Tender ID
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹24.2 LAdmitted-Fee/PreQual/Technical/Finance | L1 | Admitted-Fee/PreQual/Technical/Finance | ||
| 2 | L2₹26.2 L+₹2.0 L (8.11%)Admitted-Fee/PreQual/Technical/Finance AT PALLI P O BALIGUD P S PURI SADAR DIST PURI PIN 752045 | PURI | PURI | ODISHA | 752045 | L2 | Admitted-Fee/PreQual/Technical/Finance | ||
| 3 | L3₹32.8 L+₹8.5 L (35.1%)Admitted-Fee/PreQual/Technical/Finance | L3 | Admitted-Fee/PreQual/Technical/Finance | ||
| 4 | L3₹32.8 L+₹8.5 L (35.1%)Admitted-Fee/PreQual/Technical/Finance | L3 | Admitted-Fee/PreQual/Technical/Finance | ||
| 5 | L3₹32.8 L+₹8.5 L (35.1%)Admitted-Fee/PreQual/Technical/Finance AT KHARAVEL VIHAR P O SISUPAL P S DHENKI DIST KHORDHA PIN 751032 | KHORDHA | ODISHA | 751032 | L3 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹32.8 L
EMD Value
₹32,753
Closing Date
19 Mar 2026, 5:00 pmClosed
Er.Soumya Ranjan Dwibedi
O/o the S E R and B Division Puri
Construction of Additional Room and record rooms Sakhigopal Section Office in the District of Puri for the year 2025-26
2026_EICCL_127066_1
TCN NO 62 OF 2025-26
National Competitive Bid
Civil Works - Buildings
Percentage
120 days
Puri
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹32,753
Yes
20 Mar 2026
13 Mar 2026
20 Mar 2026
13 Mar 2026
19 Mar 2026
13 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling G.C.I. or A.C. sheet roofing after carefully removing the bolts and nuts including stacking of the materials for reuse and removing the debris within 50m lead | - | Sqm | 1 | - |
| 2 | Dismantling and removing doors, windows and ventilators including removal of frame, hinges, fastening and stacking the same for reuse and removing the debris within 50m lead | 1 | Sqm | - | - |
| 3 | Dismantling brick or stone masonry in clay under 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead | 1 | Cum | - | - |
| 4 | Clearing and grubbing roads and land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness. | 1 | Sqm | 1 | ₹1 |
| 5 | Earth work excavation in ordinary soil within 50m initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of engineer-in-charge. | - | Cum | - | - |
| 6 | Filling in Foundation, Plinth and other low laying area with excavated materials including cost of all labour, T&P etc complete including watering and ramming as directed by the Engineer-in-charge . | 1 | Cum | - | - |
| 7 | Supplying, Diluting and Preparing Chemical Emulsion like CHLORPYRIPHOS or other chemicals approved by Central Insecticides Board or as directed by the manufacturer and spraying the mixture uniformly by sprayer as pre-constructional Anti Termite Treatment and creating a chemical barrier under and around the column pits, wall trenches, basement excavation, top surface of plinth filling, junction of walls and floors along with external perimeter of the building, expansion joints, surrounding the pipes and conduits etc. complete at the rate of 7.5 liters (or as directed by the manufacturer) per sqm on vertical and 5.0 liters per sqm on horizontal surfaces, 50% of the emulsion to be filled in the holes made in trenches at 150mm center to center etc.complete as per IS:6313/1981(Part-II) and as per the direction of the Engineer-in-charge including cost of all materials, labour, taxes, etc. complete. | 1 | Sqm | - | - |
| 8 | Supplying and filling in foundation and plinth with sand including watering and ramming, poking and compacting including cost, conveyance, royalties, taxes of the materials and cost of all labour, labour cess, T&P etc. required for the work complete as directed by the engineer-in-charge. | - | Cum | - | - |
| 9 | Providing and laying Plain Cement Concrete of proportion (1:3:6) using 4 cm. size black hard crusher broken granite stone metal and screened and washed sharp sand for mortar of approved quality and from approved quarry including the cost of all materials, cost of labour, conveyance, taxes, royalties, loading, unloading, shuttering, centering, curing, labour cess, T&P, etc. all complete as per the direction of engineer-in-charge. | 1 | Cum | 1 | ₹1 |
| 10 | Terrace floor | - | Cum | 1 | - |
stage.html
html • 0.04 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.33 MB
DTCN.pdf
Tender Documents • 2.95 MB
BOQ_584511.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .