adequate experience in
handing of jobs of this nature and with the prior approval of the GIPCL / ENGINEER.
Such in-charge shall be constantly in attendance at the site during working hours.
During CONTRACTOR’S supervisory engineer absence during working hours, if
unavoidable, and also beyond working hours, when it may be necessary to give
directions, orders may be given by the ENGINEER / GIPCL and shall be received
and obeyed by the CONTRACTOR’S superintendent or Foreman who may have
charge of the particular part of the work in reference to which orders are given. If
requested to do so, the ENGINEER /GIPCL shall confirm such orders in writing.
Any directions, instructions or notices given by the ENGINEER / GIPCL to him, shall
be deemed to have been given to the CONTRACTOR. The representative of the
CONTRACTOR shall have all necessary powers to receive materials from the
GIPCL, issue valid receipts for the same, engage labour or purchase materials and
proceed with the work as required for speedy execution.
None of the CONTRACTOR’S Superintendents, engineers, supervisors or labour
should be withdrawn from the work without due notice being given to the GIPCL /
ENGINEER; further no such withdrawals shall be made if in the opinion of the
GIPCL / ENGINEER such withdrawals will jeopardize the required pace of progress
/ successful completion of the work.
The CONTRACTOR shall employ in or about execution of the work only such
persons as area careful, skilled and experienced in their respective trades, and the
GIPCL shall be at liberty to object to and require the CONTRACTOR to remove any
person employed by the CONTRACTOR in or about execution of works who in the
opinion of the ENGINEER misconducts himself or is incompetent or negligent in the
proper performance of his duties and all such persons shall not again be employed
upon the works without the prior permission of the GIPCL.
Neither the CONTRACTOR and the PURCHASER nor the ENGINEER shall hire or
employ any employee of the other party except by mutual consent.
19. CONTRACTOR TO REMOVE ALL OFFENSIVE MATTER IMMEDIATELY AND
All loose materials, wastage, packing materials, cut pieces or other matter of an
offensive nature shall not be deposited on the surface, but shall at once be carted
away by the CONTRACTOR to some pit or place provided by him away from the
site of work and approved by local authorities.
As a part of the work included in this contract, the CONTRACTOR shall completely
remove and satisfactorily dispose of all temporary works to the extent directed. He
shall tear down and dispose of all temporary works, shall remove or grade, to the
extent directed, all plant and equipment, shall satisfactorily dispose off all rubbish
resulting from the operations under this contract and shall do all work necessary to
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
restore the territory embraced within the site of his operations to at least as good
order and conditions as at the beginning of the work under this contract.
20. FACILITIES TO BE PROVIDED BY GIPCL
A. The Company shall provide the following facilities to the Contractor at the site:
a. Electricity & water at nearest available one point. Further distribution to be done
by contractor at their cost.
b. Quarter(s) for supervisor/ engineers on chargeable basis in GIPCL’s colony at
discretion of GIPCL, if available.
c. Workshop facility as available at site only on chargeable basis. However,
contractor may visit the workshop to ensure the existing facility. For the facilities
other than available, contractor has to carry out the job outside at their own
d. Space for contractor’s office & store as decided by GIPCL based on availability.
e. First aid facilities as available on chargeable basis. If not available contractor
to make his own arrangement for the same locally or as appropriate at his cost.
Apart from the above, no other facilities shall be provided by GIPCL.
B. GIPCL shall also conduct an orientation program appraising the workmen
regarding the safety norms and measures to be observed during work
operations at the colony/plant site.
21. WORK MEASUREMENT/CERTIFICATION
a. The work to be performed being a specialized nature, the contractor should be
fully conversant with modern practices and should be able to carry out works
independently of large colony of thermal power plant. The contractor shall
therefore be required to engage qualified/ experienced personnel to undertake
the work as per specifications and requirement.
b. Contractor should maintain one computer with printer for keeping daily records
and maintain the data.
c. All the work measurements shall be jointly recorded in a measurement
sheet/register/relevant documents by the contractor/ authorized representative
of the contractor and the Engineer-in-charge. The measurement shall be clearly
written indicating date of measurement, location, reference of drawings, if any,
and jointly signed.
d. The Contractor shall be required to furnish satisfactory job completion report to
GIPCL. The submission of report should be on daily basis, the monthly bill
payment shall be released based on the certified reports of the works.
e. Inspection of work will be done by Engineer-in-Charge or his authorized
representative. If the work is not found satisfactory Engineer-in-charge reserves
the right to take suitable action and shall be binding to the contractor.
22. PUBLIC HOLIDAYS
The Contractor shall be responsible for giving benefit to all his employees,
employed in whatsoever capacity, 09 Public/Paid holidays and the same shall be
notified in advance and due communication thereof shall be made to the
23. BENEFIT PAYABLE IN CASE OF ACCIDENT OCCURRING OUTSIDE
PREMISES OR BEYOND THE COURSE OF EMPLOYMENT
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
The Contractor shall provide an insurance coverage (Medical + Death Benefit) for
sum of Rs. 01/- Lakh to all his workmen/labour deployed at GIPCL-SLPP site for
the accident taking place anywhere outside the Company premises or at any place
when the workman is not in course of his employment.
24. FORCE MAJEURE
The performance of the obligations herein contemplated may be suspended without
incurring the penalty in the event of the subsistence of Force Majeure conditions.
If a Force Majeure situation arises, the affected Party shall promptly notify the other
Party in writing of such conditions and the performance shall be suspended as per
mutual agreement.
For the purposes of this clause, ‘Force Majeure’ means an event beyond the control
of the Party and not foreseeable by the Party and shall include events of floods,
explosions, riots, wars, hurricane, epidemics, any other Act of God, quarantine
restrictions, terrorism, government actions and provided always that such acts
result in the impossibility of the further performance of the contract.
The Contractor shall indemnify and keep harmless GIPCL from and against all
actions, proceedings, claims, demands, losses, costs, damages and expenses
whatsoever which may be brought against or suffered by GIPCL which it may
sustain, pay or incur as a result of or in connection with the performance/ purported
performance/ non-performance of the contract by the Contractor.
In case, in any litigation pertaining to labour employed through contractor if any
direction or order is issued by court at any point of time the contractor shall comply
with and implement such direction or order whether passed at the time of award of
contract or during the pendency of contract. Further, the Contractor shall indemnify
the GIPCL against all consequences arising and affecting GIPCL owing to the
compliance of the orders by the Contractor.
26. GOVERNING LAW AND JURISDICTION
This tender document and contract shall be governed by the laws of India and the
Courts at Surat shall have jurisdiction regarding the same.
27. Where any portion of the General Condition of Contract is repugnant to or at
variance with any provisions of the Special Condition of Contract, then unless a
different intention appears, the provision of the Special Conditions of Contract shall
prevail to the extent of such repugnancy of variance.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
SPECIAL CONDITIONS OF CONTRACT
1. DETAIL SCOPE OF WORK
PACKAGE-I (HOUSEKEEPING SERVICES):
SCOPE IN COLONY AND SCHOOL AREAS:
The scope includes housekeeping work for all the all the Quarters, Guest House,
Temple, Open Air Theater, common utilities, offices, public utility building, School
Building & Swimming pool at Colony including day to day cleaning of floors, walls,
toilets, passages, terrace etc., as mentioned in schedule given herewith including
periodically cleaning of tanks, water cooler, parking, roads, drains, swimming pool,
collection & disposal of garbage from various locations through tractor with standard
hydraulic trolley/ Hand Cart etc. as per mentioned in schedule of frequency given in
regular scope of SoR (Section-E) including periodic cleaning surrounding area of
Residential and utility building, storm water drain cleaning etc.., as per the time to
time instructions given by Engineer-in-charge as per scope of works mentioned
under special items in special Item scope of SoR (Section-E).
The scope of work also includes handling & maintenance of swimming pool for
which contractor shall arrange one cleaner & one operator cum trainer on daily basis
Contractor shall supply of housekeeping materials like Soft Brooms, Coco Brooms,
Yellow Duster, Floor Duster, Scotch Brite, Stick Mope, Rubber Brush, Steel Rubber
wiper with handle, W.C. Brush, cleaning material i.e. acid, phenyl, odonil,
naphthalene balls, washing powder, baygon spray, liquid soap, cooline, harpic,
drainex, room spray, spray pump, Urinal net, Godrej aer pocket, Phenyl, Road
Brush, PVC Pipe etc., with necessary tools, tackles, equipment, buckets and
tumblers, PVC Pipe etc.. For cleaning purpose. Contractor shall be responsible to
provide and use only good quality branded & approved cleaning materials &
tools/equipment and shall maintain sufficient stock of every items for the fulfillment
of the work. Contractor shall have to make arrangement to bring required quantity
of housekeeping materials as per schedule provided herein under clause no. 1.1.1
&1.1.2. Contractor shall ensure proper entry of all these materials inside the colony
and copy shall be submitted to Engineer-in-charge. Contractor shall also arrange
for keeping proper record of material consumption record as directed by Engineer-
The scope of work also included disposal of all collected waste materials, dust &
other unwanted materials in various area of colony during regular cleaning (as per
above scope of work & frequency) of Roads, Pathways, Stair cases in Blocks,
approach of E & F Type, Public building, Guest House etc.. once in a week by
arranging tractor & labour and also including loading, unloading & disposal of the
all waste materials outside the colony premises within 03 KM lead (one side) as
directed by engineer in-charge. (In case if contractor arrange resources & clean the
all collected waste & unwanted materials from various area of colony fortnightly/
monthly instead of weekly, it will be considered as one cleaning only)
The scope of work also includes collection of daily generated garbage from each
quarter of colony and other unwanted materials by providing Hand Cart/ tractor with
standard size hydraulic trolley attachment along with driver & labours and disposal
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
of the same at designated location on daily basis. The collected garbage shall be
disposal every monthly outside the colony premises within lead of 07 to 10 kms (one
side) using JCB & Tractor with trolley/truck. The RTO passing of Tractors &
hydraulic trolleys (minimum capacity 2.83 M3 with all four sides closed and having
hydraulic arrangement for unloading) shall be deployed under this contract along
with necessary valid legal documents like copies of RC book, PUC certificate,
Vehicle insurance policy, Vehicle fitness certificate (as applicable), valid driving
license, etc… with required manpower and consumables. If contractor failed in
disposal of the garbage outside the colony premises every fortnightly, GIPCL
imposed penalty as per penalty clause. The scope of work is also including
segregating re-cycle waste & food waste properly as directed by Engineer and in-
PACKAGE-II (NEED BASED SCOPE OF WORK):
The scope of work includes miscellaneous works to be carried out through
temporary unskilled manpower with tools-tackles, brush cutting machines, tractor
with standard size hydraulic trolley of minimum capacity 2.83 M3 with all four sides
closed, having hydraulic arrangement for unloading and also having valid legal
documents like copies of RC book, PUC certificate, Vehicle insurance policy,
Vehicle fitness certificate (as applicable), valid driving license, etc… with driver, fuel
& consumables (per day eight hour duty). The need based miscellaneous
housekeeping services such as Cleaning of storm water drains quarterly, Cleaning
of area including Grass/unwanted vegetation cutting within 5 mtr. around the
quarters, Children park, LPG Godown & disposal of the same outside the colony
premises on quarterly basis.
As per scope of work under item no. 3 of SoR (Package-II in Section-E), contractor
shall provide petrol operated brush cutting machines for grass cutting, tractor with
trolley for disposal and labour on as & when required basis. In case of break-down
of any of machine, contractor shall carry out necessary maintenance and make it
available for use within one week. If contractor failed to provide tractor with trolley
for disposal of unwanted vegetation & grass, GIPCL will imposed necessary penalty
as per clause no. 1.1.4 of Section-D.
The scope also includes all works necessary, which are not specifically mentioned
here but required, for effective execution of entire work in all respect within time
bound period and are deemed to be included in the scope of the CONTRACTOR.
All works shall conform to the specifications, safety norms, legal & statutory
1.1.1 TOOLS & TACKLES AND HOUSEKEEPING MATERIALS
For proper housekeeping of the area, the contractor is required to maintain sufficient
quantity of tools & tackles in good working condition with sufficient quantity of
housekeeping materials at site. For proper execution of the work, contractor is
required to maintain sufficient number of tools & tackles including grass/weed
cutting tools, housekeeping tools & tackles, bucket, rope, PVC pipes, Drainage
cleaning rods etc. in good working condition at site.
It is also desired from contractor to adopt mechanized housekeeping up to
maximum possible extent. Contractor is desired to provide road sweeping
equipment, floor sweeping & swabbing machines for housekeeping at large floor
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
areas like School, etc.., up to possible extent and satisfaction of Engineer-in-charge.
Necessary 15A single phase power shall be provided by GIPCL at available nearest
point. Further distribution shall be in the scope of contractor
The estimated list of housekeeping materials for Section-I is as under. Contractor
shall note that this list is not exhaustive and if any additional materials, tools &
tackles are required for proper performance of the contract and to maintain good
hygienic condition, the contractor shall also arrange the same immediately with no
extra cost to GIPCL.
Sr. Description of Tools, Tackles & Quantity per Unit
No. Materials Month
1 Washing Powder 500 GMS pack 24.00 No.
2 Flavoured Naphtha Balls 1.50 kg
3 Urinal Net 4.00 No.
4 Odonil - 75 gms. 5.00 No.
5 Godrej aer pocket of 10 gms 10.00 No.
6 Baygon/HIT Spray each 400ML 3.00 No.
7 White Phenyl confirming to IS 35.00 liter
8 Cleaning Acid 7.00 liter
9 "Rozalex" Liquid Hand wash 2.00 liter
10 Coolin 1.00 liter
11 Harpic - 500 ml. 4.00 No.
12 Dranex - 100 ml 4.00 No.
13 Room Freshner each 150ML 10.00 No.
14 Soft Brooms 30.00 No.
15 Coco Brooms 42.00 No.
16 Floor cleaning cloth 38.00 No.
17 Stick Brooms (Long Handle - 15 to 1.00 No.
18 WC Brush 2.00 No.
19 Steel Rubber Wiper with Handle for 2.00 No.
20 Long Handle Road Brush 2.00 No.
21 PVC Water Pipe (30 mtr.) 1.00 Bundle
22 Scotch Brite - 10 x 15 cms. 4.00 No.
23 Yellow Duster 6.00 No.
24 Spray pump 2.00 No.
25 Rubber butch 4.00 No.
26 Bucket 1.00 No.
27 Supadi 3.00 No.
28 Wetmope set 3 No.
Note: Above mention quantity is indicative only. However, for hygienic
& best cleaning, if more cleaning materials, tools & tackles are
required, contractor has to arrange on their own and same may
considered for bidding.
Contractor shall keep up to date record of monthly tools, tackles and material
received and location wise daily material issued quantities in a register for proper
accounting of the use of these materials. The register shall be checked by
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
concerned Engineer-in-charge periodically and if any discrepancy is observed,
Engineer-in-charge shall take suitable action.
1.1.2 MATERIALS, TOOLS & TACKLES COVERED IN CONTRACTORS SCOPE
➢ All cleaning chemicals and substances like naphthalene balls, toilet fresheners, pest
control Spray, approved liquid soap, washing powder, utensil cleaner, White phenyl,
Acid, Spray pump, Room spray, Glass cleaner, toilet/Urinal/Wash basin cleaner,
Drain chock up remover, etc… as mentioned in above clause no. 1.1 shall be
supplied by contractor and shall be maintained in sufficient quantity for maintaining
highest standard of hygiene.
➢ The contractor shall arrange quantities of above-mentioned material every month.
However, if it is found insufficient for maintaining hygiene condition, contractor
should arrange additional required material for which he will not claim any additional
➢ The contractor will have to make his own arrangement for all tools & tackles like
soft brooms, coco brooms, yellow duster, white duster, floor duster, scotch brite,
stick mope, rubber brush, steel rubber, wiper with handle, Brush for cleaning of
ceiling of open-air theater, Town Centre, Guest House, School, etc…
➢ Assessment of material consumption per month is mentioned above in clause no.
1.1.1 This assessment is minimum consumption for indication purpose only.
However, contractor shall arrange additional quantities required for maintaining
hygiene condition without any additional cost to GIPCL.
1.1.3 SCHEDULE OF HOUSEKEEPING
Contractor shall deploy suitable manpower along with supervisor to carry out
housekeeping works.
The contractor shall deploy site-in-charge cum supervisor for day to day monitoring,
to check the frequency & quality of housekeeping regularly and to get the daily
certification of work done from concerned GIPCL’s representatives. Various
housekeeping activities shall be carried out as per the frequency specified by
The work is of specialized nature and the contractor should be fully conversant with
modern practices and should be able to carry out Housekeeping works
independently. The contractor shall therefore be required to engage qualified /
experienced personnel.
1.1.4 WORK, WORKMANSHIP AND PENALTY
a. The agency has to ensure that the cleaning of colony areas, offices, furniture,
toilets etc… are completed timely every day. Other areas like lobbies, corridors,
stairs, unman areas, etc… can be cleaned on suitable timings as decided by
GIPCL. However, the agency has to ensure that minimum noise is generated
during cleaning operations.
b. The work is to be carried out for all the days throughout the contract duration of
including all Sundays and Holidays as per area wise specified frequency.
c. The time of work will be decided by GIPCL. Cleaning work shall be carried out
during shift timing also, if required.
d. The contractor will have to engage sufficient number of persons to carry out the
work effectively and efficiently to fulfill the terms and conditions of this contract.
Contractor will be responsible for the overall control and supervision of the work.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
e. The contractor shall issue Appointment letter & Identity Cards to all employees
engaged by them with the instructions that the same should be produced by
them on demand and shall, at all times, keep the Identity Card while on duties.
f. The contractor will deploy the trained, experienced supervisor, competent for
carrying out the job in a proper way.
g. The contractor shall fulfill all the legal formalities such as minimum wages,
payment of wages, labour license, employee compensation, P.F., Bonus, leave
and all other statutory provision as applicable under the contract act.
h. The contractor shall produce PF challans with ECR and other documents along
with bill for previous month of the billing month.
i. All the work must be done as per the specification properly in proper order in
time. Workmanship shall be of highest professional standard.
j. No person under the age of 18 years shall be engaged by the contractor and be
not permitted entry into work area.
k. The contractor shall observe all the safety & security rules & regulation, work
permit system of the company which is at present in force and which may come
into force during the pendency of the contract.
l. In case of any complaint on cleanliness at any place, a penalty of Rs. 300/- per
complaint per day will be deducted from the contractor’s monthly bill in addition
to measurement deduction.
m. In case, if contractor failed to attend housekeeping services in Colony premises
on demand as per scope of work and if delay more than three days without valid
reason & also if delay due to shortage of manpower, a penalty of Rs. 500/- per
day will be deducted from the contractor’s monthly bill. Contractor shall submit
work done report to the concerned GIPCL engineer.
n. The contractor’s senior executive should visit once in a month to the GIPCL’s
colony premises and note down the problems/complains and to arrange
resources accordingly to resolve the problems/complains reported by the
authorized officer.
o. No employees, agent or sub-agent of the contractor shall smoke or light
anything within the work premises or carry match box/lighter or any other
explosive and / or inflammable material inside the colony/plant.
p. The contractor or its staff/ workers shall not damage any property of GIPCL. In
case of default the damages as assessed by the authorized officer of GIPCL,
whose assessment shall be final & binding to the contractor and the same
amount will be recovered from the bills.
q. Contractor shall procure & supply required materials & consumable within
week of Bill cycle period and maintaining enough stock of this material at
site. In case of contractor failed to supply above mentioned materials 10th date
of every month without any specific reason and if above specified materials are
not available at site for more than three days, GIPCL will enforced penalty of
Rs.100/- per day to the contractor till receipt of materials.
r. As per scope of work, contractor should arrange one tractor with trolley minimum
once in a week (full day) for disposal of collected waste at various location after
cleaning of Roads, Pathways, Stair case etc.. from various locations to outside
Colony premises. In case, if contractor fails to arrange one tractor with trolley
every week, a penalty of Rs. 2500/- per week will be deducted from the
contractor’s monthly bill. Contractor shall submit work done report to the
concerned GIPCL engineer.
s. As per scope of work, contractor should arrange disposal of collected garbage
and other unwanted materials from garbage yard to outside the colony at
designated location within lead of 08 kms (one side) using JCB & Tractor with
trolley/truck every fortnightly (except monsoon season). During monsoon
season, disposal work should be taken up based on dry period as per direction
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
of GIPCL engineer in charge. In case, if contractor fails to arrange necessary
equipment i.e. like JCB, Trucks/Tractor, covering tarpaulin sheet for disposal of
collected waste/ garbage every 15 days (dry period during monsoon season), a
penalty of Rs. 5000/- per instant will be deducted from the contractor’s monthly
bill in addition to measurement deduction. Contractor shall submit work done
report to the concerned GIPCL engineer.
t. Contractor shall arrange cleaning of all bitumen road, side pathways & area
between pathways & drain including cleaning of waste tree leaves etc. with
necessary hard brooms wire brushes, mops & if required with fresh water &
disposal of the same to outside colony premises as per instruction of engineer-
in-charge as per frequency. In case, if contractor failed to carry out given scope
of road cleaning work as per given frequency, penalty of Rs. 500 per instant will
be deducted from the contractor’s monthly bill.
u. To operate and maintain the swimming pool by supplying one cleaner & one
operator cum trainer on daily basis. Contractor shall responsible for deployment
of required manpower during daily activities for swimming pool. In case of failure
by contractor to arrange manpower as specified above, following penalty will be
Absence of Manpower in any shift Rs.500/- per shift
Duty hours less than 04 hours Consider absent.
Rs. 500/- per shift
Duty hours more than 04 hours but less ten Rs.250/-per instant
Non-deployment of Manpower in case of Rs.700/- per day
long leave of deployed manpower
1.2 FAILURE DURING EMERGENCY
During any emergencies, contractor shall have to carry out this work by deploying
additional force within four hour notice period failing which GIPCL reserves the right
to carry out this work by engaging other party. The expenditure occurred due to
such situations, the Contractor will be held responsible & the same will be recovered
from the Contractor’s monthly bill / any other pending bills along with 10% overhead
charges, plus applicable GST as per extant GST Laws.
For repetitive failure of such work for more than two incidents, GIPCL reserve the
right to terminate the entire contract by forfeiting all pending dues, Security Deposit
& other retention money, if any, after giving 15 days notice to the contractor & this
will be binding to the contractor
1.3 SPILLAGE OF MATERIAL
Contractor shall take due care to avoid any spillage of material while loading /
transporting / handling. To avoid spillage of material, overloading / heaping shall be
avoided by the contractors. Trolleys shall be in good condition for any leakage of
materials. In case of any spillage, contractor shall be responsible to clean up that
area at their cost otherwise GIPCL shall get the work done by other agency at
contractor’s risk and cost with additional 10% overhead charges.
1.4 DISPOSAL OF MATERIAL
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Contractor shall be responsible for removal and disposal of garbage/waste materials
to outside premises or at designated locations as per prevailing GPCB norms. GIPCL
will not be held responsible for any subsequent consequences regarding improper
disposal of material.
Contractor shall be required to submit written undertaking along with every RA bill
as well as along with the final bill that all the material is disposed off at outside
colony/plant premises or at designated locations as per prevailing Government
guideline and contractor shall indemnify, keep harmless the GIPCL against any
future liabilities or consequences in this regard. Contractor’s final bill shall be
processed only after receipt of letter of undertaking by the contractor.
Contractor’s bills shall be processed only after written confirmation & compliance for
disposal of all such empty drums, containers, other scrapes, etc… to outside
premises in accordance with prevailing GPCB norms based on submission of letter
of undertaking by the contractor and certificate from Engineer-in-charge along with
1.5 SCOPE OF CONTRACTOR
1. All tools & tackles, housekeeping materials, required vehicles, equipments etc…
to execute the contract will be in the scope of the contractor. The contractor
should ensure for healthiness/working conditions of tools, tackles & vehicles.
2. The tractor trolley/ Hand Cart shall be in good condition i.e. free from any
corrosion, free from any holes, cracks & damages in to avoid leakages/spillages.
In due course of time, if any damage and/or corrosion are take place, contractor
shall replace or repair such trolleys immediately up to the full satisfaction of
Engineer-in-charge. GIPCL will allow tractor trolley for the work, only, after
verification of condition and healthiness of the trolley.
3. All consumable items like cloth, cotton waste, kerosene, gas, diesel, petrol,
lubricants, etc will be in the scope of the contractor.
4. All safety/PPEs required during work at site are to be arranged by the contractor.
5. The Contractor shall have to provide necessary facilities including
accommodation for their labour at their own cost.
6. Contractor has to depute their full time experienced site-in-charge cum
supervisor for work execution as per specification and for day to day work
planning & coordination with respective department’s Engineer-in-charge, to
obtain day to day Location wise work permits/instructions, to record Location
wise joint work done reports/measurements.
1.6 TO REMEDY DEFECTIVE WORK
If the work or any portion thereof shall be damaged in any way excepting by the
acts of the GIPCL, or if defects not readily detected by proper inspection shall
develop before the final completion and acceptance of the whole work, the
CONTRACTOR shall forthwith make good, without compensation, such damage or
defects in a manner satisfactory to the ENGINEER / GIPCL. In no case shall
defective or imperfect work be retained even if contractor followed all technical
specifications. GIPCL will not compromise for quality of materials, works &
The CONTRACTOR shall remain liable under the provisions of this clause
notwithstanding the passing by the GIPCL of any certificate, final or otherwise or
the passing of any accounts.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
1.7 DAILY DIARY AND PROGRESS REPORT
A daily diary register will be kept in the ENGINEER’S office. The CONTRACTOR
will supply all detailed information every day at 9:00 hours for the day preceding
and the diary will be jointly signed by the ENGINEER and the CONTRACTOR’S
representatives, every day in token of its correctness. A works instruction book,
serially numbered will also be kept in the ENGINEER’S office and all day to day
instructions will be given in that book. The CONTRACTOR’S representative shall
report every day to see these instructions and sign them at the bottom in token of
his having seen them.
The CONTRACTOR shall supply all information regarding procurement of materials
and progress of work, as is required by the ENGINEER for compiling the weekly
progress reports. This information shall be supplied by 9:00 hours on every Monday,
for the preceding week.
2. PRICE & RATES
This is SoR based tender and final item rates will be derived based on final offered
lowest price received through e-Reverse Auction on gross total price (including 18%
GST). Prorata reduction will be applied in the quoted price for all the items of SoRs
after price discovery through e-Reverse Auction. The item rates so derived shall be
inclusive of cost of all labour Manpower (including prevailing minimum wage rate
as well as specific additional adhoc allowance), supervisors, tractors, materials,
tools & tackles, consumables, transportation, vehicles, spares & maintenance,
shifting, loading, unloading, equipment, Safety, Legal & Statutory compliance,
mobilization-demobilization, uniform charges (three pair per year as per
approval), insurance charges including off duty coverage, safety equipments &
PPEs, any other cost as per applicability as mentioned in various clauses,
Royalties, Rents, Stamp Duties, Central or State Government or Local body or
Municipal Taxes or Duties or any other duty / tax (applicable GST shall be
mentioned separately on Bill Invoice as per extant GST Laws at actual as per
prevailing rates as declared by Central Government), etc levied by the Central,
State Government or other Public bodies etc… and such other costs that are not
specifically mentioned herein but will be incurred by the contractor for the
satisfactory and timely completion of the work. The whole item rates shall be
deemed to include for everything mentioned in the specification, all leads & lifts,
contractor’s overheads & profits for due performance of the work under this contract
and such other costs that are not specifically mentioned herein but will be incurred
by the contractor for the satisfactory and timely completion of the work. The rates
shall also include cost for mobilization / demobilization of manpower, equipments,
materials, etc... as per work requirement.
The rates shall be firm for entire contract period and also during extension thereof,
if required and shall not be subject to any escalation in prices, idle charges for
labour, machinery, overhead expenses etc. No price escalation / idle charges shall
be due to any reason whatsoever. The value and/or quantum of work may be
increased or decreased depending upon day to day requirement. However, item
rates will remain unchanged and the payment shall be made as per the actual
quantity executed as informed & certified by GIPCL representatives.
The prices / item rates so derived based on final recovery of lowest offer from Bidder
shall remain firm till completion of the contract period and any agreed extensions
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
thereafter and shall not be subject to any other escalation, idle charges for labour,
machinery, overhead expenses etc. No price escalation / idle charges shall be
payable due to delay in work by contractor or due to non-availability of work front
by GIPCL or any reason whatsoever.
Contractor shall at his expense comply with all labour and industrial laws and such
other acts and statutes as amended from time to time as may be applicable to this
contract in respect to pay etc. On account of any default in respect of all liabilities
and in case of non-compliance of the above, the company can withhold their
payments till all legal liabilities are discharged.
The offer price shall be considering mobilization of all required manpower, tools &
tackles, materials, equipment, vehicles, consumables, etc… for timely and
satisfactory completion of all scope of work.
3. CONTRACT PERIOD
Contract period will be two years from the date of commencement (mobilization
period will be 15 days from the date of issue of LoI or Work Order whichever earlier)
or from the date of commencement as mentioned in work order.
GIPCL reserves the right to extend the Contract Period up to 03 (three) months at
the same rates, terms & conditions without any price escalation and entering into
any new contract.
The said Contract Period can be extended if mutually agreed upon by both the
parties up to one year and in such a case a revised work order shall be issued at
the same rates, terms & condition or at negotiated rates acceptable by both parties
i.e. the Company & the Contractor.
GIPCL reserve the right to short close the contract any time by giving one month
notice period without assigning any reason whatsoever.
4. TERMS OF PAYMENT
A. Condition of Payment:
The contractor shall raise the single invoice in duplicate (one original in physical
form and soft copy in MS Excel format as directed by Engineer-in-charge) for every
month in respect of the work performed or completed during the previous month
along with the documents as mentioned hereinafter. On receipt of the invoice
complete in all respects and with all the specified documents, the payment in
respect of the same shall be made within 21 days of such receipt of a complete
invoice as per the following terms of payment:
(i) 100% of monthly RA bill along with 100% taxes shall be released against
the work executed duly certified by GIPCL. Income Tax (IT) will be
deducted at source from monthly RA bills as per the rules in force.
(ii) Security deposit at 10% of annual contract value shall be submitted as
per clause no.: 1 of Section-C. Security deposit will be returned to the
Contractor without any interest after retention period of three months from
actual contract completion date as certified by Engineer-in-charge as per
clause no.: 1 of Section-C.
(iii) GST shall be paid along with bills after fulfillment of following terms.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
(a) Submission of copy of registration certificate issued by GST Authority
(to be furnished only once).
(b) Citing the GST Registration no., HSN Code and the date of issue of
registration certificate on invoices.
(c) Citing GIPCL’s GST no. along with contractor’s GST registration no.
and the date of issue of registration certificate on invoices.
(d) Claim of GST amount with percentage (%) separately shown on the
(e) The contractor shall be required to submit the proof of payment of GST
of previous month/quarter, as may be applicable as & when demanded
by GIPCL/Owner/company.
(f) Contractor shall inform the GIPCL in the event of its registration
certificate is cancelled or discontinued for whatsoever reason.
(g) The contractor shall also mention on their invoice the HSN/SAC code
as applicable under the GST laws under which GST is levied and a self-
certified authentic third-party evidence (www.cbic-gst.gov.in) shall be
adduced to that effect by the contractor.
(iv) At the time of submission of the first monthly RA Bill, the Contractor shall
submit a certificate from Engineer-in-charge regarding availability of tools &
tackles, equipments, vehicles etc at site. The Contractor shall also furnish the
checklist as per ANNEXURE-A enclosed with the Section-F of tender
document along with the RA bill of respective month.
(v) While making running account payment, the following deductions may be
made by GIPCL, if applicable,
a. Cost of materials issued, if any, by GIPCL and to the extent consumed in
b. Security deposit recoverable if any.
c. Advance on materials/work progress advance payments, if any.
d. Penalty for delayed delivery, penalty for delayed execution of work,
recovery of charges for the work done by other contractor due to delay or
any reason, if applicable.
e. Any other dues recoverable by GIPCL from the contractor under the
(vi) The contractor, along with monthly RA/final bill shall submit copy of P.F.
Challan, wages register, attendance sheet & ECR statement indicating the
employee and employer's P.F contribution with respect of employees
employed by him for the contract at GIPCL site along with format for
submission of these documents provided in Section-F (Annexure-H).
(vii) The Contractor shall submit his Final Bill within a period of three months of
the expiration or earlier termination of the contract or any extensions that may
be granted by GIPCL to the Contractor. GIPCL shall not entertain any bill for
any work item after expiration of period of four months.
(viii) The Contractor shall include all his claims in the Final Bill submitted by him
and accordingly the final bill submitted by the Contractor shall be deemed to
be inclusive of all and whatsoever the claims that the Contractor may have
from GIPCL. The Contractor shall not be entitled to claim any amounts which
are not mentioned in the Final Bill and the Contractor shall be deemed to
have waived any claims not mentioned in the Final Bill and shall not be
entitled to recover the same from GIPCL subsequent to the submission of the
Final Bill on any account and GIPCL shall stand absolved of all its liabilities
in respect of any such claims not raised by the Contractor in his Final Bill.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
B. Validity and Uniformity of Rates
The rates shall be valid for a period of two years of the Contract Period and shall
remain unaltered during the entire contract period & any further mutual agreed
5. SUBMISSION OF TECHNICAL DOCUMENTS TO THE ENGR-IN-CHARGE
Contractor shall submit following documents to the Engineer-in-charge for
verification purpose of the bill:-
(i) Measurement sheets (both in soft copy and in physical form) of work done.
(ii) Bill of material stamped & signed by security at gate entry.
(iii) Certified Joint Measurement records of work done in the form of joint
inspection report duly signed by GIPCL’s authorized representative and
contractor’s supervisor in standard format.
(iv) Check list (Annexure-A in Section-F).
The bill will not be entertained without submission of above documents.
6. SUBMISSION OF STATUTORY COMPLIANCES WITH EACH BILL
Contractor shall submit each bill of work carried out along with following documents.
(i) Copy of statutory compliance like labour license, wages payment register, EC
Policy, PF paid Challan with ECR, TRRN confirmation by EPFO/Bank, Bank
statement, etc… along wage certificate pertaining to respective bill period /
previous month of bill period with Annexure-H provided in Section-F.
(ii) Notarized Indemnity Bond in case of Final bill.
(iii) No claim - No arbitration certificate as per Performa (Annexure-D in Section-
F), after the final bill amount is certified by GIPCL for payment and the same is
made known to the contractor by GIPCL & accepted by the contractor.
(iv) Final material reconciliations for free supplied Cement, reinforcement steel and
structural steel with final bill.
Bill submitted without any of the above documents shall not be processed for
7. MEASUREMENT & DAILY REPORTS
The unit of measurement will be as specified in respective item of Schedule
The contractor shall maintain day to day item wise and location wise record of
housekeeping work done duly verified by various concerned authorities pertaining
to utility cleaning, school building, open air theater cleaning, block cleaning, road
cleaning, parking area cleaning, toilet cleaning, disposal of waste materials, etc…
and shall submit the same with each RA bill for verification and passing of bill
accordingly. The bill will not be processed without submission of certified work done
Contractor shall be required to furnish satisfactory job completion report to
GIPCL on daily basis. The monthly bill payment shall be released based on
the certified reports of the works.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
7.1 Contractor should maintain one computer with printer for keeping daily records
and maintain the data.
7.2 The Contractor shall be required to furnish satisfactory job completion report to
GIPCL. The submission of report should be on daily basis, the monthly bill
payment shall be released based on the certified reports of the works.
7.3 Inspection of work will be done by Engineer-in-Charge or his authorized
representative. If the work is not found satisfactory engineer in charge reserves
the right to take suitable action and shall be binding to the contractor.
Wherever any dispute regarding mode of measurement arise, the decision of the
Engineer-in-charge shall be final and binding to the contractor.
8. MOBILIZATION AND EXECUTION
a) Contractor shall mobilize the resources at site within 04 hours from the time
the intimation given by GIPCL.
b) Contractor shall provide sufficient nos. of supervisors who will be
responsible for supervision and execution of job in specified time. The
supervisors shall coordinate with the Engineer-in-charge of GIPCL for
proper execution of the job.
c) The resources required for execution of above jobs will vary from time to
time, hence contractor shall mobilize the resources accordingly.
d) Contractor shall provide accommodation for the persons deployed by him
for the work at his own cost.
9. QUANTITY OF WORK
The item wise estimated quantities/frequencies specified against various items of
Section-I of SoR (Section-E) are generally being operated in line with specified
estimated frequencies for two years and contractor should achieve these
frequencies with his best efforts and by arranging required resources & supervision.
Quantities mentioned in various items of Section-II of SoR (Section-E) are
estimated quantities which will be executed during contract period on as & when
required basis for which contractor shall arrange required nos. of manpower & other
resources separately as per instructions of Engineer-in-charge.
However, the Quantities or frequency of work may likely to be changed during the
course of contract period based on the requirement of Colony or any other
unavoidable circumstances. However, the rates shall remain firm. Contractor shall
have no any right for any compensation on ground of any addition or reduction in
scope of work / quantities within overall limits of awarded contract price. GIPCL
reserves the right to operate/increase or decrease quantities/frequencies of each
item or omit any item included in Schedule of Quantity / SoR at its discretion.
Contractor shall have no claim, whatsoever, on grounds of loss of anticipated profit
etc. on account of the same.
Contractors shall engage suitable manpower/workers of required nos. (skilled /
semi-skilled / unskilled as per scope of work) along with required tools & tackle,
consumables, materials as per work load and emergency situations throughout the
contract period to perform his contractual duties/scope up to the full satisfaction of
Engineer-in-charge / area representatives.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
In case, contract quantity/amount exhausted before completion of contract period,
GIPCL reserve the rights to increase the quantities or contract amount for
successful completion of entire contract period. Contractor shall responsible to
complete the particular job/service up to entire satisfaction of Engineer-in-charge.
The item rates remain firm & unchanged till completion of the contract and any
agreed extensions thereafter and shall not be subject to any escalation, idle charges
for labor, machinery, overhead expenses etc… for any reason whatsoever. The
quantum of work of individual item may be up to any extent depending upon
requirement. However, item rate remains unchanged. Under this contract,
contractor has to execute all work as per the Plant requirement.
10. Uniform: The contractor shall issue three pairs of stitched uniform to contract
workmen (Pant-Shirt for men and Sari-Blouse to women workers). However, brand
of fabric will be MAFATLAL. The color of the uniform shall be as indicated by
GIPCL. The uniform should be issued to workmen within one month from the date
of commencement of the Contract, otherwise penalty will be imposed.
11. Adhoc Allowance: Considering the inflation and financial conditions prevailing in
the market, to compensate the contract workers towards the benefits of adhoc
allowance, contractor shall pay specified additional adhoc allowances to the
specified workmen per month which is included in estimated cost.
12. Annual Health Check-up: As per Statutory requirement Contractor has to inform
workmen deployed at Site for Annual health check-up as per schedule prepared by
• The Contractor shall be responsible for payment of overtime wages to his workmen,
if any, in case they are required to work beyond the prescribed hours under the
applicable law as per applicable rates.
• The Contractor shall not engage workmen below the age of 18 years. Employment
of women shall be strictly according to applicable laws.
• The contractor shall conduct pre-employment medical check-up and periodic
medical check-up of his workmen employed by him as per applicable laws.
• The list is indicative in nature and not an exhaustive one. Any amendment /
alteration / Notifications or addition to the existing Law or a new statute shall
automatically and immediately become applicable.
13. GENERAL CONDITIONS OF CONTRACT
General Conditions of Contract (Section-C) and detail specification prepared by the
company will be applicable for this contract. The same is enclosed herewith.
Bidders are advised to go through the same. Where any portion of the general
conditions of contract is repugnant to or at variance with any provisions of the
special conditions of contract, then unless a different intention appears, the
provision of the special conditions of contract shall prevail to the extent of such
repugnancy of variance.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
PRICE BID FORMAT
(To be quoted online only through website:
https://tender.nprocure.com)
Description SoR Amount Above/Below Contractor's Total
(1) including GST (3) percentage to Quoted
(Rs.) (in Rs.) be filled by Amount in
(2) bidder (equal, (Rs.)
Surat Lignite Power Plant - 1,23,31,249.07 Equal
4X125 MW, BRC for Above
Housekeeping services for Below
Colony & School area at
Village: Nani Naroli for two
years of contract period
2026-28 as per SoR
(including 18% GST
NOTE: Bidders have to quote their offer in % (+, - or equal) on above total
estimated SoR value in online Price Bid only. The quoted percentage rate on
above SoR item rates (Section-D of this tender) shall be inclusive of all
approved quality materials, labour cost, equipments, supervision,
consumables, tools, tackles, profit & overheads, all taxes & duties (GST 18%
is considered on total estimated SoR value), etc…
At estimated SoR value (including GST)
______%age above the estimated SoR value (including GST)
______%age below the estimated SoR value (including GST
Note:- (1) Percentage rate offer/bid price on SoR value (including 18% GST) shall be quoted through online
(n)-Procure only. Hard copy of price bid shall not be considered/accepted.
(2) Evaluation of tender will be done on gross total quoted amount (including 18% GST).
SEAL & SIGNATURE OF TENDERER : __________________________________
NAME OF AUTHORISED PERSON : __________________________________
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
SCHEDULE OF QUANTITIES & RATES
SECTION-I REGULAR ITEMS FOR (2026-28)
Sr. Item Description Quantity Unit Rate Amount (Rs.)
1 Floor cleaning by sweeping, swabbing, wet
cloth of solution using phenyl (50 ml. Per
ltr. of water) and thereafter applying wet bulk
cloth of soap solution & then applying clean
water. Sweeping work includes collection of
all sorts of debris, cobwebs & other from all
areas and disposal of the same in the dustbin
(A) Executive Guest House :
A-(1). Kitchen and dining area (One times a
2 A-(2). Linking corridor, entrance lobby court
yards, TV Rooms, linen rooms, Common stair
cases @ 2 Nos, Paved slab areas / open
court yards etc. (Twice in a week - 52x2x2)
3 B. Executive Guest House - WING-II :
Linking corridor, entrance lobby court yards,
linen rooms, Common stair cases etc. (Twice
4 C - Executive Guest House - WING-lll :
C (1) Linking corridor, entrance lobby court
yards, linen rooms, Common stair cases etc.
(twice in a week - 52x2x2) @ 170 M2 208 Nos. 154.50
5 C (2) Cleaning of 20 nos rooms including
toilets (twice in a week - 52x2x2) @400 M2 as
per detailed specification and Instructed by
Engineer in-charge. (Toilet cleaning shall be
as describe in item no. 30) 208 Nos. 293.20
6 (D) Temple @ 25M2 (Twice in a Day -
7 (E) GIPCL ACADEMY :
E (1) Linking corridor, entrance lobby etc.
(Twice a day - 304X2X2) @ 1450 M2 1216 Nos. 900.10
8 E (2) Common stair cases (Once in a day -
9 E (3) Paved slab areas / open court yards
(Twice a week - 52x2x2) @ 500 M2. 208 Nos. 185.55
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Sr. Item Description Quantity Unit Rate Amount (Rs.)
10 F- Security cabin -gate no.-1 & D.R. etc. (Once
in day) (365X2)
11 Floor cleaning of Open terrace on roof by
sweeping includes collection of all sorts of debris,
cob webs, all dirt and dust, removing and
disposal of the same outside premises etc (once
in quarter per year - 4x2)
(1) Executive Guest House @300M2 8 Nos. 102.50
12 (2) Executive Guest House wing -II @100M2
13 (3) Executive Guest House wing -III @100M2
14 (4) GIPCL Academy @ 2100 SM
15 Floor cleaning by sweeping, swabbing, wet cloth
of solution using phenyl (50 ml. Per 25 ltr. of
water) and thereafter applying wet bulk cloth of
soap solution & then applying clean water.
Sweeping work includes collection of all sorts of
debris, cobwebs & other dirt from all areas of
rooms, stage platform area, walkways in front of
seats, sweeping & cleaning all seating steps and
outside corridor/waiting passage including
disposal of the same in the dustbins including
sweeping, cleaning and washing of the toilet
blocks, bathrooms including cleaning of walls,
top ceilings (only stage area), doors, removal of
dust from windows, cleaning of fans (only room
area) etc. of OPEN AIR THEATER as and when
required and as per instruction of engineer-in-
charge. 100 Nos. 789.40
16 Toilet Blocks:-Sweeping, cleaning and washing
of the toilet blocks, bathrooms, wash basins
sinks etc. in said premises once a week
complete including using necessary cleaning
materials like hard brooms, soft brooms,
brushes, mops, acids, fenayl & cleaning powder
(1). Ex. Guest House (3 Toilet blocks)
(i) 2 Urinals + 1 WC ---- 1 No.
(ii) 1 Urinal + 1 WC ---- 1 No.
(iii) 1 Urinal + 1 WC + 1 Bathroom --- 1 No.
Total : 3 Nos.(2x52) 104 Nos. 387.50
17 (2). VIP Guest House (3 Toilet blocks)
(i) 1 Urinal + 1 WC + 2 Wash basing ---- 1 No.
(ii) 1 Urinal + 1 WC + 3 Wash basing ---- 1 No.
(iii) 1 WC + Bathroom --- 1 No.
Total : 3 Nos.(2x52) 104 Nos. 387.50
18 (3). Town Centre (Including Swimming
pool)(4 Toilet blocks)
(i) 2 Urinals + 3 WC + 2 Wash basin --- 1 No.
(ii) WC + 3 Wash basin – 1 No (iii)
Urinal + 2 WC + 2 Wash basin – 1 No.
(iv) 2WC + 2 Bathrooms- 1 No
Total: 4 Nos.(2x52) 104 Nos. 463.35
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Sr. Item Description Quantity Unit Rate Amount (Rs.)
19 (4). GIPCL ACADEMY (5 Toilet blocks)
(i) PRINCIPAL Office-1 WC + 1 Wash basing -
(ii) STAFF 2WC +2 Wash basing – 1 No.
(iii) KIDS 2 WC + 1 Wash trough – 1 No.
(iv) G.F TOILET 06Urinal +13 WC +02 Wash
basing +04 WASHTROUGH.
(v) F.F TOILET 12Urinal + 14 WC + 4 Wash
basing +04WASHTROUGH
20 (5). GIPCL ACADEMY (New Wing Area) (5
(i) 04 WC + 1 Wash basing --- 1 No.
(ii) STAFF 1WC + 2 Wash basing – 2 No.
(iii) KIDS 4 WC + 6 Wash truff – 1 No.
(iv) G.F TOILET 08 Urinal + 05 WC + 04 Wash
basing +01WASHTRUFF.
(v) F.F TOILET 15Urinal + 6 WC + 8 Wash
21 Cleaning the inspection chamber, valve chamber
by removing silt, mud, garbage etc. complete, 585 Nos. 85.10
22 Cleaning the manhole by removing & disposing
the mud, slit, sewage etc. complete for depth up
23 Removing of chocking from gulley trap including
cleaning of grating including connecting pipes
from N.T. and removing & re-fixing the covers
etc. complete 125 Nos. 185.55
24 Cleaning & washing the water coolers at various
public building / office with cleaning powder like
VIM powder by using brushes & rinsing of the
water container as directed.(onece in week
25 Cleaning & washing the underground sumps
within specified time period with required
necessary tools, plants, ladder, ropes, cleaning
powder or bleaching powder including
dewatering the left our muddy & sandy water at
the bottoms taking out the mud / sand
Underground sump of colony having capacity of
2.5 lack liter approx. 4 Nos. 913.40
26 Cleaning & washing of overhead tanks within
specified time period with required necessary
tools, plants, wire ladders, wire brushes, shelves,
buckets, rope & cleaning powder or bleaching
powder etc. including removing & disposing mud
& send & disposing the same at place as
(a) Overhead Tank of colony raw water having
capacity of 1.00 lac liter. 4 Nos. 2236.30
27 (b) Overhead Tank of D10 Block, GIPCL
ACADEMY,VIP, EGH Wing-I, WING-II & lll
having capacity of up to 10000 liter. (9x8 No).
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Sr. Item Description Quantity Unit Rate Amount (Rs.)
28 (c) Overhead Tank of colony recycled water
having capacity of 1.00 lac. liter. 3 Nos. 2189.58
29 Cleaning & washing the O.H. Tanks of PVC/RCC
at various quarters as well as public buildings.
Capacity up to 1500 liters including cleaning of
open terrace surrounding with required
necessary tools, plants, wire ladders, wire
brushes, shelves, buckets, rope & cleaning
powder or bleaching powder etc. including
removing & disposing mud & sand & disposing
the same at place as directed.
30 Sweeping & cleaning of pathways inside colony
quarter blocks with necessary hard brooms,
wire brushes, mops & if required with fresh
water. The measurement shall be paid in nos of
block work done.(once in a week)
(a). Block - A Type - 2 Block
(b). Block - B Type -11 Block
(c) Block - C Type -7 Block
(d) Block - D Type -8 Block
(e) D-D10 Block-01 Block
(Block 29x52x2) 3016 Nos. 98.15
31 As per above for
(a) Block E Type-24 Block & F Type-04 Block
(Block 28x52x2) 2912 Nos. 44.40
32 Collecting & lifting of garbage from all the
quarters (500no) & public buildings of colony &
shifting using hand cart or tractor at designated
location in colony, segregating recycling
materials (plastic, tin, glass, paper) and bio-
degraded materials etc. complete as directed by
Engineer in charge. 730 Nos. 2906.20
33 Cleaning of entire Garbage yard by loading,
shifting and unloading of all the garbage form the
Garbage yard to designated location within lead
of 07 to 10 kms (one side) and maintain the dump
yard clean at every monthly. The scope of work
includes shifting of bio-degraded materials in
plant & disposal of non-biodegraded materials at
designated locations within 5-10 km area by
arranging necessary equipment like JCB,
Trucks/Tractor, Covering tapolin sheet etc.
complete as directed by Engineer-in-charge.
(In case if contractor arrange resources & clean
the entire Garbage yard and removed all
collected Garbage after one or two months’ time
instead of monthly, it will be considered as one
cleaning only) 24 Nos. 15890.00
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Sr. Item Description Quantity Unit Rate Amount (Rs.)
34 Cleaning of wall, top ceilings, doors, removal
of dust of dust from windows, cleaning of fans,
terraces, cob webs, etc. of :
(1) GET Hostel 96 Nos. 410.10
(2) EGH WING II 96 Nos. 410.10
(3) EGH WING lll 96 Nos. 410.10
(4) GIPCL ACEADMY 96 Nos. 410.10
(5) Temple 96 Nos. 205.00
39 Cleaning of common stair cases of ground
plus one type clusters, once in a week for
sweeping and moping, provided in all A, B, C,
D Type quarters including landings and
collecting the dust from there and disposing
the same to garbage bins including removing
dust from wall & ceiling (52x2x29x4). 12064 Nos. 20.50
40 Cleaning bitumen road & side pathways
(Twice a week) including grass cutting of area
between pathways & drain starting from
houses to main road for E&F type of quarters
by hand brooms including all cleaning of
waste, trees leaves etc. & disposal of the
same to dustbins as per instruction of
engineer in-charge '@ 2600 M2. 540866 SM 0.95
41 Cleaning of all bitumen road, side pathways &
area between pathways & drain including
cleaning of waste tree leaves etc. with
necessary hard brooms wire brushes, mops &
if required with fresh water & disposal of the
same to outside colony premises as per
instruction of engineer-in-charge.
(a) Main roads from Colony entrance to F2
blocks via. Town center, D2 junction- Once in
(b) All remaining roads-Once in a month and
(c) Car Parking Area etc.-Once in a month 700000 SM 0.95
42 Removal of dead birds / snakes etc. if found in
township area and disposal of the same
outside township area as per instruction of
engineer in charge 28 Nos. 281.90
43 Removal of dead cattle/dogs/cats etc. if found
in township area and disposal of the same
outside the township area as per instruction of
engineer in charge.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Sr. Item Description Quantity Unit Rate Amount (Rs.)
44 Substation, floor, walls ceiling, ventilators,
doors, windows & cable trenches & open
terrace @ 125 M2 including keeping the area
clean around the sub-station in 5 meter of
area including removing grass from all
surrounding areas:- (Once in month).
i) Sub-station-I (2 x 12) 24 Nos. 174.30
45 ii) Substation-II (2 x 12 ) 24 Nos. 174.30
46 Cleaning of SSB areas (floor, walls &
ceilings) housed at back side of quarter block
in between two kitchen yards and below
garbage chute by sweeping (which includes
collection of all sorts of debris, cobwebs &
other dirt from all around the electric panels
including cleaning of cable trenches provide
below these all complete (once in Month) as
directed by engineer in-charge.
(i) Provided in quarters (2 x 12 ) 24 Nos. 61.67
47 (ii)Provided in town centre… 2 nos, Cricket
Ground Room, Temple Panel Room, GET,
Wing-ii & Wing-iii panel Room etc..(2 x 24 ) 24 Nos. 79.00
48 Cleaning of SSB rooms provided inside
colony by sweeping (which includes
collection of all sorts of debris, cobwebs and
other dirt) inside the room & cable trenches
including cleaning of floor, walls, ceilings,
ventilator, rolling shutter & 3 M radius area
surrounding the SSB rooms all complete as
directed by engineer- in-charge.
(i) Behind E4 & E5. (2 x 12) 24 Nos. 62.00
49 (ii) Behind E13 (2 x 12)
50 (iii) Behind E18 & 19 (2 x 12)
51 3. Sweeping, cleaning and washing of the
vacant quarters including toilet blocks,
bathrooms, wash basin sink etc. complete
before or after occupation of the quarter,
including using necessary cleaning
materials like hard brooms, soft brooms,
brushes, mops & cleaning powder etc.
(a) .A-Type (Carpet area – 500 Sq. Ft.) 3 Nos. 260.00
52 (b). B-Type (Carpet area – 700 Sq. Ft.) 40 Nos. 290.00
53 (c). C-Type (Carpet area – 800 Sq. Ft.) 155 Nos. 310.00
54 (d). D-Type (Carpet area – 1000 Sq. Ft.) 155 Nos. 385.00
55 (e). E-Type (Carpet area – 1300 Sq. Ft.) 5 Nos. 570.00
56 (f). F-Type (Carpet area – 1600 Sq. Ft.) 2 Nos. 670.00
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Sr. Item Description Quantity Unit Rate Amount (Rs.)
57 Disposal of all collected waste materials,
dust & other unwanted materials in various
area of colony during regular cleaning (as
per above scope of work & frequency) of
Roads, Pathways, Stair cases in Blocks,
approach of E & F Type, Public building,
Guest House etc.. once in a week by
arranging tractor & labour and also incluiding
loading, unloading & disposal of the all waste
materials out side the colony premises within
03 KM lead (one side) as directed by
engineer in-charge (4x24)
(In case if contractor arrange resources &
clean the all collected waste & unwanted
materials from various area of colony
fortnightly/ montly instead of weekly, it will be
considered as one cleaning only) 96 Nos. 3075.30
58 To operate and maintain the swimming pool
by supplying one cleaner & one operator
cum trainer on daily basis.
Following items to be carried out daily.
(1) Cleaning of swimming pool on daily basis
using suction sweeper attached with pump.
(2) Filtration of entire quality of water and
chlorination of water daily.
(3) Blow-down of back wash water from filter
& make of water for swimming pool.
Estimated SoR Value without GST >>>
Total Estimated SoR Value with GST >>>
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
SECTION-II HOUSEKEEPING SERVICES OF AS & WHEN REQUIRED BASIS
Sr. Description of work Quantity Unit Rate Amount
1 Supply of temporary unskilled manpower
(per day 08 hour duty) on as & when
required basis with required tools & tackles
and safety gears for miscellaneous
jobs/works such as cleaning of area,
material lifting & shifting works, etc… as
directed & required by Engineer-in-charge.
Contractor shall engage at least 50% male
labour of total labour requirement per day,
except unavoidable circumstances agreed
by Engineer-in-charge. 575.00 Man-day 494.40
2 Cleaning of storm water drains quarterly
(four) cleaning in a year in township covered
and open, including removal of tree leaves,
foreign materials dust, settle soil, stagnation
due to various reasons, removal of chocking
of water and disposal of all such debris as
specified by GIPCL. The drains are required
to be kept clean to ensure free flowing
throughout the year) Total length '@
mtr. 20800.00 Meter 4.35
3 Cleaning of area including Grass cutting
within 5 mtr. around the quarters (non paved
area outside of quarters) and triangular
portion between roads once in a three
months including cutting of grass & stage
one location of every block as directed by
engineer in-charge. Area @ 24000 m2
8.00 cleaning 49439.50
4 Cleaning of areas including cutting of Grass
including disposing of grass outside the
colony premises as directed by engineer in
charge. A) Children park
and LPG Godown @ 450 m2 8.00 cleaning 1112.39
5 Disposal of all unwanted vegetation (all
collected vegetations & cut grass after
operating above item no.3 once in a three
months) out side the colony premises within
lead of 03 KM (one side) by arranging
required resources like tractor with trolley
and necessary labours and also including
loading, unloading & shifting from various
area of colony etc. complete as directed by
engineer in-charge 8.00 Nos 31775.80
Estimated SoR Value without GST >>>
Total Estimated SoR Value with GST >>>
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Section-I Section-II (As Total amount
Section-I Section-II (As Total amount
(Regular & When (Rs.)
activities) Required
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
LIST OF ANNEXURES & FORMS
CHECKLIST FOR PASSING THE BILLS
For the month of :
1) Work Order / P.O. No. & :
2) Nature of work :
3) Duration of Work Order : From to
4) Maxi. No. of manpower per day : M F Total
deployed in the month.
5) Details of Labour License : Valid up to for
6) Details of E.C Policy : Valid up to for
7) Documents attached for verification : Wage & Attendance Sheets.
for the previous month. Yes/No
P.F Challan Yes/No
8) Documents attached for verification : Bonus Payment Register
(in case of Final Bill) Yes/No
: Leave wage register Yes/No
9) Security Deposit / Retention Money : Yes / No if yes, Rs.
Date : Signature of Contractor
with official stamp
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
PROFORMA FOR CONTRACT SECURITY-CUM-PERFORMANCE GUARANTEE
BY SELLER / CONTRACTOR
(To be executed on non-judicial stamped paper of approximate value)
1. WHEREAS Gujarat Industries Power Company Limited having its office at
PO: Ranoli, Dist. Vadodara – 391 350, Gujarat State, India (hereinafter
referred to as “The Company/Owner” which expressions shall unless
repugnant to the subject or context includes its legal representatives,
successors and assigns) has entered into a contract with M/s.
……………………………….. ………………………….(hereinafter referred to
as “Contractor(s)/ Seller(s)” which expression shall unless repugnant to the
subject or context includes their legal representatives, successors and
assigns ) for …………………………….on the terms and conditions as set out
inter alia, in the Company’s contract No./ work order
No.……………………………………………..date …………and various
documents forming part thereof hereinafter referred to as the “said contract”
which expression include all amendments, modifications and/ or variations
thereto and where as the Contractor(s)/ Seller(s) has agreed for due
execution of the entire contract and guarantees its performance including any
parts executed through any other agencies/ subcontractors
AND WHEREAS one of the conditions of the “said contract” is that
“contractor(s)/seller(s) shall furnish to the owner a Bank Guarantee from a
bank for….% (……….percent) of the total value of the “said contract” against
due and faithful performance of the “said contract” including performance
guarantee obligations of the contractor(s)/seller(s) for execution/ supplies
made under the “said contract.”
2. We …………………………….Bank having its branch office at ……….……..do
hereby agree and undertake to pay the amount due and payable under this
guarantee without any demur merely on a demand from the Company stating
that in the opinion of the Company, which is final & binding, the amount
claimed is due by reason of default made by the Contractor(s)/ Seller(s) in
performing any of the terms & conditions of the said Contract including defect
liability obligations, in fulfilling the performance guarantee obligation or loss
or damage caused to or would be caused to or suffered by the Company by
reason of any breach by the said Contractor (s)/ Seller(s) of any of the terms
& conditions of the contract. Any such demand made on the Bank by the
owner shall be conclusive as regards the amount due and payable by the
Bank under this guarantee. However our liability under this guarantee shall
be restricted to Rs.-------------------------(Rs ……………………only)
3. We undertake to pay to the Company any money so demanded not
withstanding any dispute or disputes raised by the contractor(s)/ Seller(s) in
any suit or proceeding pending before any office, court or tribunal relating
thereto our liability under this present guarantee being absolute and
unequivocal. The payment so made by us under this bond shall be a valid
discharge of our liability for payment there under. Our liability to pay is not
dependent or conditional on the owner proceeding against the Contractor(s)/
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
4. The guarantee herein contained shall not be determined or affected or
suspended by the liquidation or winding up, dissolution or change of
constitution or insolvency of the said Contractor(s)/ Seller(s) but shall in all
respect and for all purposes be binding and operative until payment of all
money due or liabilities under the said contract(s)/ Order(s) are fulfilled.
5. This guarantee will remain valid up ____________________ days or
______________ whichever is earlier. The Bank undertakes not to revoke
this guarantee during its currency without previous consent of the
OWNER/PURCHASER and further agrees that if this guarantee is extended
for a period as mutually agreed between contractor & owner/purchaser, the
guarantee shall be valid for a period so extended provided that a written
request for such extension is received before the expiry of validity of
6. We ……………Bank further agree with the Company that the company shall
have the fullest liberty without our consent and without affecting in any
manner our obligations hereunder to vary any of the terms and conditions of
the said Contract(s)/ Order(s) or to extend the time of performance by the
said Contractor(s) Seller(s) from time to time or to postpone for any time or
from time to time any of the powers exercisable by the Company against the
said Contractor(s)/ Seller(s) and to forbear or enforce any of the terms and
conditions relating to the said Contract(s)/ Order(s) and we shall not be
relieved from our liability by reason of any such variation, or extension being
granted to the said Contractor (s) / Seller(s) or for any forbearance, act or
omission on the part of the Company or any indulgence by the Company to
the said Contractor(s)/ Seller(s) or by any such matter or thing whatsoever
which under the law relating to sureties would, but for this provision, have
affect of so relieving us.
7. Notwithstanding anything contained herein before, our liability shall not
exceed Rs…………….(Rupees…………only) and shall remain in force
till..……..Unless a demand or claim under this Guarantee is made on us
within three months from the date of expiry we shall be discharged from all
the liabilities under this guarantee.
Corporate Seal of the Bank
By its constitutional Attorney
Signature of duly Authorized person
On behalf of the Bank
With Seal & Signature code
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
PROFORMA FOR BANK GUARANTEE FOR EARNEST MONEY DEPOSIT
(To be executed on non-judicial stamped paper of approximate value)
1. WHEREAS M/s.Gujarat Industries Power Company Limited having its Corporate
Office at PO: Ranoli, Dist. Vadodara – 391 350, Gujarat State, India (hereinafter
called “The Company Owner” which expression shall unless repugnant to the
subject or context includes its legal representatives, successors and assigns) has
issued tender paper vide its Tender No…………………………for -----------------------
- (hereinafter called “the said tender”)to M/s.……………………………(hereinafter
called the said Tenderer(s)” which expression shall unless repugnant to the subject
or context includes their legal representatives, successors and assigns and as per
terms and conditions of the said tender, the tenderer shall submit a Bank guarantee
for Rs.………. (Rupees……………..only) towards earnest money in lieu of cash.
2. We ……………………………..Bank having its branch office at
……… do hereby undertake to pay the amount due and payable under this
guarantee without any demur, merely on a demand from the Company stating that
in the opinion of the company which is final and binding, the amount claimed is due
because of any withdrawal of the tender or any material alteration to the tender after
the opening of the tender by way of any loss or damage caused to or would be
caused or suffered by the Company by reason of any breach by the said tenderer(s)
of any of the terms and conditions contained in the said tender or failure to accept
the letter of Intent Agreement or that the amount covered under this Guarantee is
forfeited. Any such demand made on the Bank by the owner shall be conclusive as
regards the amount due and payable by the Bank under this guarantee, However,
our liability under this guarantee shall be restricted to an amount not exceeding
Rs………………..(Rupees………………..only).
3. We undertake to pay to the Company any money so demanded not withstanding
any dispute or disputes raised by the tenderer (s) in any suit or proceeding pending
before any office, court or tribunal relating thereto our liability under this present
guarantee being absolute and unequivocal. The payment so made by us under this
bond shall be a valid discharge of our liability for payment there under. Our liability
to pay is not dependent or conditional on the owner proceeding against the
4. The guarantee herein contained shall not be determined or affected or suspended
by the liquidation or winding up, dissolution or change of constitution or insolvency
of the said tenderer(s) but shall in all respect and for all purposes be binding and
operative until payment of all money due or liabilities under the said contract(s)/
Order(s) are fulfilled.
5. We ……………..Bank Ltd. further agree that the guarantee herein contained shall
remain in full force and effect during the period that would be taken for the
finalization of the said tender and that it shall continue to be enforceable till the said
tender is finally decided and order placed on the successful tenderer(s) and or till
all the dues of the company under or by virtue of the said tender have been fully
paid and its claims satisfied or discharged or till a duly authorized officer of the
company certifies that the terms and conditions of the said tender have been fully
and properly carried out by the said tenderer (s) and accordingly discharges the
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
6. That the Owner Company will have full liberty without reference to us and without
affecting this guarantee to postpone for any time or from time to time the exercise
of any of the power of the owner under the tender.
7. Notwithstanding anything contained herein before, our liability shall not exceed
Rs…………………. (Rupees…………………………only) and shall remain in force
till…………….. (Date to be filled up shall be 180 days from the date of submission
Corporate Seal of the Bank
By its constitutional Attorney
Signature of duly Authorized person
On behalf of the Bank
With Seal & Signature code
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
PROFORMA CERTIFICATE
(No claim, No arbitration)
Chief General Manager (Thermal)
Gujarat Industries Power Company Limited,
Surat Lignite Power Plant,
Village: Nani Naroli, Ta. Mangrol,
Dist. Surat – 394112 (Gujarat).
We hereby confirm with free consent as under:-
1. The measurements certified in final bill are full and final. We accept all the certified
measurements and no claim related to the measurement is left.
2. The payment certified in that or above referred LoI / contract is full and final. We accept
this, and no claim related to payment is left.
3. The rates of the LoI / contract and its amendments are firm till completion of contract
and extension period. We shall not claim any escalation against these rates.
4. Along with the contract referred, the ARBITRATION CLAUSE also perishes i.e. we will
not resort to arbitration.
5. No extra items are left to be settled.
6. We do not have any claims against any item related to the LoI than those items certified
7. We are accepting the recoveries or hold amount from our bills, if any, made by GIPCL
against non compliance or as decided by GIPCL within terms & conditions of contract.
8. We have paid royalties, taxes for all the materials procured by us, for carrying out the
works for above LoI and we indemnify GIPCL from any liability arising thereof.
9. In case of any disputes arising in future related to payment of royalties, all liabilities of
settlement of dispute and its payment if any, will be borne by us.
10. We have paid wages to all the workmen who were deployed by us for carrying out
above referred work as per prevailing Minimum wages act. We have also fulfilled all
requirements of the P.F. Act. We have maintained all records necessary as per the
statutory requirements. We hereby indemnify GIPCL from any disputes arising in future
related to payment of labours, Provident Fund, etc.and confirm that all liabilities of
settlements of disputes and their payment is our responsibility.
The above confirmation will come into effect as soon as payment from final bill after due
recoveries will be received by us.
Signature, Stamp and date.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
List of qualifying staff to be submitted with physical documents
Sr. No. Name of Supervisor Qualification Experience
Contractor / Authorized Representative’s
Signature, Company’s / Organization’s Seal & Date
Note: Form-A of Bid without price shall be submitted with Part-I
List of Tools & Tackles to be submitted with physical documents
Sr. No. Description Nos. Status
Contractor / Authorized Representative’s
Signature, Company’s / Organization’s Seal & Date
Note: Form-B of Bid without price shall be submitted with Part-I
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Schedule of Deviation from Technical Specification and Commercial Terms
All the deviations from the terms & conditions of contract shall be filled by BIDDER
clause by clause in this schedule.
Sr. No SECTION CLAUSE AS PER DEVIATION
The bidder here by certifies that the above mentioned are the only deviations from
OWNER’s Tender enquiry. The bidder further confirms that in the events any other data
and information presented in the BIDDER’s proposal and accompanying documents are
at variance with specific requirements laid out in the OWNER’s Tender Document, then
the latter shall govern and will be binding on the BIDDER for quoted price.
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
Declaration Cum Undertaking for Safety Laws and Regulations Compliance
(To be submitted on Company’s Letter Head)
I ______________________ on behalf of ………Name of Party/Company………..hereby confirm,
agree and undertake that all the Statutory and Safety Laws and Regulations of the applicable
Authority/ies shall be strictly followed for all types of works at the site during the period of the
Contract, if awarded to me.
Signed and Stamped by the
Authorized Signatory
Declaration for Contractual Disputes/ Litigations
(To be submitted on Company’s Letter Head)
Please Tick (√) whichever is correct option
______________________ on behalf of ………Name of Party/Company………..hereby
confirm that I /We have
a. Not invoked legal recourse e.g. litigation against any Govt, of Gujarat Undertakings /
Depts. / Authorities and Govt. of Gujarat supported companies / undertakings /
organizations for the last three (03) years. There are no ongoing/pending legal matter(s)
with any of the Govt. of Gujarat Undertakings / GoG supported Companies, including
b. Invoked legal recourse e.g. litigation against any Govt, of Gujarat Undertakings /
Depts. / Authorities and Govt. of Gujarat supported companies / undertakings /
organizations for the last three( 03) years.
If “b” is applicable, please submit the details for the same.
The above is true, as on date, to the best of my knowledge. Any breach/ false statement
in this regard shall amount to disqualification of the Bid being submitted herein.
Signed and Stamped by the
Authorized Signatory
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
PARTICULARS OF THE BIDDER
Sr. Particulars Please provide
No. information here.
1. Name of Bidder
2. a. Registered Office Address:
b. Address for Correspondence:
3. Contact Details:
Contact Person Name
Telephone No. :
Year of establishment
COMPANY SEAL SIGNATURE …………………
DESIGNATION ……………..
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
10.0 ANNEXURE-H
CERTIFICATE OF COMPLIANCE BY CONTRACTOR
(To be submitted with each monthly bill on letter head along with labour compliance
of.........................to .......................... at Gujarat Industries Power Company Limited – Surat
Lignite Power Plant, Nani Naroli. I undertake to be bound by all the provisions of the
Contract Labour (Regulation & Abolition) Act 1970 and the Contract Labour (Regulation &
Abolition) Rules 1972, The Employees’ Provident Funds and Miscellaneous Provisions Act
1952, Minimum Wages Act 1948, Payment of Wages Act 1936 and Payment of Bonus Act
1965 and all other applicable labour laws in so far as the provisions are applicable to me in
respect of the employment of contract labour by me for the month of ................................
Authorized Signature with Stamp
Place: Nani Naroli
E-Tender for “Surat Lignite Power Plant - 4X125 MW, Unit # I to IV: Biennial Rate Contract for Housekeeping
services for Colony & School area at Village: Nani Naroli for two years of contract period”. Bid No.:
SLPP/Civil/colony/Housekeeping/2026-28.
11.0 ANNEXURE-I
PROCEDURE FOR MAKING ONLINE PAYMENT OF EMD/SD/TENDER FEE
1. For making online payment, first go to the website: www.gipcl.com
2. Then, click on the caption/link as can see like:
“Click here for Making Online Payment of EMD/SD, Advance for Ash, Advance for
(The link is visible as horizontal highlighted in “orange” shade below Tenders - News &
Update Section).
3. After clicking the link the new page will open. On this page, No need to enter User Name
and Password. Directly click on “Payment Form” given below the sign in option.
4. After clicking the “Payment Form”, the vendor has to enter the details asked which will
be self-explanatory. It is desired that all the information may be filled correctly so that
the payment made can be tracked.
If the some required fields are not known/available, vendor may write “Not Available” and
then proceed. E.g. some information like Party code is not available to vendor or GST No.
not available with vendor.
Optional Note: Although mentioned as above can be proceeded with “Not available”, It will
be appreciated that regular vendors may obtain the party code from Materials Dept. or
Concerned Person, so that the vendor can be identified. The same party code may be used
for future transactions also.
After entering the details, click on SUBMIT Button.
5. The vendor/Party will be redirected to Payment Gateway.
By selecting the desired payment mode, payment can be made:
6. After making the payment, the receipt will be generated which has to be shared with
Concerned Person of GIPCL.
Important Note: Please note that for making online payment through the above gateway,
the charges* as below will be applicable, which has to be borne by Vendor/Party making
Payment Mode Charges
Net Banking Rs.9 + GST
Credit Card 0.75% + GST
International Card 3.00% + GST
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
BG for EMD.pdf.pdf
Tender document Housekeeping Colony .pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .