Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹24.2 LAccepted-AOC VILLAGE P O DHALIARA TEHSIL DEHRA DISTT KANGRA H P | MANDI | HIMACHAL PRADESH | 175013 | ₹24.2 L | L1 | Accepted-AOC Eligible |
| 2 | L2₹24.2 LSame as L1Rejected-Finance | ₹24.2 LSame as L1 | L2 | Rejected-Finance In Eligible |
| 3 | L3₹25.5 L+₹1.3 L (5.43%)Rejected-Finance | ₹25.5 L+₹1.3 L (5.43%) | L3 | Rejected-Finance In Eligible |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | DINA NATH L2 | Mukul Bhopal L3 | Ishan Sharma L1 |
|---|---|---|---|---|---|---|
| 1.00 | Cutting in earth work in all kinds of soil in all leads and lifts such a spade work , pick work , jumper work Saturated/Unsaturated soil blasting work in soft/ hard rock chiseling/wedging out rock where blasting is prohibited in all leads and lifts stacking the useful material available from cutting work and handing over the useful material to the department free of cost as per direction of the Engineer in charge with in all leads and lifts. | 253.71 | Cum | 250 ₹63,427.5 | 300 ₹76,113 | 200 ₹50,742 Lowest |
| 2.00 | Excavation in foundations, trenches etc.in all kind of soil in all leads and lifts such as pick work, jumper work in saturated/unsaturated soil including bailing out water, blasting work in hard/ soft rock or chiseling in hard/soft rock where blasting is prohibited in all lifts stacking the excavated earth not more than 3 mtrs clear from the edge of excavation and then returning the stacked soil in 15 cm layers when required into plinths sides of each deposited layer by ramming and watering and then disposing of all surplus excavated earth foundations etc., consolidating as directed within all leads and lifts and handing over the useable materials available from excavation to department free of cost as per direction of Engineer-in-charge with in all leads and lifts. | 152.23 | Cum | 350 ₹53,280.5 | 400 ₹60,892 | 300 ₹45,669 Lowest |
| 3.00 | Providing and laying cement concrete 1:6:12 ( 1 cement:6 sand:12 graded stone aggregate 40 mm nominal size) and curing complete excluding cost of formwork in foundation and plinth within all leads and lifts complete in all respect. | 4.48 | Cum | 9,200 ₹41,216 | 6,000 ₹26,880 Lowest | 9,000 ₹40,320 |
| 4.00 | Providing and laying cement concrete 1:4:8( 1cement:4 sand: 8 graded stone aggregate 40 mm nominal size) and curing complete excluding the cost of form work in foundation and plinth. | 12.19 | Cum | 9,800 ₹1,19,462 | 10,000 ₹1,21,900 | 9,000 ₹1,09,710 Lowest |
| 5.00 | Providing and laying cement concrete 1:3:6(1cement:3sand:6graded stone aggregate of 40mm nominal size)and curing complete excluding cost of form work including all leads and lifts in Foundation and Plinth. | 2.94 | Cum | 10,000 ₹29,400 | 10,500 ₹30,870 | 9,500 ₹27,930 Lowest |
| 6.00Providing & laying reinforcement cement concrete 1:1.5:3(1cement:1/2sand:3graded stone agregate of 20mm nominal size) curing complete excluding cost of from work and reinforcemenr for reinforced concrete work including all leads and lifts. | ||||||
| 6.01 | Foundations , footings bases of columns and the like and mass concrete work complete in all respect. | 13.56 | Cum | 12,000 ₹1,62,720 Lowest | 12,500 ₹1,69,500 | 12,000 ₹1,62,720 Lowest |
| 6.02 | Walls any thikness but not less that 0.10 Mtrs thickness including attached pilasters, buttresses plinth and string courses etc, from top of foundation (level) upto floor two level including all leads and lifts etc. complete in all respect. | 43.35 | Cum | 13,900 ₹6,02,565 | 13,575 ₹5,88,476.25 Lowest | 14,000 ₹6,06,900 |
| 6.03 | Suspended floors, roofs, landings, shelves and their supports, balconies, beams, and girders, bressumers and cantilevers upto floor two level including all leads and lifts etc. complete in all respects. | 1.2 | Cum | 14,000 ₹16,800 Lowest | 14,000 ₹16,800 Lowest | 14,000 ₹16,800 Lowest |
| 7.00 | Tor steel reinforcement for RCC work including bending, binding & placing in position complete upto floor two level i.c cost of binding wire with in all leads and lifts as per the entire satisfaction & direction of the Engineer - in - Charge. | 4,023.98 | Kg | 105 ₹4,22,517.9 | 101 ₹4,06,421.98 | 100 ₹4,02,398 Lowest |
Tender Value
₹28.8 L
EMD Value
₹57,600
Closing Date
14 Aug 2026, 5:00 pmClosed
ERxecutive Enginner
Jal SHakti Division Kullu
SH Recovery reconstruction and strengthening of WSS Kasol Under PDNA
2026_HPIPH_140612_1
5078-5127 Kasol
Open Tender
Civil Works
Item Rate
60 days
Kasol
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,000
Executive Enginner
₹57,600
19 Sept 2026
5 Aug 2026
17 Aug 2026
5 Aug 2026
14 Aug 2026
5 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Cutting in earth work in all kinds of soil in all leads and lifts such a spade work , pick work , jumper work Saturated/Unsaturated soil blasting work in soft/ hard rock chiseling/wedging out rock where blasting is prohibited in all leads and lifts stacking the useful material available from cutting work and handing over the useful material to the department free of cost as per direction of the Engineer in charge with in all leads and lifts. | 253.71 | Cum | - | - |
| 2 | Excavation in foundations, trenches etc.in all kind of soil in all leads and lifts such as pick work, jumper work in saturated/unsaturated soil including bailing out water, blasting work in hard/ soft rock or chiseling in hard/soft rock where blasting is prohibited in all lifts stacking the excavated earth not more than 3 mtrs clear from the edge of excavation and then returning the stacked soil in 15 cm layers when required into plinths sides of each deposited layer by ramming and watering and then disposing of all surplus excavated earth foundations etc., consolidating as directed within all leads and lifts and handing over the useable materials available from excavation to department free of cost as per direction of Engineer-in-charge with in all leads and lifts. | 152.23 | Cum | - | - |
| 3 | Providing and laying cement concrete 1:6:12 ( 1 cement:6 sand:12 graded stone aggregate 40 mm nominal size) and curing complete excluding cost of formwork in foundation and plinth within all leads and lifts complete in all respect. | 4.48 | Cum | - | - |
| 4 | Providing and laying cement concrete 1:4:8( 1cement:4 sand: 8 graded stone aggregate 40 mm nominal size) and curing complete excluding the cost of form work in foundation and plinth. | 12.19 | Cum | - | - |
| 5 | Providing and laying cement concrete 1:3:6(1cement:3sand:6graded stone aggregate of 40mm nominal size)and curing complete excluding cost of form work including all leads and lifts in Foundation and Plinth. | 2.94 | Cum | - | - |
| 6Providing & laying reinforcement cement concrete 1:1.5:3(1cement:1/2sand:3graded stone agregate of 20mm nominal size) curing complete excluding cost of from work and reinforcemenr for reinforced concrete work including all leads and lifts. | |||||
| 6.01 | Foundations , footings bases of columns and the like and mass concrete work complete in all respect. | 13.56 | Cum | - | - |
| 6.02 | Walls any thikness but not less that 0.10 Mtrs thickness including attached pilasters, buttresses plinth and string courses etc, from top of foundation (level) upto floor two level including all leads and lifts etc. complete in all respect. | 43.35 | Cum | - | - |
| 6.03 | Suspended floors, roofs, landings, shelves and their supports, balconies, beams, and girders, bressumers and cantilevers upto floor two level including all leads and lifts etc. complete in all respects. | 1.2 | Cum | - | - |
| 7 | Tor steel reinforcement for RCC work including bending, binding & placing in position complete upto floor two level i.c cost of binding wire with in all leads and lifts as per the entire satisfaction & direction of the Engineer - in - Charge. | 4,023.98 | Kg | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.53 MB
FORMSIX.pdf
Tender Documents • 0.40 MB
FORMEIGHT.pdf
Tender Documents • 1.43 MB
TERMANDCONDITION.pdf
Tender Documents • 0.37 MB
BOQ_208575.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .