Loading…
Loading…
Tender Value
₹2.2 Cr
EMD Value
₹2.6 L
Closing Date
30 Jan 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
GSU ELECT
15 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less: where V= Advertised value of the tender in crores of Rupees. N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Electrical contract license: - The contractor/firm should have valid electrical contractor license
7 conditions · 2 needing a document upload
The tenderer shall submit all relevant documents as detailed in para 14 & 18.10 of Tender Form (Second Sheet) of Part I of GCC work-2022.
The tenderer shall submit copy regarding status of firm i.e. sole proprietorship, partnership, Company, Society/Trust etc. and also submit a power of attorney and other relevant documents as detailed in Para no. 15 of Tender Form (Second Sheet) of Part I of attached GCC-2022.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Contractor should quote only the above/below percentage on estimated value, in the space provided at web portal for the purpose & nowhere else. Financial & Technical conditions quoted at any place other than prescribed space shall not be entertained while evaluating the offer.
Tenderer are required to go through the documents attached along with the tender and submit their bids accordingly.
Price Variation Clause not applicable on this contract
Electrical TRD Work in connection with proposed New Block station between KKNA- KATU station of DNA-RTGH station of JU Division
GSU-ELECT-JU-07-2025-26~NWR
GSU-ELECT-JU-07-2025-26
Open
Works - General
12 Months
Jodhpur, Rajasthan
₹0
₹2.6 L
30 Jan 2026
7 Jan 2026
16 Jan 2026
16 items across 1 schedule · ₹4,61,790 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Erection of single cantilever assembly complete with insulator for conventional OHE | Numbers 40.00 | — | 2,787 | 1,11,480 |
| 2 | Erection of materials with insulator for termination of single/ double conductor of OHE | Each 10.00 Span | — | 6,276 | 62,760 |
| 3 | Erection of three Pulley type Regulating equipment (Conventional type) with complete assembly | Numbers 4.00 | — | 10,814 | 43,256 |
| 4 | Erection of Fixed Termination Anchor (FTA) standard arrangement | Numbers 2.00 | — | 2,580 | 5,160 |
| 5 | Erection of materials for termination of single/double conductor (including supply of 9 Tonne cut in insulator) of OHE | Numbers 4.00 | — | 1,821 | 7,284 |
| 6 | Erection of section insulator assembly including core and cut-in insulator | Numbers 2.00 | — | 7,915 | 15,830 |
| 7 | Erection of 25 kV single pole isolator with jumpering arrangement. | Numbers 3.00 | — | 7,623 | 22,869 |
| 8 | Erection of 9 Tonne porcelain cut in insulator (including insulator testing) | Numbers 8.00 | — | 1,305 | 10,440 |
| 9 | Erection of Anti creep arrangement with insulator | Numbers 3.00 | — | 4,283 | 12,849 |
| 10 | Erection of 130 sqmm stranded cadmium copper wire with fittings. | Metre 200.00 | — | 126 | 25,200 |
| 11 | Erection of copper jumpers ATJ/C/F type | Numbers 5.00 | — | 332 | 1,660 |
| 12 | Erection of 'G' Jumpers | Numbers 10.00 | — | 2,483 | 24,830 |
| 13 | Splicing and extension of anchor OHE | Numbers 2.00 | — | 9,106 | 18,212 |
| 14 | Dismantling of Regulating equipment | Numbers 2.00 | — | 10,310 | 20,620 |
| 15 | Dismantling of cantilever / bracket assembly | Numbers 10.00 | — | 1,822 | 18,220 |
| 16 | Checking and preparation of SED | Numbers 80.00 | — | 764 | 61,120 |
| Schedule total | ₹4,61,790 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .