| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.2 LAccepted-AOC | L1 | Accepted-AOC L1 bidder | |
| 2 | L2₹12.2 L+₹8,921.87 (0.73%)Rejected-AOC | L2 | Rejected-AOC L2 bidder |
Tender Value
₹11.2 L
EMD Value
₹27,876
Closing Date
18 Mar 2024, 6:00 pmClosed
Assistant Executive Engineer
Office of the Assistant Executive Engineer, Inland Navigation Subdivision, Varkala
LAC-ADS-Drain at Rathikkal-Construction of drain at Rathikkal in Vettoor grama panchayath-General Civil Work
2024_Irrig_662534_1
IRR/KP/TR/1000/2024_5_1_1/1
Open Tender
Civil Works - Others
Item Rate
120 days
Rathikkal
Please refer Tender documents.
10 documents required · 10 mandatory
₹2,760
Yes
₹27,876
Yes
1 Aug 2024
22 Feb 2024
20 Mar 2024
22 Feb 2024
18 Mar 2024
22 Feb 2024
Amount
Construction of drain
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
60.7.2:DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
60.6:PVC WEEP HOLES- Providing weep holes using 75mm dia. PVC pipes working pressure 4kg /sq.cm including cost of materials, conveyance, labour charges etc. complete.
2.20.1:Open timbering in trenches including strutting and shoring complete ( measurements to be taken of the face area timbered ):Depth not exceeding 1.5 m
OD39957/2023-2024:Constructing and placing of a name board of size 75x60cm installed in an appropriate place visible to the public, made of a brick wall with granite plaque of specified size to be inserted and letters engraved etc complete as per the direction of departmental officers at site
Drain
55.25:Lifting, conveying and fixing the newly casted RCC covering slabs of any thickness on top of drain in position including all labour charges and miscellaneous expenses etc complete
B UDAYAKUMAR
Bidder Name
K Madhusoodhanan Nair
B UDAYAKUMAR
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1027152.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .