345 Shree Mohini Complex Kingsway Nagpur
Rn M of Boiler Unit 2 GSECL Wanakbori TPS
2026_BHEL_59462_1
E TS No 3233
Open Tender
Machineries/ Mechanical Engg Items
Item Rate
120 days
Wanakbori
As per Annexure-1
8 documents required · 8 mandatory
₹0
₹20 L
5 May 2026
18 Mar 2026
30 Mar 2026
18 Mar 2026
30 Mar 2026
18 Mar 2026
Total Lumpsum Price for entire Scope of Work as per Tender Specification No:BHE/PW/PUR/WRB-BOILER/3233
Note : 1.Please refer "PriceBid-ExcelSheetforcalculation" Technical Conditions of Contract (TCC) for Payment Break up. 2. Price shall be quoted without GST
Excel Sheet of Schedule of Rates and Quantities for Caluculation purpose only
For the convenience of bidders, BHEL has issued this excel sheet with all requisite formulae ( percentage break up). However this excel sheet shall not form part of contract.
Broad Scope of job
E Tender Specification No
TOTAL Lumpsum value to be quoted by the bidder in VOL II Price Bid at E portal
Dismantling of Boiler Parts (80%)
Milestone Activities to complete Boiler R&M Work (20%)
Erection of component (25%)
Alignment, welding of the component (35%)
NDT of the component (20%)
Milestone Activities to complete Boiler R&M Work (20%)
Erection of component (25%)
Alignment, welding of the component (35%)
NDT of the component (20%)
Milestone Activities to complete Boiler R&M Work (20%)
Module loading 0f APH A (20%)
Module loading of APH B (20%)
APH A alignment & Trial Run (20%)
APH B alignment & Trial Run (20%)
Milestone Activities to complete Boiler R&M Work (20%)
Classifier replacement work (5.5% for each mill X 6 mills)- proportionally (33%)
Liner replacement and repairing of mills( 5.5% for each mill X 6 mills) - proportionally (33%)
Mills trial run (14%)
Milestone Activities to complete Boiler R&M Work (20%)
Erection of duct (25%)
Alignment, welding & NDT (30%)
Duct Support (10%)
ATT completion (15%)
Milestone Activities to complete Boiler R&M Work (20%)
Replacement of coal nozzle, coal pipe & bends (20%)
Replacement of scanner air system (20%)
Replacement of valves & corner skids in fuel firing system and SADC/burner tilt mechanism (20%)
Replacement of SH & RH spray valves (20%)
Milestone Activities to complete Boiler R&M Work (20%)
Erection & Commissioning of Hangers & Supports (80%)
Milestone Activities to complete Boiler R&M Work (20%)
Application of Insulation including Cladding & Refractory (80%)
Milestone Activities to complete Boiler R&M Work (20%)
Note: Kinldy do not upload this excel sheet anywhere along with your offer.
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.18 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.62 MB
BOQ_64358.xls
BOQ • 0.24 MB
NIT3233.pdf
Tender Documents • 1.61 MB
Vol-IA-NIT-TCC-3233.pdf
Tender Documents • 1.98 MB
Volume-I-BCD3233.pdf
Tender Documents • 7.27 MB
ChapterX.pdf
Tender Documents • 0.27 MB
ExcelSheetforcalculationpurposeOnly.xls
Tender Documents • 0.04 MB
Corg-05-3233.pdf
PDF • 0.25 MB
Corg-04-3233.pdf
PDF • 0.25 MB
Corg-03-3233.pdf
PDF • 0.25 MB
Corg-02-3233.pdf
PDF • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .