| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹94.2 LAccepted-AOC | L1 | Accepted-AOC L1 party | |
| 2 | L2₹99.5 L+₹5.3 L (5.68%)Rejected-Finance | L2 | Rejected-Finance L2 PARTY | |
| 3 | L3₹1.0 Cr+₹8.8 L (9.36%)Rejected-Finance | L3 | Rejected-Finance L3 PARTY | |
| 4 | L4₹1.0 Cr+₹9.5 L (10.1%)Rejected-Finance | L4 | Rejected-Finance L4 PARTY |
| Sl No | Description | Qty | Unit | Santhi constructions L4 | BIOHOMES PROJECTS PRIVATE LIMITED L1 | PRASAD PILLAI L2 | SUBERUKOYA.S L3 |
|---|---|---|---|---|---|---|---|
| 1.00Area Clearing | |||||||
| 1.01 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | 570 | sqm | 17 ₹9,690 Lowest | 18 ₹10,260 | 18 ₹10,260 | 19.65 ₹11,197.76 |
| 2.00Filling with Contractors earth | |||||||
| 2.01 | Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge | 1,609 | cum | 890 ₹14,32,010 | 729 ₹11,72,961 Lowest | 900 ₹14,48,100 | 787.74 ₹12,67,475.59 |
| 3.00Compaction with Vibratory roller | |||||||
| 3.01 | Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and rerolling the sub grade and disposal of surplus earth with lead upto 50 metres. | 475 | sqm | 300 ₹1,42,500 | 226 ₹1,07,350 | 200 ₹95,000 Lowest | 244.48 ₹1,16,127.81 |
| 4.00Demolition of PCC | |||||||
| 4.01 | Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | 20 | cum | 2,000 ₹40,000 | 1,554 ₹31,080 | 1,500 ₹30,000 Lowest | 1,678.78 ₹33,575.69 |
| 5.00Demolition of RCC | |||||||
| 5.01 | Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. | 15 | cum | 3,500 ₹52,500 Lowest | 3,671 ₹55,065 | 3,500 ₹52,500 Lowest | 3,965.64 ₹59,484.62 |
Tender Value
₹95.3 L
EMD Value
₹50,000
Closing Date
5 Jun 2026, 3:00 pmClosed
HOU(TP)
KMML, CHAVARA
Site clearing, filling of drainage,demolition of PCC/RCC,area levelling and compaction,PCC/RCC works,RRM foundation, plastering and painting
2026_KMML_851423_1
EAF/CIV/0034/2026-2027 Dtd27/04/2026
Open Tender
Civil Works - Others
Item Rate
120 days
KMML, CHAVARA
Refer tender documents.
6 documents required · 6 mandatory
₹2,950
₹50,000
12 Oct 2026
23 May 2026
6 Jun 2026
23 May 2026
5 Jun 2026
23 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Area Clearing | |||||
| 1.01 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | - | sqm | - | - |
| 2Filling with Contractors earth | |||||
| 2.01 | Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge | - | cum | - | - |
| 3Compaction with Vibratory roller | |||||
| 3.01 | Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and rerolling the sub grade and disposal of surplus earth with lead upto 50 metres. | - | sqm | - | - |
| 4Demolition of PCC | |||||
| 4.01 | Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | - | cum | - | - |
| 5Demolition of RCC | |||||
| 5.01 | Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. | - | cum | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.28 MB
TD.pdf
Tender Documents • 7.94 MB
make.pdf
Other Document • 0.25 MB
BOQ_1438623.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .