Loading…
Loading…
Tender Value
₹2.1 Cr
EMD Value
₹2.1 L
Closing Date
3 Oct 2026, 6:30 pm6d left
EXECUTIVE ENGINEER, DAHOD IRRIGATION DIVISION, DAHOD
Construction of New Lift Irrigation Scheme At. Village. Zapatiya, Ta.D.Bariya, Dist.Dahod (3rd Attempt)
346908
13 of 2026-27
Open
Civil - All
Works
Dahod
10 documents required · 10 mandatory
₹3,600
EXECUTIVE ENGINEER, DAHOD IRRIGATION DIVISION, DAHOD
₹2.1 L
19 Sept 2026
19 Sept 2026
19 Sept 2026
3 Oct 2026
19 Sept 2026
Name of Work: Construction A New Lift Irrigation Scheme At. Village. Zapatiya,
Ta.Dhanpur, Dist.Dahod
D.T.P. for the above work amounting to Rs. 21228949.11(Rupees Two Crores Twelve
Lacs Twenty-Eight Thousand Nine Hundred Forty Nine) are verified and recommended
Deputy Executive Engineer Sr.Divisional Accounts Officer
Koliyari Sub Division No.1 Dahod Irrigation Division
Devgadh Baria Dahod
Executive Engineer
Dahod Irrigation Division
TO BE CHECKED BY P.B. FOR APPROVAL OF D.T.P.
1. What is the basis of Schedule-B of D.T.P.? : As per approved Estimate.
Sanctioned or submitted estimate?
2. Does description of items tally what that in : Yes
3. What items if any are not put to tender & : GST as per 18 %, i.e. Rs.
4. Do leads and lift tally with those in : NA
5. Are units for rates, O.K.? : Yes
6. Check mode for measurement for each : Yes
item and state if it is O.K.
7. Are any rates prescribed on truck trip basis : NA
or borrow area measurement or lump sum
8. What are the items with scope for excess : At present there are no scopes for any excess or saving.
and/or reduced quantities?
9. Is royalty etc., refund clause necessary and : NA
10. It is necessary to hire Govt. machinery and : No
is this provision for the same.
11. Check quantities of materials as per : Schedule-A materials are not proposed.
Schedule - A are these quantities justified
for work quantities as per Schedule-B.
12. Is there any material to be issued which : No
may not be required for actual use in item
13. Check specifications are they in order? : Yes
14. Is time limit in order? : Yes
15. What time is available for doing work after : 11 (Eleven) Months.
allowing for monsoon? Is it adequate? Yes, it is adequate.
16. Any special points with the Junior : No
Engineer/Supervisor want to suggest
regarding these DTP?
Deputy Executive Engineer Sr.Divisional Accounts Officer
Koliyari Sub Division No.1 Dahod Irrigation Division
Devgadh Baria Dahod
Executive Engineer
Dahod Irrigation Division
1. Whether tender agreement form is as per latest corrected form : Yes
as prescribed by Govt.
2. If clause regarding refund of royalty deleted? : NA
3. Whether special condition regarding refund of royalty etc. is : NA
adopted, also where if required for the particulars type of work.
4. Whether latest modified clause-1 to 79 are adopted. : As per SBD
5. If rates provided in Schedule-A are in order? : NA
6. Are proper site of delivery of materials specified in Schedule- : NA
7. For non-return of empty cement bags is penalty rate prescribed. : As per SBD
8. Whether prescribed rates of progress in clause-2 are in order as : As per SBD
9. Whether security deposit rates and recovery rates are in order : As per SBD
10. Is form for Bank Guarantee for Earnest money or Security : As per SBD
Deposit as prescribed by Govt. given.
12. Whether required tender notice period is given as per manual. : As per SBD
14. Whether 1st invitation of tender or 2nd? : First invitation
15. Whether tender for whole work is invited or there is a split up. : Tender is invited for whole works.
16. Whether split up is approved by Competent authority. : NA
17. Whether estimate is sanctioned by competent authority. : Yes
18. What is the basis for invitation of tender viz. sanctioned or : Sanctioned estimate
submitted estimate?
19. Whether estimated amount put to tender is in order. : Yes
20. Whether corrected tender fees are prescribed. : Yes
21. Special points which a tender clerk may like to bring to the : No
notice of the Chief Engineer.
22. Overall review by Tender Clerk. : DTP is in Order and submitted for
approval please.
23 Land Acquisition : Not Applicable
Deputy Executive Engineer Sr.Divisional Accounts Officer
Koliyari Sub Division No.1 Dahod Irrigation Division
Devgadh Baria Dahod
Executive Engineer
Dahod Irrigation Division
STANDARD BIDDING DOCUMENT PROCUREMENT
DRAFT TENDER PAPERS FOR
Construction A New Lift Irrigation Scheme At. Village. Zapatiya, Ta.Dhanpur,
ESTIMATED COST RS.
START DATE FOR DOWNLOADING Date and Time for online Tendering shall be as per
online Notice Inviting Tender ( NIT ) as published on
LAST DATE OF ONLINE SUBMISSION
www.nwr.nprocure.com
LAST DATE FOR SUBMISSION OF (Tender Notice No. of Year 2025-2026)
TEDNDER FEE EMD AND OTHER DOCUMENTS
DATE OF OPENING
STANDARD BIDDING DOCUMENT
GOVERNMENT OF GUJARAT
NARMADA WATER RESOURCES, WATER SUPPLY
AND KALPASAR DEPARTMENT
Dahod Irrigation Division, Dahod
Sr No Section Description Page No
1 Invitation for Bid (IFB)
2 Section -1 Instructions to Bidders
3 Section -2 Qualification Information
4 Section -3 Conditions of Contract
5 Section -4 Contract Data
6 Section -5 Technical Specification
7 Section -6 Form of Bid
8 Section -7 Bill of Quantities
9 Section -8 Securities and Other Forms
10 Section -9 Drawings
11 Section -10 Documents to be furnished by Bidder
INVITATION FOR BID
NATIONAL COMPETITIVE BIDDING
1. The EXECUTIVE ENGINEER, DAHOD IRRIGATION DN NO 1 DAHOD invites bids for the
construction of works detailed in the table.
The bidders may submit bids for any or all of the following works.
Package Name of work Approximat Bid Cost of Period of #Class of
No. e value of security document completion Registration /
works (Rs.) (Rs.) Category of
(Rs.) contractor if
1 Construction of New Lift 21228949.11 213000.00 3600/- 11 Class B &
Irrigation Scheme At. MONTHS Above
Village. Zapatiya, (Experienced
Ta.D.Bariya, Dist.Dahod contractors of
2. Prospective / Interested bidder may download the Bid Documents from website
https://www.nprocure.com free of cost till the Time and Date as mentioned on online NIT at
website https://www.nprocure.com.
3. However, Bidder who is submitting the Bid Online will have to pay the Bid Document Fee
/ Tender Fee through Demand Draft only of any Schedule Bank payable at
“Dahod” and in favour of ”EXECUTIVE ENGINEER, Dahod Irrigation Division”. Once the Bid
is received online, Bid Document / Tender Fee will not be refundable. As Per GoG R&B
Department’s Circular No. PARACH/102/000/IB/221/(59)/C Dated.24/01/2007
The Demand Draft for Bid Document / Tender fee and FDR / Bank Guarantee against Bid
Security / EMD shall be submitted in electronic format through online (by scanning) while
uploading the bid, this submission shall mean that bid document / tender fee and Bid Security /
EMD has been received. Accordingly, the offer of only those shall be opened whose Bid
Document / Tender Fee and Bid Security / EMD have been received electronically. However, for
the purpose of realization of Demand Draft, and FDR / Bank Guarantee bidder shall send the
same in original through R.P.A.D. so as to reach to #‘‘EXECUTIVE ENGINEER, DAHOD IRR.
DN DAHOD’’ within 7 Days from the last day of bid submission.
Penaltative action for not submitting Demand Draft / FDR / Bank Guarantee in original
to Executive Engineer / Tender Inviting Authority by bidder shall be initiated. WRD GR No.
PRC-102014-1-MICell-K.1 Dated: 29/10/2014
4. Bids received online, will be opened on the time, date and place as specified in the online NIT at
website https://www.nprocure.com in the presence of the bidders or their authorized
representatives, who wish to remain present.
If the office happens to be closed on the day of opening of the bids as specified, the bids will be
opened on the next working day at the same time and venue.
5. A pre bid meeting will be held on ………………………………at ………………………..hrs. at
the office of ......................................... to clarify the issues and to answer questions on any
matter that may be raised at that stage as stated in clause 9.2 of ‘instructions to Bidders’ of
the bidding documents.
6. #Bid Security (EMD) is equal to 1% of Estimated Amount put to bid / tender and should be
rounded off to the next thousand rupees.
7. Other Information is as under:
A. Agencies can prepare and edit their offers a number of times before the end of the tender
submission date and time. After the tender submission date and time, the bidder cannot
modify / edit / withdraw their submitted offer in any case. No written or online request in this
regard shall be granted.
B. Offers in physical form will not be accepted in any case.
C. Demand Draft purchased by the other then bidder and issued after the last date of submission
of Bids, will not be considered or accepted.
D. The cost incurred by the contractor for this offer for clarification or attending discussion,
conferences or site visits will not be reimbursed by the Employer or Engineer-in-Charge.
E. Conditional tender shall not be accepted.
F. Any changes, addition, alternation made in the prescribed form attached with tender are liable
to be rejected.
G. Any change in format or conditional Bank Guarantee will not be accepted and the bidder will
be considered non-responsive.
H. All the bidders are instructed to fill in information strictly in accordance with the format
given in the checklist /qualification document / tender document.
I. It is mandatory for the bidders to supply each and every information as asked strictly in
electronic format at appropriate places only.
J. Blank / insufficient information shall be treated as nil information and shall result in
disqualification.
K. Even if the bidder has been qualified in a similar or larger size of project in the past, it shall
not be deemed to be a ground / reason for not giving required information for this work / bid.
L. Information supplied for earlier projects shall not be considered while evaluation of this bid.
The Government will not ask for any other information, unless it is found absolutely
necessary by the competent authority.
M. If found necessary, the contractor will be intimated for negotiation,
# For the works costing up to Rs. 7.5 crore (WRD Works), Rs. 7.0 crore (ROAD/ BRIDGE/
BUILDING WORKS), Rs. 0.5 Crore (Electrical Works) kindly refer to GoG NWRWS &
K Department’s Circular No. Paracha/1097/1397(11)/pa.fa./ MICELL(k-1) dated
For the works costing under Rs. 7.5 crore for Construction work of Water Resources
Department, Rs. 7.0 crore for Roads, Bridges and Building and Rs. 0.50 crore for Electrical work
following documents shall be submitted in electronic format only through online by scanning
and the (i) Bid Document Fee / Tender Fee (ii) Bid Security / EMD should be sent in original to
the Tender opening authority through RPAD, so as to reach the Executive Engineer within
days from last day of submission of Bid.
(1) Bid Document Fee / Tender Fee in shape of D.D.
(2) Bid Security / EMD or Valid EMD Exemption Certificate of Appropriate Class of Registration of
Approved Contractors Fixed Deposit Receipts / D.D.
(3) Registration Certificate of Appropriate Class.
(4) Current labour license,
(5) PAN Number,
(6) Good & Service Tax Number,
(7) Original Affidavit declaring bidder’s eligibility as per Annexure-L for uploading tender document.
(8) Work Experience, if necessary, Other Documents, as required…
(9) Liquid Assets and/or availability of credit facilities up to 25 percent of the value of the contract. (Bank
Certificate). issued by any Nationalized/scheduled bank for Current Calendar Year.
Submission of Bank Certificate is mandatory. The Bank Certificate issued by any
Nationalized/Scheduled Bank shall clearly indicate availability of liquid assets and/or credit
facilities equal to minimum 25% of the estimated contract value. Bids not supported by the
required Bank Certificate shall be treated as non-responsive.
(10) Work Experience (Lift Irrigation Scheme With 50 Hac)with form 3A
INSTRUCTIONS TO
Section 1: Instructions to Bidders
Table of Clauses
Page No. Page No.
A. General D. Submission of Bids
1. Scope of Bid 19. Sealing & Marking of Bids
2. Source of Funds 20. Deadline for Submission of
3. Eligible Bidders 21. Late Bids
4. Qualification of the 22. Modification and
Bidder Withdrawal of Bids
5. One Bid per Bidder
6. Cost of Bidding E. Bid Opening and Evaluation
7. Site Visit 23. Bid Opening
B. Bidding Documents 25. Clarification of Financial
8. Content of Bidding 26. Examination of Bids and
Documents Determination of
9. Clarification of Bidding 27. Correction of Errors
10. Amendment of Bidding 28. Deleted
29. Evaluation and Comparison
of Financial Bids
C. Preparation of Bids 30. Deleted
11. Language of Bid
12. Documents Comprising F. Award of Contract
13. Bid Prices 31. Award Criteria
14. Currencies of Bid and 32. Employer’s Right to Accept
Payment any Bid and to Reject any
15. Bid Validity 33. Notification of Award and
Signing of Agreement
16. Bid Security 34. Performance Security
17. Alternative Proposals By 35. Advance Payment and
Bidders Security
18. Format and Signing of Bid 36. Dispute Review Expert
37. Corrupt or Fraudulent
1. Scope of Bid
1.1 The Employer (Named in Appendix to ITB) invites bids for the Construction of works (as
defined in these documents and referred to as ‘the works”) detailed in the table given in IFB.
The bidders may submit bids for any or all of the works detailed in the table given in IFB.
1.2 The successful bidder will be expected to complete the works by the intended completion
date specified in the Contract data.
1.3 Throughout these bidding documents, the terms ‘bid’ and ‘tender’ and their derivatives
(bidder/ tenderer, bid / tender, bidding/ tendering, etc.) are synonymous.
2. Source of Funds
2.1 The expenditure on this project will be met from the budget of Govt. of Gujarat / Govt. of
India for centrally sponsored projects.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all eligible bidders.
3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a
statement that the Bidder is neither associated, nor has been associated, directly or
indirectly, with the consultant or any other entity that has prepared the design,
specifications, and other documents for the Project or being proposed as Project Manager
for the Contract. A firm that has been engaged by the Employer to provide consulting
services for the preparation or supervision of the works, and any of its affiliates, shall not
be eligible to bid.
4. Qualification of the Bidder
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a
preliminary description of the proposed work method and schedule, including drawings and
charts, as necessary. The proposed methodology should include a program of construction
backed with equipment planning and deployment duly supported with broad calculations
and quality assurance procedures proposed to be adopted justifying their capability of
execution and completion of work as per technical specifications, within stipulated period
#4.5 QUALIFICATION CRITERIA:
(Applicable for the works which require Pre Qualification) As Per GoG NWRWS & K
Department’s Circular No. Paracha/1097/1397(11)/pa.fa./MICELL(k-1) Dated 18/01/2018
4.5.1 Qualification will be based on Applicant’s meeting all the following minimum pass/ fail
criteria regarding the Applicant’s general and particular experience, personnel and
equipment capabilities and financial positions, as demonstrated by the applicant’s responses
in the forms attached to the letter of application ( specified requirement for joint ventures
are given under para 4.6 below ) Subcontractors experience and resources shall not be taken
in to account in determining the applicants compliance with the qualifying criteria
To qualify for more than one contract, the applicant must demonstrate having experience
and resources sufficient to meet the aggregate of the qualification criteria for each contract
given in paragraphs 4.5.4, 4.5.5 and 4.5.9 below
4.5.2 Base year and Escalation
The base year shall be taken as Current financial year
Following enhancement factors will be used for the costs of works executed and the financial
figure to a common base value for works completed in India.
Year Financial Year Multiplying factor
Base year of inviting tender 2025-2026
Applicant should indicate actual figures of costs and amount for the works executed
by them without accounting for the above-mentioned factors.
In case the financial figures and value of completed works are in foreign currency
the above enhanced multiplying factors will not be applied. Instead, the current market
exchange rate (State Bank of India BC Selling rate as on the last date of submission of the
bid) will be applied for the purpose of conversion of the amount in foreign currency into
4.5.3. General Experience.
The Applicant shall meet with the following minimum criteria: (a) Achieved a minimum annual
financial turnover of Rs.------ Crore for works in progress and completed in all classes of civil
engineering construction works in any one year, over the last five financial years. (b) Experience
in successfully completing or substantially completing at least one contract of similar work -----
--- crore within the last five financial years. The works may have been executed by the applicant
as prime contractor or as a member of a joint venture or as a nominated sub-contractor. As
subcontractor, he should have acquired the experience of execution of all major items of works
under the proposed contract. In case a project has been executed by a joint venture, weight
towards experience of the project would be given to each joint venture in proportion to their
financial participation in the joint venture if work executed jointly otherwise as per the scope of
work define in Joint Venture agreement. Substantially completed works means those works
which are at least 90 % completed as on the date of submission (i.e. gross value of work done up
to the last date of submission is 90 % or more of the original contract price) and continuing
satisfactorily. For these, a certificate from the employers shall be submitted along with the
application incorporating clearly the name of the work, contract value, billing amount, date of
commencement of works, satisfactory performance of the contractor and any other relevant
information. The experience certificate should be signed by the officer not below the rank of EE)
(c) Contractor should have completed construction work of 1 Nos. of lift Irrigation Scheme of
command Area 50 Ha or more within last five finical years. Certificate of competent authority
of work done with detail shall be produced.
4.5.4. Personnel Capabilities.
Availability for his work of personnel with adequate experience as required; as per
4.5.5. Equipment Capabilities
Based on the studies carried out by the Engineer, the minimum suggested major equipment
to attain the completion of works in accordance with the prescribed construction schedule
are shown in the Appendix.
The bidders should, however, undertake their own studies and furnish with their bid,
a detailed construction planning and methodology supported with layout and necessary
drawings and calculations to allow the employer to review their proposals. The numbers,
types and capacities of each plant/equipment shall be shown in the proposals along with the
cycle time for each operation for the given production capacity to match the requirements.
4.5.6. Financial Position
The Applicant shall provide documentary evidence in the form of a Bank Certificate issued
by any Nationalized/Scheduled Bank certifying that the bidder has access to, or availability
of, liquid assets and/or uncommitted credit facilities amounting to not less than 25% of the
estimated contract value. Submission of this Bank Certificate is mandatory for qualification.
4.5.7. The audited balance sheets for the last five years should be submitted, which must demonstrate
the soundness of the applicant’s financial position, showing long – term profitability including
an estimated financial projection for the next two years If necessary, the employer will make
inquiries with the applicant’s bankers.
4.5.8. Litigation History
The Applicant should provide accurate information on any litigation or arbitration resulting
from contracts completed or under execution by him over the last five financial years. A
consistent history of awards against the Applicant or any partner of a joint venture may result
in failure of the applicant.
4.5.9. Disqualification
Even though the applicants meet the above criteria, they are subject to be disqualified if
Made misleading or false representation in the forms, statements submitted, and / or Record
of poor performance such as abandoning the work, rescinding of contract for which the
reasons are attributable to the non – performance of the contractor; consistent history of
litigation awarded against the applicant or financial failure due to bankruptcy. The
rescinding of contract of a joint venture on account of reasons other than non – performance,
such as Most Experienced partner of joint venture pulling out, court directions leading to
breaking up of a joint venture before the start of work, which are not attributable to the poor
performance of the contractor will, however, not affect the qualification of the individual
4.5.10. The bidder who have applied for corporate Debt Restructuring (CDR) / facing recovery
proceedings from financial institutions / facing winding up processing / those under BIFR in the
last 5 financial year shall be considered for bid qualification. However if the bank / financial
institution has accepted the proposal of debt restructuring on or before the last date of online
submission, the same shall be considered for further evaluation. An affidavit by bidder along with
certificate from bank must be produced in such cases. In case of Joint Venture agreement, this
provision shall be applicable for both lead partner and JV partner.
#4.6 JOINT VENTURE: (Maximum 3 Members i.e. 1 Lead & 2 Others)
(Applicable only for estimated project cost of 50 Crore and above)
4.6.1. As per Pre-qualification Criteria refers same documents
(a) Following are the minimum qualification requirements:
(i) The lead partner shall meet not less than 50 percent of all criteria given in para 4.5.3 & 4.5.6 above. The
joint venture must collectively satisfy the criteria of para 4.5.3 & 4.5.6 above. The experience of the
other joint venture partners shall be considered if it is not less than 30 percent of the qualifying criteria
in para 4.5.3 & 4.5.6 above.
(ii) Individually each member must satisfy the requirements of para 4.5.7 & 4.5.8 above.
(b) Bid shall be signed so as to legally bind all partners, jointly and severally, and shall be submitted with a
copy of the joint venture agreement providing the joint and several liabilities with respect to the contract.
4.6.2. Qualification of a joint venture does not necessarily qualify any of its partners individually or
as a partner in any other joint venture. In case dissolution of a joint venture, each one of the
constituent firms may qualify if they meet all the qualification requirements, subject to the
written approval of the Employer.
4.7. Bid Capacity.
Applicants who meet the minimum qualification criteria will be qualified only if their
available bid capacity at the expected time of bidding is more than the total estimated cost
of the works. The available bid capacity will be calculated as under:
Assessed Available Bid Capacity = ( A*N*2-B), where
A = Maximum value of work executed in any one year during the last five years (updated
to the price level of the year indicated in appendix) taking into account the completed
as well as works in Progress.
B = Value at current price level of the existing commitments and ongoing works to be
completed during the next (period of completion of work for which bids are invited);
N = Number of years prescribed for completion of the works for which the bids are invited.
Note :- In Case of joint venture, the available bid capacity will be applied for each
partner to the extent of his proposed participation in the execution of the
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be
disqualified if they have:
- Made misleading or false representation in the forms, statements and Attachments
the submitted in proof the qualification requirements; and / or
Record of poor performance such as abandoning the works, not properly completing the
contract, inordinate delay in completion, litigation history, or financial failures etc.; and/ or
- Participated in the previous bidding for the same work and had quoted unreasonably
high bid prices and could not furnish rational justification to the employer.
5. One bid per bidder
5.1. Each bidder shall submit only one bid for one package. A bidder who submits or participates
in more than one bid (other than as a subcontractor or in cases of alternatives that have been
permitted or requested) will cause all the proposals with the bidder’s participation to be
6. Cost of Bidding
6.1. The bidder shall bear all costs associated with the preparation and submission of his Bid,
and the Employer will in no case be responsible and liable for those costs.
7.1. The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and examine
the Site of work and its surrounding and obtain all information that may be necessary for
preparing the Bid and entering into a contract for construction of the Works before
submission of their bids.
The costs of visiting the site shall be at the Bidder’s own expense.
B. BIDDING DOCUMENTS
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed below and addenda issued
in accordance with Clause 10:
Section Particulars Volume No.
- Invitation for Bids
1 Instructions to Bidders I
2 Qualification Information, and other forms
3 Conditions of Contract
4 Contract Data
5 Technical Specifications II
6 Form of Bid III
7 Bill of Quantities
8 Securities and other forms
10 Documents to be furnished by bidder V
8.2. Volumes I, II, III and IV are available online and documents to be furnished by the bidder
in compliance to section 2 will be prepared by him and furnished as Volume- V in two
parts (refer clause 12).
8.3. The bidder is expected to examine carefully all instructions, conditions of contract, contract
data, forms, terms, technical specifications, bill of quantities, forms, Annexes and drawings
in the Bid Document. Failure to comply with the requirements of Bid Documents shall be
at the bidder’s own risk. Pursuant to clause 26 hereof, bids which are not substantially
responsive to the requirements of the Bid Documents shall be rejected.
9. Clarification Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents may notify the
Employer in writing or through E-mail at the Employer’s address indicated in the
invitation to bid. The Employer will respond to any request for clarification which he
received earlier than 15 days prior to the deadline for submission of bids. Employer’s
response will be published on website including a description of the enquiry but without
identifying its source.
9.2. Pre-bid meeting
9.2.1. The bidder or his official representative is invited to attend a pre-bid meeting which will
take place at the address, venue, time and date as indicated in the appendix.
9.2.2. The purpose of the meeting will be to clarify issues and to answer questions on any matter
that may be raised at that stage.
9.2.3. The bidder shall be required to submit any questions in writing or e-mail to reach the
Employer not later than 03 days before the meeting.
9.2.4 Minutes of the meeting, including the question raised (Without identifying the source of
enquiry) and the responses given will be published without delay on the tender website
i.e. www.nprocure.com. Any modification of the bidding documents listed in sub-Clause
8.1 which may become necessary as a result of the pre-bid meeting shall be made by the
Employer exclusively through the issue of an Addendum pursuant to Clause 10 and not
through the minutes of the pre-bid meeting.
9.2.5. Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
10. Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding
documents by issuing addenda.
10.2. Any addendum thus issued shall be part of the bidding documents. The Employer will
assume no responsibility for the same.
10.3. To give prospective bidders reasonable time in which to take an addendum into account
in preparing their bids, the Employer may, at his discretion, extend as necessary the
deadline for submission of bids, in accordance with Sub-Clause 20.2 below.
C. PREPARATION OF BIDS
11. Language of the Bid
11.1 All documents relating to the bid shall be in the English language.
12. Documents Comprising the Bid
12.1. The bid be submitted by the bidder as Volume V of the bid document (refer Clause 8.1)
shall be in two separate parts:
Part I shall be named “Technical Bid” and shall comprise
(i) Bid Security in the form specified in Section
(ii) Qualification Information and supporting documents as specified in Section
(iii) Certificates, undertakings, affidavits as specified in Section
(iv) Any other information pursuant to Clause 4.5 of these instructions
(v) Undertaking that the bid shall remain valid for the period specified in Clause
Part II shall be named “Financial Bid” and shall comprise
(i) Form of Bid as specified in Section
(ii) Priced Bill of Quantities for items specified in Section
12.2. The Bidder shall submit the details / information pertaining to each part i.e. technical as
well as financial and must be submitted online only.
12.3. Following documents will be deemed to be part of the bid.
Section Particulars Volume No.
Invitation for Bids (IFB)
1 Instruction to Bidders Volume I
3 Conditions of Contract
4 Contract Data
5 Specifications Volume II
9 Drawings Volume IV
13.1 The Contract shall be for the whole works as described in Sub-Clause 1.1, based on the
priced Bill of Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line item total (both in figures and words) for all
items of the Works described in the Bill of Quantities along with total bid price
(Both in figures and words). Items for which no rate or price is entered by the bidder will
not be paid for by the Bill of Quantities.
13.3 All duties, taxes, and other levies except GST payable by the contractor under the contract,
or for any other cause shall be included in the rates, prices and total Bid Price submitted by
the Bidder. (GST will be paid extra)
13.5 The rates and prices quoted by the bidder are subject to adjustment during the performance
of the Contract in accordance with the provisions of Clause 47 of the Condition of Contract
(Irrespective of the time limit and Bid Amount)
14. Currencies of Bid and Payment
14.1 The unit rates and the prices quoted by the bidder shall be entirely in Indian Rupees. All
payments shall be made in Indian Rupees.
15. Bid Validity
15.1 Bids shall remain valid for a period of not less than 120 days after the deadline date for bid
submission specified in Clause
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may
request that the bidders may extend the period of validity for a specified period. A bidder
may refuse the request without forfeiting his bid security. A bidder agreeing to the request
will not be required or permitted to modify his bid, but will be required to extend the validity
of his security for a period of the extension, and in compliance with Clause 16 in all respects.
#16. Bid Security
16.1. The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in column
4 of the table of IFB for this particular work. This Bid security shall be in favor of
Employer as named in Appendix and may be in one of the following forms;
a. Bank Guarantee from any scheduled Indian bank, in the format given in Volume III.
(Bank Guarantee is applicable only for Bid Estimated Amount of 01 Crore and above)
and Bank Guarantee of Schedule and Private Banks shall be considered as per GoG Finance
Department’s Circular No. FD/MSM/e- file/4/2023/0057/D.M.O. Date 21/04/2023 or as per
their latest amendment.
b. Fixed Deposit Receipt issued by any Scheduled Indian Bank or a foreign Bank
approved by the Reserve Bank of India.
# A Valid Bid Security / EMD Exemption Certificate issued by (1) Road & Building
Department or (2) Narmada Water Resources, Water Supply and Kalpsar Department of
Govt of Gujarat. Exemption Certificate is applicable only when Registration Certificate
of Appropriate Class and Category of Approved Contractors is required as eligible
criteria of bidder.
16.2. Bank guarantees (and other instruments having fixed validity) issued as surety for the bid
shall be valid for 45 days beyond the validity of the bid i.e. total validity of 120 + 45 =
16.3. Any bid not accompanied by an acceptable Bid Security and not secured as indicated in
Sub-Clauses 16.1 and 16.2 above shall be rejected by the Employer as non-responsive.
16.4. The Bid Security of unsuccessful bidders will be returned within 28 days of the end of the
bid validity period specified in Sub-Clause
16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed the
Agreement and furnished the required Performance Security.
16.6. The bid Security may be forfeited
(a) If the Bidder withdraws the bid after Bid opening during the period of Bid validity.
(b) If the Bidder does not accept the correction of the Bid Price, if any or
(c) In the case of a successful Bidders, if the Bidder fails the specified time limit to
(i) Sign the Agreement; or
(ii) Furnish the requirement Performance Security.
(d) #If found necessary, the bidder will be intimated for negotiation, He will be intimated
maximum three times within the validity period for negotiation, If contractor does not
respond in time, his Bid Security (EMD) will be forfeited and his tender will be rejected.
Punitive action will be taken on such contractors. (As per GoG R&B Dept’s Gr. No.
17. Alternative Proposals by Bidders.
17.1. Bidders shall submit offers that fully comply with the requirements of the bidding
documents, including the conditions of contract (including mobilization advance or time for
completion), basic technical design as indicated in the drawing and specifications.
Conditional offers or alternative offers will not be considered further in the process of
tender evaluation.
18. Format and Signing of Bid
18.1. The Bidder shall prepare documents comprising the bid as described in Clause 12 of these
Instructions to bidder as the “Technical Bid “and “Financial Bid” in separate parts to be
D. SUBMISSION OF BIDS
20. Deadline for Submission of the Bids
20.1. Complete Bids must be received online by the Employer at the tender website specified
above not later than the date indicated in appendix.
20.2. The Employer may extend the deadline for submission of bids by issuing an amendment in
accordance with Clause 10, in which case all right and obligation of the Employer and the
bidders previously subject to the original deadline will then be subject to the new deadline.
22. Modification and Withdrawal of Bids
22.1. Bidders may modify or withdraw their bids online before the deadline prescribed in Clause
20 or pursuant to Clause
22.3. No bid shall be modified or withdrawn after the deadline for submission of Bid.
22.4. Withdrawal or modification of a bid between the deadline for submission of bids and the
expiration of the original period of bid validity specified in Clause 15.1 above or as
extended pursuant to Clause 15.2 may result in the forfeiture of the Bid security pursuant
E. BID OPENING AND EVALUATION
23. Bid Opening
23.1 The Employer will open all the Bids received including modifications made pursuant to
Clause 22, in the presence of the Bidders or their representatives who choose to attend at
time, date and the place specified in Appendix in the manner specified in Clauses 20 and
23.3, In the event of the specified date of Bid opening being declared a holiday for the
Employer, the Bids will be opened at the appointed time and location on the next working
23.3. The “Technical Bid” shall be opened. The amount, form and validity of the bid security
furnished with each bid will be announced. If the bid security furnished does not conform to
the amount and validity period as specified in the invitation for bid (ref. Column 4 and
paragraph 3), and has not been furnished in the form specified in Clause 16, the technical
bid will not be opened.
23.4. (i) Subject to confirmation of the bid security by the issuing Bank, the bids
accompanied with valid bid security will be taken up for evaluation with respect to
the Qualification information and other information furnished in part I of the bid
pursuant to Clause 12.1.
(ii) If required, the bidder will be asked in writing to clarify his Qualification Documents
with respect to any required clarification.
(iii) The bidders will respond in not more than 7 days of issue of the clarification letter.
(iv) Immediately (usually within 3 or 4 days), on receipt of these clarification the
Evaluation Committee will finalize the list of responsive bidders whose financial
bids are eligible for consideration.
23.6 At the time of opening of “Financial Bid”, the names of the bidders were found responsive
in accordance with Clause 23.4(iv) will be announced. The bids of only these bidders will
be opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid,
be opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid,
any discount and such other details as the Employer may consider appropriate, will be
announced by the Employer at the opening.
23.7 the time of opening of “Financial Bid”, the names of the bidders were found responsive in
accordance with Clause 23.4(iv) will be announced. The bids of only these bidders will be
opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid, any
opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid, any
discount, and such other details as the Employer may consider appropriate, will be
announced by the Employer at the opening.
23.8 In case bids are invited for more than one package, the order for opening of the “Financial
Bid” shall be in order of Estimated amount of Bids from highest to lowest.
23.9 The Employer shall prepare minutes of the Bid opening, including the information
disclosed to those present in accordance with Sub-Clause 23.6.
24.1 Information relating to the examination, clarification, evaluation, and comparison of Bids
and recommendations for the award of a contract shall not be disclosed to Bidders or any
other persons not officially concerned with such process until the award to the successful
Bidder has been announced. Any effort by Bidder to influence the Employer’s processing
of Bids or award decisions may result in the rejection of his Bid.
25. Clarification of Financial Bids
25.1. To assist in the examination, evaluation, and comparison of Bids, the Employer may, at his
discretion, ask any Bidder for clarification of his Bid, including breakdowns of unit rates.
The request for clarification and the response shall be in writing or by e- mail, but no change
in the price or substances of the Bid shall be sought, offered, or permitted except as required
to confirm the correction of arithmetic errors discovered by the Employer in the evaluation
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to
his Bid opening to the contract is awarded. If the Bidder wishes to bring additional
information to the notice of the Employer, it should do so in writing.
25.3. Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid
comparison or contract award decision may result in the rejection of the Bidders’ bid.
26. Examinations of Bids and Determination of Responsiveness
26.1 During the detail evaluation of "Technical Bid", the Employer will determine whether each
Bid (a) meets the eligibility criteria defined in Clause 3 and 4; (b) has been properly signed;
(c) is accompanied by the required securities and; (d) is substantially responsive to the
requirements of the Bidding document.
During the detailed evaluation of the “Financial Bid”, the responsiveness of the bids will be
further determined with respect to the remaining bid conditions, i.e., priced bill of quantities,
technical specifications, and drawings.
26.2 A substantially responsive “Financial Bid” is one which confirms all the terms, conditions
and specifications of bidding documents, without material deviation or reservation. A
material deviation or reservation is one (a) which affects in any substantial way the scope,
quality, or performance of the Works; (b) which limits in any substantial way, inconsistent
with the Bidding documents, the Employer’s rights or the Bidder’s obligations under the
Contract; or (c) whose rectification would affect unfairly the competitive position of other
Bidders presenting substantially responsive Bids.
26.3 If a “Financial Bid” is not substantially responsive, it will be rejected by the Employer,
and may not subsequently be made responsive by correction or withdrawal of the non-
conforming deviation or reservation.
29. Evaluation and Comparison of Financial Bids
29.1. The Employer will evaluate and compare only the Bids determined to be substantially
responsive in accordance with Sub-Clause 26.2.
29.3. The Employer reserves the right to accept or reject any variation or deviation. Variation and
deviations and other factors, which are in excess of the requirements of the Bidding
documents or otherwise result in unsolicited benefits for the Employer, shall not be taken
in to account in Bid evaluation.
29.4. The estimated effect of the price adjustment conditions under Clause 47 of the Conditions
of Contact, during the period of implementation of the Contract, will not be taken in to
account in Bid evaluation.
29.5. If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer’s
estimate of the cost of work to be performed under the contract the Employer may require
the Bidder to produce detailed consistency of those prices with the construction methods
and schedule proposed. After evaluation of the price analyses, the Employer may require
that the amount of the performance security set forth in Clause 34 be increased at the
expense of the successful /bidder to a level sufficient to protect the Employer against
financial loss in the event of default of the successful Bidder under the Contract.
29.6. A bid which contains several items in the bill of Quantities which are unrealistically priced
low and which cannot be substantiated satisfactorily by the bidder may be rejected as non-
F. AWARD OF CONTRACT
31. Award Criteria
31.1. Subject to Clause 32, the Employer will award the contract to the Bidder whose Bid has
been determined.
(i) to be substantially responsive to the Bidding documents and who has offered the
lowest evaluated Bid Price; and
(ii) to be within the available bid capacity adjusted to account for his bid price which is
the lowest evaluation in any of the packages opened earlier than the one
In no case, the contract shall be awarded to any bidder whose available bid capacity
is less than the evaluated bid price, even if the said bid is the lowest evaluated bid. The
contract will in such cases be awarded to the next lowest bidder at his evaluation bid price.
32. Employer’s Right to Accept any Bid and to Reject any or all Bids
32.1. Notwithstanding Clause 31, the Employer reserves the right to accept or reject any Bid, and
to cancel the Bidding process and reject all Bids, at any time prior to the award of contract,
without thereby incurring any liability to the affected bidder or Bidder or any obligation to
inform the affected Bidder or Bidders of the grounds for the Employer’s action.
33. Notification of Award and Signing of Agreement
33.1. The Bidder whose Bid has been accepted will be notified of the award by the Employer
prior to expiration of the Bid validity period by cable, telex or facsimile confirmed by
registered letter. This letter (hereinafter and in the condition of contract called the “Letter
of Acceptance”) will state the sum that the Employer will pay the Contractor in
consideration of the execution, completion, and maintenance of the Works by the Contractor
as prescribed by the Contract (hereinafter and in the Contract called the “Contract Price”).
33.2 The notification of award will constitute the formation of the contract, subject only to the
furnishing of a performance security in accordance with the provisions of Clause.
33.3. The Agreement will incorporate all agreements between the Employer and the successful
Bidder. It will be signed by the Employer and to the successful Bidder, within 28 days
following the notification of award along with the Letter of Acceptance. Within 21 days of
receipt, the successful Bidder will sign the Agreement and deliver it to the Employer.
33.4. Upon the furnishing by the successful Bidder of the Performance Security, the Employer
will promptly notify the other Bidders that their Bids have been unsuccessful.
34. Performance Security
34.1. (A) Within 10 (Ten) days of receipt of Letter of Acceptance, the successful Bidder shall
furnish to the Employer an irrevocable and unconditional guarantee from a Bank in the
form set forth in Section 8 (the “Performance Security”) for an amount equal to 5%
(five percent) of its Contract Price. In case of bids mentioned below, the successful
Bidder, along with the Performance Security,
shall also furnish to the Authority an irrevocable and unconditional guarantee from a
Bank in the same form given at Section 8 towards an Additional Performance Security
(The “Additional Performance Security”) for an amount calculated as under:
(a) If the Contract Price offered by the Selected Bidder is lower than 10% but upto
20% of the Estimated Project Cost, then the Additional Performance Security
shall be calculated @ 20% of the difference in the (i) Estimated Project Cost
(as mentioned in Bid Document) - Minus 10% of the Estimated Project Cost
and (ii) Contract Price offered by the selected Bidder.
(b) If the Contract Price offered by the Selected Bidder is lower than 20% of the
Estimated Project Cost, then the Additional Performance Security shall be
calculated @ 30% of the difference in the (i) Estimated Project Cost (as
mentioned in Bid Document) - Minus 10% of the Estimated Project Cost and
(ii) Contract Price offered by the selected Bidder.
(c) This Additional Performance Security shall be treated as part of the
Performance Security.
(B) The Performance Security shall be valid beyond 60(sixty) days of the Defects Liability
Period and the Additional Performance Security shall be valid beyond 28 (twenty-
eight) days of Project Completion Date.
34.2. If the performance security is provided by the successful Bidder in the form of a Bank
Guarantee, it shall be issued either (a) at the Bidder’s option, by a Nationalized/Scheduled
Indian bank or (b) by a foreign bank located in India and acceptable to the Employer. As
per GoG Finance Department’s Circular No. FD/MSM/e-file/4/2023/0057/D.M.O. Date
21/04/2023 or as per their latest amendment.
34.3. Failure of the successful Bidder to comply with the requirement of Sub-Clause 34.1 shall
constitute sufficient grounds for cancellation of the award and forfeiture of the Bid
35 Advance Payment and Security
35.1 The Employer will provide an Advance payment on the Contract Price as stipulated in the
Conditions of Contract, subject to maximum amount, as stated in the Contract Data.
37. Corrupt of Fraudulent Practices
37.1 The Employer will reject a proposal if it determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in completing for the contract in
question and will declare the firm ineligible, either indefinitely or for a stated period of
time, to be awarded a contract with National Highways Authority of India/ State PWD and
any other agencies, if it at any time determines that the firm has engaged in corrupt or
fraudulent practices in completing for the contractor, or in execution.
37.2 Furthermore, Bidders shall be aware of the provision stated in Sub- Clause 59.2 of the
Conditions of Contract.
APPENDIX TO ITB
Clause Reference
With respect to
1. The Name of the Employer is EXECUTIVE ENGINEER, DAHOD IRR. [ Cl.1.1]
2. The last five financial years.
3. This Annual Financial Turnover Amount is Rs. 2.15 crore [Cl.4.5.3 (a)]
4. Value of Work is Rs.
6. The cost of electric work is Rs.
7. The cost of water supply / sanitary works is Rs.
8. Liquid assets and / or availability of credit facilities is Rs. 53,10,000 [Cl.4.5.6 ]
9. Price level of the financial year 2025-2026 [Cl. 4.5.2]
10. The pre-bid meeting will take place at Office of the Executive [Cl. 9.2.1]
Engineer, Dahod Irrigation Division, Dahod.
11. The technical Bid will be opened at the office of the EXECUTIVE
ENGINEER, DAHOD IRR. DN DAHOD on date As stated in Online
NIT, at As stated in Online NIT.
12. Address of the Employer: Office of the Executive Engineer, Dahod
Irrigation Division,Dahod Gujarat
14. The bid should be submitted latest by As stated on online [Cl. 20.1 & 20.2]
15. The bid will be opened at EXECUTIVE ENGINEER, DAHOD IRR. DN, [Cl. 23.1 ]
DAHOD As stated on online NIT
16. The Bank Draft in favor of EXECUTIVE ENGINEER, DAHOD IRR. DN,
18. Escalation factors (for the cost of works executed and financial figure [Cl.4.5.2]
to a common base
value) for works completed
Year Financial Year Multiplying factor
Base year of inviting tender 2025-2026
#LIST OF KEY PLANT & EQUIPMENT TO BE DEPLOYED ON CONTRACT
[Reference CL. 4.5.5]
The contractors shall also may give a list of machineries in his possession and which they propose
to use on the work.
Sr. Plant or Location Age of Make Capacity Approximate Remark
No. Machinery Machinery Value
List of Key Personnel to be deployed on Contract Work (Reference Cl.
# Employment of a qualified site Engineer by the Contractor.
The Contractor shall employ full-time technically qualified staff during the execution of this work
1. Two graduate Civil Engineers and three diploma Civil Engineers when cost of the work to be
executed is more than Rs.50 lakhs.
2. One graduate & two Diploma, Civil Engineers when the cost of the work to be executed is
more than Rs.15 lakhs but less than Rs.50 lakhs.
3. Minimum Two Diploma Civil Engineer when the cost of work is less than Rs.15 lakhs but
more than Rs.5 lakhs.
4. Minimum One Diploma Civil Engineers for the work when the cost of work to be executed
is less than Rs. 5 lakhs. The Engineer so employed for the Government work must have
sufficient experience to handle the work independently. Such an Engineer shall have to stay
at the site of work and he shall not be entrusted with other duty except this work.
In case the contractor or partner of the contractor firm is a Civil Graduate Engineer,
Employment of a separate Engineer will not be necessary provided that the Engineer partner
himself attends the execution of the work on the site.
Within 15 days of issue of work-order the Contractor will have to furnish to the Deputy
Executive Engineer-in-charge of the work the Name, Qualifications, copy of marksheet, Color
Photograph and the appointment order issued such engineers engaged for this contract work.
If 15 days after issue of work order such designated Site Engineers do not resume or do not
remain present on site of work, the recovery at the rate of Rs.15,000-00 per month per
Engineer will be made from the bills/deposit/dues of the contractor. Such recovery shall be
non-refundable.
QUALIFICATION INFORMATION
QUALIFICATION INFORMATION
The information to be filled in by the Bidder in the following pages will be used for the
purpose of post qualification as provided for in Clause 4 of the Instruction to Bidders. This
information will not be incorporated in the Contract.
1. For Individual Bidders
1.1 Constitution or legal status of Bidder
Place of registration
Principal place of business
Power of attorney of signatory of Bid
1.2 Total value of Civil engineering constructions
performed in the last five years 20
(in Rs. Lakhs) 20
15.2.1 Work performed as prime contractor, work performed in the past as a nominated sub-
contractor will also be considered the sub-contract involved execution of all main items of
work described in the bid documents, provided further that all other qualification criteria
are satisfied (in the same name) on works of a similar nature over the last five years** and
in current year before the submission of the bid.
Project Name of Description Contract Value of Date Stipulated Actual date Remark
Name the of work No. contract of period of of explaining
Employer (Rs. issue completion completion* reasons for
Crore) of delay &
order Completed
*Attach certificate(s) from the Engineer(s)in-charge
** Immediately preceding the financial year in which bids are received.
#1.3.2 Quantities of work executed as prime contractor, work performed, in the past as a nominated
sub-contractor, will also be considered provided the sub-contract involved execution of all
main items of work described in the bid document, provided, further that all other
qualification criteria are called (in the same name and style) in the last five years** and in
current year before the submission of the bid.
*To be modified as per the nature and scope of work
Year Name Name of Quantity of work performed (Cum/MT) Remarks*
of the the Cement Masonry Earth Bituminous (indicate
Work Employer Concrete ITEM 2 Works Work contract Ref)
(Including ITEM ITEM
1.4 Information on Bid Capacity (works for which bids have been submitted and works which
are yet to be completed) as on the date of this bid.
(A) Existing commitments and on-going works:
Description Place Contract Name & Value Stipulated Value of Anticipated
of works & No. Address Contract Period of Works* of
State of (Rs. Cr) Completion remaining completion
*Attach certificate (s) from the Engineer(s) in-charge
** Immediately preceding the financial year in which bids are received.
1.5 Availability of key items of Contractors Equipment for carrying out the works (Ref.
Clause 4.5.5). The Bidder should list all the information requested below.
Item of Requirement Availability Proposals Remarks
Equipment NO Capacity Owned/ Nos/. Age/ (from
Leased to be Capacity Conditions whom to
1.6 Qualifications and experience of key personnel required for administration and execution
of the contract. Attach biographical data. Refer also to Sub Clause 9.1 of the Conditions of
Position Name Qualification Year of Year of
Experience experience in
(General) the proposed
Project Manager
1.7 Proposed sub-contract and firms involved
Sections of the Value of Sub- Sub-Contractor Experience in
works Contractor (Name & similar work
Attach copies of certificates on possession of valid license for executing water supply/
sanitary work/ building electrification works.
1.8 Financial reports for the last five years: balance sheets, profit and loss statements, auditors’
reports (in case of companies/corporations), etc. List them below and attach copies.
1.9 Evidence of access to financial resources to meet the qualification requirements: cash
in hand, lines of credit, etc. List them below and attach copied documents.
1.10 Name, address, and telephone, telex, and fax numbers of the Bidders bankers who may
provide references if contacted by the Employer.
1.11 Information on Litigation history in which the Bidder is involved.
Other Party Employer Cause of Amount Remarks
(ies) Dispute Involved showing
1.12. Statement of compliance under the requirements of Sub Clause 3.2 of the instruction to
Bidders. (Name of Consultant engaged for project preparations is * ................................. )
1.13 Proposed work method and schedule. The Bidder should attach descriptions, drawings and
charts as necessary to comply with the requirements of the Bidding documents. (Refer ITB
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the
requirements of Clause 4 of the Instructions to the Bidders, if applicable.
(ii) Undertaking
* Fill the name of Consultant
SAMPLE FORMAT FOR EVIDENCE OF ACCESS
TO OR AVAILABILITY OF CREDIT FACILITIES
(CLAUSE 4.5.6 OF
This is to certify that M/s. is a reputed company
with a good financial standing.
If the contract for the work, namely is awarded to the
above firm, we shall be able to provide overdraft/credit facilities to the extent of
Rs. to meet their working capital requirements for executing the above
during the contract period.
Senior Bank Manager
Address of the Bank
1. I, the undersigned, do hereby certify that all the statements made in the required
attachments are true and correct.
2. The undersigned also hereby certifies that neither our firm M/s.
have not abandoned any work of
Government of Gujarat/Government of India/any Board or Corporation under
Government of Gujarat/Government of India nor any contract awarded to us for such
works have been rescinded, during last five years prior to the date of this bid.
3. The undersigned hereby authorize(s) and request (s) any bank, person, firm or
corporation to furnish pertinent information deemed necessary and requested by the
Department to verify this statement or regarding any (our) competence and general
4. The Undersigned understands and agrees that further qualifying information may be
requested, and agrees to furnish any such information at the request of the Department/
Project implementing agency.
(Signed by an Authorized Officer of the Firm)
Title of Officer
I, the undersigned do hereby undertake
..would invest a minimum cash up to 25% of the value of the work during implementation of the
(Signed by an Authorized officer of the firm)
Title of officer
CONDITIONS OF CONTRACT
Conditions of Contract
Table of Contents
A General Page D. Cost Control
1 Definitions 37 Bill of Quantities
2 Interpretation 38 Changes in the Quantities
3 Language and Law 39 Variations
4 Engineer’s Decisions 40 Payments for Variations
5 Delegations 41 Cash Flow Forecasts
6 Communications 42 Payment Certificates
7 Sub-Contractors 43 Payments
8 Other Contractors 44 Compensations Events
9 Personnel 45 Tax
10 Employer’s & Contractor Risk 46 Currencies
11 Employers Risks 47 Price Adjustment
12 Contractor’s Risk 48 Retention
13 Insurance 49 Liquidated damages
14 Site Investigations Reports 50 Bonus
15 Queries about the Contract 51 Advance Payment
16 Contractors to Construct the works 52 Securities
17 The Works to be Completed By 53 Deleted
the Intended Completion Date
18 Approval by the Engineer 54 Cost of Repair
20 Discoveries E. Finishing the Contract
21 Possession of the Site 55 Completion
22 Access to the Site 56 Taking Over
23 Instructions 57 Final Account
24 Disputes 58 Operating and Maintenance
25 Procedure for Disputes
26 Deleted 59 Terminations
60 Payment upon Terminations
B. Time Control 61 Property
27 Programme 62 Release from Performance
28 Extensions of the Intended
completion date
29 Deleted F.Special Conditions of
30 Delays Ordered by The 63 Labour
Engineer 64 Compliance with labour
31 Management Meetings 65 Arbitration
32 Early Warning
C. Quality Control
33 Identifying Defects
35 Correction of Defects
36 Uncorrected Defects
CONDITIONS OF CONTRACT
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of
Contract but keep their defined meaning.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the
Compensation Events are those defined in Clause 44 hereunder
The Completion Date is the date of completion of the Works as certified by the Engineer
in accordance with Sub Clause
The Contract is the contract between the Employer and Contractor to execute, complete
and maintain the Works till the completion of Defects Liability Period. It consists of
the documents listed in Clause 2.3 below.
The Contract data defines the documents and other information which comprise the
The Contractor is a person or corporate body whose Bid to carry out the Work has been
accepted by the Employer.
The Contractor’s Bid is the completed Bidding document submitted by the Contractor
to the Employer and includes Technical and Financial Bids.
The Contract Price is the price stated in the Letter of Acceptance and thereafter as
adjusted in accordance with the provisions of the Contract.
Days are calendar days: months are calendar months.
The Defects Liability Period is the period named in the Contract Data and calculated
from the Completion Date.
The Employer is the party who will employ the Contractor to carry out the Work.
The Engineer is the person named in the Contract Data (or any other
competent person appointed and notified to the contractor to act in replacement of the
Engineer) who is responsible for supervising the Contractor, administering the Contract,
certifying payments due to the Contractor, issuing and valuing Variations to the Contract,
awarding extensions of time, and valuing the Compensations Events.
Equipment is Contractor’s machinery and vehicles brought temporarily to the site to
construct the Works.
The Initial Contract Price is the Contract Price listed in the Employer’s Letter of
The Intended Completion Date is the date on which it is intended that the
Contractor shall complete the Works. The Intended Completion Date is specified in the
Contract Data. The Intended Completion Date may be revised only by the Engineer by
issuing an extension of time.
Materials are all supplies, including consumables, used by the contractor for incorporation
Plant is any integral part of the work which is to have mechanical, electrical, electronic or
chemical or biological functions.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the Bidding documents and
are factual interpretive reports about the surface and subsurface conditions at the site.
Specifications means the Specifications of the works included in the Contract and any
modification or addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the Contractor shall
commence execution of the works. It does not necessarily coincide with any of the Site
Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with the Contractor to
carry out a part of the work in the Contract which includes work on the Site.
Temporary Works are works designed, constructed, installed, and removed by the
Contractor which are needed for construction or installation of the Works.
A Variation is an instruction given by the Engineer, which varies the Works.
The Works are what the Contract requires the Contractor to construct, install, and turn
over to the Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also
means female or neuter and the other way around. Heading have no significance.
Words have their normal meaning under the language of the Contract unless
specifically defined. The Engineer will provide instructions clarifying queries about
Conditions of Contract.
2.2 If sectional completion is specified in the Contract Data, references in the Conditions
of Contract to the Works, the Completion date, and Intended Completion Date apply
to any Section of the Works (other than references to the Completion Date and
Intended Completion date for the whole works)
2.3 The documents forming the Contract shall be interpreted in the following order of
(2) Letter of Acceptance, notice to proceed with works
(3) Contractor’s Bid
(4) Contract Data
(5) Conditions of Contract including Conditions of Contract
(6) Specifications
(8) Bills of quantities and
(9) Any other document listed in the Contract Data as forming part of the
3. Language and Law
3.1 The language of the Contract and the law governing the Contract are stated in the
4. Engineers Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual
matters between the Employer and the Contractor in the role representing the
5.1 The Engineer may delegate any of his duties and responsibilities to other people
after notifying the Contractor and may cancel any delegation after notifying the
6. Communications
6.1 Communications between parties which are referred to in the conditions are effective
only when in writing. A notice shall be effective only when it is delivered (in terms
of Indian Contract Act).
7. Sub-Contracting
7.1 The Contractor may subcontract any portion of work, up to a limit specified in
contract data, with the approval of the engineer but may not assign the Contract
without the approval of the Employer in writing. Subcontracting shall not alter the
Contractor’s obligations. Sub-contracting of supply or specific items of work is
7.2 The sub-contractor must be registered in appropriate class and category for the part
of work to be subcontracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities and the Employer between the dates given in the Schedule of
other Contractor. The Contractors shall as refer to in the Contract Data, also provide
facilities and services for them as described in the Schedule. The employer may
modify the schedule of other contractors and shall notify the contractor of any such
9.1 The Contractor shall employ the key personnel named in the Schedule of Key
Personnel as referred to in the Contract Data to carry out the functions stated in the
Schedule or other personnel approved by the Engineer. The Engineer will approve
any proposed replacement of key personnel only if their qualifications, abilities, and
relevant experience are substantially equal to or better than those of the personnel
listed in the Schedule.
9.2 If the engineer asks the Contractor to remove a person who is a member of the
Contractor Staff or his work force stating the reasons the Contractor shall ensure that
the person leaves the Site within seven days and has no further connection with the
work in the Contract.
10. Employer’s and Contractors Risks
10.1 The Employer carries the risk which these Contract states are Employer’s risks, and
the Contractor carries the risks which these Contracts states are Contractors risk.
11. Employer’s Risks
11.1 The employer is responsible for the excepted risks which are (a) in so far as they
directly affect the execution of the Works, the risks of war, hostilities, invasion, act
of foreign enemies, rebellion, revolution, insurrection or military or usurped power,
civil war, riot commotion or disorder (unless restricted to the Contractor’s
employees), and contamination from any nuclear fuel or nuclear waste or radioactive
toxic explosive.
12. Contractor’s Risks
12.1 All risks of loss of or damages to physical property and of personal injury and death
which arise during and in consequence of the performance of the Contract other than
the excepted risks are the responsibility of the Contractor.
13.1 The Contractor shall provide, in the joint names of the Employer and the Contractor,
insurance cover from the Start date to the end of the Defects Liability Period, in the
amounts and deductibles stated in the Contract data for the following events which
are due to the Contractor’s risks:
(a) Loss of or damage to the works, Plant and materials,
(b) Loss of or damage to Equipment
(c) Loss of or damages of property (expect the Works, Plant, Materials and
Equipment) in connection with the Contract; and
(d) Personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the Contractor to the
Engineer for the Engineer’s approval before the Start Date. All such insurance shall
provide for compensation to be payable in the types and proportions of currencies
required to rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates required, the
Employer may affect the insurance which the Contractor should have provided and
recover the premiums the Employer has paid from payments otherwise due to the
Contractor or, if no payment is due, the payment of the premiums shall be a debt
13.4 Alterations to the terms of an insurance shall not be made without the approval of
13.5 Both parties shall comply with any conditions of the insurance policies.
14. Site Investigation Report
14.1 The Contractor in preparing the Bid shall rely on any site Investigation reports
referred to in the Contract Data, supplemented by any information available to the
15. Queries about the Contract data
15.1 The engineer will clarify queries on the Contract Data
16. Contractor to Construct the Works
16.1 The Contractor shall construct and install the works in accordance with the
specification and Drawings.
17. The Works to be completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Works on the Start Date and shall
carry out the Works in accordance with the programme submitted by the Contractor,
as updated with the approval of the Engineer, and complete them by the Intended
Completion date
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing the proposed
Temporary works to the Engineer, who is to approve them if they comply with the
Specifications and drawings.
18.2 The Contractor shall be responsible for design of temporary works.
18.3 The Engineer’s approval shall not alter the contractor responsibility for design of
the Temporary works.
18.4 The Contractor shall obtain approval of third parties to the design of the Temporary
works where required.
18.5 All Drawings prepared by the Contractors for the execution of the temporary or
permanent work are subject to prior approval by the Engineer before their use.
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly
discovered on the site is the property of the Employer. The contractor is to notify
the engineer of such discoveries and carry out the Engineer’s instructions for dealing
21. Possession of the Site
21.1 The Employer shall give possession of all parts of the site to the Contractor. If
possession of a part is not given by the date stated in the Contract Data the Employer
is deemed to have delayed the start of the relevant activities and this will be a
Compensation Event.
21.2 If within 25% of the time limit of the project, 80% of possession of the site is not
handed over to the Contractor, then contractor/ Employer may fore-close the
contract. Contractor/Employer has to foreclose the work within 30 days after lapse
of 25%-time limit and after 30 days foreclosure option will be closed.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized by the Engineer
access to the Site, to any place where work in connection with the Contract is being
carried out or is intended to be carried out and to any place where materials or plants
are being manufactured/ fabricated/ assembled for the works.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining to works
which comply with the applicable laws where the site is located.
23.2 The Contractor shall permit the Employer to inspect the Contractor’s accounts and
records relating to the performance of the Contractor and to have them audited by
auditors appointed by the Employer, if so required by the Employer.
24.1 If the Contractor is of the view that a decision taken by the Engineer was either
outside the authority given to the Engineer by the Contract or that the decision was
wrongly taken, the decision shall be referred to #Superintending Engineer (Panam
Project Circle) within 14 days of the notification of the Engineer's decision. If the issue
is not resolved, any party can refer the matter for conciliation within 15 days from the
decision given by the #Superintending Engineer (Panam Project Circle).
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the
decision of the #Superintending Engineer (Panam Project Circle), both
the parties have to refer to the Chief Engineer, Central Gujarat concern for the
conciliationprocess.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied with
the decision of the #Superintending Engineer (Panam Project Circle), both
the parties have to refer to the #Secretary, Water Resources Department,
Government of Gujarat for the conciliation process.
If the dispute is not resolved through the conciliation process, he may refer the
dispute to Gujarat Public Works Contract Dispute Arbitration Tribunal. If the
Contractor fails to refer a claim / dispute to the Higher Authority within 14 days of
the notification of the Engineer's decision, the Contractor shall not be entitled to any
additional payment/claim if he doesn’t follow the above sequence in stipulated time
and he should not stop the work.
25. Procedure for Disputers
25.1 The arbitration shall be conducted in accordance with the arbitration procedure
stated in the Special Conditions of Contract.
B. TIME CONTROL
27.1 Within the time stated in the Contract Data the Contractor shall submit to the
Engineer for approval a Programme showing the general methods, arrangements
orders, and timing for all the activities in the works along with monthly cash flow
27.2 An update of the Programme shall be a programme showing the actual progress
achieved on each activity and the effect of the progress achieved on the timing of
the remaining work including any changes to the sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval an updated programme at
intervals no longer than the period stated in the Contract data. If the Contractor does
not submit an updated programme within this period, the Engineer may withhold the
amount stated in the Contract data from the next payment after the date on which
the overdue programme has been submitted.
27.4 The Engineer’s approval of the programme shall not alter the Contractor’s
obligations. The Contractor may revise the programme and submit it to the Engineer
again at any time. A revised programme is to show the effect of Variations and
Compensations events.
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if a compensation Event
occurs or a Variation is issued which makes it impossible for completion to be
achieved by the Intended Completion Date without the Contractor taking steps to
accelerate the remaining work and which would cause the Contractor to incur
additional cost.
28.2 The Engineer shall decide whether and by how much to extend the Intended
Completion Date within 35 days of the Contractor asking the Engineer for a decision
upon the effect of a compensation event or Variation and submitting full supporting
information. If the Contractor has failed to give early warning of a delay or has failed
to cooperate in dealing with a delay, the delay by this failure shall not be considered
in assessing the new Intended Completion Date.
28.3 The Engineer shall within 14 days of receiving full justification from the contractor
for extension of Intended Completion Date refer to the Employer his decision. The
employer shall in not more than 21 days communicate to the engineer the acceptance
or otherwise of the Engineer’s decision. If the employer fails to give his acceptance,
the Engineer shall not grant the extension and the contractor may refer the matter
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or progress of any activity
within the works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other to attend a management
meeting. The business of a management meeting shall be to review the plans for
remaining work and to deal with matters raised in accordance with the early warning
31.2 The Engineer shall record the business of management meetings and is to provide
copies of his record to those attending the meeting and to the Employer. The
responsibility of the parties for actions to be taken is to be decided by the Engineer
either at the management meeting or after the management meeting and stated in
writing to all who attended the meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely
future events or circumstances that may adversely affect the quality of the work,
increase the Contract price or delay the execution of works. The Engineer may
require the contractor to provide an estimate of the expected effect of the future
event or circumstance on the contract price and completion date. The estimate is to
be provided by the Contractor as soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and considering
proposals for how the effect of such an event or circumstance can be avoided or
reduced by anyone involved in the work and in carrying out any resulting instruction
of the Engineer.
C. QUALITY CONTROL
# 33. Identifying Defects/ Defect liability period
33.1 : Defect liability period: The contractor shall be responsible to make good and remedy
at his own expense any defect which may develop or may be noticed before the
period mentioned hereunder from the certified date of completion. The Engineer in
charge shall give the contractor a notice in writing about the defects and the
contractor shall make good the same within 15 days of receipt of the notice. In the
case of failure on the part of the contractor, the Engineer- in-charge may rectify or
remove or re-execute the work at the risk & cost of the contractor. The Engineer-in-
charge shall be entitled to appropriate the whole or any part of the amount of security
deposit towards the expenses, if any, Incurred by him in rectification, removal or re-
execution. The Defects Liability period shall be as under….
A. For works of WRD Except Building
(a) (1) For all works costing up to Rs. 50,000 (amount put to tender), the period shall be
3 Months from the certified date of completion.
(b) (1) For WRD works likes Check Dam/ Canal / Drainage / Road Structure tender
amount from RS. 50,000 to 10,00,000, the defect liability period shall be 12 months
from the certified date of completion.
(2) For WRD work except likes Check Dam/ Canal / Drainage / Road Structure
tender amount from RS. 50,000 to 10,00,000, the defect liability period shall be
months from the certified date of completion.
(c) (1) For WRD works likes Check Dam/ Canal / Drainage / Road Structure tender
amount more than RS. 10,00,000, the defect liability period shall be 3 Years from
the certified date of completion.
(2) For WRD work except likes Check Dam/ Canal / Drainage / Road Structure
tender amount from RS. 10,00,000 to 1 Crore, the defect liability period shall be
months from the certified date of completion.
(d) (1) For all WRD works of tender amount more than RS. 1 Crore, the defect liability
period shall be 3 Years from the certified date of completion
B. For Building works of WRD:-
For Building works of WRD, Follow the R&B Circular dated.03/12/2009
For original building works the defect liability period will be 4 years or elapse of
monsoon period following date of possession of building taken over by user agency
following the certified date of completion, whichever is later.
For the purpose of deciding the monsoon period, the 30th September shall be treated
as the last date.
WRD Circular No. Matas/102013/MICELL(K-1) Dated 13/12/2013
33.2 For Road works :
Free maintenance guarantee period for works of Road/Bridge construction
(a) For resurfacing work of road free maintenance guarantee period one year from
the date of completion.
(b) In case of widening of the road/strengthening of the road/bridge, the contractor
shall have to give four years free maintenance guarantee from the certified date
of completion. During this period the contractor shall visit the site every six
months along with the concerned Section Officer / Deputy Executive Engineer
and will examine the work already carried out in this contract like road work,
jungle cutting, side shoulders, side gutter, road furniture, patta etc. and will
prepare Km. wise inspection report duly signed by all concerned and any defect
observed shall be done within 15 days by the contractor at his risk and cost as
per the direction of Engineer in charge. The contractor needs to do videography
of these visits and require to submit at the time of release of FMG. If B.T. the
the maintenance period of 4 years is worn out then agency shall have to provide
renewal coating as per tender item as directed by the Engineer-in- charge. The
amount equivalent to 5% of each running bill shall be withheld and will be
released after the free maintenance guarantee period (i.e. 4 years) is over.
However, this amount shall be released against fixed deposit or bank
guarantee pledged in the name of Executive Engineer after completion
certificate of work is issued.
(1) The flakiness and elongation index (combined) for coarse aggregates under no
circumstances shall exceed the allowable limit set forth in the relevant clause for
the material in question.
(2) 2% of the amount eligible for the payment of bituminous items shall be withheld
till the miscellaneous items like earthwork in embankment / cutting for side
shoulders, side gutters, kilometer / indicator / guard stones, sign boards etc. are
completed in all respect by the contractor. After completion of the miscellaneous
items, the above said 2% withheld amount shall be released.
(Govt. of Gujarat's G.R. No.: TNC-10-2013-3(Part-3)/C, Dtd. 13/12/2013).
(3) Videography for the surface under Maintenance Guarantee is to be done as per
Govt. letter No.: SSR/10/2015-16/26/C, Dtd. 26/11/15 for the work costing more
than Rs. 5.00 Crore.
(4) Setting up of adequate laboratory & deployment of quality engineers.
The contractor shall have to set up the laboratory with adequate equipment. Till
the setting up of adequate laboratory is completed & reported of this to the
engineer (subject to due verification by engineer’s representative) by contractor
in writing, Rs.2,00,000/- shall be withheld. The qualified quality Engineer shall
be deployed exclusively for this contract by the contractors. If quality Engineer
is not deployed by contractor within one month after the date of work order, the
amount equivalent to Rs.20,000 per month shall be recovered till the actual
deployment of quality engineer. The amount so recovered towards the
deployment of quality engineers shall not be refunded.
(5) Asphalt work will have to be cross checked as per G.R. No.: RGN/60/2006/35/C,
dtd.31/05/07 before final bill is paid.
(6) Maintenance during Construction Period
During the Construction Period, the Contractor shall maintain, at his own risk
and cost, the existing lane(s) of the road so that the traffic worthiness and safety
thereof are at no time materially inferior as compared to their condition 10 (ten)
days prior to the date of the Agreement, and shall undertake the necessary repair
and maintenance works for this purpose; provided that the Contractor may, at
his cost, interrupt and divert the flow
of traffic if such interruption and diversion is necessary for the efficient progress
of works and conforms to Good Industry Practice; provided
further that such interruption and diversion shall be undertaken by the Contractor
only with the prior written approval of the Executive Engineer which approval
shall not be unreasonably withheld. For the avoidance of doubt, it is agreed that
the Contractor shall at all times be responsible for ensuring safe operation of the
33.3 The Engineer shall check the Contractor’s work and notify the Contractor of any
defects that are found. Such checking shall not affect the Contractor’s
responsibilities the Engineer may instruct the Contractor to search for a Defect and
to uncover and test any work that the Engineer considers may have a Defect.
34.1 If the engineer instructs the Contractor to carry out a test not specified in the
Specification to check whether any work has a Defect and the test shows that it
does, the Contractor shall pay for the test and any samples. If there is no defect the
test shall be a Compensation Event.
34.2 #1% of the amount of work done for works upto Rs. 10 crore of estimate cost should
be deducted from R.A. Bill of the contractor for testing the quality of material
workmanship. Whereas for estimated cost of works more than 10 crore, the charges
for testing of quality of material workmanship shall be deducted from R.A. bill of
contractor as per actual charges. As Per GoG NWRWS & K Department’s Circular
No. PARCH/132023/401/MICELL Dated: 05/10/2023
34.3 Agency has to establish testing laboratory on site for the various test to be carried
out in the work for this purpose agency shall construct a pukka laboratory building
with all facility on site at location specified by the engineer in charge.
35. Correction of defects
35.1 The engineer shall give notice to the Contractor of any defects before the end of the
defects Liability Period, which begins at Completion and is defined in the contract
data. The Defects Liability Period shall be extended for as long as Defects remain
to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified defect
within the length of time specified by the Engineer’s notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a defect within the time specified in the
Engineer’s notice, the Engineer will assess the cost of having the Defect corrected,
and the Contractor will pay this amount.
D. COST CONTROL
37. Bill of Quantities
37.1 The bill of Quantities shall contain items for the constructions, installation,
testing and commissioning work to be done by the Contractor.
37.2 The bill of Quantities is used to calculate the Contract price. The Contractor is paid
for the quantity of the work done at the rate in the Bill of Quantities for each item.
38. Change in the Quantities
38.1 The Engineer shall have power to make any alterations in or addition to the original
specifications , drawings, designs and instructions that may appear to him to be
necessary or advisable during the progress of the work and the contractor shall be
bound to carry out the work in accordance with any instruction in this connection
which may be given to him in writing signed by the Engineer and such alteration
shall not invalidate the contract and any additional work which the contractor may
be directed to do in the manner above specified as part of the work shall be carried
out by the contractor on the same conditions in all respects on which he agreed to
do the main work and at the same rate as are specified in the tender for the main
Except that when the quantity of any item exceeds the quantity as in the tender by
more than 130%, the contractor will be paid for the quantity in excess of 130%, at
the rate entered in the SOR of the year during which the excess in quantity is first
39.1 All Variations shall be included in updated programmes produced by the Contractor.
40. Payments for Variations
40.1 If the additional or altered work includes any class of work for which no rate is
specified in this contract, then such class of work shall be carried out as under.
(i) At the rate derived from the item within the contract which is comparable to the one
involving additional or altered class of work; where there are more than one
comparable items, the item of the contract which is nearest in comparison with
regard to class or classes of the work involved shall be selected and the decision of
the Superintending Engineer as to the nearest comparable item shall be final and
binding on the contractor.
(ii)If the rate cannot be derived in accordance with (i) above, such class of works shall
be carried out at the rate entered in the Schedule of Rates of the division
for the year in which the tender was received, increased or decreased by the
percentage by which the tender amount is more or less as compared to the amount
arrived at the rates in the “Schedule of Rates” of the Division in the year in which
the tender was received. If the Schedule of rates of the Division does not contain all
the items, the percentage increase or decrease of the tender shall be calculated
considering such items which were included in the “Scheduled Rates” of the division
for the year and for materials consumed on such item the rate to be charged would
be the basic rate taken into account for fixing the rate in S.O.R. referred to above.
(iii) If it is not possible to arrive at the rate from (i) and (ii) above, such class of work
shall be carried out at the rate decided by the competent authorities on the basis of
detailed rate analysis after hearing the contractor before a Committee of two
Superintending Engineers stationed at the same place or the nearest place.
40.2 If the additional or altered work, for which no rate is entered in the “Schedule of
Rates” of the Division is ordered to be carried out before the rate is agreed upon,
then the contractor shall within seven days of the date of receipt by him of the order
to carry out the work, inform the Engineer-in-charge of the rate, which it is his
intention to charge for such class of work and if the Engineer in charge does not
agree to this rates, he shall by notice in writing be at liberty to cancel his order to
carry out such class of work and arrange to carry it out in such manner as he may
consider it advisable, provided always that if the contractor shall commence work
or incur any expenditure in regard thereof before the rates shall have been
determined as lastly herein before mentioned, then in such cases he shall only be
entitled to be paid in respect of the work carried out or expenditure incurred by him
prior to the date of the determination of the rate as aforesaid according to such rate
or rates as shall be fixed by the Engineer-in-charge. In the event of the dispute, the
decision of the Superintending Engineer of the Circle shall be final.
Where, however, the work is to be executed according to the designs,
drawings and specifications recommended by the contractor and accepted by the
competent authority, the alternation above referred to shall be within the scope of
such designs, drawings and specifications appended to the tenders.
The time limit for the completion of the work shall be extended in the
proportion that the increase in the cost occasioned by alterations bears to the cost of
the original work and the certificate of the Engineer-in-charge as to such proportion
shall be final and conclusive.
41. Cash Flow Forecasts
41.1 When the programme is updated, the contractor is to provide the engineer with an
updated cash flow forecast.
42. Payment certificates.
42.1 The Contractor shall submit to the Engineer monthly statements of the estimated
value of the work completed less the cumulative amount certified previously.
42.2 The Engineer shall check the Contractor’s monthly statement within 14 days and
certify the amount to be paid to the Contractor after taking in to account any credit
or debit for the month in question in respect of materials for the works in the relevant
amounts and under conditions set forth in sub-clause
32.3 of the Contract Data (secured Advance).
42.3 The value of work executed shall be determined by the Engineer.
42.4 The value of work executed shall comprise the value of the quantities of the items
in the Bill of Quantities completed.
42.5 The value of work executed shall include the valuation of variations and
compensation events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the
proportion of any item previously certified in any certificate in the light of later
43.1 Payments shall be adjusted for deductions for advance payments, retention, other
recoveries in terms of the contract and taxes at source, as applicable under the law.
The Employer shall pay the Contractor the amounts certified by the Engineer within
28 days of the date of each certificate.
43.2 Payment of GST (prevailing rates) on the amount payable under the contract to the
Contractor will be made by the Employer. Hence, it is the responsibility of the
contractor to pay the GST to the concerned Authority.
43.3 Items of the works for which no rate or price has been entered in will not be paid by
the Employer and shall be deemed covered by other rates and prices in the Contract.
44. Compensation events
44.1 The following are compensation Events unless they are caused by the Contractor:
(a) The Employer does not give access to a part of the Site by the site
Possession date stated in Contract data to the Contractor
44.2 In case of compensation event occurs and it prevents the work being completed
beyond the Intended Completion Date then Authority will approve EOT with
eligible contractual price escalation.
45.1 The rates quoted by the Contractor must be inclusive of all taxes prevailing on due
date of bid submission except GST. However, any subsequent changes in the tax
structure by Government after due date of bid submission will be compensated (+/-
) on availability or submission of actual documentation. Contractor will have to
intimate Engineer regarding changes occurred in the tax structure after bid
submission. If the contractor fails to provide such information and if any financial
obligation may arise due to change in tax structure, same will be recovered from the
45.2 GST will be paid separately on the bills. Hence, it is the responsibility of the
contractor to pay the GST to the concerned Authority.
46. Currencies.
46.1 All payment shall be made in Indian Rupees.
47. Price Adjustment
47.1 Contract price shall be adjusted for increase or decrease in rates and price of labour,
materials, fuels and lubricants in accordance with the following principles and
procedures and as per formula given in the contract data:
(a) The price adjustment shall apply for the work done from the start date given in
the contract data up to end of the initial intended completion date or extensions
granted by the Engineer and shall not apply to the work carried out beyond the
stipulated time for reasons attributable to the contractor.
(b) The price adjustment shall be determined during each month from the formula
given in the contract data.
(c) Following expressions and meanings during to the work done during each month
R = Total value of work done during the month. It would include the amount of
secured advance granted, if any, during the month less the amount of secured
advance recovered, if any during the month. It will exclude value for works
executed under variations for which price adjustment will be worked separately
based on the terms mutually agreed.
47.2 To the extent that full compensation for any rise or fall in costs to the contractor is
not covered by the provisions of this or other clause in the contract, the unit rates
and prices included in the contract shall be deemed to include amounts to cover the
contingency of such other rise or fall in costs.
48.1 The Employer shall retain from each payment due to Contractor theproportion stated
in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to
48.2 On Completion of the whole of the Works half the total amount retained is repaid to
the Contractor and half when the Defects Liability Period has passed and the
Engineer has certified that all Defects notified by the Engineer to the Contractor
before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money
with an “on demand” Bank guarantee.
In case, Contractor requests for refund of the Retention Money deducted by
the Employer under the provision of this clause, Employer shall consider the said
request of the Contractor provided that the refund hereunder shall be made in
tranches of not less than 1% (One Percent) of the Contract Price and Contractor
furnishes an irrevocable and unconditional Bank guarantee for an equal amount
substantially in the format of Bank Guarantee for Performance Guarantee enclosed
with SBD and valid up to 60 day beyond the scheduled / extended Defects Liability
Period. On completion of the whole works, the contractor has however an option to
submit a fresh irrevocable and unconditional Bank Guarantee for an amount equal
to 5% of the total value of work executed substantially in the format of Bank
Guarantee for Performance Guarantee enclosed with SBD and valid up to 60 days
beyond the Defect Liability Period and yet refund the Retention Money Bank
Guarantee submitted for refund of Retention Money.
49. Liquidated Damages
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day
stated in the Contract Data for each day that the Completion Date is later than the
Intended Completion Date (for the whole works or the milestone as stated in the
contract data). The total amount of liquidated damages shall not exceed the amount
contract data). The total amount of liquidated damages shall not exceed the amount
defined in the Contract Data. The Employer may deduct liquidated damages from
payment due to the Contractor. Payment of liquidated damages does not affect the
Contractor’s liabilities.
49.2 If the Intended Completion Date is extended after liquidated damages have been
paid, the Engineer shall correct any overpayment of liquidated damages by the
Contractor by adjusting the next payment certificate. The Contractor shall not be
entitled for any interest on the over payment calculated from the date of payment to
the date of repayment.
49.3 If the contractor fails to comply with the time for completion as stipulated in the
tender, then the contractor shall pay to the employer the relevant sum stated in the
Contract Data as Liquidated damages for such default and not as penalty for
everyday or part of day which shall elapse between relevant time for completion and
the date stated in the taking over certificate of the whole of the works on the relevant
section, subject to the limit stated in the contract data.
The employer may, without prejudice to any other method of recovery
deduct the amount of such damages from any monies due or to become due to the
contractor. The payment or deduction of such damages shall not relieve
the contractor from his obligation to complete the works on from any other of his
obligations and liabilities under the contract.
49.4 If, before the Time for Completion of the whole of the Works or, if applicable any
Section, a Taking Over Certificate has been issued for any part of the Works or of a
Section, the liquidated damages for delay in completion of the remainder of the
Works or of that Section shall, for any period of delay after the date stated in such
Taking-Over-Certificate, and in the absence of alternative provisions in the Contract,
be reduced in the proportion which the value of the part so certified bears to the
value of the whole of the Works or Section, as applicable. The provisions of this
Sub-clause shall only apply to the rate of liquidated damages and shall not affect the
50.1 If the contractor achieves completion of the whole of the works prior to the intended
Completion Date prescribed in Contract Data the Employer shall pay to the
contractor a sum stated in Contract Data as bonus for every completed month but
subjected to maximum amount as stated in Contract Data; which shall elapse
between the date of completion of all items of works as stipulated in the contract,
including variations ordered by the Engineer and the time prescribed in Clause
50.2 Bonus shall be paid only to works amounting to above INR 5 crore with time limit
of the works is equal or more than 6 months. The bonus would be paid as under
% of Time Saved % of Initial Contract Price
entitled for Bonus
Less than 10% 0%
51. Advance Payment.
51.1 The Employer shall make advance payment (not to be paid less than two installments
except in special circumstances for which the reason to be Recorded in writing) to
the Contractor of the amounts stated in the Contract Date by the date stated in the
Contract Date, against provision by the Contactor of an Unconditional Bank
Guarantee in a form and by a bank acceptable to the Employer in amounts and
currencies equal to be at least 110% of the advance payment. The guarantee shall
remain effective until the
advance payment has been repaid, but the amount of the guarantee shall be
progressively reduced by the amounts repaid by the Contractor. The Mobilization
advance would be deemed as interest bearing advance at an interest rate of 10 % to
be compounded, quarterly.
51.2 The Contractor is to use the advance payment only to pay for Equipment, plant
and Mobilization expenses required specifically for execution of the Works. The
Contractor shall demonstrate that advance payment has been used in this way by
supplying copies of invoices or other documents to the engineer.
51.3 The advance payment shall be repaid by deduction proportionate amount from
payments otherwise due to the Contractor, following the schedule of completed
percentages of the Works on a payment basis. No account shall be taken of the
advance payment or its repayment in assessing valuations of work done, variations,
price adjustments, Compensation Events, or Liquidated damages.
52.1 The performance Security (including additional security for unbalanced bids) shall
be provided to the Employer no later than the date specified in the Letter of
Acceptance and shall be issued in an amount and form and by a bank or surety
acceptable to the Employer, and denominated in Indian Rupees. The performance
Security shall be valid until a date 60 days from the date of expiry of Defects
Liability Period and the additional security for unbalanced bids shall be valid until
a date 28 days from the date of issue of the certificate of completion.
54. Cost of Repairs.
54.1 Loss or damage to the Works or Materials to be incorporated in the Works between
the Start date and the end of Defects Correction periods shall be remedied by the
Contractor at the Contractor’s cost if the loss or damages arises from the
Contractor’s acts or omissions.
E. FINISHING THE CONTRACT
55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of the
works and the Engineer will do so upon deciding that the work is completed.
56. Taking Over
56.1 The Employer shall take over the Site and the Works within seven days of the
Engineer issuing a certificate of Completion.
57. Final Account
57.1 The Contractor shall supply to the Engineer a detailed final account of the total
amount that the Contractor considers payable as full and final settlement of all claims
under the Contract for items before the end of the Defects Liability Period. The
Engineer shall issue a Defect Liability Certificate and certify any final payment that
is due to the Contractor within 56 days of receiving the Contractor's account if it is
correct and complete. If it is not, the Engineer shall issue within 56 days a schedule
that states the scope of the corrections or additions that are necessary. If the Final
Account is still unsatisfactory after it has been resubmitted, the Engineer shall decide
on the amount payable to the Contractor and issue a payment certificate, within
days of receiving the Contractor’s revised account.
57.2 If reversal in characteristic of tender (L1 becoming L2) on account of excesses and
savings in final account is observed, the Engineer/Employer shall be at liberty to
restrict the final payment of BOQ items to the lowest amount evaluated of the bids
considering the final quantities and the rates quoted including the rebates if any.
Payment of variation items shall however be made at the rates approved by the
Employer, within 90 days from the physical completion of work.
58. Operating and Maintenance Manuals
58.1 If “as built” drawings and/or operating and maintenance manuals are required, the
Contractor shall supply them by the dates stated in the Contract data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated
in the Contract data, or they do not receive the Engineer’s approval, the Engineer
shall withhold the amount stated in the Contract Data from payments due to the
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party causes
a fundamental breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited to the following:
1. The contractor stops work for 28 days when no stoppage of work is shown on
the current programme and the stoppage has not been authorized by the Engineer
2. The Engineer instructs the Contractor to delay the progress of the Works and the
instructions is not withdrawn within 28 days;
3. The Employer or the Contractor is made bankrupt or goes into liquidation other
than for a reconstructions or amalgamation
4. A payment certified by the Engineer is not paid by the Employer to the
Contractor within 56 days of the date of the Engineer’s certificate
5. The Engineer gives Notice that failure to correct a particular Defect is a
fundamental breach of Contract and the Contractor fails to correct it within a
reasonable period of time determined by the Engineer;
6. The Contractor does not maintain a security which is required;
7. The Contractor has delayed the completion of works by the number of days
for which the maximum amount of liquidated damages can be paid as defined in
the Contract data; and
8. If the Contractor, in the judgment of the Employer has engaged in corrupt or
fraudulent practices in competing for or in executing the Contract.
For the purpose of this paragraph: “corrupt practice” means the offering,
giving, receiving or soliciting of anything of value to influence the action of a public
official in the procurement process or in contract execution. “Fraudulent practice”
means a misrepresentation of facts in order to influence a procurement process or the
execution of a contract to the detriment of the borrower, and includes collusive
practice among Bidders (prior to or after bid submission) designed to establish bid
prices at artificial non-competitive levels and to deprive the Borrower of the benefits
of free and open competition.
59.3 When either party to the Contract gives notice of a breach of contract to the Engineer
for a cause other than those listed under Sub Clause 59.2 above, the Engineer shall
decide whether the breach is fundamental or not.
59.4 Notwithstanding the above, the employer may terminate the Contract for
60. Payment upon Termination
60.1 If the Contract is terminated because of a fundamental breach of Contract by the
Contractor, the Engineer shall issue a Certificate for the value of the work done less
advance payments received up to the date of the issue of the
certificate, less other recoveries due in terms of the contract, less taxes due to
deducted at source as per applicable law and less the percentage to apply to the work
not completed as indicated in the Contract data. Additional Liquidated Damages
shall not apply. If the total amount due to the Employer exceeds any payment due to
shall not apply. If the total amount due to the Employer exceeds any payment due to
the Contractor the difference shall be a debt payable to the Employer.
60.2 If the Contract is terminated at the Employer’s convenience or because of a
fundamental breach of Contract by the Employer, the Engineer shall issue a
certificate for the value of the work done, the cost of balance material brought by
the contractor and available at site, the reasonable cost of removal of equipment,
repatriation of the Contractor’s personnel employed solely on the works, and the
Contractor’s cost of protecting and securing the Works and less advance payment
received up to the date of the certificate, less other recoveries due in terms of the
contract and less taxes due to deducted at source as per applicable law.
61.1 All materials on the Site, Plant Equipments, Temporary Works and Works are
deemed to be property of the Employer, if the Contract is terminated because of a
Contractor’s default.
62. Release from Performance
62.1 If the Contract is frustrated by the outbreak of war of by any other event entirely
outside the control of either the Employer or the Contractor the Engineer shall certify
that the Contract has been frustrated. The Contractor shall make the Site safe and
stop work as quickly as possible after receiving this certificate and shall be paid for
all work carried out before receiving it and for any work carried out afterwards to
which commitment was made.
F. SPECIAL CONDITIONS OF CONTRACT
The Contractor shall, unless otherwise provided in the Contract, make his
own arrangements for the engagement of all staff and labour, local or other, and for
their payment of housing, feeding and transport.
The Contractor shall, if required by the Engineer, deliver to the Engineer a
return in detail, in such form and at such intervals as the Engineer may prescribe,
showing the staff and the numbers of the several classes of labour from time to time
employed by the Contractor on the site and such other information as the Engineer
64. COMPLIANCE WITH LABOUR REGULATIONS
During continuance of the contact, the Contractor and his sub- contractor
shall abide at all times by all existing labour enactments and rules made thereunder,
regulations, notification and bye laws of the State or central Government or local
authority and any other labour law (including rules), regulations, bye laws that may
be passed or notifications that may be issued under any labour law in future either
by the State or the Central Government or the local authority. Salient features of
some of the major labour laws that are applicable to the construction industry are
given below. The Contractor shall keep the Employer indemnified in case any action
is taken against the Employer by the competent authority on account of
contravention of any of the provisions of any Act or rules made thereunder,
regulations or notifications including amendments. If the Employer is caused to pay
or reimburse, such amounts as may be necessary to cause or observe, or for
observance of the provisions stipulated in the notifications/bye
laws/Acts/Rules/regulations including amendments, if any, on the part of the
Contractor, the Engineer/employer shall have the right to deduct any money due to
the Contractor including his amount of performance security. The
Employer/Engineer shall also have the right to recover from the Contractor any sum
required or estimated to be required for making good the loss or damage suffered by
The employees of the Contractor and the Sub-Contractor in no case shall be
treated as the employees of the Employer at any point to time.
SALIENT FEATURES OF SOME MAJOR LABOUR AND OTHER LAWS
APPLICABLE TO ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER
CONSTRUCTIONS WORK
A) Workmen Compensation Act 1923: - The Act provides for compensation in case of
injury by accident arising out of and during the course of employment.
B) Payment of Gratuity Act. 1972: - Gratuity is payable to an employee under the Act on
satisfaction of certain conditions on separation if an employee has completed 5 years’
service or more on death, the rate of 15 days’ wages for every completed year of service.
The Act is applicable to all establishments employing 10 or more employees.
C) Employees P.F. and Miscellaneous Provision Act 1952: - The Act Provides for
monthly contributions by the employer plus workers @ 10% or 8.33% The benefits
payable under the Act are:
1. Pension or family pension on retirement or death, as the case may be.
2. Deposit linked insurance on the death in harness of the worker.
3. Payment of P.F. accumulation on retirement/death etc.
D) Maternity Benefit Act 1951 :- The Act provides for leave and some other benefits to
women employees in case of confinement or miscarriage etc.
E) Contract Labour (Regulation & Abolition) Act 1970 : The Act provides for certain
welfare measures to be provided by the Contractor to contract labour and in case the
Contractor fails to provide, the same are required to be provided, by the Principal
Employer by Law. The principal Employer is required to take Certificate of Registration
and the Contractor is required to take license from the designated Officer. The Act is
applicable to the establishments or Contractor of Principal Employer, if they employ
or more contract labour.
F) Minimum Wages Act 1948 :- The Employer is supposed to pay not less than the
Minimum Wages fixed by appropriate Government as per provisions of the Act, if the
employment is a scheduled employment. Construction of Building, Roads, Runways are
scheduled employment.
G) Payments of wages Act 1936:- It lays down as to by what date the wages are to be
paid, when it will be paid and what deductions can be made from the wages of the
H) Equal remunerations Act 1979 :- The Act provides for payment of equal wages for
work of equal nature to Male and Female workers and for not making discrimination
against female employees in the matter of transfer, training and promotions etc.
I) Payments of Bonus Act 1965 :- The Act is applicable to all establishments employing
20 or more employees. The Act provides for payments of annual bonus subject to a
minimum of 8.33% of wages and maximum of 20 % of wages to employees drawing
Rs. 3500/- per month or less. The bonus to be paid to employees getting Rs, 2500/- per
month or above Rs. 3500/- per month shall be worked out by taking wages as Rs.
2500/- per month only. The Act does not
apply to certain establishments. The newly set-up establishments are exempted for five
years in certain circumstances. Some of the State Governments have reduced the
employment size from 20 to 10 for the purpose of applicability of this Act.
J) Industrial Disputes Act 1947 :- The Act lays down the machinery and procedure for
resolutions of Industrial disputes, in what situations a strike or lock-out becomes illegal
and what are the requirements for laying off or retrenching the employees or closing
down the establishment.
K) Industrial employment (standing Orders) Act 1946 :- It is applicable to all
establishments employing 100 or more workmen (employment size reduced by some
of the State and Central Government to 50). The Act provides for laying down rules
governing the conditions of employment by the Employer on matters provided in the
Act and get the same certified by the designated Authority.
L) Trade Unions Act 1926:- The Act lays the procedure for registration of trade unions
of workmen and employers. The Trade Unions registered under the Act have given
certain immunities from civil and criminal liabilities.
M) Child Labour (Prohibition & Regulation Act 1986 :- The Act prohibits employment
of children below 14 years of age in certain occupations and process and provides for
regulation of employment of children in all other occupations and processes.
Employment of Child labour is prohibited in Building and Construction Industry.
N) Inter – State Migrant workmen’s (Regulation of Employment & Conditions of
service) Act 1979:- The Act is applicable to an establishment which employs 5 or more
inter-state migrant workmen through an intermediary (who has recruited workmen in
one state for employment in the establishment situated in another state).The inter-state
migrant workmen, is an establishment to which this Act becomes applicable, are
required to be provided certain facilities such as housing, medical aid, traveling
expenses from home upto the establishment and back, etc.
O) The Building and Other Construction workers (Regulation of employment and
Conditions of Service) Act 1996 and the Cess Act of 1996:- All the establishments
who carry on any building or other constructions work and employ 10 or more workers
are covered under this Act.
All such establishments are required to pay cess at the rate not exceeding 2% of the
cost of construction as may be modified by the government. The Employer of the
establishment is required to provide safety measures at the Building or construction
work and other welfare measures, such as canteens, First Aid facilities, Ambulance,
Housing accommodations for workers near the workplace etc. The Employer to whom
the Act applies has to obtain a registration certificate from the Registering Officers
appointed by the Government.
P) Factories Act 1948 :- The Act lays down the procedure for approval of plans before
setting up a factory, health and safety provisions, welfare provisions, working hours,
annual earned leave and rendering information regarding accidents or dangerous
occurrences to designated authorities. It is applicable to premises employing 10 persons
or more with aid of power or 20 or more persons without the aid of power engaged in
the manufacturing process.
Q) Royalty charges-The contractor shall pay the royalty to the competent authority as per
rule. The royalty charges paid shall be borne by the contractor and shall not be
reimbursed by the Employer.
R) Following Pollution Control Acts and amendments made thereof from time to
time shall be applicable.
1. Water (Preservation and control of Pollution) Act,
2. Air (Prevention and Control of Pollution Act
3. Environmental (Protection) Act
The contractor must commit to adopting Environmental management plan for
best energy use, waste management, the reduction of pollution as in EMS
(Environmental Management system) ISO-14001-
65. ARBITRATION (GCC Clause 24)
The procedure for arbitration will be as follows: -
24.1 If the Contractor is of the view that a decision taken by the Engineer was either outside
the authority given to the Engineer by the Contract or that the decision was wrongly
taken, the decision shall be referred to #Superintending Engineer (Higher
Authority) (Panam Project Circle, Godhara) within 14 days of the notification of
the Engineer's decision. If the issue is not resolved, any party can refer the matter for
conciliation within 15 days from the decision given by the #Superintending Engineer.
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the
decision of the #Superintending Engineer Panam Project Circle, Godhara), both
the parties have to refer to the #Chief Engineer concerned for the conciliation
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied with
the decision of the Superintending Engineer, both parties have to refer to the
#Secretary, Water Resources Department, Government of Gujarat for the
conciliation process.
If the dispute is not resolved through the conciliation process, contractor
may refer the dispute to Gujarat Public Works Contract Dispute Arbitration
Tribunal. If the Contractor fails to refer a claim / dispute to the Higher Authority
within 14 days of the notification of the Engineer's decision, the Contractor shall
not be entitled to any additional payment/claim if he doesn’t follow the above
sequence in stipulated time. However, during such period, he would not stop the
work in any case.
Clause Reference With
respect To section
Item marked “N/A” do not apply to this Contract.
1. The Employers is [CL.1.1]
Name: Executive Engineer
Address: Dahod Irrigation Division, Dahod.
Name of authorized Representative (will be intimated later)
2. The Engineer is Executive Engineer, Dahod Irrigation Division, Dahod.
Name of Authorized Representative: (will be intimated later)
3. The Defects Liability Period is 3 Years from the date of [CL.1.1&33]
4. The Start Date shall be 1st days for the date of issue of the Notice to [CL.1.1]
proceed with the work.
5. The Intended Completion Date for the whole of the works is [CL.1.1,17&2]
11 Months after start of work with the following milestones:
Milestone dates: [CL.2.2&
Physical works to be completed Period from the start date 49.1]
Milestone 1 i.e. 10 % 84 days.
Milestone 2 i.e. 35 % 168 days.
Milestone 3 i.e. 75 % 252 days.
Milestone 4 i.e. 100 % 335 days.
6. The Site is located at villages: Modhva of Ta: Dhanpur, Dist. Dahod. [CL.1.1]
7. The name and identification number of the Contract is: [CL.1.1]
8. The works consist of Providing Services of Security and operation of gate [CL.1.1]
system work with items as per B.O.Q. The works shall, inter alia, include
the following, as Specified or as directed:
(A)Lift Irrigation Work
1. The bids invited for construction of lift irrigation scheme at village –
Zapatiya Taluka – Dhanpur of Dahod District. It is proposed to construct
jack well and pump house at River @ village. Zapatiya
2. The alignment of pipeline passes through private land for about ……..km
length. It is also planned to construct to outlet Kundies and other
associated works.
3. The major scope of Work includes the following components but not
i. Construction of Outlets, Pump house, M.D.C. Intake well/Jack
well/RCC Ovara etc.
ii. Providing, lowering, laying, jointing of P.V.C. & M.S. Pipe line.
iii. Providing, and erecting pumping machinery with accessories.
iv. Providing, and Erecting Electrical works and its allied works.
v. Formation and Registration of Co-operative society of
vi. Operation & Maintenance of Lift Irrigation Scheme with Civil,
Mechanical and Electrical maintenance
vii. Handing over charge of scheme to the Registered Society of
farmers and procedure of transfer of electric connection in the
name of Registered Society of farmers before completion of O & M
4. Third party Inspection Agency if engage for construction work, Cost there
of shall be borne by NWRWS &K. However, the contractor shall co-
ordinate with them and meets the necessary requirements.
5. The time limit for construction work is 11 months (including monsoon).
On completion of construction work the pumping machinery, pipeline,
and other remaining components of the project are to be constructed,
completed and commissioned within this time limit.
6. On commissioning of the project Operation and Maintenance period
starts immediately. The total period of operation and maintenance is
years. Bidders are instructed to refer carefully the scope and technical
specification as well as requirements etc. For the operation and
maintenance period and quote the bid accordingly.
7. The contractor shall take all necessary action for obtaining electric
connection for the power supply to pump machinery and other
installation for this project. The department will only sign necessary
documents for obtain power connection from concern electric company
and pay the charges/ deposits for electric connection to the electric
However, the contractor shall carry out all the activities including
commissioning of the project, in such a way that on completion of
construction activities, the commissioning and operation of the project
can be made immediately.
All necessary coordination with the department, local authorities,
electric company etc. shall be made by the contractor at no extra cost
and no time is spent in want of electric connection.
(B) Other Items
Any Other Items as required to fulfill all contractual obligations as per the Bid
10. The following documents also form part of the Contract:
Pre-qualification criteria As per clause 2-3
11. The law which applies to the Contract is the law of Union of India [CL.3.1]
12. The language of the Contract documents is English [CL.3.1]
13. Limit of subcontracting 25% of the Initial Contract Price [CL.7.1]
14. The Schedule of Other Contractors [CL.8]
15. The Schedule of Key Personnel as per Annex – II to Section I [CL.9]
16. The minimum insurance cover for physical property, injury and death is Rs. [CL.13]
5 lakhs per occurrence with the number of occurrences limited to four.
After each occurrence, the contractor will pay an additional premium
necessary to make insurance valid for four occurrences always.
17. Site Investigation report [CL.14]
18. The Site Possession dates shall be …………………… [CL.21]
19. The period for submission of programme for approval of the engineer shall [CL. 27.1]
be 21 days from the issue of Letter of Acceptance.
20. The period between program updates will be …….. days. [CL.27.3]
21. The amount to be withheld for late submission of an updated programme [CL. 27.3]
22. The following events shall also be Compensation Events [CL. 44]
Substantially adverse ground conditions encountered during the course of
execution of work not provided for in the bidding document.
(i) Removal of underground utilities detected subsequently
(ii) Significant changes in classification of soil requiring additional
mobilization by the contractor, e.g. ordinary soil to rock
(iii) Removal of unsuitable material like marsh, debris dumps, etc.
not caused by the contractor.
(iv)Artesian conditions
(v) Seepage, erosion landslide
(vi)River training requiring protection of permanent work
Presence of historical, archeological or religious structures,
monuments interfering with the works
(viii) Restriction of access to ground imposed by civil, judicial, or
military authority
23. The currency of the Contract is Indian Rupees [CL. 46]
24. The formula (e) for adjustment of prices are as under: [CL.47]
• If any of the commodities like Cement, Steel or Bitumen are not found
applicable in a work, the weight component of that commodities {i.e.
‘Cement’ (Pc), ‘Steel’ (Ps) or ‘Bitumen' (Pb) as indicated in SBD for the
purpose of Price Adjustment} shall be clubbed with the weight
component of ‘Other Material’ (Pm), such that the gross % weight of the
components shall remain as 100% .
R = value of work as defined in Clause 47.1 of Conditions of Contract
Adjustment for labour component
(i) Price adjustment for increase or decrease in the cost due to
labour shall be paid in accordance with the following formula:
VL = Increase or decrease in the cost of work during the month
under consideration due to changes in rates for local labour
L0 = The consumer price index for industrial workers for the State on
28 days preceding the scheduled date of opening of technical
Bids as published by Labour Bureau, Ministry of Labour,
Government of India
Li = The consumer price index for industrial workers for the State for
the month under consideration as published by the Labour
Bureau, Ministry of Labour, Government of India.
Pl = Percentage of labor component of the work.
Adjustment for cement component.
(ii) Prices adjustment for increase or decrease in the cost of
cement procured by the contractor
Vc = Increase or decrease in the cost of work during the month
under consideration due to changes in rates for cement.
C0 = The all India wholesale price index for Ordinary Portland
Cement on 28 days preceding the scheduled date of
opening of technical bid as published by the Office of the
Economic Adviser,
Department for Promotion of Industry and Internal
Trade, Ministry of Commerce & Industry.
Ci = The all India average wholesale price index for Ordinary Portland
Cement for the month under consideration as published by
Office of the Economic Adviser, Department for Promotion
of Industry and Internal Trade, Ministry of Commerce &
Pc = Percentage of cement component of the work
Adjustment for steel component
(iii) Price adjustment for increase or decrease in the cost of steel procured by the
contractor shall be paid in accordance with the following formula
Vs= Increase or decrease in the cost of work during the month under consideration due
to changes in the rates for steel
So= The all India wholesale price index for steel (Mild Steel - Long Products Rebars) on
28 days preceding the date of opening of Bids as published by the Office of the
Economic Adviser, Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Si= The all India average wholesale price index for steel (Mild Steel - Long Products
Rebars) for the month under consideration as published by Office of the
Economic Adviser, Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Ps = Percentage of steel component of the work
Note : For the application of this clause, the index of Mild Steel- Long products
Rebars has been chosen to represent the steel group.
Adjustments of bitumen component
(iv) Price adjustment for increase in the cost of bitumen shall be paid in
accordance with the following formula
Vb = Increase or decrease in the cost of work during the month under
consideration due to changes in rates for bitumen.
Bo = The official retail price of bitumen at the IOC depot at the nearest centre
on the day 28 days prior to the scheduled date of opening of technical bid.
Bi = The official retail price of bitumen of IOC depot at the nearest centre
for the 15th day of the month under consideration.
Pb = Percentage of bitumen component of the work
Adjustment of POL (fuel and lubricant) component
(v) Price adjustment for increase or decrease in cost of POL (fuel and lubricant)
shall be paid in accordance with the following formula
Vf = Increase or decrease in the cost of work during the month under
consideration due to changes in rates for fuel and lubricants.
Fo = The official retail price of High Speed Diesel (HSD) at the existing
consumer pumps of IOC at the nearest centre on the day 28 prior to the date
of opening of Bids.
Fi = The official retail price of HSD at the existing consumer pumps of IOC
at the nearest centre for the 15th day of the month of the under consideration.
Pf = Percentage of fuel and lubricants component of the work
Note: For the application of this clause, the price of High-Speed diesel Oil has
been chosen to represent the fuel and lubricants group.
Adjustment for Construction Machinery
(vi) Price adjustment for increase or decrease in the cost of plant and Machinery
spare procured by the Contractor shall be paid in accordance with the
following formula
Vp= Increase or decrease in the cost of work during the month under
consideration due to changes in rates for plant and machinery spares
P0 = The all India wholesale price index for manufacturer of machinery
for mining, quarrying and Construction for the month under
consideration as published Office of the Economic Adviser, Department
for Promotion of Industry and Internal Trade, Ministry of Commerce
Pi = The all India average wholesale price index for manufacturer of
machinery for mining, quarrying and Construction for the month under
consideration as published Office of the Economic Adviser, Department
for Promotion of Industry and Internal Trade, Ministry of Commerce
Pp = Percentage of plant and machinery spares component of the work.
Note: For the application of this clause, index of Heavy Machinery and parts has
been chosen to represent the Plant and Machinery Spares group
Adjustment of other materials Component
(vii) Price adjustment for increase or decrease in cost of local materials other than
cement, steel, bitumen and POL procured by the contractor shall be paid in
accordance with the following formula
Vm = Increase or decrease in the cost of work during the month under
consideration due to change in rates for local materials other than cement,
steel, bitumen and POL.
M0 = The All Indian wholesale price index (all commodities) on 28 days
preceding the scheduled date of opening of technical Bids, as published by
the Office of the Economic Adviser, Department for Promotion of
Industry and Internal Trade, Ministry of Commerce & Industry.
Mi= The All India wholesale price index (all commodities) for the month
under consideration as published by the Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade, Ministry of
Commerce & Industry.
Pm = Percentage of local material components (other than cement, steel,
bitumen and POL) of the work.
The following percentage will govern the price adjustment for the
entire contract:
1. Labour –Pl = 20.91 %
2. Cement – Pc = 2.76 %
3. Steel - Ps = 8.15 %
5. Plant & Machinery Spares Pp = 8.00 %
6. Other Materials – Pm = 49.24 %
25. The proportion of payments retained (retention money) shall be 6% {CL. 48} from
each bill subject to a maximum of 5% of final contract price.
26. Amount of Liquidated damages for For Whole of work {CL.49}
delay in completion of works (1/2000)th of the Initial contract
price, rounded off to the nearest
Thousand, per day. For sectional
Completion (wherever specified In item
6 of Contract data) (1/2000)th of initial
contract price for #5 km Section,
rounded off to the nearest thousand per
27. Maximum limit of liquidated damages 10 percent of the Initial {CL. 49}
For delay in completion work Contract Price rounded off to
the nearest thousand
28. Amount of Bonus for early completion Amount of bonus for early
completion of work shall be given as
per CL.50 of Section-3
29. Maximum limit of bonus for early 5 percent of the Contract {CL. 50}
Completion of work Price
30. The amount of the advance payment are: {CL. 51 & 52}
#Nature of Advances Amount (Rs.) Conditions to
i Mobilization 10% of the contract On submission of unconditional
Price Bank Guarantee. (to be drawn
before the end of 20% of the
contract period). The contractor
may furnish four bank guarantees of
2.5 % of each valid for the full
ii Equipment 90% for new and 50% of After equipment is brought to site
depreciated value for old (provided the Engineer is satisfied
equipment. Total amount That the equipment is required for
equipment. Total amount That the equipment is required for
will be subject to a performance of the contract) and on
maximum of 5% of the submission of unconditional Bank
Contract Price Guarantee for
amount of advance
iii Secured Deleted
Brought to site
(The advance payment will be paid to the Contractor no later than 28 days after fulfillment
of the above conditions).
31. Repayment of advance payment for mobilization and equipment {CL. 51.3}
The advance loan shall be repaid with percentage deduction from the interim payments
certified by the Engineer under the Contract. Deduction shall commence in the next
Interim Payment Certificate following that in which the
total of all such payments to the Contractor has reached not less than 20 percent of the
Contract Price or 6 (six) months from the date of payment of first installment of advance,
whichever period concludes earlier, and shall be made at the rate of 20 percent
(collectively for both Mobilization Advance and Equipment Advance) of the
amounts of all Interim Payment Certificate until such time as the loan has been repaid,
always provided that the loan shall be completely repaid prior to the expiry of the
original time for completion pursuant to Clause 17 and
33. The securities shall be for the following minimum amounts equivalent {CL. 52} As
a percentage of the Contract Price:
Performance Security for 5 percent of contract price plus Rs. …………….. (to be
decided after evaluation of the bid) as additional security in terms of ITB Clause
The standard form of Performance security acceptable to the Employer shall be an
unconditional Bank Guarantee of the type as presented in Section 8 of the Bidding
34. The Schedule of Operating and maintenance Manuals…..N/A. {CL. 58}
35. The date by which “as– built” drawings (in scale as directed) in 2 sets {CL. 58} are
required within 28 days of the issue of certificate of completion of the whole or section
of the work, as the case may be.
36. The amount to be withheld for failing to supply “as built” drawings {CL. 58} by the
Date required is Rs .................. Lakhs.
37. The following events shall also be fundamentals breach of contract: {CL.59.2} “The
Contractor has contravened Sub- clause 7.1 and Clause 9 of GCC”
38. The percentage to apply the value of the work not completed representing {Cl 60} the
Employer’s additional cost for completing the Works shall be 20 per cent.
TECHNICAL SPECIFICATION
GENERAL TECHNICAL SPECIFICATIONS
(1) In the specification" as directed "/" Approved" shall be taken to mean "as directed"/ Approved" by the
Engineer- in charge. "
(2) Wherever a reference to any Indian Standard appears in the specification; it shall be taken to mean as a
reference to the latest edition of the same in force on the date of agreement.
(3) In " Mode of Measurement" in the specification wherever a dispute arises in the absence of specific
mention of a particular point or aspect, the provisions on these particular point or aspect in the relevant
Indian Standard shall be referred to.
(4) All measurement and computations, unless otherwise specified, shall be carried out nearest to the following
(i) Length, width and depth (height) 0.01 Metre
(ii) Areas 0.01 Smt
(iii) Cubic Contents 0.01 Cum
In recording dimensions of work the sequence of length, width, height (depth) or thickness shall be
(5) The distance which constitutes lead shall be determined along the shortest practical route and not
necessarily the route actually taken. The decision of the Engineer- in charge in this regard shall be taken as
(6) Where no lead is specified, it shall mean "all leads"
(7) Lift shall be measured from plinth level.
(8) Reference to specifications of materials as made in the detailed specification of the items of work is in the
form of a designation containing the number of the specification of the material and prefix 'M' e.g. M-5.
(9) Approval to the samples of various materials given by the Engineer - in - charge shall not absolve the
contractor from the responsibility of replacing defective material given on site or materials used in the work
found defective at a later date. The contractor shall have no claim to any payment or compensation
whatsoever on account of any such materials being rejected by the Engineer-in-charge.
(10) The contract rate of the item of work shall be for the work completed in all respects.
(11) No collection of materials shall be allowed before it is got approved from the Engineer-in-charge.
(12) Collection of approved material shall be done at site of work in a systematic manner. Materials shall be
stored in such a manner as to prevent damage, deterioration or intrusion of foreign matter and to ensure the
preservation of their quality and fitness for the work.
(13) Materials, if and when rejected by the Engineer- in- charge, shall be immediately removed from the site of
(14) No materials shall be stored prior to, during and after execution of a work in such a way as to cause or lead
to damage or over loading of such various components of the structures.
(15) All works shall be carried out in a workmanlike manner as per the best techniques for the particular item.
(16) All tools, templates, machinery and equipment for correct execution of the work as well as for checking
lines, levels, alignment of the work during execution shall be kept in sufficient numbers and in good
working condition on the site of work by the contractor.
(17) The mode, procedure and manner of execution shall be such that it does not cause damage or over loading
of the various components of the structure during execution or after completion of the structure.
(18) The cement shall be conveyed and stored in Govt, store. The required quantities of cement for average
work week consumption shall be transferred or conveyed to site store. The site store shall have double
locking arrangement and only one exit. In case of more than one exist, all exist shall have locking
arrangement from in side of store.
(19) The representative i.e. work assistant from the department and contractor will keep day to day cement stock
balance report for main store as well as site store.
(20) 1% quality control charges shall be deducted from the bill amount up to 1% of the estimated cost
(21) All the materials, labours required for the specimen of test shall be born by the contractor.
(22) Curing shall be carried out as mentioned in the details specification, in case of further new work over the
previously carried out cement work, the curing on the superficial work shall be continued, accordingly and
(23) The earth embankment work by suitable or approved material shall be collected from the borrow area
specified by the department
(24) The lead mentioned in the tender is tentative. In case of availability of material from shorter lead, the rates
shall be reduced accordingly on the basis of S.O.R. increase or decrease by the percentage by which the
tender is above or below in the year in which tender is received.
(25) In case of availability of good I.P. or S.P. material, from shorter lead, the material shall be got approved by
the Engineer-in-charge. No extra payment for the cost of land or revenue charges shall be paid.
(26) No mixer machine or surface vibrator shall be given or arranged by the department.
(27) In case of failure of providing satisfactory curing arrangement the department will arrange of the same after
giving only one hour notice. only for once. On failure of none providing satisfactory arrangement the
department will provide the same and the charges will be deducted from the bills of the contractor.
(28) The dismantled lining shall be taken and stacked as per instruction of Engineer-in- charge. The property of
such dismantling shall be of department.
(29) The stacking of the materials required for the work shall be done in such a way as not to hamper or obstruct
the vehicular traffic of every kind.
(30) The sub-grade after demolition of existing lining shall be got approved form the Engineer-in-charge before
laying the concrete for lining. If the sub-grade is found porous and full of voids or consisting of rocky
mass, such material shall be removed up to maximum 1 mtr. depth and got filled up with good I.P. material
which is to be brought from surrounding borrow area with minimum lead as directed by Engineer- in-
charge. This earth filling shall be watered and compacted to the satisfaction of Engineer-in-charge.
(31) No deviation shall be made in the alignment of water course prior approval from the competent authority.
Signature of contractor Executive Engineer
Dahod Irrigation Division
SPECIFICATIONS OF MATERIALS
1.1 Water shall not be salty or blackish and shall be clean, reasonably clear and free from objectionable
qualities of silt and trace of oil injuries alkalis, salts, organic matter and other deleterious material which
will either weaken the mortar or concrete or cause efflorescence or attack the steel in R.C.C. Container for
transport, storage and handling of water shall be clean.
1.2 If required by Engineer-in-charge it shall be tested by comparison with distilled water. Comparison shall be
made by means of standard cement test soundness, time of setting and mortar strength. Any indicator of
unsoundness, change in time of setting by 30 minutes or more or decrease of more than 10% in strength of
mortar prepared with water samples when compared with mortar prepared with the result obtained with
mortar prepared with distilled water shall be sufficient cause for rejection of water under test.
1.3 Water for curing mortar, concrete or masonry should not be too acidic or too alkaline. The PH value of
water shall be in between 7 to 8. It shall be free of elements which significantly affect the hydration
reaction or otherwise interfere with the hardening of concrete during curing or those which produce
objectionable stains or other unsightly deposits on concrete or mortar surface.
1.4 Hard and bitter water shall not be used for curing.
1.5 Potable water will be generally found suitable for curing mortar or concrete.
2.1 Sand shall be natural sand, clean, well graded, hard strong durable and gritty participle free from injurious
amounts of dust clay, kankar, nodules, soft or flaky particles shale, alkali, salts organic matter, loam, mica
or other deleterious substance and still be got approved from the Engineer-in-charge. The sand shall not
contain more than 5% of silt as determined by field test. If necessary, the sand shall be washed to make it
2.2 COARSE SAND:-
The fineness modules of coarse sand shall not be less than 2.5 and shall not exceed 3. The sieve analysis of
coarse sand shall be as under as per I.S.
I.S. SIEVE PERCENTAGE BY WEIGHT
DESIGNATION PASSING SIEVE
600 Micron 30 to
300 Micron 5 to
150 Micron 0 to
3.1. Cement shall be used for the work, shall be ordinary Portland cement confirming to Indian standard
"specification for ordinary and low heat Portland cement I.S.269. The cement shall be procured by the
contractor. The contractor shall take every precaution to store cement properly, so that it may not spoiled
by dampness etc. Cement required for use shall be as fresh as possible and stored on wooden planks raised
15 to 20 cm. above the floor and stacked 20 cm. away from the wall in suitable closed weather proof
godown at the site of work. Necessary delivery challan and or bill from authorized dealer or manufacturing
company or authorized supplier shall be produced before making payment. The cement shall be of
recognized brand or company having production capacity of 2000 M.T. per day.
3.2. Cement shall be stored in such a away so as to allow the removal and use of cement in chronological order
of receipt i.e. first received being first used. Nor more than 15 bags shall be stacked vertically in one pile
and width of the piles shall not be more than 3 meters. Any cement which has deteriorated or which has set
or partially set shall not be used in the work.
3.3. TESTING OF CEMENT:-
The cement brought to the site for use in the work shall be tested for its compressive strength and setting
time before its use in the work in accordance with Indian standard method or physical tests for hydraulic
cement IS 4031. The compressive strength of cement shall be as under.
Type of Cement Strength in Kg/Cm2 After 28 days
Ordinary Portland Cement 100 220 --
Portland Puzolona cement - 220
For setting time of cement shall be as under:-
Type of Cement Minimum Initial time in Maxinyn setting time in
minutes minutes
Ordinary Portland Cement 30
Portland Puzolona cement 30
Frequency of collection and testing of cement for compressive strength and setting time shall be at least one
for each of 50 tones and at least once from each consignment of less than 50 tones.
M-4 GRAVEL OR BROKEN METAL AS COARSE AGGREGATE:-
4.1. Broken metal as coarse aggregate shall be of machine crushed of black trap or equivalent hard rock. The
coarse aggregate shall be hard, strong, dense, durable, clean and free from skin and coating likely to
prevent proper adhesion of mortar.
4.2. The aggregate shall generally be cubical in shape. Aggregate shall have no deleterious reaction with
cement. The size of coarse aggregate for plain cement concrete and ordinary reinforced cement concrete
shall be as per table given below. However in case of reinforced cement concrete the maximum limit may
be restricted to 6 mm. less than the minimum lateral clear distance between bars or 6 mm. less than cover,
whichever is smaller.
I.S. Sieve Percentage Passing for single I.S. Sieve Percentage Passing for
Designation sized aggregate of Designation single sized aggregate of
Nominal 40mm 20mm 16mm Sized 40mm 20mm 16mm
This percentage may be varied some what by the Engineer-in-charge. When consider necessary for
obtaining better density and strength of concrete.
4.3. The gradation test shall be taken in the beginning and at the change of source of materials. The necessary
test indicated in IS-383 and IS-456 shall have to be carried out to ensure the acceptability. The aggregate
shall be stored separately and handled in such a manner as to prevent the inter mining of different
aggregates. If the aggregates are covered with dust they shall be washed with water to make them clean.
M-5 CEMENT MORTAR:-
5-1. Water shall confirm to specification M-1. Cement shall confirm to specification M-Sand shall confirm to
specification M-2.
5.2. PROPORTION OF MIX:-
Cement and sand shall be mixed to specified proportion. Sand shall be measured by measuring boxes. The
proportion of cement will be by volume on the basis of 50 kg. bag of cement being equal to 0.0342 cum.
The mortar may be hand mixed or machine mixed as directed.
5.3 PROPORTION OF MORTAR:-
In hand mixed mortar cement and sand in the specified proportion shall be thoroughly mixed dry on a clean
impervious platform by turning over at least two times or more till a homogeneous mixture of uniform
colour is achieved. Mixing platform shall be so arranged that no deleterious extraneous material shall get
mixed with mortar or mortar shall flow out. While mixing, the water shall be gradually added and
thoroughly mixed to for a stiff plastic mass of uniform colour, so that each particle of sand shall be
completely covered with a film of wet cement. The cement ratio shall be adopted as directed.
5.4. The mortar so prepared shall be used within 30 minutes after adding water. Only such quantity of mortar
shall be prepared as can be used within 30 minutes.
6.1. The stone shall be of good hard stones. The stone shall be hard, sound, durable and free from defects, like
cavities, cracks and holes, flows injurious weans patches of loose or soft materials etc. and weathered
portions and other structural defects or tending to affect their materials etc. and strength. The stone with
round surface shall not be used. The percentage of water absorption shall not be more than 5% of dry
weight, when tested in accordance with IS 1134. The minimum crushing strength shall be 200 kg/Sq.cm.
unless otherwise specified.
6.2 The samples of the stone to be used shall be got approved before the work is started.
6.3 The Khanki facing stone shall be dressed by chisel as specified in the item for Khanki, facing of required
shape and size. The face of stone be so dressed that the placing on the exposed face shall not project by
more than 40 mm. from the general wall surface and on face to be plastered it shall not project by more
than 19 mm. not shall it have depressions more than 10 mm. from the average wall surface.
7.1. The brick shall be hand or machine moulded and made from suitable soils and kiln- burnt. They shall be
free from crack and nodules of free lime. They shall have smooth rectangular faces with sharp corners and
shall be uniform colour. The brick shall be moulded with a frog of 100 mm x 40 mm and 10 mm to 20 mm
deep-on one of its flat sides. The bricks shall not break when thrown on the ground from a height of
mm. The size of modular bricks shall be 190 mm x 90 mm x 90 mm.
7.2. The size of the conventional bricks shall be as under.
23 cms x 11.5 cms x 7.5 cms ( 9" x 4" x 3")
7.3. Only bricks of one standard size permitted in the conventional size or available from commercial market of
the jurisdiction pertain shall be used on one work. The following tolerances shall be permitted in the
conventional size adopted in a particular work. Length: 1/8" (3.0 mm) Width: 1/16" (1.5 mm) Height: 1/16"
7.4. The crushing strength of the bricks shall not be less than 35 kg/ Sq.cm. The average water absorption shall
not be more than 20% by weight. Necessary tests for crushing strength and water absorption etc. shall be
carried out as per I.S. 3495 (Part-I-IV).
M-8 STRUCTURAL STEEL :-
8.1. All structural steel shall conform to I.S. 226-1965. The steel shall be free from the defects mentioned in
L.S. 226-1975 and shall have a smooth finish. The material shall and be free from loose mild scale, rust pits
or other defects affecting the strength durability. Rivet bars shall conform to I.S.
8.2. When the steel is supplied by the contractor test certificates of the manufactures shall be obtained according
to I.S. 226-1975 and other relevant Indian standards if required by the Engineer-in-charge.
M-9 MILD STEEL BARS:-
9.1. Mild steel bars reinforcement for R.C.C. work shall conform to I.S.432 (Part: II) and shall be of tested
quality. It shall also comply with relevant part of I.S. 456. All the reinforcement shall be clean and free
from dirt, paint, grease, oil scales or loose or thick rust at the time of placing.
9.2. For the purpose of payment the bars shall be measured up to 10 mm. length and weight payable worked out
at the rate specified below as per IS-456.
1. 6 mm 0.22 Kg./Rmt.
2. 8 mm 0.39 Kg./Rmt.
3. 10 mm 0.62 Kg./Rmt.
4.. 12 mm 0.89 Kg./Rmt.
5. 14 mm 1.21 Kg./Rmt.
6. 16 mm 1.58 Kg./Rmt.
7 18 mm 2.00 Kg./Rmt.
8. 20 mm 2.47 Kg/Rmt.
9. 22 mm 2.98 Kg/Rmt.
10. 25 mm 3.85 Kg/Rmt.
11. 28 mm 4.83 Kg/Rmt.
12. 32 mm 6.31 Kg/Rmt.
13. 36 mm 7.99 Kg/Rmt.
14. 40 mm 9.86 Kg/Rmt.
The wastage and overlap exceeding 5 % shall be borne by the contractor.
M-10 R.C.C. NP-2 CLASS PIPES & COLLERS :-
The pipes & collars of NP-2 class as specified in, IS-458-1988 shall be used. All the relevant materials used
in pipes shall confirm to relevant latest Indian standard.
Contractor shall inform the department from which factory the pipes are to be procured and Engineer-in-
charge shall visit the factory and shall be tested for the following.
(i) For adequate quantity and quality cement, steel as per latest IS-458 -
(ii) For adequacy of dimensions.
(iii) Surface finishes.
(iv) Strength to withstand hydrostatic pressure satisfactorily.
To get okayed by the Engineer- in-charge and marked are only carted at site.
M-11 CHICKENMESH:-
The item includes the material cost, galvanizing, knitting, loading conveyance charges, unloading and
stacking as directed by the Engineer-in-charge.
The wire mesh shall of size 3/4 inch hexagonal. The wire mesh shall be galvanized of 20 gauge. The
thickness of the wire mesh shall be uniform. The tolerance limit in thickness shall not exceed 0.15 mm.
The wires are manufactured from mild steel / Electrode/ Em.1/quality steel wire rods and have following
chemical composition.
GRAEE MILD STEEL ELECTRODE/EM1.
% Carbon 0.23 Max. 0.10 Max.
% Manganese 1.50 Max. 0.38 to
% Silicon 0.35 Max. 0.03 Max
% Sutter 0.06 Max. 0.03 Max
% Phosphorus 0.06 Max. 0.03 Max
The tensile strength of the wire shall not be less than 55 kg/mm square. % age Elongation GL shall not
exceed 12% .Mini. Zinc coating shall not be less than 22 gram/Sqmt.. Conventional size of Chicken mesh roll of
mt. length & 0.90 mt. width shall have weight of 14.00 kgs. If the size of roll is 51 mt. x 0.90 mt. the weight shall
The wire net shall be hand or auto-knitted. The tolerance limit of opening shall not exceed 1.5 mm.
Wire net shall be treated with anticorrosive solution in tunnel type plant. The wire net after preparation
shall be galvanized with hot dip method in conveyor belt type plant. The payment shall be made on Smt. basis. The
length and width shall be measured in meter up to 0.01 decimal. Any deviation from above specified material or
norms in supply of mesh for the item shall be rejected by the competent authority and at contractor's cost. Before
laying chicken mesh on actual site of work all physical parameter shall got checked from Engineer-in-charge.
Signature of Deputy Executive Engineer Executive Engineer,
Contractor. Koliyari Sub Division No.1 Dahod Irrigation Division
Devgadh Baria Dahod
10.0 GENERAL CONDITIONS
10.1 DEFINITION OF TERMS :-
10.2 In constructing these general conditions and contract documents, the
following expressions shall have the meaning herein assigned to them unless
there is something in the subject or context inconsistent with such
10.3 The “ Government “ shall mean the Governor of Gujarat and shall unless
excluded by or repugnant to the context, include his successors in offices and
accepted assigns.
10.4 The “ Contractor “ shall mean the tenderer whole tender has been accepted
by the Government and shall include tender’s legal personal representative,
successors and assigns. The “ Sub-contractor “ shall mean the person named
in the contract for any part of the work or any person to whom any part of the
contractor has been sublet with the consent in writing of the Engineer and the
legal representatives, successors and assign of such person.
10.5 The “ Engineer “ or “ Engineer-in-charge “ or the “ Executive Engineer “ shall
mean the Executive Engineer, Deesa Irrigation Division, Deesa, for the time
being or such other officer as may be duly authorised and appointed in writing
by the Government to act as the Engineer for the purpose of the contract.
10.6 The Engineer where named as final authority for decision shall mean the
Superintending Engineer, in charge of the work to whom the Contractor shall
have a right of appeal when the contractor is not satisfied with the decision of
the Executive Engineer.
10.7 The “ Chief Engineer “ shall mean the Chief Engineer (CG) & Additional
Secretary, Narmada, Water Resources, Water Supply & Kalpasar
Department, Gujarat State, Gandhinagar.
10.8 The “ Contract “ shall mean and include the documents specifying invitation
for tenders, work and site conditions, General Conditions, Special Conditions
Printed SBD form with all its appendices, and technical specifications, the
contract between the contractor and the Government.
10.9 The “ Specifications “ shall mean the specifications included laid down or
implied in the contract documents.
10.10 The “ Site “ shall mean the lands and the other places, on under in or through
which works are to be executed or carried out or any lands or places provided
by the Govt. for the purpose of the contract and includes such other are as
approved by the Superintending Engineer
10.11 “ Construction Plant “ shall mean all appliances, machineries, equipment like
stock or things of whatsoever nature together with necessary supplies or
upkeep and maintenance required in or about the proper execution,
completion or maintenance of the works or temporary works, but does not
include materials or other things intended to form or forming part of the
permanent works.
10.12 “ Temporary work “ shall mean all temporary works of every kind requiring
in or about the proper execution, completion or maintenance of the work.
10.13 “ Month “ shall mean the calendar month.
10.14 “ Writing “ shall include any manuscript, type written or printed statement
under or over signature and / or a seal as the case may be.
10.15 “Tendered rates” shall mean the estimated rates entered in work in Bill of
Quantity (Schedule-B) of the tender reduced or increased by the percentage
entered by the contractor in tender for works and accepted by the
10.16 Tender for works and accepted by the Government.
Deputy Executive Engineer
Dated signature of Contractor
Koliyari Sub Division No.1
WORK & SITE CONDITION
1.0WORK TO BE EXECUTED UNDER THIS TENDER:
10.17 The present tender cover the work of Construction A New Lift Irrigation
Scheme At. Village. Zapatiya, Ta.Dhanpur, Dist.Dahod. The above
information is only a general out line and dose not in any way limit the scope
of work under this tender. No claim shall be entertained if any of the items or
individual works are deleted or minor charge in location after tender is
10.18 No extra rate over tender rate shall be payable out side the terms of tender
agreement for variation of quantities on any account. Tendered rate shall be
inclusive of all the expense to complete the work as per Schedule ‘B’
10.19 LOCATION :
10.20 The location of work is shown in Index plan included in the tender drawing.
The site of work under this tender is situated Near , Ta.Dhanpur, Dist.Dahod
10.21 COMMUNICATION :
10.22 The nearest town is Dhanpur, and work site is situated near the Village
Zapatiya, Ta.Dhanpur, Dist.Dahod.
10.23 The nearest railway station is Piplod and is on Delhi-Bombay railway line.
10.24 The nearest post office and telephone office at Dhanpur which is situated at a
distance of about 14 km. from site. There is also a branch of state Bank at
10.25 LABOUR,HOUSING ,WATER SUPPLY AND DRAINAGE
10.26 Some unskilled labour may be available locally but skilled labour will hardly
be available in required numbers at work site for this type of work. The
contractor shall however make his own inquiries and arrangement for skill and unskilled
10.27 No local housing is likely to be available. The contractor should plan for
suitable housing for his staff and labour within the area as may be available
to him on rental basis.
10.28 The contractor will have to make his own arrangement of water supply for his
work and camp. The contractor shall have to make his own arrangement for
pumping, purification, installing pipeline etc. as necessary at his own cost.
10.29 Suitable and adequate arrangements shall be made by the contractor for
drainage of domestic and rain water around his camp and the work spots.
10.30 The contractor shall be responsible for maintaining law and order in his camp
and on his work by keeping, Watchmen and other person as required “
Unauthorized or Undesirable persons” shall be excluded from the camp and
from the works., if in the opinion (which shall not be questioned) of the
Engineer any employee or agent of the contractor misbehaves and/or causes
obstruction in the proper execution of work or other wise make himself
undesirable the contractor shall on receipt of the instruction to do so.
10.31 MEDICAL AID :
10.32 The nearby Govt. dispensary is at Dhanpur Moreover there are private
dispensaries also at village Dhanpur etc. which are nearer to the site of work.
10.33 The contractor shall also provide at his own cost first aid arrangement at the
various work spots in accordance with the labour rules and regulations and as
may be directed by the Engineer in charge.
10.34 POST, TELEGRAM AND TELEPHONES:
There is a general post office at Dhanpur, 14 km away from this work. There is
telephone exchange at dhanpur 14 km away from this work.
CLIMATIC CONDITION:
10.35 The work area is situated in relatively medium rainfall zone. The rainy season
commence normally from the middle of June and last up to end of September.
It has been observed that works are required to be totally closed in monsoon
but in the part of it, can be continued with precautions in dry spells during
10.36 SUPPLY OF PATROL AND DIESEL:
10.37 The contractor is advised to make his own arrangement for his requirements
of petrol and diesel. The nearest consumers pump is available at Pipero.
10.38 MATERIALS:
10.39 Cement shall be provided by the contractor as per actual requirement on site
of work or as per provision of Schedule “A” shall be followed. The cement is
to be purchased from the manufacturer who manufactures the cement as per
10.40 I.S. Specification. Necessary test results should be produced before utilization
in the work. The purchase bill will have to be produced to the department with
10.41 Sand is available in River Panam near site with average lead of 17 km at
Godha Village. However ,screening will be necessary to obtain required
gradation for all work.
10.42 The above information is given for general guidance to the tenderer and it doe
not in any way limit the performance of work under this tender, The tenderer
shall have to make his own arrangement of the quality and the quantity of the
construction materials as also requiring the accessibility to the structures,
locations nature of work etc. Department does not bind itself to any
conclusion or towards any conclusion that may be made by the tenderer in
this respect from this information and no claims on this account shall be
LOCATION OF SUB-DIVISION/DIVISION OFFICE.
10.43 The office of the Executive Engineer, Dahod Irrigation Division,Dahod, is
located at : Machhan Nala Colony, near Burhani Society, Station Road,
Dahod and can be contacted on Office Phone No.(02673) 224526, Dahod.
The sub- division office in charge of the work Namely DEPUTY
EXECUTIVE ENGINEER, Koliyari Sub Division No.1,Devgadh Baria
SPECIAL CONDITION
1.0 ACCURACY OF LINES, LEVELS AND GRADES :
The various works shall be done true to line, level and grade. The periodical checking of
these by the Government staff shall not absolve the contractor or his responsibility
regarding their accuracy. In case of any deviation or discrepancy in line level or grade at
the meeting faces the contractor shall make good the discrepancy at his cost and without
any for the additional work if any involved. Whenever each a discrepancy is found to arise
at the junction of work of difference contractors, the relative liability to set right their
respective discrepancy shall be fixed by the Engineer whose decision shall be final and
binding on the contractors concerned. The Engineer, shall further have the unquestioned
right, if need be, to rectify the discrepancies and recover the costs from the contractor or
contractors according to proportions as he may consider reasonable.
2.0 TESTING OF MATERIALS :
2.1 All materials before being incorporated in the work shall be inspected and tested before
using the same for the work, any work, on which such materials are used without prior
inspection (and when necessary testing) and without approval or written permission of the
Engineer-in-charge is liable to be considered as unauthorized defective and not acceptable.
2.2 All labour for collecting and transporting samples to Govt. Laboratory for tests will be
supplied contractor free of cost to Government. Testing charges will be born by the Govt.
Necessary arrangement for proper curing of cast specimen on work site and transport if
field samples from work site to laboratory shall be arranged by the contractor at his cost.
The contractor shall supply necessary materials at testing laboratory at his own cost.
3.0 SECURITY MEASURES :
In view of the strategic importance of all irrigation and power project and installations
security restriction may be imposed by the Executive Engineer
as per direction of the security authorities and the contractor shall abide by all such
instruction scrupulously. In case of identity card is introduced, the contractor shall at his
own cost provide for his persons, all such identity cards with photos, if necessary and get
these duly signed by the Executive Engineer of his authorized representative. The
contractor shall also keep the Executive Engineer informed regarding all visitors and obtain
proper permits for their visit to the work. No unauthorized visitors will be allowed on work
4.0 TREATMENT DURING MONSOON :
If during time, the works are in progress, the monsoon breaks, in it shall be the
responsibility of the contractor to preserve and maintain the safe condition of all materials,
machinery, tools and work sites from the floods due to seasonal or unseasonable rains,
cyclone etc. The damages to the work plant, Materials, Machinery etc. shall be good by the
contractor without any claims.
5.0 INSPECTION FACILITIES:
A motor able inspection road shall be maintained by contractor for inspection of the work
during construction in working period necessary temporary inspection facilities for the
detailed inspection shall also provide necessary temporary inspection facilities for the
detailed inspection of the work.
Proper diversion roads, for highway road traffic shall be maintained by the contractor with
proper signboards and red lights on entry and exist of the division etc. as directed by the
Engineer in charge in during currency of the contract without any type extra payment.
7.0 DELETION CHANGE TYPE AND/OR LOCATION OF STRUCTURE
The drawing supplied to the contractor are works to the carried out shall be as per the
details furnished by the Department form time to time. If any of the items of particular
works is required it be omitted due to bonafied reasons, the same shall be deemed to be
withdrawn from the contractor and no claim
what-so-ever on account of minor change of locations in site shall be entertained.
Deductions form running account bill of the following items shall be made to the extant
mentioned against each item.
1. Securities deposit at stipulated rates.
2. Penalty if any in full.
3. Expenditure in incurred by Government on behalf of the contractor
4. Recoveries on account of secured advance on materials in full.
5. Hire charge to plant and equipment in full.
6. Other recoveries in full.
7. Income tax deduction. (TDS 2%)
9. Labour Welfare Cess 1%
10. Testing charges 1% of estimated amount.
9.0 All the expenses for sampling and testing charges for all materials shall be born by the
List of I. S. Code and other publication
1.0 Applicable Publications.
Generally Bureau of Indian standard codes (latest version of I. S. code) shall be
followed for all items of works, Wherever such code does not exist, the reference shall be taken
from other technical publications as directed by Engineer- In- Charge.
1.1 Indian Standards and Other Publications : ( for Earthwork )
1 IS: 1498 -1970 Classification and identification of soils for
general engineering purposes (first revision)
(Amendment Nos.1 and 2)
2 IS: 2809 -1972 Glossary of terms and symbols relating to
soil engineering (first revision).
3 IS: 3764 -1966 Safety code for excavation work
(Amendment No. 1)
4 IS: 7293 -1974 Safety code for working with construction
5 IS: 4701 -1982 Code of practice for earthwork on canals
(first revision)
6 IS: 1720 -1978 (Part I to xx) Methods for testing of soils
7 IS: 2720 -1983 Methods of test for soils
(Part - I to X & Part 14)
8 IS: 1888 -1982 Methods of load test on soil( second
9 IS: 2131 -1981 Method of standard penetration test for soils
(first revision)
10 IS: 5529 -1985 (Part-I ) Test in overburden ( first revision)
11 IS: 7894 -1975 Code of practice for stability analysis of
earth dams (Amendment-No.1)
12 IS: 8237 -1985 Code of practice for protection of slopes for
reservoir embankments (first revision)
0 -1 U.S.B.R. (United State Earth manual
Bureau of Reclamation) (Second edition 1974, reprinted 1985)
0 - 2 Central Water commission Safety manual
1.2 Indian Standards and Other Publications: (for Concrete work )
1 IS :8112 Specification for 43 grade ordinary Portland cement
(First revision)
2 IS:12269 Specification for 53 grade ordinary Portland cement.
3 IS :455 Specification for Portland Slag Cement (Fourth
4 IS :1489 Specification for Portland pozzolana cement
(Third revision) (Part I & II)
5 IS :3535 Method of sampling hydraulic cement ( First revision)
6 IS :4845 Definitions and terminology relating to hydraulic
cement (Reaffirmed 1987)
7 IS :4031 Methods of physical tests for hydraulic cement
( part 1 - 13) (First revision)
8 IS :4032 Method of chemical analysis of hydraulic cement (First
9 IS:8041 Specification for rapid hardening Portland cement
(Second revision )
10 IS:8043 Specification for Hydrophobic Portland cement
( Second revision)
11 IS :5512 Specification for flow table for use in test of hydraulic
cement and pozzolanic materials (First revision)
12 IS :2580 Jute sacking bags for packing cement (Second revision)
(With Amendment No. 1 to 3 )
13 IS :650 Specification for standard sand for testing of cement
(First revision) (Amendment No.1,2&3)
14 IS :383 Specification for coarse & fine aggregate from natural
sources for concrete (Second revision)
15 IS :460 Specification for test sieves (Part 1 to 3 )
16 IS :2430 Methods for sampling of aggregates for concrete (First
17 IS :2386 Method of test for aggregates for concrete.
(Part I - VIII)
18 IS :5640 Method of test for determining aggregated impact value
of soft coarse aggregates.
19 IS :456 Code of practice for plain & reinforced concrete
(Fourth revision)
20 IS :457 Code of practice for general construction of plain and
reinforced concrete for dams & other massive structures.
21 IS :4926 Specification for ready mixed concrete (First revision)
22 IS :1199 Method of sampling and analysis of concrete.
23 IS :516 Method of test for strength of concrete (Amendment
24 IS :3085 Methods of test for permeability of cement, mortar and
25 IS:1791 Specification for batch type concrete mixers (Second
26 IS :2722 Specification for portable swing weigh batchers for
concrete (Single & double bucket type)
27 IS :4634 Methods for testing performance of batch type concrete
28 IS :5892 Specification for concrete transit mixer and agitators.
29 IS :7245 Specification for concrete pavers.
30 IS :4925 Specification for concrete batching & mixing plant.
31 IS : 6461 Glossary of terms relating to cement concrete vibrators.
(Part I to XII)
32 IS :2505 General requirement for concrete vibrators (immersion
type) (Second revision)
33 IS :2506 General requirements for screed board concrete
34 IS :4656 Specification for form vibrators for concrete.
35 IS :6923 Methods of test for performance of screed board
concrete vibrators.
36 IS :5889 Specification for vibratory plate compactor.
37 IS :3558 Code of practice for use of immersion vibrators for
consolidating concrete.
38 IS :4558 Code of practice for under drainage of lined canals
(First revision)
39 IS :3873 Code of practice for laying in situ cement concrete lining
of Canal ( First revision )
40 IS :5256 Code of practice for sealing joints in concrete lining on
41 IS :7861 Code of practice for extreme weather concreting.
42 IS :5513 Specification for vicat apparatus(First revision)
(Amendment No.1)
43 IS :5515 Compacting factor apparatus (First revision )
44 IS :5529 Code of practice for in-situ permeability test.
45 IS:5816 Method of test for splitting tensile strength of concrete
cylinders.(First revision)
46 IS :7320 Specification for concrete slump test apparatus
(Amendment No.1 )
47 IS :9284 Method of test for abrasion resistance of concrete.
48 IS :8142 Method of test for determining setting time of concrete
by penetration resistance.
49 IS :9013 Method of making curing & determining compressive
strength of accelerated cured concrete test specimen.
50 IS :9103 Specification for admixtures for concrete. (First
51 IS :6925 Methods of test for determination of water soluble
chlorides in concrete admixtures.
52 IS:12200 Code of practice for provision of water stops at
transverse and construction joints in masonry and
53 IS :8989 Safety code for erection of concrete frame structures.
54 IS :303 Specification for plywood for general purposes (Second
revision) (Amendment No.1 to4)
55 IS :883 Code of practice for design of structural timber in
building (third revision)
56 IS :4990 Specification for plywood for concrete shuttering work
(First revision ( Amendment No.1)
57 SP:16 (S & T) Design aids for reinforced concrete to IS :
58 SP:23 Handbook for Concrete Mix.
59 IS:3370 Code of practice for concrete structures for the storage
of liquids ( part I to IV)
0 - 1 Indian Standard specification and code of practice for Road
Road Congress Bridges.
(IRC) Section – I, Section – II, Section – III
0 - 2 The United Concrete Manual (Eighth Edition) (Revised– 1981)
State Bureau of
0 - 3 American All relevant codes.
0 - 4 ACI codes and All relevant codes.
0 - 5 CBIP Manual on canal lining
0 - 6 MORT & H Specifications for Road & Bridge works (fourth
revision, August 2001, reprinted in January 2002)
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Construction A New Lift Irrigation Scheme At Village Zapatiya.pdf
Nivida No 13 full.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .