Loading…
Loading…
Tender Value
₹1.6 Cr
EMD Value
₹10.2 L
Closing Date
29 Sept 2026, 12:00 pm6d left
Superintending Engineer
Superintending Engineer, Badaun/Pilibhit Circle, PWD Bareilly
Construction of 40 Capacity Hostel/Barrack and 01 Investigation Room in Thana Sehramau Uttari Distt-Pilibhit
2026_CEBLY_1187772_2
4308/76C(A)(ET)/08/2026-27 Date 17.07.2026
Open Tender
Civil Works - Buildings
Fixed-rate
180 days
Pilibhit
Construction of 40 Capacity Hostel/Barrack and 01 Investigation Room in Thana Sehramau Uttari Distt-Pilibhit
3 documents required · 3 mandatory
₹2,714
₹10.2 L
Yes
Bareilly
19 Sept 2026
19 Sept 2026
29 Sept 2026
19 Sept 2026
29 Sept 2026
19 Sept 2026
19 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge. All kinds of soil 2.6.1 (Barrack, Vivechna Room, Interlocking, Septik Tank) | 503.67 | Cum. | 122 | ₹61,447.74 |
| - | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:4:8 (1 Cement 4 coarse sand (zone-III): 8 graded stone aggregate 40 mm (nominal size) 4.1.8 (Barrack, Vivechna Room, Interlocking, Septik Tank) | 57 | Cum. | 4,712 | ₹2,68,584 |
| - | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. 2.27 (Barrack, Vivechna Room) | 30.31 | Cum. | 1,469 | ₹44,525.39 |
| - | Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration 2.35.3.1(Barrack, Vivechna Room) | 202.6 | Sqm. | 214 | ₹43,356.4 |
| - | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 5.1.2 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) Footing foundation 5.1.2(Barrack, Vivechna Room) | 50.85 | Cum. | 6,257 | ₹3,18,168.45 |
| - | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 5.1.2 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) Plinth Beam 5.1.2(Barrack, Vivechna Room) | 8.7 | Cum. | 6,257 | ₹54,435.9 |
| - | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources(Column) 5.2.2(Barrack, Vivechna Room) | 36.82 | Cum. | 7,507 | ₹2,76,407.74 |
| - | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). Lintel 5.3(Barrack, Vivechna Room) | 10.89 | Cum. | 7,958 | ₹86,662.62 |
| - | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).Projection 5.3(Barrack, Vivechna Room) | 12.47 | Cum. | 7,958 | ₹99,236.26 |
| - | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). Beam (Barrack, Vivechna Room) | 60.56 | Cum. | 7,958 | ₹4,81,936.48 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.47 MB
BOQ_2236878.xls
BOQ • 0.45 MB
T2.pdf
Tender Documents • 1.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .