ENGINEER (PROJECTS)
KEL MAMALA KOCHI
GENERAL-KEL Kundara-Construction of General Purpose Alternator Plant by Renovating of Old Foundry Building - Flooring Works at KEL, Kundara,Kollam (Dist.)
2025_KEL_770911_1
KRO/BDC/2000/2025
Open Tender
Civil Works - Buildings
Item Rate
KEL MAMALA
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,950
₹50,000
Yes
2 Jul 2025
21 Jun 2025
1 Jul 2025
21 Jun 2025
30 Jun 2025
21 Jun 2025
21 Jun 2025 - 30 Jun 2025
Amount
CIVIL WORKS
2.6.1 Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
OD63448/2025-2026 4.1.A.1. Granular Sub-base with Well Graded Material (Table 400.1) (A) By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (i) For Grading I Material
4.1.6 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)
5.22A.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
5.33.1.1 Providing and laying in position machine batched and machine mixed design mix M25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is payable or recoverable separately. All work upto plinth levelConcrete of M25 grade with minimum cement content of 330 kg /cum
OD53213/2025-2026 Providing vaccum dewatered flooring on a concrete surface including laying of MS channels to the desired thickness as, vibrating the concrete with screed vibrator, Vaccum Dewatering Pump with mat for dewatering the concrete with concrete pumps and finishing the top surface with power floater and power trowel including supply and spreading of non metalic hardner @ 5Kg/sqm
OD63382/2025-2026 Add for plaster drip course / groove in plastered surface or moulding to RCC projections. Cutting the groove 5mm width and 15mm depth, cleaning the groove and filling with polysulphide sealant
EXCLUSIVE OF GST
Note :1 All materials, Items, Equipment shall be best branded items with IS and approved by client/KEL
2:Rate should be inclusive of Insurance,Transportation, delivery and installation cost for all items
3.Rate should be Exclusive of GST.
4.Work should be executed as per DSR/PWD specification and direction of Engineer at site.
5.CEMENT: Make use Malabar cement only as per Govt. direction and in case of non availabilty of Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference.
6.RCC: (Assessment of strength of concrete by Cube testing at Approved Govt labs as per IS) Cement make: Use Malabar cement only as per Govt. direction and in case of non availabilty of Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference.
7.STEEL REINFORCEMENT: Make: Tata,Vaishak, SAIL, JSW or eq primary make in the order of preference
8.CENTERING & SHUTTERING: (Centering and shuttering for different category of work may be considered separately.)
9.GRANULAR SUB BASE: Quantity by level calculation & reporting to CTE as per norms
CUBIX INFRASTRUCTURES (BID ID -2235087)
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .