Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-AOC | ₹1.1 Cr | L1 | Accepted-AOC Agreement executed |
| 2 | L2₹1.0 Cr−₹5.5 L (5.23%)Rejected-Finance | ₹1.0 Cr−₹5.5 L (5.23%) | L2 | Rejected-Finance Since L1 accepted |
| 3 | Rejected-Technical | - | - | Rejected-Technical EMD not submitted |
Tender Value
₹87.1 L
EMD Value
₹50,000
Closing Date
10 Aug 2022, 6:00 pmClosed
Superintending Engineer HESC TVM
Superintending Engineer, Harbour Engineering South Circle, Kamaleswaram, Manacaud (PO), Thiruvananthapuram-9
Concrete road, road filling, protection wall and guard stone, side drain, coconut piling etc.
2022_HED_496157_1
01/HESC/2022-23/S
Open Tender
Civil Works - Roads
Item Rate
270 days
West Kallada Panchayath in Kunnathur LAC
Please refer Tender documents.
6 documents required · 6 mandatory
₹3,260
₹50,000
Yes
30 Dec 2022
22 Jun 2022
12 Aug 2022
22 Jun 2022
10 Aug 2022
22 Jun 2022
Amount
APPENDIX:- A - CONSTRUCTION OF CONCRETE ROAD
11.4.1.1 : Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203I.P.C.C grade M 10(i)Nominal mix 1:3:6
11.4.3.1 : Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203III.P.C.C. grade M 20 (i)Nominal mix (1:2:4)
For road filling
51.2.3 : Filling with Quarry Muck <br> Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
od5796/2018_2019 : GSB using Quarry Waste - Construction of granular sub-base by providing local material like quarry waste spreading in uniform layers with motor grader on prepared surface, and compacting with smooth wheel roller to achieve the desired density complete.
Appendix B - Construction of protection wall and Guard stone
11.1.5 : Excavation for StructuresEarthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.V. Marshy soil
12.4.3.3 : Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704, 1202 and 1204III. Random rubble masonry (iii)In cement mortar (1:5)
11.4.3.1 : Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203III.P.C.C. grade M 20 (i)Nominal mix (1:2:4)
12.5.3 : Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204For height upto 5 m III.R.C.C grade M 20
12.7 : Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
For Protection Wall
60.7.3 : DISMANTLING DR - Dismanling , clearing away and carefully stacking materials useful for reuse for any thickness of walls in DR masonry including disposal of debris within a distance of 150m.
60.7.8 : DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
Appendix C - Construction of side drain, cross drain And NP3 pipe
11.1.5 : Excavation for StructuresEarthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.V. Marshy soil
14.1 : Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and technical specifications Clause 1301
11.4.1.1 : Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203I.P.C.C grade M 10(i)Nominal mix 1:3:6
12.5.4 : Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204For height upto 5 mIV.R.C.C. grade M 25
12.7 : Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
9.3.C : Providing and Laying Reinforced Cement Concrete pipe NP3 as per design in Single RowProviding and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement motar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106.(C)750 mm dia
Coconut piling for side drain
60.64.1 : Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete.
60.64.4 : Coconut Pile - Driving down coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end
60.64.6 : Cutting and removing the excess length of wooden piles to lines and levels and removing the cut end of piles and stacking within 150m
60.1.1 : RING BUND Type-I-Putting up ring bund as per approved shape 2.5m bottom width, 1m top width using empty gunny/polythene bags filled with earth placed in 2 rows at 0.6m apart and filled in between with puddle clay to form bund for an average height 2.00m including labour dismantling the bund after completion of the work etc. complete.
60.2.2 : Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
Lifting and placing of cover slab
od6703/2019_2020 : Lifting, conveying and placing pre-cast drain cover slabs in lines and levels as per the direction of officers at site including all cost, labour charges etc complete.
BABU T
ABDUL KHADER NIYAS M
Bidder Name
BABU T
MBM ENGINEERING WORKS
ABDUL KHADER NIYAS M
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_711737.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .