| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹7.2 LAdmitted-Finance | -16.99% | ₹7.2 L | L1 | Admitted-Finance |
| 2 | L2₹7.4 LAdmitted-Finance | -15.01% | ₹7.4 L | L2 | Admitted-Finance |
| 3 | L3₹7.6 LAdmitted-Finance | -12.51% | ₹7.6 L | L3 | Admitted-Finance |
| 4 | L4₹8.0 LAdmitted-Finance | -7.70% | ₹8.0 L | L4 | Admitted-Finance |
Tender Value
₹8.7 L
EMD Value
₹17,360
Closing Date
3 Feb 2026, 6:00 pmClosed
EXECUTIVE ENGINEER, PWD CITY DIVISION, JODHPUR
EXECUTIVE ENGINEER, PWD CITY DIVISION, JODHPUR
Repair work of Sewerage line at Women Prisoner Correctional Home, Jodhpur at women Jail Jodhpur
2026_CEPWD_531459_7
NIT No 38 of 2025-26
Open Tender
Civil Works
30 days
Jodhpur
Please refer Tender documents.
3 documents required · 3 mandatory
₹500
E E, PWD CITY DIVISION, JODHPUR/MDRISL JAIPUR
₹17,360
Yes
6 Feb 2026
23 Jan 2026
4 Feb 2026
23 Jan 2026
3 Feb 2026
23 Jan 2026
Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including disposal of excavated earth, lead upto 50m and lift upto 1.5 m , disposed earth to be levelled and neatly dressed : All kinds of soil
Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer-in-charge. 1: 3: 6 or richer mix.
Providing, Laying & Jointing R.C.C. class NP-2 Non-Pressure pipes (IS : 458mark) of approved make with collars, jointed with C.M. 1:2 or having Spigot and socket ends with flexible rubber rings joint including testing of joints etc. complete : 300mm dia Internal
Providing & Laying C.C. 1:5:10 (Stone aggregate 40mm nominal size) all around S.W. pipe including 15 Cm. thick bed concrete (Width W= Diameter of pipe in Cm+30 Cm.)( Excluding cost of pipe) 300mm dia S.W. pipe
Providing and Fixing Unplasticized Poly Vinyl Chloride (UPVC) SWR Pipes Type B for sciland waste discharge system (IS:13592 : 1992 Marked) of approved quality /make 110 mm dia
Construction of manhole in all type of soil inner size 90 X 60 Cm. 300 mm thick masonry in CM 1:6, 10 Cm. thick cement concrete 1:5:10 in foundation, 20 mm thick inside plaster in CM 1:6, finished with floating neat cement, 50mm thick M-15 grade C.C. flooring, making channels, 80mm thick stone slab covering with 40mm thick M-15 grade C.C. flooring, Cement cover with frame of 450mm dia, earthwork etc. complete as per design including disposal of surplus earth within 50 mtr. lead. Depth up to 0.5 M
Construction of manhole in all type of soil inner size 90 X 60 Cm. 300 mm thick masonry in CM 1:6, 10 Cm. thick cement concrete 1:5:10 in foundation, 20 mm thick inside plaster in CM 1:6, finished with floating neat cement, 50mm thick M-15 grade C.C. flooring, making channels, 80mm thick stone slab covering with 40mm thick M-15 grade C.C. flooring, Cement cover with frame of 450mm dia, earthwork etc. complete as per design including disposal of surplus earth within 50 mtr. lead. Add extra over item 3.19.1 for every additional 0.10m depth above 0.5 m depth.
Construction of soakage well in all type of soil with 300 mm thick dry masonry, top and bottom 300 mm course in CM 1:6, 80mm thick stone slab, jointing of slab in CM 1 : 3, Ralthal, Kharanja, 40 mm thick M-15 grade C.C flooring , earthwork complete as per approved drawing including disposal of earth within a lead of 50 mtr.: Size 300 Cm. dia outside & 300 Cm. depth.
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 P.C.C grade M 10 Nominal mix 1:3:6
Construction of un-reinforced, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 602.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 31.5 mm, mixed in a concrete mixer of not less than 0.5 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed Side Formwork (steel channel, laying and fixing of 150 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, using water finishing to lines and grade as per drawing and MoRTH Specification Clause 602 including vaccum dewatering process with all required equipments (Dowel Bars will be paid seprately)
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.64 MB
Tendernotice_2.pdf
PDF • 0.26 MB
Tendernotice_3.pdf
PDF • 1.69 MB
Tendernotice_4.pdf
PDF • 0.28 MB
BOQ_947377.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid