| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹3.0 LAccepted-Finance VILLAGE AND PO SHIYAH TEHSIL BHUNTAR DISTT KULLU H P | ₹3.0 L | L-1 | Accepted-Finance Found Lowest one |
| 2 | L-2₹3.0 LRejected-Finance 346 2 RAMBIR COLONY RAILWAY ROAD JIND JIND JIND JIND HARYANA 126102 | JIND | HARYANA | 126102 | ₹3.0 L | L-2 | Rejected-Finance High rate qouted |
| 3 | L-3₹3.1 LRejected-Finance NOT AVAILABLE | ₹3.1 L | L-3 | Rejected-Finance High rate qouted |
| Sl No | Description | Qty | Unit | Ankit L3 | Raj Kumar L2 | ASHISH KUMAR L1 |
|---|---|---|---|---|---|---|
| 1.00 | Excavation in drain and channels etc. in all kinds of soil such as pick work,jumper work,blasting work soft and hard rock and saturated soil including dressing of sides and beds and disposing of excavated earth within all leads and lifts as per the direction of Engineer-in-charge. | 28.5 | Cubic metre | 180 ₹5,130 | 250 ₹7,125 | 200 ₹5,700 |
| 2.00 | Providing and laying cement concrete 1:4:8 (One cement is to four sand is to eight graded stone aggregate 40 milimetre nominal size) and curing complete excluding the cost of form work in foundation and plinth within all leads and lifts as per the direction of Engineer-in-charge. | 8.55 | Cubic metre | 5,600 ₹47,880 | 5,000 ₹42,750 | 4,650 ₹39,757.50 |
| 3.00Providing and laying cement concrete 1:2:4 (One cement is to two sand is to four graded stone aggregate 20 milimetre nominal size) and curing complete excluding the cost of form work and reinforcement for reinforced cement concrete work in:- | ||||||
| 4.00 | a) Foundation,footings bases of column and the like mass concrete within all leads and lifts as per the direction of Engineer-in-charge. | 11.4 | Cubic metre | 6,700 ₹76,380 | 6,100 ₹69,540 | 6,050 ₹68,970 |
| 5.00 | b) Walls (any thickness) butt not less then 0.10 metre thickness) attached pillasters, buttresses, plinth and string courses etc. from top of foundation up to floor two level with in all leads and lifts as per the direction of Engineer-in-charge. | 15.2 | Cubic metre | 6,700 ₹1.0 L | 6,200 ₹94,240 | 6,250 ₹95,000 |
| 6.00Providing form work with steel plates 3.15 milimetre thick welded with angle iron in frame 30x30x5 milimetre so as to give a fair finish including centring, shuttering, strutting and propping etc. with wooden battens ballies,height of propping and centring below supporting floor two ceiling not exceeding 4 metre and removal of the same for in-situ-reinforced concrete and plain concrete work in:- | ||||||
| 7.00 | a) Vertical surfaces such as walls(any thickness)partitions walls and the like including attached pillasters,buttreses plinth string courses and the like within all leads and lifts as per the direction of Engineer-in-charge. | 152 | Square metre | 150 ₹22,800 | 205 ₹31,160 | 220 ₹33,440 |
| 8.00 | Providing and laying mild steel/tor steel reinforcement for reinforced cement concrete work including bending binding and placing in position complete upto floor two level within all leads and lifts as per the direction of Engineer-in-charge. | 665 | Killogramme | 88 ₹58,520 | 85 ₹56,525 | 85 ₹56,525 |
Tender Value
Refer Docs
EMD Value
₹7,530
Closing Date
24 Nov 2025, 5:00 pmClosed
EXECUTIVE ENGINEER
JAL SHAKTI DIVISION PALAMPUR
Construction of RCC Branch Channel RD 200 to 390 190 Running metre
2025_HPIPH_120549_1
HP IPH 7030-7075 DATED 14.11.2025
Open Tender
Civil Works
90 days
PALAMPUR
Please refer Tender documents.
7 documents required · 7 mandatory
₹500
EXECUTIVE ENGINEER
₹7,530
7 Feb 2026
14 Nov 2025
25 Nov 2025
14 Nov 2025
24 Nov 2025
14 Nov 2025
Excavation in drain and channels etc. in all kinds of soil such as pick work,jumper work,blasting work soft and hard rock and saturated soil including dressing of sides and beds and disposing of excavated earth within all leads and lifts as per the direction of Engineer-in-charge.
Providing and laying cement concrete 1:4:8 (One cement is to four sand is to eight graded stone aggregate 40 milimetre nominal size) and curing complete excluding the cost of form work in foundation and plinth within all leads and lifts as per the direction of Engineer-in-charge.
a) Foundation,footings bases of column and the like mass concrete within all leads and lifts as per the direction of Engineer-in-charge.
b) Walls (any thickness) butt not less then 0.10 metre thickness) attached pillasters, buttresses, plinth and string courses etc. from top of foundation up to floor two level with in all leads and lifts as per the direction of Engineer-in-charge.
a) Vertical surfaces such as walls(any thickness)partitions walls and the like including attached pillasters,buttreses plinth string courses and the like within all leads and lifts as per the direction of Engineer-in-charge.
Providing and laying mild steel/tor steel reinforcement for reinforced cement concrete work including bending binding and placing in position complete upto floor two level within all leads and lifts as per the direction of Engineer-in-charge.
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.37 MB
Form6.pdf
Tender Documents • 0.27 MB
Form8.pdf
Tender Documents • 0.99 MB
Termsandconditions.pdf
Tender Documents • 0.08 MB
BOQ_176646.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid