Loading…
Loading…
Tender Value
₹1.5 Cr
EMD Value
₹3.0 L
Closing Date
10 Jul 2026, 11:00 amClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
BRIDGE
18 conditions · 4 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or V which ever is less: where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
As a proof of technical experience/competence, (a)The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i)Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii)Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii)One similar work costing not less than the amount equal to 60% of advertised value of the tender. (b)(1) In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i)Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii)Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii)One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note for b(1): Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components. (b)(2)In such cases, what constitutes a component in a composite work shall be clearly pre- defined with estimated tender cost of it, as part of the tender documents without any ambiguity. (b) (3) To evaluate the technical eligibility of tenderer, only components of work as stipulated in tender documents for evaluation of technical eligibility, shall be considered. The scope of work covered in other remaining components shall be either executed by tenderer himself if he has work experience as mentioned in clause 7 of the Standard GCC through subcontractor fulfilling the requirements as per clause 7 of the Standard GCC or jointly i.e., partly himself and remaining through subcontractor, with prior approval of Chief Engineer in writing. However, if required in tender documents by way of Special Conditions, a formal agreement duly notarised, legally enforceable in the court of law, shall be executed by the main contractor with the subcontractor for the component(s) of work proposed to be executed by the subcontractor(s), and shall be submitted along with the offer for considering subletting of that scope of work towards fulfilment of technical eligibility. Such subcontractor must fulfill technical eligibility criteria as follows: The subcontractor shall have successfully completed at least one work similar to work proposed for subcontract, costing not less than 35% value of work to be subletted, in last 5 years, ending last day of month previous to the one in which tender is invited through a works contract. Note: for subletting of work costing up to Rs 50 lakh, no previous work experience of subcontractor shall be asked for by the Railway. (refer Clause 10.1 Part-I of SGCC 2022)
Defination of Similar Work :- Any bridge/ROB/RUB/LUS/FOB of RCC/PSC Composite Construction, either precast outside and launched/pushed in or cast in situ after inserting temporary girders.
In case after award of contract or during execution of work it becomes necessary for contractor to change subcontractor, the same shall be done with subcontractor(s) fulfilling the requirements as per clause 7 of the GCC with prior approval of Chief Engineer in writing
The tenderer must ensure that the quantum of similar nature of work done has to be specifically mentioned in the uploaded experience 1.2.1 certificate by the concerned authority whom the certificate is issued .Otherwise ,the offer is liable to be rejected
Work experience certificate from private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organisation, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate 1.2.2 has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate.
Defination of Similar Work :- Any bridge/ROB/RUB/LUS/FOB of RCC/PSC/Composite Construction, either precast outside and launched/pushed in or cast in situ after inserting temporary girders
60 conditions · 17 needing a document upload
Whether required test certificates/ samples, if any have been uploaded?
The tenderer whether sole proprietor / a company or a partnership firm / joint venture (JV) / registered society / registered trust / HUF / LLP etc if they want to act through agent or individual partner(s), should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, specifically authorizing him/them to sign the tender, submit the tender and further to deal with the Tender/ Contract up to the stage of signing the agreement except in case where such specific person is authorized for above purposes through a provision made in the partnership deed / Memorandum of Understanding / Article of Association Board resolution, failing which tender shall be summarily rejected. A separate power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, shall be submitted after award of work, specifically authorizing him/them to deal with all other contractual activities subsequent to signing of agreement, if required. Note: A Power of Attorney executed and issued overseas, the document will also have to be legalized by the Indian Embassy and notarized in the jurisdiction where the Power of Attorney is being issued. However, the Power of Attorney provided by Bidders from countries that have signed the Hague Legislation Convention 1961 are not required to be legalized by the Indian Embassy if it carries a conforming Appostille certificate.
The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or on behalf of a Partnership Firm/Company/Joint Venture (JV)/Registered Society/Registered Trust/Hindu Undivided Family (HUF)/Limited Liability Partnership (LLP) etc. The tenderer(s) shall enclose the attested copies of the requisite documents (including Power of Attorney, if opted) for constitution of their concern as per Cl. 14 of GCC-Part-1 and as per a)Clause 17 of GCC - Part - 1, for JV b)Clause 18 of GCC - Part - 1, for Partnership Firm.
Copies of the following documents are to be uploaded:- i)Details such as Name of the tenderer/contractor, Validity of DSC, Complete address with pin code, Contact Number ii)Copy of PAN card iii)Copy of GSTIN card
A copy of NEFT form duly filled in the details as necessary to be uploaded. (The Tenderer/Contractor not having NEFT form may download the empty NEFT form available in document site)
Submission of Annexure-V(A) under Document Verification Certificate In case of other than Company/Proprietary firm, Annexure-V(A) shall also be submitted by the each member of a Partnership Firm / Joint Venture (JV) / Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc. as the case may b e . Non-submission of the above Certificate(s) by the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon the tenderer to identify, state and submit the supporting documents duly self attested / digitally signed by which they/he are/is qualifying the Qualifying Criteria mentioned in the Tender Document.
As per Rly Board vide letter No2022/CE-I/CT/GCC Correspondence dated 14/05/2024, it was advised that " On IREPS Module a facility has already been created for online submission of Annexure V. Therefore, the provision of downloading of Annexure V of GCC & uploading of physically signed Annexure V by the tenderer had been discontinued on IREPS" . Hence the tenderers advised to use this option in IREPS module to submit certification related to Annexure V. The tenderers are advised to follow the instructions stated in IREPS module regarding this.
Scanned copy of PAN card has to be enclosed
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
All works tenders or service tenders invited by railways through e-tendering on IREPS, having advertised value of Rs 10 lakh and above, contractors are eligible to take payment from Railways through a Letter of credit (LC) arrangement. (Ref: RB letter no.2018/CE-I/CT/9 dated 04.06.18) (i) For all the tenders having advertised cost of Rs 10 lakh or above, the contractor shall have the option to take payment from Railways through a letter of credit (LC) arrangement. (ii) T h i s option of taking payment through L C arrangement h a s t o be exercised in !REPS (Indian Railway Electronic Procurement System - the e-application on which tenders are called by Railways) by the tenderer at the time of bidding itself, and the tenderer shall affirm having read over and agreed to the terms and conditions of the LC option.(iii) The option so exercised, shall be an integral part of the bidder's offer. (iv) T h e above option of taking payment through LC arrangement, once exercised by tenderer at the time of bidding, shall be final and no change shall be permitted, thereafter, during execution of contract. (v) In case tenderer opts for payment through LC, necessary procedure for LC mode of payment shall be followed to deal release of payment through LC:
In case, submission of Bid Security in the form of Bank Guarantee, following shall be ensured: i.A scanned copy of the Bank Guarantee shall be uploaded on e-Procurement Portal (IREPS) while applying to the tender. ii.The original Bank Guarantee should be delivered in person to the official nominated as indicated in the tender document before closing date of submission of bids ( i.e. excluding the last date of submission of bids). 1. The Bid Security shall be deposited either in cash through e-payment gateway or submitted as Bank Guarantee bond from a scheduled commercial bank of India or as mentioned in tender documents. The Bank Guarantee bond shall be as per Annexure- VIA and shall be valid for a period of 90days beyond the bid validity period. iii.Non submission of scanned copy of Bank Guarantee with the bid on e-tendering portal (IREPS) and/or non submission of original Bank Guarantee within the specified period shall lead to summary rejection of bid. iv.The Tender Security shall remain valid for a period of 90 days beyond the validity period for the Tender. v The details of the BG, physically submitted should match with the details available in the scanned copy and the data entered during bid submission time, failing which the bid will be rejected vi The Bank Guarantee shall be placed in an envelope, which shall be sealed. The envelope shall clearly bear the identification "Bid for the ***** Project" and shall clearly indicate the name and address of the Bidder. In addition, the Bid Due Date should be indicated on the right hand top corner of the envelope. vii The envelope shall be addressed to the officer and address as mentioned in the tender document. viii If the envelope is not sealed and marked as instructed above, the Railway assumes no responsibility for the misplacement or premature opening of the contents of the Bid submitted and consequent losses, if any, suffered by the Bidder.
Subject to exemptions provided under para 5(1) (a) of Part-1 (ITT) of SGCC 2022, the tender must be accompanied by a Bid Security as mentioned in tender documents, failing which the tender shall be summarily rejected.
ERS - KTYM - KYJ Section - Pro. Reconstruction of Exg. Bridge No. 297 (1 x 4.57m PSC slab ) as 1 x 6.10m RCC box at km. 58 / 000 - 100 between Ettumanur and Kottayam stations.
22-TVC-6-2026
22-TVC-6-2026
Open
Works - General
12 Months
Thiruvananthapuram, Kerala
₹0
₹3.0 L
10 Jul 2026
18 Jun 2026
26 Jun 2026
50 items across 1 schedule · ₹57,53,945.14 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Manufacturing and supply of blanketing material by wet mixing of different types of naturally available suitable soil including additional blending with naturally available or manufactured material as required to achieve specified gradation, in designed proportion in Pug mill or wet mix plant to have uniform gradation as per RDSO Specification No. RDSO/2020/GE: IRS-0004 with latest correction slips including all incidental transportation and stacking at site in Stacks. Note: Measurement shall be done in as per Stack measurement. | cum | 60.00 | 1,519.79 | 91,187.4 |
| 2 | Driving rails 90R/52 Kg section below average ground level within the slope/toe of embankment including making of nose with contractor's own arrangement complete in all respect Note: Payment will be made as per actual driven length of rail which will be supplied free by Railways at the site of work. | Metre | 125.00 | 131.97 | 16,496.25 |
| 3 | Shoring with 'Z' section MS sheet piles side by side in all kinds of soil mechanically or manually as per approved drawing with contractor's own arrangement complete in all respects and removal of sheet piles after completion of the work as directed by engineer in- charge Note: Payment will be made as per actual driven length of pile. | Sqm | 45.00 | 1,104.42 | 49,698.9 |
| 4 | On top of subgrade or prepared subgrade before laying blanketing layer with minimum strengths in Grab test, Trapezoidal Tear test and Puncture test of 700N, 250 N and 1800 N respectively. | Sqm | 100.00 | 232.13 | 23,213 |
| 5 | All kinds of soils | cum | 360.00 | 232.59 | 83,732.4 |
| 6 | Soft rock (not requiring blasting) | cum | 90.00 | 513.32 | 46,198.8 |
| 7 | Providing and laying in position machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using 20mm graded crushed stone aggregate and coarse sand of approved quality in RCC raft foundation & Pile cap including finishing, using Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability complete as per specifications and direction of the Engineer in charge. Note: 1. Payment for cement, reinforcement and shuttering shall be made extra under relevant item. 2. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons for not using plasticiser at the stage of Mix Design and in that case deduction shall be made as per relevant item. | cum | 45.00 | 4,994.99 | 2,24,774.55 |
| 8 | Providing and laying Plain Cement Concrete 1:3:6 with graded stone aggregate of 40mm nominal size, in foundation and floors, retaining walls of b r i d g e s including mechanical mixing, vibrating, pumping and bailing out water where ever required with all materials and labour complete but excluding the cost of cement and shuttering as per drawings and technical specifications as directed by Engineer. | cum | 35.00 | 5,190.51 | 1,81,667.85 |
| 9 | Providing and fixing Weep Holes in Abutments, Wing walls and Return walls etc., of new bridges with 110mm dia UPVC pipe Type A ISI marked with all contractor's men, material, transportation, all taxes as per specifications and as directed by Engineer-in-Charge. | Metre | 40.00 | 382.46 | 15,298.4 |
| 10 | Providing and casting machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix, mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants, (Cast in- Situ/Pre-cast) in bottom/top slab, side walls, toe wall and sumps haunch filling head walls, thrust bed or any other component using 20mm graded crushed stone aggregate and coarse sand of approved quality of RCC box of any size including finishing, Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability, complete as per drawings and technical specifications as directed by Engineer in charge. Note: 1. Payment for cement, reinforcement and shuttering shall be made extra under relevant item. 2. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons at the stage of Mix Design and in that case deduction shall be made as per relevant item. | cum | 160.00 | 5,494.49 | 8,79,118.4 |
| 11 | Providing and applying two coats of coal tar or bitumen confirming to IS:3117- latest version on the top and sides of RCC box/slabs @ 1.70 kg/sqm after cleaning the surface with all labour and materials complete job as directed by the Engineer. | Sqm | 165.00 | 190.27 | 31,394.55 |
| 12 | All types of bridge sub-structures, e.g. pier, abutment, wing wall, retaining wall, RCC box type foundations, Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Fender wall, Diaphragm wall etc. up to 5m above ground level | Sqm | 480.00 | 853.04 | 4,09,459.2 |
| 13 | Casting and installation of single/twin RCC box of all sizes with or without common web section after supporting the track on temporary girders including design of pushing scheme, thrust bed, casting of all RCC components, with specified grade of controlled concrete, pushing it in correct position and alignment below Railway track/Road following all measures of track safety by 'Air pushing technique" as per approved drawings/scheme, in all types of soils with disposal of surplus earth away from vent up to 1 Km, fixing arrangement for all services & utilities including parapet walls on both sides, wearing course, foot paths, plaques, drainage arrangements etc. and all other incidental works to complete the ROB/RUB/Canal crossing in all respect as per specifications to the satisfaction of Engineer-in-Charge. N o t e : (1) The rate includes all items of work/supplies for complete job in all respects except "cost of Reinforced cement concrete, cement, reinforcement & shuttering" of (i) main RCC Box; (ii) Thrust Bed; (iii) Footpath (iv) Parapet wall and (v) wearing Course only, which shall be paid extra under relevant items of USSOR. (2) The CC Cribs as required and Temporary Girder shall be supplied by Railways at available location. (3) Transportation of Temporary Girder to site shall be paid separately under relevant item.. (4) The payment for this item shall be made for the clear inner cross section area of the parent RCC Box/Boxes and barrel length i.e. clear inner volume of parent RCC Box/Boxes. | cum | 136.00 | 4,892.26 | 6,65,347.36 |
| 14 | With epoxy concrete grouting. | Kg | 180.00 | 183.03 | 32,945.4 |
| 15 | 150 MT capacity | Day | 1.00 | 1,92,930.61 | 1,92,930.61 |
| 16 | With one coat ready mix Zinc Chromate conforming to IS:104 with DFT of 25-30 Microns followed by one coat of Zinc Chromate red oxide conforming to IS:2074 DFT of 25 Microns | Sqm | 70.00 | 103.47 | 7,242.9 |
| 17 | With two coats of Aluminium paint in dual containers conforming to IS:2339 with DFT of 15 - 20 Microns for each coat. | Sqm | 70.00 | 121.84 | 8,528.8 |
| 18 | Supplying fabricating and erecting welded and/or bolted and/or riveted steel work in built up sections, trusses and framed work, staging, racks, Height Gauge etc. for Steel Structures other than bridge girders, using RSJ, tees, angles and channels/flats, plates, gussets, round or square bars, cleats, bolts etc., with contractors own steel including cutting, bending, straightening, drilling, riveting, hoisting, fixing, erecting, welding, bolting etc., with Providing stiffeners wherever required as per approved drawing including applying a priming coat of a approved steel primer with all contractor's materials, labour, tools & plants, lead & lift including crossing of tracks if required etc., complete as per specification and as directed by Engineer- in-charge. Note: The payment shall be made on the theoretical weight of main components and gusset plates only. | MT | 10.00 | 1,40,659.15 | 14,06,591.5 |
| 19 | Supplying of stone boulders weighing not less than 35 kg each at specified bridge locations. | cum | 25.00 | 1,739.32 | 43,483 |
| 20 | Providing and laying Pitching with Stone Boulders, weighing not less than 35kg each with voids filled with cement sand mortar 1:4 on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical Specifications (filter media to be paid separately under the relevant item). Rate is excluding cost of cement which shall be paid extra under relevant item. | cum | 30.00 | 4,869.91 | 1,46,097.3 |
| 21 | Providing and laying flooring with rubble stone, laid over 15cm thick CC 1:2:4 and the voids filled with CC 1:2:4 complete with the joints pointed with 1:2 Cement Sand mortar as per drawing and Technical specifications. Payment for cement to be done separately. Voids in the rubble stone to be taken as 35% of the gross volume of the stone layer. Note: Base concrete shall be paid extra under relevant item. | cum | 30.00 | 4,195.03 | 1,25,850.9 |
| 22 | Supply and laying of quarry dust including consolidation, supply of all materials, labour, lead, lift, tools, plants, crossing of tracks as per drawing and technical specification as directed by the Engineer in charge in case loose slush is encountered at site of foundation before casting the foundation or laying the filtering media. | cum | 50.00 | 2,657.59 | 1,32,879.5 |
| 23 | Neat Cement Grout with 20% anti shrinkage compound w.r.t. cement. | Kg | 280.00 | 470.47 | 1,31,731.6 |
| 24 | Providing cast in situ bridge number plaques as per Railway drawing in cement concrete 1:2:4 mix using 20mm hard stone aggregate embedded in 30mm notch in Bridge parapet coping duly engraving the letter and figures and an arrow indicating the direction of flow and finishing the top exposed surface with cement mortar 1:3, painting letters and figures with two coats of black enamel paint on two coats of white background with all labour, tools, cement, paint etc. with all leads and lifts. | Each | 4.00 | 1,206.22 | 4,824.88 |
| 25 | 600mm dia. | Metre | 20.00 | 3,548.99 | 70,979.8 |
| 26 | Providing Boulder Backing behind wing wall, return wall, retaining wall with hand packed boulders & cobbles with smaller size boulders toward the back including all lead, lift, labour & other incidental charges as complete work in all respect. Payment for boulder/cobbles will be done extra. | cum | 30.00 | 466.53 | 13,995.9 |
| 27 | Dewatering of natural or accumulated water from any location. Payment to be done for Horse power of pump multiplied by pumping hours. | HP Hour | 250.00 | 67.48 | 16,870 |
| 28 | Lifting and packing for regrading the existing PSC sleeper track to required height / level in stages not exceeding 75mm or part thereof at a time, providing permissible ramp for the track, insertion of moorum / sand / stone ballast uniformly under the existing track and placing the same to safe approved gradient, gauge, cushion including levelling and one round of through packing to allow train movement at restricted speed of 30 kmph for a specified length with all leads & lifts and fixing, marking, painting rail level pegs at every 30m interval. Note: Lifting of track shall be done in stages as per procedure prescribed in latest edition of IRPWM to get the proposed final level as per approved working profile, as directed by Engineer in-charge. | TRM | 100.00 | 211.2 | 21,120 |
| 29 | Extra for additional lift over 75mm for every 50mm lift or part thereof up to 275mm for item nos. 083010 for each TRM. | TRM | 100.00 | 32.79 | 3,279 |
| 30 | Dismantling of existing LWR/SWR track of any structure, removing rails, sleepers, fish plates, cutting of rails, segregation and stacking of released Rails, Sleepers and fitting at nominated location in countable manner within a free lead of 500m, levelling of ballast to correct profile for laying new track over it, all as per direction of Engineer-in-Charge. | TRM | 50.00 | 249.73 | 12,486.5 |
| 31 | For one shift ( 12 Hrs) | Each | 20.00 | 1,387.44 | 27,748.8 |
| 32 | For PSC Sleeper Track with Sleeper Density of 1540 | TRM | 100.00 | 147.73 | 14,773 |
| 33 | For PSC Sleeper Track with Sleeper Density of 1540 | TRM | 100.00 | 113.64 | 11,364 |
| 34 | HFL, FSL & DL on Bridge Pier / Abutment | Each | 2.00 | 770.07 | 1,540.14 |
| 35 | 60 Kg - 90 UTS- On Running Line | Each | 20.00 | 557.86 | 11,157.2 |
| 36 | I n Wagon where mechanical handling is possible and traffic block is not required or in Truck/trailer. | MT | 8.00 | 161.08 | 1,288.64 |
| 37 | From Wagon where mechanical handling is possible a n d traffic block is not required or in Truck / trailer. | MT | 8.00 | 118.81 | 950.48 |
| 38 | I n Wagon/Truck / trailer where mechanical handling is possible and traffic block is not required. | MT | 10.00 | 157.58 | 1,575.8 |
| 39 | Unloading all types of P.Way fittings and fastenings for Railway usage from Truck and stacking with lead up to 250 metre & lift up to 5 metre. | MT | 10.00 | 164.77 | 1,647.7 |
| 40 | Dismantling exiting Rail Height Gauge carefully and stacking the released material in countable manner, free from any infringements as directed by Engineer in-Charge including removal of cement concrete foundation and making surface clean. | Each | 2.00 | 4,365.86 | 8,731.72 |
| 41 | Fabrication including cutting, bending/machining and fixing of check rails of all rail sections over PSC Sleepers as per Railway's approved drawings & specifications for level crossings / trolley paths/inspection lines in yards duly cutting rail flanges, wherever required to correct alignment and level, drilling of holes with machine in check rails and fixing to Running rail and sleepers with all Railway's fittings, e.g. rail screws / grip expansion bolts, brackets, packing pieces, bolts, washers etc including grinding of brackets if required, fixing of Railway's wooden blocks at flare ends duly cutting and plaining, crossing of tracks and as directed by the engineer in- charge Note: 1. Drilling of holes in PSC Sleeper and fixing of dowels shall be paid under relevant item. 2. Required P.Way materials will be supplied at SSE/P.Way stores. | TRM | 20.00 | 1,352.77 | 27,055.4 |
| 42 | RH /Temporary girder of length above 16.3m and up to 26.00 using Road crane capacity of 80 MT | Each | 1.00 | 2,00,812.59 | 2,00,812.59 |
| 43 | Manufacturing and using wooden sleepers/blocks required for matting and bearing as per approved design for use below and above CC Crib for insertion of Temporary Girder etc.. Note: The item is for one time use and released wooden sleepers/blocks shall be the property of the Contractor. | cum | 30.00 | 2,017.82 | 60,534.6 |
| 44 | RH /Temporary girder of length above 16.3m and up to 26.00 using Road crane capacity of 80 MT | Each | 1.00 | 2,16,448.04 | 2,16,448.04 |
| 45 | Manufacture of flared portion of Guard Rail by cutting and bending to required shape & RDSO's approved drawings. N o t e : (1) Rails shall be supplied by Railways. (2) One set consists of two rails i.e. both left and right. | Set | 2.00 | 5,104.94 | 10,209.88 |
| 46 | Drilling holes 25mm to 40mm dia. with drill twist in the foot of guard rails for fixing guard rails on bridge as directed. | Each | 40.00 | 86.15 | 3,446 |
| 47 | Drilling of 25mm to 40mm dia. holes in PSC sleepers with suitable rotary hammer / drilling machine at indicated location for fixing of guard rails on bridges & its approaches as per approved drawing and fixing of contractor's HDPE dowels and adhesive of approved quality to Drawing no. RDSO/T-3002, procured from RDSO's approved sources with contractor's materials and consumable. | Each | 40.00 | 288.57 | 11,542.8 |
| 48 | JCB Backhoe Loaders 3DX Plus or similar with minimum 1.10 cum bucket capacity | Hour | 50.00 | 975.39 | 48,769.5 |
| 49 | Supplying and filling 50 kg size empty cement polythene bags with Rly. Ballast/moorum/earth/Sand/quarry dust etc. placing the filled bags on the high banks /bridge approaches/nominated place etc. dumping and spreading at the nominated locations to profile under block period with all contractor's labour, tools, plants, loading, unloading, filling, spreading including all lead/lift etc. complete and as directed by the Engineer in charge at site including crossing of track where necessary. | Each | 150.00 | 14.22 | 2,133 |
| 50 | cum | 60.00 | 46.52 | 2,791.2 | |
| Schedule total | ₹57,53,945.14 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
CorrectionslipGCC-1-11.pdf
ATTACHMENT
cmn.pdf
ATTACHMENT
Generalconditionoftrack.pdf
ATTACHMENT
SafetyprecautionsfromTRDsideforenggtenderdoc.pdf Safety
ATTACHMENT
GCCApril22.pdf
ATTACHMENT
Regulations.pdf
ATTACHMENT
BidsecuAnnexureVIAandVIB.pdf
ATTACHMENT
NEWPerformaofBGtowardsPG.pdf
ATTACHMENT
AnnexureVA.pdf
ATTACHMENT
ClarificationregsubmissionofAnnexV.pdf
ATTACHMENT
BridgeCondition.pdf
ATTACHMENT
BridgePlan.pdf
ATTACHMENT
Civil.pdf
ATTACHMENT
SafetyprecautionsfromTRDsideforenggtenderdoc.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .