Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹313.2 Cr
EMD Value
₹6.3 Cr
Closing Date
18 Mar 2027, 1:45 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Yes (up to 4 members)
Yes (up to 4 members)
Two Packet System
EPC [ Single Stage ]
Yes
31/12/2026 15:30
Lowest to Highest
180 days
Expenditure
Deposit Work
TENDER
19 conditions · 8 needing a document upload
As per RFP document attached & edition with EPC Amendment No - 04. dt 31- 08 - 2026.
As per RFP document attached & edition with EPC Amendment No - 04. dt 31- 08 - 2026.
Similar Nature of Work "Construction of new railway line / doubling / multi tracking/ metro rail / DFC line/ highway corridor involving viaducts/ Major/Important bridges of minimum total length of 654 m'."
Similar nature of work: - " Any Civil Engineering work involving bridge work with pile/open/well foundation. They should have also completed supply, fabrication, erection/launching of plate girder/composite girder/open web girder of minimum individual span of 12.2m with cumulative span of 66m in same or another completed work"
Similar nature of work: - "Any Civil Engineering work involving bridge work with pile/open/well foundation. They should have also completed supply, fabrication, erection/launching of plate girder/composite girder/open web girder of minimum individual span of 12.2m with cumulative span of 66m in same or another completed work"
Similar nature of work: - "Any Civil Engineering work involving bridge work with pile/open/well foundation. They should have also completed supply, fabrication, erection/launching of plate girder/composite girder/open web girder of minimum individual span of 12.2m with cumulative span of 66m in same or another completed work."
As per RFP document attached & edition with EPC Amendment No - 04. dt 31- 08 - 2026.
As per RFP document attached & edition with EPC Amendment No - 04. dt 31- 08 - 2026.
7 conditions · 4 needing a document upload
As per RFP Document & edition with EPC Amendment No - 04. dt 31- 08 - 2026.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
As per RFP and draft agreement document & edition with EPC Amendment No - 04. dt 31- 08 - 2026.
Engineering, Procurement and Construction (EPC) for"Construction of new B.G. railway line work including earth work,blanketing, minor bridges, major bridges, ROBs, LHS/RUBs, trackworks, platform work, station building, other buildings, andassociated miscellaneous works for 32.5 Ton DFC Standard Loadingfrom Chetar station to Banhardih captive mine of PVUNL New Linein Dhanbad Division of East Central Railway."
ECR-CAO-C-S-EPC-10-26-27~ECR
ECR-CAO-C-S-EPC-10-26-27
Open
Works - General
548 Days
Purbi Champaran, Bihar
₹0
₹6.3 Cr
17 Nov 2026
17 Nov 2026
4 Mar 2027
31 Dec 2026
180 days
41 items across 4 schedules · ₹30,96,46,371.76 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | All kinds of soils | cum | 3800.00 | 192.15 | 7,30,170 |
| 2 | Soft rock (not requiring blasting) | cum | 650.00 | 394.4 | 2,56,360 |
| 3 | Hard rock (requiring blasting) | cum | 1650.00 | 728.12 | 12,01,398 |
| 4 | 1:1½:3 (1 Cement: 1½ coarse sand (zone- III) : 3 graded stone aggregate 20 mm nominal size) | cum | 255.49 | 4,483.1 | 11,45,387.22 |
| 5 | 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) | cum | 200.00 | 4,663.17 | 9,32,634 |
| 6 | 1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size) | cum | 50.00 | 4,806.76 | 2,40,338 |
| 7 | Providing and laying in position machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using 20mm graded crushed stone aggregate and coarse sand of approved quality in RCC raft foundation & Pile cap including finishing, using Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability complete as per specifications and direction of the Engineer in charge. N o t e : 1. Payment for cement, reinforcement and shuttering shall be made extra under relevant item. 2. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons for not using plasticiser at the stage of Mix Design and in that case deduction shall be made as per relevant item. | cum | 5791.93 | 4,700.79 | 2,72,26,646.62 |
| 8 | Abutment & Pier | cum | 1330.00 | 4,777.56 | 63,54,154.8 |
| 9 | Wing wall and Return wall | cum | 874.06 | 4,777.56 | 41,75,874.09 |
| 10 | Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Fender wall, Diaphragm wall etc. | cum | 846.79 | 4,815.95 | 40,78,098.3 |
| 11 | Extra for every increase of 1m or part thereof in the height above 9.0 m | cum | 2000.00 | 76.77 | 1,53,540 |
| 12 | Providing and fixing Weep Holes in Abutments, Wing walls and Return walls etc., of new bridges with 110mm dia UPVC pipe Type A ISI marked with all contractor's men, material, transportation, all taxes as per specifications and as directed by Engineer-in-Charge. | Metre | 1320.81 | 299.21 | 3,95,199.56 |
| 13 | 1200mm diameter | Metre | 1350.00 | 11,392.46 | 1,53,79,821 |
| 14 | Providing, fabricating and installing permanent casing pipe for bored piles for all diameters with specified thickness of steel plate including all labour, materials, tools & complete as per approved drawing & specifications complete in all respect as per the direction of Engineer in charge. Note: Payment shall be made as per the weight of circular plate of casing pipe only. | MT | 6.00 | 1,36,024.61 | 8,16,147.66 |
| 15 | 1200mm diameter pile | Metre | 50.00 | 4,074.96 | 2,03,748 |
| 16 | Initial load test above 100 ton and up to 250 T capacity pile | Each | 1.00 | 87,650.98 | 87,650.98 |
| 17 | Extra for every increase of 50 ton in pile capacity or part thereof over 250 ton | Each | 1.00 | 4,566.65 | 4,566.65 |
| 18 | Routine Load Test above 100 ton capacity up to 250 ton capacity pile | Each | 1.00 | 43,825.49 | 43,825.49 |
| 19 | Piles with lateral load capacity of up to 50 ton | Each | 36.00 | 18,382.91 | 6,61,784.76 |
| 20 | Pulse Echo Test (PET) for integrity testing of piles with contractor's men, materials and machines. The rate includes cost of Inspection of site, preparation of pile head and any other unforeseen cost required for the test, submission of reports in triplicate as per satisfaction of the Engineer in Charge. | Each | 10.00 | 6,626.51 | 66,265.1 |
| 21 | All types of bridge sub-structures, e.g. pier, abutment, wing wall, retaining wall, RCC box type foundations, Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Fender wall, Diaphragm wall etc. up to 5m above ground level | Sqm | 1781.87 | 649.96 | 11,58,144.23 |
| 22 | All types of bridge super-structures, e.g. slabs, I-girders, T-girders, Box girders etc. up to 5m above ground level. | Sqm | 500.00 | 840.22 | 4,20,110 |
| 23 | Extra for additional height over item no. 025031 & 025032 wherever required with adequate bracing, propping etc. over initial height of 5 metres for every additional height of 1 metre or part thereof. | Sqm | 500.00 | 99.69 | 49,845 |
| 24 | Extra for inserting of dowel bars of specified dia. (cost of rods to be paid extra) | Metre | 2000.00 | 12.87 | 25,740 |
| 25 | Providing Flood Level Gauges on abutments and piers, made by 20mm thick 1:4 cement plaster for a width of not less than 300mm, duly engraving markings & figures in metres, divided into 10 parts commencing from under-side of girders towards bed, painting markings & figures with black enamel paint in three coats on white background including painting HFL Mark in white by side of gauge with year of occurrence with all Contractor's materials, labour, tools, scaffolding and supports, lead & lifts, curing etc. complete as per approved drawing and as directed by the Engineer in- charge excluding cost of cement which shall be paid extra. | Sqm | 12.00 | 509.54 | 6,114.48 |
| 26 | With epoxy concrete grouting. | Kg | 500.00 | 147.9 | 73,950 |
| 27 | Supplying, Fabricating and fixing access ladders, inspection platforms, Trolley refuges etc., on bridges with structural steel conforming to IS:2062 including welding / bolting, priming painting with one coat of ready mixed paint of Zinc Chromate (IS:104) with DFT of 25-30 microns followed by one coat of Zinc Chrome Red Oxide (IS:2074) with DFT of 25 microns with all material, labour, T&P as a complete job. Note: Painting shall be paid separately under relevant item. | MT | 30.00 | 1,09,740.39 | 32,92,211.7 |
| 28 | Providing and laying Pitching with Stone Boulders, weighing not less than 35kg each with voids filled with spalls on slopes, laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical Specifications (filter media to be paid separately under the relevant item). | cum | 1142.59 | 2,463.61 | 28,14,896.15 |
| 29 | Providing and laying Filter Material as per RDSO Specifications underneath pitching in slopes complete as per drawing and Technical Specification. | cum | 160.00 | 3,311.4 | 5,29,824 |
| 30 | Providing and laying of filter media consisting of granular materials of GW, GP, SW groups as per IS:1498 (latest) in required profile behind boulder filling of abutments, wing walls / return walls etc. above bed level with all labour and material complete job as per drawing and technical specification of RDSO Guidelines. | cum | 21341.34 | 2,918.98 | 6,22,94,944.63 |
| 31 | Providing Boulder Backing behind wing wall, return wall, retaining wall with hand packed boulders & cobbles with smaller size boulders toward the back including all lead, lift, labour & other incidental charges as complete work in all respect. Payment for boulder/cobbles will be done extra. | cum | 870.00 | 325.68 | 2,83,341.6 |
| 32 | Dewatering of natural or accumulated water from any location. Payment to be done for Horse power of pump multiplied by pumping hours. | HP Hour | 2000.68 | 30 | 60,020.4 |
| Schedule total | ₹13,51,62,752.42 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
VCDetails.pdf
ATTACHMENT
Bankaccountdetails.pdf
ATTACHMENT
EPCAmendmentNo.-4Dated31.08.2026.pdf
ATTACHMENT
LinkforDrawing.pdf
ATTACHMENT
RFPtenderDOCUMENT.pdf
ATTACHMENT
2026_06_16Acceptanceofe-BankGuaranteee-BGinWorksContractsandPGMS_PMS_PSSAGC1.pdf
ATTACHMENT
EPCDOCUMENTtenderChetarBanhardih.pdf
ATTACHMENT
VCDetails.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .