Loading…
Loading…
Tender Value
₹63.8 L
EMD Value
₹63,900
Closing Date
19 Jun 2026, 6:00 pm
Executive Engineer, R&B Division, Anand
Dhobikui Approach Road. Km.0/00 to 1/200. (Proposed Work : Resurfacing Road, Road Furniture & Other Misc. Works)
311164
02 of 2026-2027 (Sr. No.05)
Open
Civil Works - Others
Anand
1 document required · 1 mandatory
₹2,400
Executive Engineer, R and B Division, Anand
₹63,900
4 Jun 2026
4 Jun 2026
4 Jun 2026
19 Jun 2026
4 Jun 2026
Name of Work :- Dhobikui Approach Road Km 0/00 to 1/200 (Proposed Work:
Resurfacing of Road, Road Furniture & other Miscellaneous works)
Clause No. Page No.
1. Principle Approval Date and Amount Date:
(Attach letter) Rs. 141.60 Lakh
2. Administrative Approval Date and Date: 09.03.2026
Amount (Attach letter) Rs. 141.60 Lakh
3. Technical Approval Date and Amount Date: 01.05.2026
(Attach letter) Rs.
4. SOR Year 2024 -
2025 (Current SOR)
5. DTP amount IFB 4 Rs.
6. Tender Fee Rs. Rs.
(As per GR- PRCH-102000-lB- 221 (59)
Above 10.0 Cr.- Rs 18000)
7. Earnest Money Deposit (Bid Security IFB 4 Rs.
1% of DTP amount) Rs.
8. Time Limit (Months) Section 3 41 06 (Six) Months
9. Annual Financial Turnover Amount Rs. Section 1
IO. Defect Liability Period (In Months & Section 3 46 12 (Twelve) months
includes No of Monsoons) cl. 33.1 or 01 Monsoons
11. Free Maintenance Guarantee Period Section 3
(for Road & Bridge Construction) cl.
12. Registration / Category required "B" Class & Road Category-III &
13. Site Possession Date Section 3 42 ISt day of Work order#
14. Period between Program Update Section 3 44 45 Days
15. Amount to be withheld for late Section 3 44 1 Lakh
submission of Program cl.
16. Milestone Section 3 64 Days
(A) Milestone 1 25 45 Days
(B) Milestone 2 50 90 Days
(C) Milestone 3 75 135 Days
(D) Milestone 4 100 180 Days
#1n case of LA/ FRA is in progress give likely date.
Clause No. Page No.
17. Price Adjustment Components Section 4 66 0/0
(A) Labour, PL Section 4 66 16.14% Lo =
(B) Cement, PC Section 4 66 0.21% co =
(C) steel, Ps Section 4 67 0.00% so =
(D) Bitumen, Pb Section 4 67 59.94% Bo =
POL, Pf Section 4 68 4.27% Fo =
(F) Plant and Machinery Spares, Pp Section 4 68 pp = 4.04% Po =
(G) Other Materials, m Section 4 69 pm = 15.40% Mo =
18. Amount to be withheld for failing to Section 3 56 Rs. 5.00 Lacs
supply "as built" drawings cl.
19. Percentage Rate Contract (up to INR Section 7 78 Percentage Rate Contract
50 Cr.) / Item Rate Contract (above
*Input index / price for each component on 28 days preceding the date of opening of technical bid
shall be noted.
This is to certify that the contract document prepared for the work Dhobikui Approach Road Km
0/00 to 1/200 (Proposed Work: Resurfacing of Road, Road Furniture & other Miscellaneous works) is
based on the Standard Bidding Document Procurement of Civil Works published by R & B Department letter
No. RBD / 0346 / 10 / 2023 Date: 12/10/2023. No further modification and alteration in this standard format
has been made by this office.
ngineer Executi Engineer
R & B Sub Division, R & B Division,
GOVERNMENT OF GUJARAT
STANDARD BIDDING DOCUMENT
PROCUREMENT OF cuviL WORKS
COMPLETE BIDDING DOCUMENT
Name ofWork ohobi Kut appsoazh R.oci& o doo -to ao
c pnposea kesuø-seaino
goa F uz•e ot-het rn&elkq us
Divisional Accountant Executive Engineer
This is a generic SBD to be useck!er
needs to examine and put up their pa
criteria, contract Data etc., marked at [#1 'while finalizing their bidding precess,
Depu e Engineer Executiv Engineer
R & B Sub R& B Division
Sr No Section Description Page No
1 Invitation for Bid (IFB)
2 Section -i Instructions to Bidders
3 Section -2 Qualification Information
4 Section -3 Conditions of Contract
5 Section -4 Contract Data
6 Section -5 Technical Specification
7 Section -6 Form of Bid
8 Section -7 Bill of Quantities
9 Section -8 Secürities and Other
10 Section -9 Drawings
11 Section -10 Documents to be furnished by Bidder
INVITATION FOR BID
NATIONAL COMPETITIVE BIDDING
1. The invites bids for the construction of works detailed in
the table. The bidders may submit bids for any or all of the following works.
Package Name Approximate Bid Cost of Period of #Class of
No. of work value of works (Rs.) security document completion Registration /
(Rs.) (Rs.) Category of
L ohobiUu;npptouch Road zvoe.'oo
Fuminweeo.her .
Interested bidder may download the Bid Documents from website
https://www.nprocure.com free of cost till the Time and Date as mentioned on online NIT at website
https://www.nprocure.com. o
3. However, Bidder who is submitting the Bid Online will have to pay the Bid Document Fee / Tender Fee
through Demand Draft only of any Schedule Bank payable at and
in favour of 'Executive
the Bid is received online, Bid Document/ Tender Fee will not be refundable.
The Demand Draft for Bid Document / Tender fee and FDR / Bank Guarantee against Bid Security / EMD
shall •be submitted in electronic format through online (by scanning) while uploading the bid,
this submission shall mean that bid document / tender fee and Bid Security / EMD has been
received. Accordingly, the offer of only those shall be opened whose Bid Document / Tender Fee and Bid
Security I EMD have been received electronically. However, for the purpose of realization
of Demand Draft, and FDR / Bank Guarantee bidder shall send the same in original through
R.P.A.D. so as to reach to #Executive Engineer,
from the last day of bid submission.
a within 7 Days
Penaltative action for not submitting Demand Draft / FDR / Bank Guarantee in original to Executive
Engineer / Tender Inviting Authority by bidder shall be initiated.
4. Bids received online, will be opened on the time, date and place as specified in the online NIT at website
https://vwm.nprocure.com in the ofthe bidders or their authorized representatives, who wish to
remain present.
If the office happens to be closed on the day of opening of the bids as specified, the bids will be opened on
the next working day at the same time and venue.
5. A pre bid meeting will be held on .. .. at. ..hrs. at the
to clarify the issues and to answer questions on any
matter that may be raised at that stage as stated in clause 92 of 'instructions to Bidders' of the bidding
6. #Bid Security (EMD) is equal to
% of Estimated Amount put to bid / tender and should be rounded off to
the next thousand rupees.
7. Other Information is as under:
A. Agencies can prepare and edit their offers a number of times before the end of the tender
submission date and time. After the tender submission date and time, the bidder cannot modify /
edit/withdraw their submitted offer in any case. No written or online request in this regard shall
B. Offers in physical form will not be accepted in any case.
R & B Sub Division
Executiv Engineer
C, Demand Draft purchased by the other then bidder and issued after the last date of submission of
Bids, will not be considered
D. The cost incurred by the contractor for this offer for clarification or attending discussion,
conferences or site visits will not be reimbursed by the Employer or Engineer-in-Charge.
E, Conditional tender shall not be accepted.
Any changes, additioh, alternation made in the prescribed form attached with tender are liable to
G. Any change in format or conditional Bank Guarantee will not be accepted and the bidder will be
considered non-responsive.
H. All the bidders are instructed to fill in information strictly in accordance with the format given in the
checklist /qualification document/ tender document.
It is mandatory for the bidders to supply each and
every information as asked strictly in electronic
format at appropriate places only,
J, Blank / insufficient information shall be treated as nil information and shall result in
disqualification.
K. Even ifthe bidder has been qualified in a similar or larger size of project in the past, it shall not be
deemed to be a ground / reason for not giving required information forthiswork I bid.
L. Information supplied for earlier projects shall not be considered while evaluation of this bid. The
Government will not'ask for any other information, unless it is found absolutely necessary
competent authority.
M. Iffound necessary,the contractorwill be intimated for negotiation,
For the works costing up to 7.5 crore (ROAD), 7.0 crore (BUILDING
kindly refer to SSR-10-2015-17-C dated
For the works costing under 7.5 crore for Road Works and 7.0 crore for Building and Bridge Works
following documents shall be submitted in electronic format only through online by scanning and the
(i) Bid Document Fee / Tender Fee (ii) Bid Security / EMD should be sent in original to the Tender
opening authority through RPAD, so as to reach the Executive Engineer within 7 days from last day
of submission of Bid.
Bid Document Fee / Tender Fee
Bid Security [ EMD or Valid EMD Exemption Certificate of Appropriate Class of
Registration of Approved Contractors
(iii) Registration Certificate of Appropriate Class
Registration Certificate of Special Category Road / Bridge Building and
Category I / II / Ill, if required
(vi) Work Experience, necessary, e.
(vii) Other Documents, as required. ..
INSTRUCTIONS TO BIDDERS
Section 1: Instructions to Bidders
Table of Clauses
Page No. Page No.
A. General D. Submission of Bids
19. Sealing & Marking of Bids
1. Scope of Bid
2. Source of Funds
20. Deadline for Submission of
3. Eligible Bidders 8 21. Late Bids
4. Qualification of the Bidder 8 22. Modification •and
Withdrawal of Bids
5. One Bid per Bidder
6. Cost of Bidding
E. Bid Opening and Evaluation
23. Bid Opening
B. Bidding Documents 25. Clarification of Financial Bids
8. Content of Bidding 13 26. Examination of Bids and
Documents Determination of
9. Clarification of Bidding
Documents 27. Correction of Errors
10. Amendment of Bidding
Documents 29. Evaluation and Comparison
of Financial Bids
C. Preparation of Bids
11. Language of Bid
F. Award of Contract
12. Documents Comprising 15 31. Award Criteria
32. Employer's Right to Accept
13. Bid Prices 15 any Bid and to Reject any
14. Currencies of Bid and
33, Notification of Award and
Signing of Agreement
15. Bid Validity
34. Performance Security
16. Bid Security 16 35. Advance Payment and
17. Alternative Proposals By 17 Security
Bidders 36. Dispute Review Expert
18. Format and Signing of Bid 17 37. Correct or Fraudulent
1. Scope of Bid
1.1 The Employer (Named in Appendix to IT B) invites bids for the Construction of works (as defined in
these documents and referred to as 'the works") detailed in the table given in IFB. The bidders may
submit bids for any or all of the works detailed in the table given in IFB.
1.2 The successful bidder will be expected to complete the works by the intended completion date
specified in the Contract data.
1.3 Throughout these bidding documents, the terms 'bid' and 'tender' and their derivatives (bidder/
tenderer, bid / tender, bidding/ tendering, etc.) are synonymous.
2. Source of Funds
2.1 The expenditure on this project will be met from the budget of Govt. of Gujarat / Govt. of India for
centrally sponsored projects.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all eligible bidders.
3.2 All bidders shall provide in Section2, Forms of Bid and Qualification Information, a statement that the
Bidder is neither associated, nor has been associated, directly or indirectly, with the consultant or any
other entity that has prepared the design, specifications, and otherdocuments for the Project or being
proposed as Project Manager for the Contract. A firm that has been engaged by the Employer to
provide consulting services for the preparation or supervision of the works, and any of its affiliates,
shall not be eligible to bid.
4. Qualification of the Bidder
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary
description of the proposed work method and schedule, including drawings and charts, as
necessary. The proposed methodology should include a program of construction backed with
equipment planning and deployment duly supported with broad calculations and quality assurance
procedures proposed to be adopted Justifying their capability of execution and completion of work as
per technical specifications, within stipulated period of completion.
#4.5 QUALIFICATION CRITERIA:
(Applicable for the works which require Post Qualification)
4.5.1 Qualification will be based on Applicant's meeting all the following minimum pass/ fail criteria
regarding the Applicant's general and particular experience, personnel and equipment capabilities
and financial positions, as demonstrated by the applicant's responses in the forms attached to the
letter of application ( specified requirement for joint Ventures are given under para 4.6 below )
Subcontractors experience and resources shall not be taken in to account in determining the
applicants compliance with the qualifying criteria.
To qualify for more than one contract, the applicant must demonstrate having experience and
resources sufficient to meet the aggregate of the qualification criteria for each contract given in
paragraphs 4.5.4, 4.5.5 and 4.5,9 below:
4.5.2 Base year and Escalation
The base year shall be taken as Current financial year
Following enhancement factors will be used forthe costs ofworks executed and the financial figure to
a common base value for works completed in India,
Year Financial Year Multiplying factor
Base year of inviting tender 20
Applicant should indicate actual figures of costs and amount for the works executed by them
without accounting for the above-mentioned factors.
In case the financial figures and yalue of completed works
are in foreign currency the above
enhanced multiplying factors will not be applied. Instead, the current market exchange rate (State
Bank of.lndia BC Selling rate as on the last date of submission of the bid) will be applied for the
purpose of conversion of the amount in foreign currency into India rupees.
4.5.3. General Experience.
The Applicant shall meet with the following minimum criteria:
(a) Achieved a minimum annual financial turnover (defined as billing for works -in progress and
completed in all classes of civil engineering construction works only) in any one year; over the
last five years of the annual value of contract/ contracts applied for.
(b) Experience in successfully completing or substantially' completing at least one contract of
highway (road and / or bridge works) airport 'runwayof at least 40 percent of the value of
proposed contract within the last five years.
The works may have been executed by the applicant as prime contractor or as a member of a
joint venture or as a nominated sub-contractor. As subcontractor, he should have acquired the
experience of execution of all major items of works under the proposed contract. In case a
project has been executed by a joint venture, weight towards experience of the project would
be given to each joint venture in proportion to their financial participation in thejointventure.
Substantially completed works means those 'works which are at least 90 %
completed as on the date of submission (i.e. gross value of work done up to the
Deputy e Engineer Executiv Engineer
R & B Sub Division R& B Division
last date of submission is 90 % or more of the original contract price) and continuing
satisfactorily.
For these, a certificate from the employers shall be submitted along with the application
incorporating clearly the nameof the work, contract value, billing amount, date of
commencement of works, satisfactory performance of the contractor and any other relevant
4.5.4. Personnel Capabilities.
Availability for his work of personnel with adequate experience as required; as per Appendix.
4.5.5. Equipment Capabilities
Based on the studies carried out by the Engineer, the minimum suggested majorequipment to attain
the completion of works in accordance with the prescribed construction schedule are shown in the
The bidders should, however, undertake their own studies and furnish with their bid, a detailed
construction planning and methodology supported with layout and necessary drawings and
calculations to allow the employer to review their proposals. The numbers, types and capacities of
each plant/equipment shall be shown in the proposals along with the cycle time for each operation for
the given production capacity to match the requirements.
4.5.6. Financial Position
The Applicant should give undertaking that he has access to, or has available, liquid assets
(aggregate of working capital, cash in hand and uncommitted bank guarantees) and / or credit
facilities up to 25 percent of the value of the contract/ contracts applied.
4.5.7. The audited balance sheets for the last five years should be submitted, which must demonstrate the
soundness of the applicant's financial position, showing long term profitability including an
estimated financial projection for the next two years If necessary, the employer will make inquiries
with the applicant's bankers.
4.5.8. Litigation History
The Applicant should provide accurate information on any litigation or arbitration resulting from
contracts completed or under execution by him over the last five years. A consistent history of awards
against the Applicant or any partner of a joint venture may result in failure of the applicant.
4.5.9. Disqualification
Even though the applicants meet the above criteria, they are subject to be disqualified ifthey have:
Made misleading or false representation in the forms, statements submitted, and / or Record of
poor performance such as abandoning the work, rescinding of contract for which the reasons are
attributable to the non performance of the contractor; consistent history Of litigation awarded
against the applicant or financial failure due to bankruptcy. The rescinding of contract of a joint
venture on account of reasons other than non — performance, such as Most Experienced partner
of joint venture pulling out, court directions leading to breaking up of a joint venture before the start
are not attributable to the poor performance of the contractor will, however, not
affect the qualification of the individual partners.
#4.6 JOINT VENTURE: (Maximum 3 Members i.e. 1 Lead & 2 Others)
(Applicable only for estimated project cost of 50 Crore and above)
4.6.1. Joint ventures must complywith thefoflowing requirement:
(a) Following are the minimum qualification requirements:
(i) The lead partner shall meet not less than 50 percent of all criteria given in para 4.5.3&4.56
above, The joint venture must collectively satisfy the criteria of para 4.5.3 4,5.6 above. The
experience of the otherjoint venture partners shall be considered if it is not less than 30 percent
ofthe qualifying criteria in para 4.5.3 & 4.56 above.
(ii) Individually each member must satisfy the requirements of para 4.5.7&4.5.8 above.
(b) Bid shall be signed so as to legally bind all partners, jointly and severally, and shall be submitted
with a copy of the joint venture agreement providing the joint and several
liabilitieswith respect
to the contract.
4.6.2. Qualification of a joint venture does not necessarily qualify any of its partners individually
partner jn any other joint venture. In
case dissolution of a joint venture, each one of the constituent
firms may qualify if they meet all the qualification requirements, subject to the written approval of the
4.7. Bid Capacity.
Applicants who meet the minimum qualification criteria will be qualified only if their available bid
capacity at the expected time of bidding is
more than the total estimated cost of the Works. The
available bid capacity will be calculated as under:
Assessed Available Bid Capacity = (A*N*2-B), where
Maximum value of work executed in any one year during the last five years (updated to the
price level of the year indicated in appendix) taking into account the completed as well as
works in Progress.
Value at current price level of the existing commitments and ongoing works to be
during the next ( period of completion ofworkforwhich bids
are invited ); and
'Number ofyears prescribed for completionofthe works for which the bids are invited.
Note :-ln Case of joint venture, the available bid capacity will be applied for each partner to the
extent of his proposed participation in the execution of the work.
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified
Made misleading or •false representation in the forms, statements and Attachments the
submitted in proof the qualification requirements; and / or
Record of poor performance such as abandoning the works, not properly completing the
contract, inordinate delay in completion, litigation history, or financial failures etc.; and/ or
Participated in the previous bidding for the same work and had quoted unreasonably high bid
prices and could not furnish rationaljustification to the employer.
5. One bid per bidder
Each bidder shall submit only one bid for one package. A bidder who submits or participates in more
than one bid (other than as a subcontractor or in cases of alternatives that have been permitted or
requested) will cause all the proposals with the bidder's participation to be disqualified.
6. Cost of Bidding
6.1. The bidder shall bear all costs associated with the preparation -and submission of his Bid, and the
Employer will in no case be responsible and liable for those costs.
7.1. The Bidder, at the Bidder's own responsibility and risk is encouraged to visit and examine the Site of
work and its surrounding and obtain all information that may be necessary for preparing the Bid and
entering into a contract for construction ofthe Works.
The costs ofvisiting the site shall be at the Bidder's own expense.
B. BIDDING DOCUMENTS
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed below and addenda issued in
accordance with Clause 10:
Section Particulars Volume No,
Invitation for Bids
1 Instructions to Bidders
2 Qualification Information, and other forms
3 Conditions of Contract
5 Technical Specifications II
7 Bill of Quantities
8 Securities and other forms
10 Documents to be fumished by bidder
8.2. Volumes l, II, Ill and IV are available online and documents to be furnished by the bidder in compliance
to section 2 will be prepared by him and fumished as Volume-V in two parts (refer clause 12).
8.3. The bidder is expected to examine carefully all instructions, conditions of contract, contract data,
forms, terms, technical specifications, bill of quantities, forms, Annexes and drawings in the Bid
Document. Failure to comply with the requirements of Bid Documents shall be at the bidder's own
risk. Pursuant to clause 26 hereof bids which are not substantially responsive to the requirements
of the Bid Documents shall be rejected E
9. Clarification Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents may notify the Employer in
writing or through E-mail at the Employer's address indicated in the invitation to bid. The Employer
will respond to any request for clarification which he received earlier than 15 days prior to the deadline
for submission of bids. Employer's response will be published on website including a description of
the enquiry but without identifying its source.
9.2. Pre-bid meeting
9.2.1 The bidder or his official representative is invited to attend a pre-bid meeting which will take place at
the address, venue, time and date as indicated in the appendix.
9.2.2 The purpose of the meeting will be to clarify issues and to answer questions on any matter that may
be raised at that stage.
9.2.3. The bidder shall be required to submit any questions in writing or e-mail to reach the Employer not
later than 03 days before the meeting.
9.2.4 Minutes of the meeting, including the question raised (Without identifying the source of enquiry) and
the responses given will be published without delay on the tender website i.e. www.nprocure.com.
Any modification of the bidding documents listed in sub-Clause 8. I which may become necessary as
a result of the pre-bid meeting shall be made by the Employer exclusively through the issue of an
Addendum pursuant to Clause 10 and not through the minutes ofthe pre-bid meeting.
9.2.5 Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
10. Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding documents by
issuing addenda.
10.2. Any addendum thus issued shall be part of the bidding documents. The Employer will assume no
responsibility for the same.
103 To give prospective bidders reasonable time in which to take an addendum into account in preparing
their bids, the Employer may, at his discretion, extend as necessary the deadline for submission of
bids, in accordance with Sub-Clause 20.2 below.
C. PREPARATION OF BIDS
Language ofthe Bid
1.1 All documents relating to the bid shall be in the English language.
2. Documents Comprising the Bid
12.1. The bid be submitted by the bidder as Volume V ofthe• bid document (refer Clause 8.1 ) shall be in two
separate parts:
Part/ shall be named "Technical Bid" and shall comprise
(i) Bid Security in the form specified in Section
Qualification Information and supporting documents as specified in Section
(iii) Certificates,•undertakings,affidavits as specified in Section
(iv) Any other information pursuant to Clause 4.5 ofthese instructions
Undertaking that the bid shall remain valid for the period specified in Clause
Pan II shall be named "Financial Bid" and shall comprise
(i) Form ofBid as specified in Section
(ii) Piiced Bill ofQuantities for items specified in Section
12.2. The Bidder shall submit the details / informatioh pertaining to each part i.e. technical as well as
financial and must be submitted online only.
12.3. Following documents will be deemed to be part ofthe bid.
Section Particulars Volume No.
Invitation for Bids (IFB)
Instruction to Bidders Volume I
3 Conditions of Contract
4 Contract Data
5 Specifications Volume II
9 Drawings Volume IV
13.1 The Contract shall be for the whole works as described in Sub-Clause I .1 based on the priced Bill of
Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line item total (both in figures and words)
for all items of the Works described in the Bill of Quantities along with total bid. price
(Both in figures and words). Items for which no rate or price is entered by the bidder will not be
paid for by the Bill ofQuantities.
13.3 Al duties, taxes, and other levies except GST are payable by the contractor under the contract, or for
any other cause shall be included in the
rates, prices and total Bid Price submitted by the Bidder.
(GSTwill be paid extra)
13.5 The rates and prices quoted by the bidder are subject to adjustment during the performance of the
Contract in accordance with the provisions of Clause 47 of the Condition of Contract (Irrespective of
the time limit and Bid Amount)
14. Currencies of Bid and Payment
14.1 The unit rates and the prices quoted by the bidder shall be entirely in Indian Rupees. All payments
shall be made in Indian Rupees.
15. Bid Validity
15.1 Bids shall remain valid for a period of not less than 120 days after the deadline date forbid submission
specified in Clause
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may request that
the bidders extend the period ofvalidity for a specified period. A bidder may refuse the request without
forfeiting his bid security. A bidder agreeing to the request will not be required or permitted to modify
his bid, but will be required to extend the validity of his security for a period of the extension, and in
compliance with Clause 16 in all respects.
#16. Bid Security
16.1. The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in column 4 of the
table of IFB for this particular work. This Bid security shall be in favor of Employer as named in
Appendix and may be in one ofthe following forms;
a. Bank Guarantee from any scheduled Indian bank, in the format given in Volume Ill. (Bank
Guarantee is applicable only for Bid Estimated Amount of 01 Crore and above) and Bank
Guarantee of Schedule and Private Banks shall be considered as per GOG Finance
Department's Circular No. FD/MSM/e- file/4/2023/0057/D.M.O. Date 21/04/2023 or as per their
latest amendment.
b. Fixed Deposit Receipt issued by any Scheduled Indian Bank or a foreign Bank approved by the
Reserve Bank of India.
#A Valid Bid Security / EMD Exemption Certificate issued by (I) Road & Building Department or
(2) Narmada Water Resources, Water Supply and Kalpsar Department of Govt of Gujarat.
Exemption Certificate is applicable only when Registration Certificate of Appropriate
Class and Category of Approved Contractors is required as eligible criteria of bidder.
16.2. Bank guarantees (and other instruments having fixed validity) issued assurety for the bid shall be
valid for45 days beyond the validity ofthe bid i.e. total validity of 120+45 = 165 Days
16.3. Any bid not accompanied by an acceptable Bid Security and not secured as indicated in Sub-Clauses
16.1 and 16.2 above shall be rejected by the Employer as non-responsive.
16.4. The Bid Security of unsuccessful bidders will be returned within 28 days of the end of the bid validity
period specified in Sub-Clause
16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed the
Agreement and furnished the required PerformanceSecurity.
16.6. The bid Security may be forfeited
(a) Ifthe Bidderwithdraws the bid after Bid opening during the period ofBid validity.
(b) Ifthe Biddprdoes not accept the correction ofthe Bid Price, ifanyor
(c) In the case ofa successful Bidders, ifthe Bidderfails the specified time limitto
(i) Sign the Agreement; or
(ii) Furnish the requirement Performance Security,
(d) found necessary, the bidder will be intimated for negotiation, He will be intimated maximum
three times within the validity period for negotiation, If contractor does not respond in time, his
Bid Security (EMD) will be forfeited and his tender will be rejected. Punitive action will be taken
on such contractors. (As per GoG Dept's Gr. No. S/22/2017/6369/D, Dt.08/06/2018)
17. Alternative Proposals by Bidders.
17.1. Bidders shall submit offers that fully comply with the requirements of the bidding documents,
(7 including the conditions of contract (including mobilization advance or time for completion), basic
technical design as indicated in the drawing and specifications. Conditional offers or alternative offers
will not be considered further in the process of tender evaluation.
18. Format and Signing of Bid
18.1. The Bidder shall prepare documents comprising the bid as described in Clause 12 of these
Instructions to bidder as the "Technical Bid "and 'Financial Bid" in separate parts to be uploaded.
D. SUBMISSION OF BIDS
20. Deadline for Submission of the Bids
20.1 Complete Bids must be received online by the Employer at the tender website specified above not
later than the date indicated in appendix.
20.2 The Employer may extend the deadline for submission of bids by issuing an amendment in
accordance with Clause 10, jn which case all right and obligation of the Employer and the bidders
previously subject to the original deadline will then be subject to the new deadline.
22. Modification and Withdrawal of Bids
22.1 Bidders may modify or withdraw their bids online before the deadline prescribed in Clause 20 or
pursuant to Clause
22.3. No bid shall be modified orwithdrawn after the deadline for submission of Bid.
22.4. Withdrawal or modification of a bid between the deadline for submission of bids and the expiration of
the original period of bid validity specified in Clause 15.1 above or as extended pursuant to Clause
15.2 may result in the forfeiture of the Bid security pursuant to Clause
E. BID OPENING AND EVALUATION
23. Bid Opening
23.1 The Employer will open all the Bids received including modifications made pursuant to Clause 22, in
the presence ofthe Bidders or their representatives who choose to attend at time, date and the place
specified in Appendix in the
manner specified in Clauses 20 and 23.3, In the event of the specified
date of Bid opening being declared a holiday for the Employer, the Bids will be opened at the
appointed time and locationon the nextworking day.
23.3. The "Technical Bid" shall be opened. The amount, form and validity of the bid security furnished With
each bid will be announcéd. Ifthe bid security furnished does not conform to the amount and validity
as specified in the invitation for bid (ref. Column 4 and paragraph 3), and has not been
furnished in the form specified in Clause 16, the technical bid will not be opened.
23.4. (i) Subject to confirmation ofthe bid security by the issuing Bank, the bids accompanied with valid
bid security will be taken up for evaluation with respect to the Qualification information and other
informationfurnished in part I ofthe bid pursuant to Clause 12.1.
If required, the bidder will be asked in writing to clarify his Qualification Documents with respect
to any required clarification.
(iii) The bidderswill respond in not more than 7 days of issue ofthe clarification letter.
(iv) Immediately (usually within 3 or4 days), on receipt-oftheseclarification the Evaluation Committee
will finalize the list of responsive bidders whose financial bids are eligible for consideration.
23.6 At the time of opening of "Financial Bid", the.names of the bidders those who are
responsive accordance with Clause 23.4(iv) will be announced. The bids of only these bidders will
be opened. The responsive Bidders' names, the Bid prices, the totål amount of each bid, any discount
and such other details as the Employer may consider appropriate, will be announced by the
Employer at the opening.
23.7 the time of opening of "Financial Bid", the names of the bidders found responsive in accordance with
Clause 23.4(iv) will be announced. The bids of only these bidders will be opened those who are
declared responsive. The responsive Bidders' names, the Bid prices, the total amount of each bid,
declared responsive. The responsive Bidders' names, the Bid prices, the total amount of each bid,
any discount, and such Other details as the Employer may consider appropriate, will be announced
by the Employer at the time of opening.
23.8 In case bids are invited for more than one package, the order for opening of the "Financial Bid" shall
be in order of Estimated amount of Bids from highest to lowest.
23.9 The Employer shall prepare minutes of the Bid opening, including the•infomation disclosed to those
present in accordance with Sub-Clause 23.6.
24.1 Information relating examination, clarification, evaluation, and comparison of Bids and
recommendations for the award of a contract shall not be disclosed to Bidders or any other persons
not officially concerned with such process until the award to the successful Bidder has been
announced. Any effort by Bidder to influence the Employer's processing of Bids or award decisions
may result in the rejection of his Bid,
25. Clarification of Financial Bids
25.1. To assist in the examination, evaluation, and comparison of Bids, the Employer may, at his discretion,
ask any Bidder for clarification of his Bid, including breakdowns of unit rates. The request for
clarification and the response shall be in writing or by e- mail, but no change in the price or substances
of the Bid shall be sought, offered, or permitted except as required to confirm the correction of
arithmetic errors discovered by the Employer in the evaluation of the Bids.
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to his Bid
opening to the contract is awarded. If the Bidder wishes to bring additional information to the notice of
the Employer, it should do so in writing.
25.3. Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid comparison or
contract award decision may result in the rejection of the Bidders' bid.
26. Examinations of Bids and Determination of Responsiveness
26.1 During the detail evaluation of "Technical Bid", the Employer will determine whether each Bid (a)
meets the eligibility criteria defined in Clause 3 and 4; (b) has been properly signed; (c) is
accompanied by the required securities and; (d) is substantially responsive to the requirements of the
Bidding document. During the detailed evaluation of the "Financial Bid", the responsiveness of the
bids will be further determined with respect to the remaining bid conditions, i.e., priced bill of
quantities, technical specifications, and drawings.
26.2 A substantially responsive "Financial Bid" is one which confirms all the terms, conditions and
specifications of bidding documents, without material deviation or reservation. A material deviation or
reservation is one (a) which affects in any substantial way the scope, quality, or performance of the
Works; (b) which limits in any substantial way, inconsistent with the Bidding documents, the
Employer's rights or the Bidder's obligations under the Contract; or (c) whose rectification would
affect unfairly the competitive position of other Bidders presenting substantially responsive Bids.
26.3 If a "Financial Bid" is not substantially responsive, it will be rejected by the Employer, and may not
subsequently be made responsive by correction or withdrawal of the non-conforming deviation or
29. Evaluation and Comparison of Financial Bids
29.1. The Employer will evaluate and compare only the Bids determined to be substantially responsive in
accordance with Sub-Clause 26.2.
29.3. The Employer reserves the right to accept or reject any variation or deviation. Variation and
deviations and other factors, which are in excess of the requirements of the Bidding documents or
otherwise result in unsolicited benefitsfor the Employer, shall not be taken in to account in Bid
29.4. The estimated effect of the price adjustment conditions under Clause 47 of the Conditions of Contact,
during the period of implementation ofthe Contract, will not be taken in to account in Bid evalüation.
29.5. Ifthe Bid of the successful Bidder is seriously unbalanced in relation to the Engineer's estimate of the
cost of work to be performed under the contract the Employer may require the Bidder to produce
detailed consistency of those prices with the construction methods and schedule proposed. After
evaluation of the price analyses, the Employer may require that the amount of the performance
security set forth in Clause 34 be increased at •the expense of the successful /bidder to a level
sufficient to protect the Employer against financial loss 'in the event of default of the successful Bidder
underthe Contract.
29.6. A bid which contains several items in the bill of Quantities which are unrealistically priced low and
which cannot be substantiated satisfactorily by the bidder may be rejected as non-responsive.
F. AWARD OF CONTRACT
31. Award Criteria
31.1. Subject to Clause 32, the Employer will award the contract to the Bidder whose Bid has been
(i) to be substantially responsive to the Bidding documents and who has offered the lowest
evaluated Bid Price; and
(ii) to be within the available bid capacity adjusted to account for his bid price which is the lowest
evaluation in any ofthe packages opened earlier than the one consideration.
In no case, the contract shall be awarded to any bidder whose available bid capacity is less than
the evaluated bid price, even if the said bid is the lowest evaluated bid. The contract will in such
next lowest bidder at his evaluation bid price.
cases be awarded to the
32. Employer's Right to Accept any Bid and to Reject any or all Bids
32.1 Notwithstanding Clause 31 the Employer reserves the right to accept or reject any Bid, and to cancel
the Bidding process and reject all Bids, at any time prior to the award of contract, without thereby
incurring any liability to the affected bidder or Bidder or any obligation to inform the affected Bidderor
Bidders of the grounds for the Employer's action.
33. Notification of Award and Signing of Agreement
33.1 The Bidder whose Bid has been accepted will be notified of the award by the Employer prior to
expiration of the Bid validity period.by cable, telex or facsimile confirmed by registered letter. This
letter (hereinafter and in the condition of contract called the "Letter of Acceptance") will state the sum
that the Employer will pay the Contractor in consideration of the execution, completion, and
maintenance of the Works by the Contractor as prescribed by the Contract (hereinafter and in the
Contract called the "Contract Price").
33.2 The notification of award will constitute the formation of the contract, subject only to the furnishing of a
performance security in accordance with the provisions OfClause.
33.3. The Agreement will incorporate all agreements between the Employer and the successful Bidder. It
will be signed hy the Employer and to the successful Bidder, within 28 days following the notification
of award along with the Letter of Acceptance. Within 21 days of receipt, the successful Bidder will sign
the Agreement and deliver it to the Employer.
33.4. Upon the furnishing by the successful Bidder of the Performance Security, the Employer will promptly
notify the other Bidders that their Bids have been unsuccessful.
34. Performance Security
(A) Within 10 (Ten) days of receipt of Letter of Acceptance, the successful Bidder shall furnish to the
Employer an irrevocable and unconditional guarantee from a Bank in the form set forth in Section
8 (the "Performance Security") for an amount equal to 5% (five percent) of its Contract Price. In
case of bids mentioned below, the successful Bidder, along with the Performance Security,
shall also furnish to the Authority an irrevocable and unconditionål guarantee from a Bank in the
same form given at Section 8 towards an Additional Performance Security (The "Additional
Performance Security") for an amount calculated as under:
(a) If the Contract Price offered by the Selected
is lower than but up to 20% ofthe
Estimated Project Cost, then the Additional Performance Security shall be calculated
20% of the difference in the (i) Estimated Project Cost (as mentioned in Bid Document) -
Minus 10% of the Estimated Project Cost and (ii) Contract Price offered by the selected
(b) If the Contract Price offeredby the Selected Bidder is lower than 20% of the Estimated
Project.Cost, then the Additional Performance Security shall be calculated
difference in the (i) Estimated Project Cost (as mentioned in Bid Document) Minus 10%
of the Estimated Project Cost and (ii) Contract Price offered by the selected Bidder.
(c) ThisAdditional Perfprmance Security shall be treated as part ofthe Performance Security,
(BY 'The Performance Security shall be valid beyond 60(sixty) days Of the Defects Liability Period
and the Additipnal Performance Security shall be valid beyond 28 (twenty-eight) days of Project
Completion Date.
34.2. If the performance security is provided by the successful Bidder in the form ofa Bank Guarantee, it .
shall be issued either (a) at the Bidder's option, by a Nationalized/ScheduIéd Indian bank or (b) by a
foreign bank located in India and acceptable to the Employer, As per GOG Finance Department's
Circular No. FD/MSM/e-file/4/2023/0057/D.tvl.O. Date 21/04/2023 per theirlatest amendment.
34.3. Failure of the successful Bidder to comply with the requirement Of Sub-Clause 34.1 shall constitute
sufficient grounds for cancellation of the award and forfeiture ofthe Bid Security.
35 Advance Payment and Security
35.1 The Employer will provide an Advance payment on the Contract Price as stipulated in the Conditions
of Contract, subject to maximum amount,
as stated in the Contract Data.
37. Corrupt of Fraudulent Practices
37.1 The Employer will rejecta proposal if it determines that the Bidder recommended for award has
engaged incorrupt or fraudulent practices in completing for the contract in question and will declare
the firm ineligible, either indefinitely or for a stated period of time, to be awarded a contract with
National Highways Authority of India/ State PWD and any other agencies, if it at any time determines
that the firm has engaged in corrupt or fraudulent practices in completing for the contractor, or in
37.2 Furthermore, Bidders shall be aware of the provision stated in Sub- Clause 59.2 of the Conditions of
APPENDIX TO ITB
Clause Reference
With respect to
1. The Name of the Employer is G-'l&.nøa..e-
eme:..ø..deecøtmeotå [Cl.l.l]
2. The last five years.
3. This Annual Financial Turnover Amount is Rs. [Cl.4.5.3
4. Value of Work is Rs. ...NO....
6. The cost of electric work is Rs. O,.QÖ....
The cost of water supply / sanitary works is Rs. 0..00....
8. Liquid assets and / or availability of credit [Cl.4.5.6 ]
facilities is Rs. .6.,.0.0
9. Price level of the financial year ..2DZQ.mZOZS.. [Cl. 4.5.2]
10. The pre-bid meeting will take place at [Cl. 9.2.11
11. The technical Bid will be opened at the office of CO
12. Address of the Employer: glDC&.ÆQ
14, The bid should be submitted latest by [Cl. 20.1 & 20.2]
As stated on online NIT
15. The bid will be opened at ..EAE...D.G•AU [Cl. 23.1 ]
As stated on online NIT
The Bank Draft in favor of nard. o
18. Escalation factors (for the cost of works executed and [Cl.4.5.2]
financial figure to a common base value) for works completed
Year Financial Year Multiplying factor
Base year of inviting tender 206 -20%
Dep xecuti Engineer
R & B Sub Division
Executiv Engineer
#LIST OF KEY PLANT & EQUIPMENT TO BE DEPLOYED ON CONTRACT WORK
[Reference CL. 4.5.5]
The contractors shall also give a list of machineries in his possession and which they propose to use
Sr. Plant or Locatibn Age of Make Capacity Approximate Remark
No, Machinery Machinery Value
(maximum 15 years)
List of Key Personnel to be deployed on Contract Work
(Reference Cl. 4.5.4)
# Employment of a qualified site Engineer by the Contractor.
The Contractor shall employ full-time technically qualified staff during the execution of this work as
1. Two graduate Civil Engineers and three diploma Civil Engineers when cost of the work to be executed
is more than Rs.50 lakhs.
2. One graduate & two Diploma, Civil Engineers when the cost of the work to be executed is more than
Rs. 15 lakhs but less than Rs.50 lakhs.
3. Minimum one Diploma Civil Engineer when the cost of work is less than Rs. 1 5 lakhs but more than
4. Minimum two Diploma Civil Engineers for the work when the cost of work to be executed is less than O
Rs. 5 lakhs. The Engineer so employed for the Government work must have sufficient experience to
handle the work independently. Such an Engineer shall have to stay at the site of work and he shall
not be entrusted with other duty except this work.
In case the contractor or partner of the contractor firm is a Civil Graduate Engineer, Employment of a
separate Engineer will not be necessary provided that the Engineer partner himself attends the
execution of the work on the site.
Within 15 days of issue of work-order the Contractor will have to furnish to the Deputy Executive
Engineer-in-charge of the work the Name, Qualifications, copy of marksheet, Colour Photograph and
the appointment order issued such engineers engaged for this contract work. If 1 5 days after issue of
work order such designated Site Engineers do not resume or do remain present on site of work,
the recovery at the rate of Rs. 15,000-00 per month per Engineer will be made from the
bills/deposit/dues ofthe contractor.Such recovery shall be non-refundable.
QUALIFICATION INFORMATION
QUALIFICATION INFORMATION
The information to be filled in by the Bidder in the following pages will be used for the purpose of post
be incorporated
qualification as provided for in Clause 4 of the Instruction to Bidders. This information will not
in the Contract.
For Individual Bidders
Constitution or legal status of Bidder
Place of registration
Principal place of business
Power of attorney of signatory of Bid
1.2 Total value of Civil engineering constructions 20. -
work performed in the last five years 20. -
(in Rs. Lakhs) 20. -
1.3.1 Work performed as prime contractor, work performed in the past as a nominated sub-contractor will
also be considered the sub-contract involved execution of all main items of work described in the bid
documents, provided further that all other qualification criteria are satisfied (in the same name) on
works of a similar nature over the last five years* and in current year before the submission ofthe bid.
Project Name of Description Contract Value of Date of Stipulated Actual Remark
Name the of work No. contract issue of period of date of explaining
Employer (Rs. work completion completion* reasons for
*Attach certificate(s) from the Engineer(s)in-charge
Immediately preceding the financial year in which bids are received.
#1.3.2 Quantities of work executed as prime contractor, work performed, in the past as a nominated sub-contractor,
will also be considered provided the sub-contract involved execution of all main items of work described in the
bid document, provided, further that all other qualification criteria are called (in the same name and style) in the
lastfive yeårs** and in current year before the submission ofthe bid.
Year Name of Name of Quantity of work performed (CumlMT) Remarks*
the work the (indicate
Employer Cement Masonry Earth Bituminous contract Ref)
Concrete Works Work
1.4 Information on Bid Capacity (works forwhich bids have been submitted and works which are yet to be
completed) as on the date ofthis bid.
(A) Existing commitments and on-going works:
Description Place Contract Name & Value Stipulated Value Of Anticipated
of No. Address Contract Period Works* of
works State of (Rs. cr) of remaining cbmpletion
Employer Completion to be
*Attach certificate (s) from the Engineer(s) in-charge
Immediately preceding the financial year in which bids are received.
1.5 'Availability of key items of Contractors Equipment for carrying out the works (Ref. Clause 4.5,5).
The Bidder should list all the information requested below;
Item of Requirement Availability Proposals Remarks
Equipment (from whom
NO Capacity Owned/Leased Nosl. to be
to be Capacity Conditions purchased
1.6 Qualifications and experience of key personnel required for administration and execution of the
contract. Attach biographical data. Refer also to Sub Clause 9.1 of the Conditions of Contract.
Position Name Qualification Year of Year of
Experience experience in
(General) the proposed
Project Manager
1.7 Proposed sub-contract and firms involved
Sections of Value of Sub-Contractor Experience in
the works Sub-Contractor (Name & Address) similar work
Attach copies of certificates on possession of valid license for executing water supply/ sanitary work]
building electrification works.
1.8 Financial reports for the last five years: balance sheets, profit and loss statements, auditors' repotts
(incase of companies/corporations), etc. List them below and attach copies.
1.9 Evidence of access to financial resourcesto meet the qualification requirements: cash in hand, lines
of credit, etc. List them below and attach copied documents.
1.10 Name, address, and telephonem telex, and fax numbers of the Bidders bankers who may provide
references if contacted bythe Employer.
1.11 Information on Litigation history in which the Bidder is involved.
Other Party Employer Cause of Dispute Amount Involved Remarks
1.12. Statement of compliance under the requirements of Sub Clause 3.2 of the instruction to Bidders,
(Name of Consultant engaged for project preparations is *
1,13 Proposed work method and schedule, The Bidder should attach descriptions, drawings änd charts as
necessary to comply with the requirements ofthe Bidding documents. (Refer ITB Clause 4.1)
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the requirements of Clause-4 of
the Instructions to the Bidders, if applicable.
(ii) Undenaking
Fill the name of Consultant
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR
AVAILABILITY OF CREDIT FACILITIES
(CLAUSE 4,5.6 OF ITB)
BANK CERTIFICATE
This is to certify that M/s.
reputed company with a good financial standing.
If the contract for the work, namely
the above firm,
we shall be able to provide
overdraft/credit facilities to the extent of
.. to meet their working capital requirements for executing the above
during the contract period.
Senior Bank Manager
Address of the Bank
1. l, the undersigned, do hereby certify that all the statements made in the required attachments are
true and correct.
2. The undersigned also hereby Certifies that neither our firm Mis.
have not abandoned any work of Government of Gujarat/
Government of India/any Board or Corporation under Government of Gujarat]Government of India
nor any contract awarded to us for such works have been rescinded, during last five years prior to
the date ofthis bid,
3. The undersigned hereby authorize(s) and request (s) any bank, person, firm or corporation to
fumish pertinentinformation deemed necessary and requested by the Department to verify this
statement or regarding any (our) competence and general reputation.
4. The Undersigned understands and agrees that further qualifying information may be requested,
and agrees to furnish any such information at the request of the Department/ Project implementing
.(Signed by an Authorized Officer of the Firm)
(Title of Officer)
l, the undersigned do hereby undertake that our firm M/s
would invest a minimum cash up to 25% of the value of the
work during implementation ofthe contract.
(Signed by an Authorized Officer of the Firm)
(Title of Officer)
CONDITIONS OF CONTRACT
CONDITIONS OF CONTRACT
Table of Contents
Page No. Page No.
A. General D. Cost Control
37 37 *ill of Quantities
2 Interpretation 38 38 Changes in the Quantities
39 39 Variations
3 Language and Law
40 Payments for Variations
4 Engineer's Decisions
39 41 Cash Flow Forecasts
6 Communications 39 42 Payment Certificates
7 Sub-Contractors 39 43 Payments
8 Other Contractors 39 44 Compensations Events
9 Personnel 40 45 Tax
IO Employer's & Contractor Risk 40 46 Currencies
Employers Risks 40 47 Price Adjustment
12 Contractor's Risk 40 48 Retention
13 Insurance 40 49 Liquidated damages
14 Site Investigations Reports 41 50 Bonus
15 Queries about the Contract 41 51 Advance Payment
16 Contractors to Construct the works 41 52 Securities
17 The Works to be Completed By the 53 Deleted
Intended Completion Date 41 54 Cost of Repair
18 Approval by the Engineer
19 Safety 41 E. Finishing the Contract
20 Discoveries 42 55 Completion
21 Possession of the Site 42 56 Taking Over
22 Access to the Site 42 57 Final Account
23 Instructions 42 58 Operating and Maintenance manuals
24 Disputes 42 59 Terminations
25 Procedure for Disputes
60 Payment upon Terminations
B. Time Control 62 Release from Performance
28 Extensions of the Ir:tended F. Special Conditions of Contract
completion date 44 63 Labour
29 Deleted 44 64 Compliance with labour regulations
30 Delays Ordered by The Engineer 44 65 Arbitration
31 Management Meetings
32 Early Warning
C. Quality Control
33 Identifying Defects
35 Correction of Defects
36 Uncorrected Defects
CONDITIONS OF CONTRACT
1.1 Terms which are defined in .the Contract Data are not also defined in the Conditions of Contract but
keep their defined meaning.
Bill of Quantities means the priced and completed Billof Quantities forming part ofthe Bid
Compensation Events are those defined in Clause 44 hereunder
The Completion Date is the date of completion of the Works
as certified by the Engineer in
accordance with Sub Clause
The Contract is the contract between the Employer and Contractor to execute, complete and
maintain the Works till the completion of Defects
Liability Period, It consists of the documents
listed in Clause 2.3 below.
The Contract data defines the documents and otherinformation which comprise thé Contract.
The Contractor is a person or Qorporate body whose Bid to
carry out the Work has been
accepted by the Employer.
The Contractor's Bid is the completed Bidding document submitted by the Contraétor to the
Employer and includes Technical and Financial Bids.
The Contract Pric.e is the price stated in the Letter ofAcceptance and thereafter
accordance with the provisions of the Contract.
Days are calendar days: months are calendar months,
The Defects Liability Period is the period named in the Contract Data and calculated from the
Completion Date.
The Employer is the party who Will employ the Contractor to carry out the Works.
The Engineer is the person named in the Contract Data (or any other competent person
appointed and notified to the contractor to act in replacement of the Engineer) who is responsible for
supervising the Contractor, administering the Contract, certifying payments due to the Contractor,
issuing and valuing Variations to the Contract, awarding extensions of time, and valuing the
Compensations Events.
Equipment is Contractor's machinery and vehicles brought temporarily to the site to construct
The Initial Contract Price is the Contract Price listed in the Employer's Letter ofAcceptänce.
The Intended Completion Date is the date on which it is intended that the Contractor shall
complete the Works. The Intended Completion Date is specified in the Contract Data. The Intended
Completion Date may be revised only by the Engineer by issuing an extension of time.
incorporation in
Materials are all supplies, including consumables, used by the contractor for
Plant is any integral part of the work which is to have mechanical, electrical,
chemical or biological functions.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the
Bidding documents and are
factual interpretive reports aboutthe surface and subsurface conditions at the site.
Specifications means the Specifications of the works included in the Contract and any.
modification or addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the Contractor shall commence
execution ofthe works. It does not necessarily coincide with any of the Site Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with the Contractor to carry
out a part of the work in the Contract which includes work on the Site.
installed, and removed by the Contractor
Temporary Works are works designed, constructed,
which are needed for construction or installation of the Works,
A Variation is an instruction given by the Engineer, which varies the Works.
The Works are what the Contract requires the Contractor to construct, install, and turn over to
the Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also means female or
neuter and the other way around. Heading have no significance. Words have their normal meaning
under the language of the Contract unless specifically defined. The Engineer will provide instructions
clarifying queries about Conditions of Contract.
2.2 If sectional completion is specified in the Contract Data, references in the Conditions of Contract to
the Works, the Completion date, and Intended Completion Date apply to any Section of the Works
(other than references to the Completion Date and Intended Completion date for the whole works)
2.3 The documents forming the Contract shall be interpreted in the following order of priority
(2) Letter of Acceptance, notice to proceed with works
(3) Contractor's Bid
(4) Contract Data
(5) Conditions of Contract including Conditions of Contract
(6) Specifications
(8) Bills ofquantities and
(9) Any other document listed jn the Contract Data as forming part of the Contract,
3. Language and Law
3.1 The language ofthe Contract and the law governing the Contract are stated in the Contract Data.
4. Engineers. Decisions
4.1 Except where otherwise specifically stated, the Engiheer will decide contractual matters between the
Employer and the Contractor in the role representing the Employer.
5.1 The Engineer may delegate any of his duties and responsibilities to other people after notifying the
Contractor and may cancel any delegation after notifying the Contractor
6. Communications
6.1 Communications between parties which are referred to in the conditions are effective only when in
writing. A notice shall be effective only when it is delivered (in terms of Indian ContractAct).
Sub-Contracting
The Contractor may subcontract any portion of work, up to a limit specified in contract data, with the
approval of the engineer but may not assign the Contract without the approval of the Employer in
writing. Subcontracting shall not alter the Contractor's obligations. Sub-contracting of supply
specific items ofwork is not allowed.
7.2 The sub-contractor must be registered in appropriate class and category for the part of work to be
8. Other Contractors
The Contractor Shal! cooperate and share the Site with other contractors, public authorities, utilities
and the Employer between the dates given in the Schedule of other Contractor. The Contractors shall
as refer to in the Contract Data, also provide facilities and services for them as described in the
Schedule. The employer may modify the schedule of other.contractors and shall notify the contractor
of any such modifications.
9.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel as referred
to in the Contract Data to carry out the functions stated in the Schedule or other personnel approved
by the Engineer. The Engineer will approve any proposed replacement of key personnel only if their
qualifications, abilities, and relevant experience are substantially equal to or better than those of the
personnel listed in the Schedule.
9.2 If the engineer asks the Contractor to remove a person who is a member of the Contractor Staff or his
work force stating the reasons the Contractor shall ensure that the person leaves the Site within
seven days and has no further connection with the work in the Contract.
10. Employer's and Contractors Risks
10.1 The Employer carries the risk which these Contract states are Employer's risks, and the Contractor
carries the risks which these Contracts states are Contractors risk.
11. Employer's Risks
11.1 The employer is responsible for the excepted risks which are (a) in so far as they directly affect the
execution of the Works, the risks of war, hostilities, invasion, act of foreign enemies, rebellion,
revolution, insurrection or military or usurped power, civil war, riot commotion or disorder (unless
restricted to the Contractor's employees), and contamination from any nuclear fuel or nuclear waste
or radioactive toxic explosive.
12. Contractor's Risks
12.1 All risks of loss of or damages to physical property and of personal injury and death which arise during
and in consequence of the performance of the Contract other than the excepted risks are the
responsibility of the Contractor.
13.1 The Contractor shall provide, in the joint names of the Employer and the Contractor, insurance cover
from the Start date to the end of the Defects Liability Period in the amounts and deductibles stated in
the Contract data for the following events which are due to the Contractor's risks:
(a) Loss ofordamage to the works, Plant and materials,
(b) Loss of or damage to Equipment
(c) Loss of or damages of property (expect the Works, Plant, Materials and équipment) in
connection with the Contract;and
(d) Personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for the
Engineer's approval before the Start Date. All such insurance shall provide for compensation to be
payable in the types and proportions of currencies required to rectify the loss or damage incurred.
13.3 Ifthe Contractor does not provide any of the policies and cettificates required, the Employer may
affect the insurance which the Contractor should have provided and
recoverthe premiums the
Employer has paid from payments othetwise due to the Contractor or, if no payment is due, the
payment ofthe premiums shall be a debt due,
13.4 Alterationsto the terms ofaninsuranceshall not be made withoutthe approval ofthe Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies.
14. Site Investigation Report
The Contractor in preparing the Bid shall rely on any site Investigation reports referred to in the
Contract Data, supplemented by any information qvåilable to the Bidder.
15. Queries about the Contract data
(0 15.1 The engineer will clarify queries on the Contract Data
16. Contractorto Construct the Works
16.1 The Contractor shall construct' and install the works in accordance with the specification and
17. ,The Works to be completed by the Intended Completion Date
17.1 The Contractor may commence execution of 'the Works on the Start Date and shall carry out the
Works in accordance with the programme submitted by the Contractor, as updated with the approval
ofthe Engineer,and complete them by th6 Intended Completion date
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary works to
the Engineer, who is to approve them ifthéy comply with the Specifications and drawings.
18.2 shall.be responsible for design oftemporary works.
18.3 The Engineer's approval shall not alter the contractor responsibility for design of the Temporary
18.4 The Contractor shall obtain approval. of third parties to the design of the Temporary works where
18.5 All Drawings prepared by the Contractors for the execution of the temporary or permanent work are
subject to prior approval by the Engineer before their use.
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly discovered on the site is the
property of the Employer. The contractor is to notify the engineer of such discoveries and carry out the
Engineer's instructions for dealing with them.
21. Possession of the Site
21.1 The Employer shall give possession of all parts of the site to the Contractor. If possession
not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of
the relevant activities and this will be a Compensation Event.
If within 25% of the time limit of the project, 80% of possession of the site is not handed over to the
Contractor, then contractor/ Employer may fore-close the contract. Contractor/Employer has to
foreclose the work within 30 days after lapse of 25%-time limit and after 30 days foreclosure
will be closed.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized by the Engineer access
Site, to any place where work in connection with the Contract is being carried out or is intended to be
carried out and to any place where materials or plants are being manufactured/ fabricated/
assembled for the works.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining to works which comply
the applicable laws where the site is located.
23.2 The Contractor shall permit the Employer to inspect the Contractor's accounts and records relating to
the performance of the Contractor and to have them audited by auditors appointed by the Employer, if
so required by the Employer.
24.1 If the Contractor is of the view that a decision taken by the Engineer was either outside the authority
given to the Engineer by the Contract or that the decision was wrongly taken, the decision shall be
referred to #Superintending Engineer (Higher Authority)within 14 days of the notification of the
Engineer's decision. If the issue is not resolved, any party can refer the matter for conciliation within
1 5 days from the decision given by the #Superintending Engineer.
24.2 (a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the decision of the
#Superintending Engineer, both the parties have to refer to the Chief Engineer concern for the
conciliation process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied with the decision of the
#Superintending Engineer, both the parties have to refer to the #Secretary, Roads & Building
Department, Government of Gujarat for the conciliation process.
Ifthe dispute is not resolved through the conciliation process, he may refer the dispute to Gujarat
Public Works Contract Dispute Arbitration Tribunal. If the Contractor fails to refer a claim I dispute to
the Higher Authority within 14 days of the notification of the Engineer's decision, the Contractor shall
not be entitled to any additional payment/claim if he doesnit follow the above sequence in stipulated
time and he should not stop thework.
25, Procedure for Disputers
25.1 The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special
Conditions of Contract.
B. TIME CONTROL
27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a
Programme showing the general methods, arrangements orders, and timing for all the activities in the
works along with monthly cash flow forecast,
27.2 An update of the Programme shall be a programme showing the actual progress achieved on each
activity and the effect of the progress achieved on the timing of the remaining work including any
changes to the sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval an updated programme at intervals no
longer than the period stated in the Contract data. If the Contractor does not submit an updated
programme within this period, the Engineer may withhold the amount stated in the Contract data from
the next payment after the date on which the overdue programme has been submitted.
27.4 The Engineer's approval of the programme shall not alter the Contractor's obligations. The
Contractor may revise the programme and submit it to the Engineer again at any time. A revised
programme is to show the effect of Variations and Compensations events.
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if a compensation Event occurs or a
Variation is issued which makes it impossible for completion to be achieved by the Intended
Completion Date without the Contractor taking steps to accelerate the remaining work and which
would cause the Contractor to incur additional cost.
28.2 The Engineer shall decide whether and by how much to extend the Intended Completion Date within
35 days of the Contractor asking the Engineer for a decision upon the effect of a compensation event
or Variation and submitting full supporting information. If the Contractor has failed to give early
warning of a delay or has failed to cooperate in dealing with a delay, the delay by this failure shall not
be considered in assessing the new Intended Completion Date.
28.3 The Engineer shall within •14 days of receiving full justification from the contractor for extension of
Intended Completion Date refer to the Employer his decision. The employer shall in not more than
days communicate to the engineer the acceptance or otherwise of the Engineer's decision. If the
employer fails to give his acceptance, the Engineer shall not grant the extension and the contractor
may refer the matter under Clause
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or progress of any activity within the works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other .to attend a management meeting. The
business of a management meeting shall be to review the plans for remaining work and to deal with
matters raised in accordance with the early warning procedure.
31.2 The Engineer shall record the business of management meetings and is to provide copies of his
record to those attending the meeting and to the Employer.The responsibility of the parties for actions
to be taken is to be decided by the Engineer either at the management meeting or after the
management meeting and stated in writing to all who-attendedthe meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely future events or
Circumstances that may adversely affect the quality of the work, increase-the Contract price or delay
the execution of works, The Engineer may require the contractor to provide an estimate of the
expected effect of the future event or circumstance on the contract price and completion date. The
estimate is to be provided by the Contractor as soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and cpnsidering proposals for how the
effect of such an event or circumstance can be avoidéd or reduced by anyone involved in the work
and in carrying out any resulting instruction of the Engineer,
C. QUALITY CONTROL
Identifying Defects/ Defect liability period
33.1 Defect liability period : The contractor shall be responsible to make good and remedy at his own
expense any defect which may develop or may be noticed before the period mentioned hereunder
from the certified date of completion. The Engineer in charge shall give the contractor a notice in
writing about the defects and the contractor shall make good the same within 15 days of receipt of
the notice. In the case of failure on the part of the contractor, the Engineer- in-charge may rectify
or remove or re-execute the work at the risk & cost of the contractor. The Engineer-in-charge
shall be entitled to appropriate the whole or any part of the amount of security deposit towards the
expenses, if any, Incurred by him in rectification, removal or re-execution. The Defects Liability
period shall be as under....
(a) For all works costing up to RS. 50,000 (amount put to tender), the period shall be 3 Months from
the certified date ofcompletion.
(b) For all works costing more than Rs. 50,000 and up to Rs. 1 crore (amount put tender), the
period shall be 12 (Twelve) months from the certified date of completion or one monsoon,
whichever is later.
(c) For majorprojects costing more than Rs. 1 crore, the period shall be 36 Months from the certified
date of completion which should include three monsoons.
(d) For original building works the defect liability period will be 4 years or elapse of4 monsoon period
following date of possession of building taken over by user agency following the certified date of
completion, whichever is later. For the purpose of deciding the monsoon period, the 30th
September shall be treated as the last date.
Modified vide R & B D Circular No. PAC-II-102008-2076-N dated 31/8/2009, PRCH/102013
(2976) 2759-N, Dated 27/05/2013 and Circular No.TNC/10/2016/Clause 17A (Correction/(l
33.2 Free maintenance guarantee period for works of Road/Bridge construction
(a) For resurfacing work of road free maintenance guarantee period one year from the date of
(b) In case ofwidening of the road/strengthening ofthe road/bridge, the contractor shall have to give
four years free maintenance guarantee from the certified date of completion. During this period
the contractor shall visit the site
every six months along with the concerned Section Officer /
Deputy Executive Engineer and will examine the work already carried out in this contract like
road work, jungle cutting, side shoulders, side gutter, road furniture, patta etc. and will prepare
Km. wise inspection report duly signed by all concerned and any defect observed shall be done
within 1 5 days by the contractor at his risk and cost as per the direction of Engineer in charge. The
contractor needs to do videography of these visits and require to submit at the time of release of
FMG. If B.T. the surface during the maintenance period of 4 years is worn out then agency shall
have to provide renewal coating as per tender item as directed by the Engineer-in- charge. The
amount equivalent to 5% of each running bill shall be withheld and will be released after the free
maintenance guarantee period (i.e. 4 years) is over.
However, this amount shall be released against fixed deposit or bank guarantee pledged in the
name of Executive Engineer after completion certificate ofwork is issued.
(1) The flakiness and elongation index (combined) for coarse aggregates under no circumstances
shall exceed the allowable limit set forth 'in the relevant clause for the material in question.
(2) 2% of the amount eligible for the payment' of bituminous items shall be withheld till the
miscellaneous items like earthwork in embankment/ cutting for side shoulders, side gutters,
kilometer / indicator ] guard stones, sign boards etc, are completed in all respect by the
contractor. After completion of the miscellaneous items, the above said 2% withheld amount
shall be released.
(Govt. of Gujarat's G.R. No.: Dtd. 13/12/2013).
(3) Videography for the surface under Maintenance Guarantee is to be done as per Govt. letter No.;
SSR/10/2015-16/26/C, Dtd. 26/11/15 forthe work costing morethan Rs. 5.00 Crore.
(4) Setting up ofadequate laboratory & deploymentofquality engineers.
The contractor shall have to setup the laboratory with adequate equipmentTlll the setting up of.
adequate laboratory is completed & reported of this to the engineer (subject to due verification by
engineer's representative) by contractor in writing, shall be withheld. The qualified
'quality Engineer shall be deployed exclusively for this contract by the contractors, If quality
Engineer is not deployed by contractor within one month after the date of work order, the amount
equivalent to Rs.20,000 per month shall be recovered till the actual deployment of quality
engineer. 'The amount so recovered towards the deployment of quality engineers shall not be
(5) Asphalt work will have to be cross checked as per G.R No.: RGN/60/2006/35/Ci dtd.31/05/07
before final bill ispaid.
(6) Maintenance during Construction Period
During the Construction Period%the Contractor shall maintain, at his own risk and cost, the
existing lane(s) of the road so that the traffic worthiness and safety thereof are at no time
materially inferior as Oompared to their condition 1 0 (ten) days prior to the date ofthe Agreement,
and shall undertake the necessary repair and maintenance works for this purpose; provided that
the Contractor may, at his cost, interrupt and divert the flow of traffic if such interruption and
diversion is necessary for the efficient progress of works and conforms to Good Industry
Practice; provided further that such interruption and diversioh shall be undertaken by the
Contractor only with the prior written approval of the Executive Engineer which approval shall not
be unreasonably withheld. For the avoidance of doubt, it is agreed that the Contractor shall at all
times be responsible for ensuring safe operation of the road,
33,3 The Engineer shall check the Contractor's work and notify the Contractor of any defects that are found.
Such checking shall not affect the Contractor's responsibilities the Engineer may instruct the Contractor
to search for a Defect and to uncover and test any work that the Engineer considers may have a Defect
34.1 If the engineer instructs the Contractor to carry out a test not specified in the Specification to check
whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test
and any samples. Ifthere is no defect the test shall be a Compensation Event.
34.2 #1 % of the amount of work done should be deducted from R.A. Bill of the contractor for testing the
quality of material workmanship, irrespective of actual charges.
34.3 Agency has to establish testing laboratory on site for the various test to be carried out in the work for
this purpose agency shall construct a pukka laboratory building with all facility on site at location
specified by the engineer in charge.
35. Correction of defects
35.1 The engineer shall give notice to the Contractor of any defects before the end of the defects Liability
Period, which begins at Completion and is defined in the contract data. The Defects Liability Period
shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified defect within the length
of time specified by the Engineer's notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a defect within the time specified in the Engineer's notice, the
Engineer will assess the cost of having the Defect corrected, and the Contractor will pay this amount.
D. COST CONTROL
37. Bill of Quantities
37.1 The bill of Quantities shall contain items for the constructions, installation, testing and commissioning
work to be done by the Contractor.
37.2 The bill of Quantitiesis used to calculate the Contract price, The Contractor is paid for the quantity of
the work done at the rate in the Bill ofQuantitiesfor each item.
38. Change in the Quantities
38.1 The Engineer shall have power to make any alterations in or addition to the original specifications
drawings, designs and instructions that may appear to him to be necessary or advisable during the
progress of the work and the contractor shall be bound to carry out the work in accordance with any
instruction in this connection which may be given to him in writing signed by the Engineer and such
alteration shall not invalidate the contract and any additional work which the contractor may be
directed to do in the manner .above specified as part of the work shall be carried out by the contractor
on the same conditions in all respects on which he agreed to do the main work and at the same rate as
arespecified in the tender for the main work.
Except that when the quantity of any item exceeds the quantity as in the tender by more than 130%,
the contractor will be paid for the quantity in excess of 130%, at the rate entered in the SOR ofthe year
during which the excess in quantity is first executed.
39.1 All Variations shall be included in updated programmes produced bythe Contracto•r.
40. Payments for Variations
40.1 If the additional or altered work includes any class of work for which no rate is specified in this
contract, then such class ofworkshall be carried out as under.
(i) At the rate derived from the item within the contract which is comparable to the one involving
additional or altered class of work;where there are more than one comparable items, the item of
the contract which is nearest in comparison with regard to class or classes of the work involved
shall be selected and the decision of the Superintending Engineer as to the nearest comparable
item shall be final and binding on the contractor.
If the rate cannot be derived in accordance with (i) above, stich class of works shall be carried out
at the rate entered in thé Schedule of Rates of the division for the year in which the tender was
received, increased or decreased by the percentage by which the tender amount is more or less
as compared to the amount arrived at the rates in the "Schedule of Rates" of the Division
not contain all
year in which the tender was received. Ifthe Schedule Of rates of the Division does
the items, the percentage increase or decrease of the tender shall be calculated considering
such items which were included in the "Scheduled Rates" of the division for the year and for
.materials consumed on such item the rate to be charged would be the basic rate taken into
account for fixing the rate in S.O.R. referred to above.
(iii) If it is not possible to arrive at the rate from (i) and (ii) above, such class of work shall be carried
out at the rate decided by the competent authorities on the basis of detailed rate analysis after
hearing the contractor before a Committee of two Superintending Engineers stationed at the
same place orthe nearest place.
40.2 If the additional or altered work, for which no rate is entered in the "Schedule of Rates" of the Division
is ordered to be carried out before the rate is agreed upon, then the contractor shall within seven days
of the date of receipt by him of the order to carry out the works inform the Engineer-in-charge of the
rate, which it is his intention to charge for such class of work and if the Engineer in charge does not
agree to this rates, he shall by notice in writing be at liberty to cancel his order to carry
of work and arrange to carry it out in such manner as he may consider it advisable, provided always
that if the contractor shall commence work or incur any expenditure in regard thereof before the rates
shall have been determined as lastly herein before mentioned, then in such cases he shall only be
entitled to be paid in respect of the work carried out or expenditure incurred by him prior to the date of
the determination of the rate as aforesaid according to such rate or rates as shall be fixed by the
Engineer-in-charge. In the event of the dispute, the decision of the Superintending Engineer of the
Circle shall be final.
Where, however, the work is to be executed according to the designs, drawings and specifications
recommended by the contractor and accepted by the competent authority, the alternation above
referred to shall be within the scope of such designs, drawings and specifications appended to the
The time limit for the completion of the work shall be extended in the proportion that the increase in the
cost occasioned by alterations bears to the cost of the original work and the certificate of the
Engineer-in-charge as to such proportion shall be final and conclusive.
41. Cash Flow Forecasts
41.1 When the programme is updated, the contractor is to provide the engineer with an updated cash flow
42. Payment certificates.
42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work
completed less thecumulative amount certified previously,
42.2 The Engineer shall check the Contractor's monthly statement within 14 days and certify the amount to
be paid to the Contractor after taking in to account any credit or debit for the month in question in
respect of materials for the works in the relevant amounts and under conditions set forth in sub-
clause-32.3 of the Contract Data (secured Advance).
42.3 The value ofwork executed shall be determined by the Engineer.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of
Quantities completed.
42:5 The value of work executed shall include the valuation of variations .and compensation events.
42.6 The Engineer may exclude any item certified in aprevjouscertificate or reduce theproportion ofany
item previously certified in any certificate in the light of later information
43.1 Payments shall be-adjusted for deductions for advance payments, retention, other recoveries in
terms of the contract and taxes at source, as applicable under the law. The Employer shall
Contractor the amounts certified by the Engineerwithin 28 days of the date of each certificate,
43.2 Payment of GST (prevailing rates) on the amount payable under the contact to the Contractor will be
made by the Employer. Hence, it is the responsibility -of the contractor to pay the GST to the
concernedAuthority.
43.3 Items of the works foiwhich no rate or price has been entered in will not be paid by the Employer and
shall be deemed covered by other.rates and pricesin the Contract.
44. Compensation events
44.1 The following äre compensation Events unless they are caused bythe Contractor:
(a) The Employer does not give access to a part of the Site by the site Possession date stated in
Contract data to the Contractor
44.2 In case of compensation event
occurs and itprevents the work being completed beyond the Intended
Completion Date thenAuthority will approve EOT with eligible contractual price escalation,
45.1 The rates quoted by the Contractor must be inclusive of all taxes prevailing on due date of bid
submission except GST. However, any subsequent changes in the tax structure by Government after
due date of bid submission will be compensated (+/-) on availability or submission of actual
documentation. Contractor will have to intimate Engineer regarding changes occurred in the tax
structure after bid submission. If the contractor fails to provide such information and if any financial
obligation may arise due to change in tax structure, same will be recovered from the contractor.
45.2 GST will be paid separately on the bills. Hence, it is the responsibility of the contractor to pay the GST
to the concerned Authority.
46. Currencies.
46.1 All payment shall be made in Indian Rupees.
47. PriceAdjustment
47.1 Contract price shall be adjusted for increase or decrease in rates and price of labour, materials, fuels
and lubricants in accordance with the following principles and procedures and as per formula given in
the contract data:
(a) The price adjustment shall apply for the work done from the start date given in the contract data
up to end of the initial intended completion date or extensions granted by the Engineer and shall
not apply to the work carried out beyond the stipulated time for reasons attributable to the
(b) The price adjustment shall be determined during each month from the formula given in the
(c) Following expressions and meanings during to the work done during each month
R = Total value of work done during the month. It would include the amount of secured advance
granted, if any, during the month less the amount of secured advance recovered if any during the
month. It will exclude value for works executed under variations for which price adjustment will be
worked separately based on the terms mutually agreed.
47.2 To the extent that full compensation for any rise or fall in costs to the contractor is not covered by
the provisions of this or other clause in the contract, the unit rates and prices included in the
contract shall be deemed to inclvde amounts to cover the contingency of such other rise or fall in
48.1 The Employer shall retain from each payment due to Contractor the proportion stated in the Contract
Data until Completion of the whole of the Works.
48.2 On Completion ofthewhole oftheWorks halfthetotal amount retained is repaidto the Contractorand
48.2 On Completion ofthewhole oftheWorks halfthetotal amount retained is repaidto the Contractorand
half when the Defects Liability Period has passed and the Engineer has certified that all Defects
notified by the Engineer to the Contractorbefore the end ofthis period have been correctede
48.3 On completion of the whole works: the contractor may substitute retention money with an "on
demand" Bank guarantee.
In case, Contractor requests for refund of the Retention Money deducted by the Employer under the
provision of this clause, Employer shall consider the said request ofthe Contractor provided that the
refund hereunder shall be made in teaches of not less than 1% (One Percent) of the Contract Price
and Contractor furnishes an irrevocable and unconditional Bank guarantee for an equal amount
substantially jn the format of Bank Guarantee for Performance Guarantee Unclosedwith SBD and
valid up to 60 day beyond the scheduled I extended Defects Liability Period. On completion of the
whole works, the contractor has hoWever an option to submit a fresh irrevocable and unconditional
Bank Guarantee for an amount equal to 5% of theetotal value of work executed substantially in the
format of Bank Guarantee for Performance Guarantee enclosed with SBD and valid up to 60 days
beyond the Defect Liability Period and yet refund the Retention Money Bank Guarantee submitted for
refund of Retention Money.
49. Liquidated Damages
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the
Contract Data for each day that the Completion Date islater than the Intended Completion Date (for
the whole works or the milestone as stated in the contract data). The total amount of liquidated
the whole works or the milestone as stated in the contract data). The total amount of liquidated
damages shall not exceed the amount defined in thé Contract Data. The Employer may deduct
liquidated damages from payment due to the Contractor. Payment of liquidated damages does not
affect the Contractor's liabilities,
49.2 Ifthe Intended Completion Date is extended after liquidated damages have been paid, the Engineer
shall correct any overpayment of liquidated damages by the Contractor by adjusting the next
payment certificate. The Contractor shall not be entitled for any interest on the over payment
.calculated from the date of payment to the date of repayment.
49.3 If the contractor fails to comply with the time for completion
as stipulated in the tender, then the
contractor shall pay to the employer the relevant
sum stated in the Contract Data as Liquidated
damages for such default and not as penaltyfor everyday or part of day which shall elapse between
relevant time for completion and the date stated in thetaking overcertificate ofthe whole ofthe works
onthe relevant section, subject to the limitstated in the contract data,
The employer may, without prejudice to any other method of recovery deduct the amount of such
damages from any monies due orto become due to the contractor. The payment or deduction of such
damages shall not relieve the contractor from his obligation to complete the works on from any other
of his obligations and liabilities under the contract.
49,4 If, before the Time for Completion of the whole of the Works or, if applicable any Section, a Taking
Over Certificate has been issued for any Pärt of the Works or of a Section, the liquidated damages for
delay in completion of the remainder of the Works or of that Section shall, for any period of delay after
the date stated in such Taking-Over-Certificate, and in the absence of alternative provisions in the
Contract, be reduced in the proportion which the value of the part so certified bears to the value of the
whole of the Works or Section, as applicable. The provisions of this Sub-clause shall only apply to the
rate of liquidated damages and shall not affect the limit thereof.
50.1 If the contractor achieves completion of the whole of the works prior to the intended Completion Date
prescribed in Contract Data the Employer shall pay to the contractor a sum stated in Contract Data as
bonus for every completed month but subjected to maximum amount as stated in Contract Data;
which shall elapse between the date of completion of all items of works as stipulated in the contract,
including variations ordered by the Engineer and the time prescribed in Clause '17.
50.2 Bonus shall be paid only to works amounting to above INR 5 crore with time limit of the works is equal
or more than 6 months. The bonus would be paid as under
% of Time Saved % of Initial Contract Price
entitled for Bonus
51. Advance Payment.
51.1 The Employer shall make advance payment (not IO be paid less than two installments except in
special circumstances for which the
reason to be Recorded in writing) to the Contractor of the
amounts stated in the Contract Date by the date stated in the Contract Date, against provision by the
Contractor of an Unconditional Bank Guarantee in a form and by a bank acceptable to the Employer
in amounts and currencies equal to be at least 110% of the adv.ance payment. The guarantee shall
remain effective until the advance payment has been repaid, but the amount ofthe guarantee shall be
progressively reduced by the amounts repaid by the Contractor.The Mobilization advance would be
deemed as interest bearing advance at an interest rate of 10 % to be compounded, quarterly.
512 The Contractor is to use the advance payment only to pay for Equipment, plant and Mobilization
expenses required specifically for execution of the Works. The Contractor shall demonstrate that
advance payment has been used in this way by supplying copies of invoices or other documents to
51.3 The advance payment shall be repaid by deduction proportionate amount from payments othemise
due to the Contractor, following the schedule of completed percentages of the Works on
basis. No account shall be taken of the advance payment or its repayment in assessing valuations of
work done, variations, price adjustments, Compensation Eventsr or Liquidated damages.
52.1 The performance Security (including additional security for unbalanced bids) shall be provided to the
Employer no later than the date specified in the Letter ofAcceptange and shall be Issued in an amount
and form and by a bank or surety acceptåble to the Employer; and denominated in Indian Rupees.
The performance Security shall be valid until a date 60 days from the date of expiry of Defects Liability
Period and the additional security for unbalanced bids shall be valid until
a date 28 days from the date
of issue of the certificate of completion.
54. Cost of Repairs.
54.1 Loss or damage to the Works or Materials to be incorporated in the Works between the Start date and
the end of Defects Correction periods shall be remedied-by the Contractor at the Contractor's cost if
the loss or damages arises fromthe Contractor's acts or omissions.
E. FINISHING THE CONTRACT
55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of the works and the
Engineer will do so upon deciding that the work is completed.
56. Taking Over
56.1 The Employer shall take over the Site and the Works within seven days of the Engineer issuing a
certificate of Completiom
57. Final Account
57.1 The Contractor shall supply to the Engineer a detailed final account of the total amount that the
57.1 The Contractor shall supply to the Engineer a detailed final account of the total amount that the
Contractor considers payable as full and final settlement of all claims under the Contract for items before
the end of the Defects Liability Period, The Engineer shall issue a Defect Liability Certificate and certify
any final payment that is due to the Contractor within 56 days of receiving the Contractor's account if it is
correct and complete. If it is not, the Engineer shall issue within 56 days a schedule that states the scope
of the corrections or additions that are necessary. If the Final Accountis still unsatisfactory after it has
been resubmitted, the Engineer shall decide on the amount payable to the Contractor and issue a
payment certificate, within 56 days of receiving the Contractor's revised account.
57.2 If reversal in characteristic of tender (LI becoming L2) on account of excesses and savings in final
account is observed, the Engineer/Employer Shaf} be at liberty to restrict the final payment of BOQ
items to the lowest amount evaluated of the bids considering the final quantities and the rates quoted
including the rebates if any. Payment of variation items shall however be made at the rates approved
by the Employer, within 90 days from the physical completion of work.
58. Operating and Maintenance Manuals
58.1 If "as built" drawings and/or operating and maintenance manuals are required, the Contractor shall
supply them by the dates stated in the Contract data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the Contract
data, or they do not receive the Engineer's approval, the Engineer shall withhold the amount stated in
the Contract Data from payments due to the Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party causes a fundamental
breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited to the following:
The contractor stops work for 28 days when no stoppage of work is shown on the current
programme and the stoppage has not been authorized bythe Engineer
2. The Engineer instructs the Contractor to delay the progress of the Works and the instructions is
not withdrawn within 28 days;
3. The Employer or the Contraotor is made bankrupt or goes into liquidation other than for a
reconstructions or amalgamation
4. A payment certified bythe Engineer is not paid by the Employer to the Contractor within 56 days
of the date ofthe Engineer's certificate
5. The Engineer gives Notice that failure to correct a particular Defect is a fundamental breach of
Contract and the. Contractor fails to correct it within a reasonable period of time determined by
6. The Contractor does not maintain a securitywhich is required;
7. The Contractor has delayed the completioh of works by the number of days for which the
maximum amount of liquidated damages can be paid as defined in the Contract data; and
8, Ifthe Contractor, in the judgment ofthe Employer has engaged in corrupt orfraudulent practices
in competing for or in executing the Contract,
For'the purpose of this paragraph; "corrupt practice" means the offering, giving, receiving or soliciting
of anything ofvalue to influence the action of a public official. in the procurement process or in contract
execution. "Fraudulent practice" means a misrepresentation' of facts in order to influence a
procurement process or the execution of a contract to the detriment of the borrower, and includes
o collusive practice among Bidders (prior to or after bid submission) designed to establish bid prices at
artificial non-competitive levels and to deprive the Borrower of the benefits of free and open
59.3 When either party to the Contract gives notice of a breach of contract to the Engineer for a cause other
than those listed under Sub Clause 592 above, the Engineer shall decide whether the breach is
fundamental or hot.
59.4 Notwithstandingthe above, the employer may terminate the Contract for convenience.
60. Payment upon Termination
60.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the
Engineer shall issue a Certificate for the value of the work done less advance payments received up
to the date of the issue of thecettificate, less other recoveries due in terms of the contract, less taxes
due to deducted at source as per applicable law and less the percentage to apply to the work not
completed as indicated in the Contract data. Additional Liquidated Damages shall not apply, If the
total amount due to the Employer exceeds any payment due to the Contractor the difference shall be
total amount due to the Employer exceeds any payment due to the Contractor the difference shall be
a debt payable to the Employer.
602 If the Contract is terminated at the Employer's convenience or because of a fundamental breach of
Contract by the Employer, the Engineer shall issue a certificate for the value of the work doney the
cost of balance material brought by the contractor and available at site, the reasonable cost of
removal of equipment, repatriation of the Contractor's personnel employed solely on the works, and
the Contractor's cost of protecting and securing the Works and less advance payment received up to
the date of the certificate, less other recoveries due in terms of the contract and less taxes due to
deducted at source as per applicable law.
61.1 All materials on the Site, Plant Equipments, Temporary Works and Works are deemed to be property
of the Employer, ifthe Contract is terminated because of a Contractor's default.
62. Release from Performance
62.1 If the Contract is frustrated by the outbreak of war of by any other event entirely outside the control of
either the Employer or the Contractor the Engineer shall certify that the Contract has been frustrated.
The Contractor shall make the Site safe and stop work as quickly as possible after receiving this
certificate and shall be paid for all work carried out before receiving it and for any work carried out
afterwards to which commitment was made,
E SPECIAL CONDITIONS OF CONTRACT
The Contractor shall, unless otherwise provided in the Contract, make his own arrangements for the
engagement of all staff and labour, local or other, and for their payment of housing, feeding and
The Contractor shall, if required bythe Engineer, deliver to the Engineer a return in detail, in such form
and at such intervals as the Engineer may prescribe, showing the staffand the Humbers
classes of labour from time to time employed by the Contractor on the site and such other information
as the Engineer may require,
64. COMPLIANCE WITH LABOUR REGULATIONS
During continuance ofthe contäct, the Contractor and his sub- contractor.shall abide at all times by all
existing labour enactments and rules made thereunder, regulations, notification and bye laws of the
State or centräl Government or local authority and any other labour law (including rules), regulations,
bye laws that may be passed or notifications that may be issued under any labour law in future either
by the State or the Central Government or the local authority„ Salient features of
some of the major
labour laws that are applicable to the construction industry are given below. The Contractor shall
keep the Employer indemnified in case any action is taken against the Employer by the competent
authority on account of contravention of any of the provisions of any Act or rules made thereunder,
regulations or notifications including amendments. If the Employer js caused to pay or reimburse,
such amounts as may be necessary to cause or observe, or for observance of the provisions
stipulated in the notifications/bye laws/Acts/Rules/regulations including amendments, if any, on the
part of the Contractor, the Engineer/employer shall have the right to deduct
any money due to the
Contractor including his amount of performance security. The Employer/Engineer shall also have the
right to recover from the Contractor any
sum required or estimated to be required formaking good the
loss or damage suffered by the Employer.
The employees of the Contractor and the Sub-Contractor in no case shall be treated as the
employees ofthe Employer at any point to time.
SALIENT FEATURES OF SOME MAJOR LABOUR AND OTHER LAWS APPLICABLE TO
ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTIONS WORK
Workmen Compensation Act 1923 The Act provides for compensation in case of injury by
accident arising out of and during the course of employment
(B) Payment of Gratuity Act. 1972 :- Gratuity is payable to an employee under the Act on satisfaction of
certain conditions on separation if an employee has completed 5 years service or more on death, the
rate of 15 days wages for every completed year of service. The Act is applicable to all establishments
employing 10 or. more employees.
(C) Employees P.F. and Misßellarxepus Proyjsion Act '1952:- The Act Provides for monthly
contributions by the employer plus workers or 8.33% The benefits payable under the Act are :
1. Pension or family pension on retirement or death, as the case may be.
2. Deposit linked insurance cn the death in harness of the worker.
3. Payment of P.F. accumulation on retirement]death etc.
(D) Maternity Benefit Act 1951 The Act provides for leave and some other benefits to women
employees in case of confinement or miscarriage etc.
(E) (Regulation & Act 1970 : The Act provides for certain welfare
measures to be provided by the Contractor to contract labour and in case the Contractor fails to
provide, the same are required to be provided, by the Principal Employer by Law. The principal
Employer is required to take Certificate of Registration and the Contractor is required to take license
from the designated Officer. The Act is applicable to the establishments or Contractor of Principal
Employer, if they employ 20 or more contract labour.
(F) Minimum Wages Act 1946 The Employer is supposed to pay not less than the Minimum Wages
fixed by appropriate Government as per provisions of the Act, if the employment is a scheduled
employment. Construction of Building, Roads, Runways are scheduled employment.
(G) Pgyunents of wages Act 1936:- It lays down as to by what date the wages are to be paid, when it will
be paid and what deductions can be made from the wages of the workers.
(H) Equal remunerations Act 1979 :- The Act provides for payment of equal wages for work of equal
nature to Male and Female workers and for not rnaking discrimination against female employees in
the matter of transfer, training and promotions etc.
Payments of Bonus Act | 965 The Act is applicable to all establishments employing 20 or more
employees. The Act provides for payments of annual bonus subject to a minimum of 8.33% of
wages and maximum of 20 % of wages to employees drawing Rs, 3500/- per month or less. The
bonus to be paid to employees getting Rs, 2500/- per month or above Rs. 3500/- per month shall be
worked out by taking •wages as Rs, 2500/- per month only. The Act does not apply to certain
establishments. The newly set-up establishments are exempted for five years in certain
circumstances, Some ofthe State Governments have reduced the employment size from 20 to IO
for the purpose of applicabi!ity of this Act.
(J) Industrial Disputes Act 1947 The Act lays down the machinery and procedure for resolutions of
'Industrial disputes, in what situations a strike or lock-out becomes illegal and what are the
requirements for laying off or retrenching the employees or closing down the establishment.
(K) Industrial employment (Standing Orders) Act 1946 It is applicable to all establishments
employing 100 or more workmen (employment size reduced by some of the State and Central
Government to 50). The Act provides for laying down .rulesgoverning the conditions of employment
by the Employer on matters provided in theAct and get thé same Certified by the designatedAuthority.
(L) Trade Unions Act 1926:- The Act lays the procedure for registration of trade unions of workmen and
employers. The Trade Unions registered under the Act have given certain immunities from civil and
criminal liabilities,
(M) Child Labour (Prohibition & Regulation Act 1986 The Act prohibits employment of children
below 14 years of age in certain occupations and process and provides for regulation of employment
of children in all other occupations and
processes. Employment of Child labour js prohibited in
Building and Construction Industry.
(N) Inter - state Migrant workmen's (Regulation of
1979:- The Act is applicable to an establishment which employs 5 or more inter-state migrant
workmen through an intermediary (who has recruited workmen in one state fqr employment in the
establishment situated in another state).The inter-state migrant workmen, is an establishment to
which this Act becomes applicable, are required to be provided certain facilities Such as housing,
medical aid, traveling expenses from home upto the establishment and back, etc.
(0) The Building and Other Constructign workers (Regulation of employment and Conditions Qt
Service) Act 1996 and the Cess Act of 1996:-All the establishments who carry on any building or
other constructions work and employ 10 or more workers are covered underthis Act.
All such establishments are required to
pay cess at the rate not exceeding 2% of the cost of
construction as may be modified by the goyernment The Employer of the establishment is required
to provide safety
measures at the Building or construction work and other welfare measures, such as
canteens, First Aid facilities, Ambulance, Housing accommodations for workers near the workplace
etc. The Employer to whom the Act applies has to obtain registration certificate from the Registering
Offioers appointed by the Government.
Eac$ories Act 1943 The Act lays down the procedure for approval of plans before setting up a
factory, health and safety provisions, welfare provisions, working hours, annual earned leave and
rendering information regarding accidents or dangerous occurrences to designated authorities. It is
applicable to premises employing 10 persons or more with aid of power or 20 or more persons without
the aid of power engaged in the manufacturing process.
(Q) Royalty charges-The contractor shall pay the royalty to the competent authority as per rule. The
royalty charges paid shall be borne by the contractor and shall not be reimbursed by the Employer.
(R) Following Pollution control Acts and amendments made thereof from time to time shall be
1. Water (Preservation and control of Pollution) Act,
2. Air (Prevention and Control of PollutionAct
3. Environmental (Protection)Act
The contractor must cömmit to adopting Environmental management plan for best energy use, waste
management, the reduction of pollution as in EMS (Environmental Management system)lSO-
65. ARBITRATION (GCC Clause 24)
The procedure for arbitration will be as follows: -
24.1 If the Contractor is of the view that a decision taken by the Engineer was either outside the authority
given to the Engineer by the Contract or that the decision was wrongly taken, the decision shall be
referred to #Superintending Engineer (Higher Authority) within 14 days of the notification of the
Engineer's decision. If the issue is not resolved, any party can refer the matter for conciliation within
15 days from the decision given by the #Superintending Engineer.
24.2 (a) For the work up to Rs. 100 Cr., if any of the parties is not satisfied with the decision of the
#Superintending Engineer, both the parties have to refer to the #Chief Engineer concerned for
the conciliation process.
(b) For the work more than Rs, 100 Cr., if any of the parties is not satisfied with the decision of the
Superintending Engineer, both parties have to refer to the #Secretary, Roads & Building
Department, Government of Gujarat for the conciliation process.
If the dispute is not resolved through the conciliation process, contractor may refer the dispute to
Gujarat Public Works Contract Dispute Arbitration Tribunal. If the Contractor fails to refer a claim /
dispute to the Higher Authority within 14 days of the notification of the Engineer's decision, the
Contractor shall not be entitled to any additional payment/claim if he doesn't follow the above
sequence in stipulated time. However, during such period, he would not stop the work in any case.
Clause Reference With
respect To section
Item marked "N/A" do not apply to this Contract.
1. The Employers is [CL.I.I]
Name of authorized Representative (will be intimated later)
2. The Engineeris .aecuehte.EG.im.e.er
Name of Authorized Representative:
3. The Defects Liability Period is .....-,LA..... years from the date of completion. [CL. 1.1&33]
4. The Start Date shall be 1st days for the date of issue of the Notice to
proceed with the work. [CL.I.I]
5. The Intended Completion Date for the whole of the works is
.c...... Months after start of work with the following milestones:
Milestone dates: [CL.2.2& 49.1]
Physical works to be completed Period fromthe stad date
Milestone 1 i.e. .4.5.. days.
Milestone 2 i.e. 49...0/0 :.3.9..days.
Milestone 3 i.e. .73..0/0 135... days.
Milestone 4 i.e. LEO..days.
6. The Site is located at [CL.I.I]
The name and identification number of the Contract is: [CL.I.I]
8. The works consist of .......Rodd- .
.................with items as per B.O.Q. [CL.I.I]
The works shall, inter alia, include the following, as Specified or as directed:
(A) Road Works :
Site clearance; setting out and layout; widening of existing carriageway
and strengthening including camber corrections; construction of new
road/ Parallel service road; bituminous pavements remodeling/
construction of Junctions, intersections, bus bays, lay-bays; supplying
and placing of drainage Channels, flumes, guard posts and guard other
related items; construction/extension of cross drainage works, bridge,
approaches and other related stones; protective works for roads/bridge;
all aspects of quality assurance of various components of the works;
rectification of The defects in the completed works during the Defects
Liability Period; submission Of "As- built" drawings and any other related
documents; and other item of work as may be required to be carried out for
completing the work inaccordance with the draWings and the provisions of
the contract and to ensure safety.
Depu xecuti e Engineer
& B sub Division
(B) Bridge Works
Site clearance; setting out, provision offoundations, piers abutments and
bearing; prestressed/reinforced cement concrete superstructu re;wearing
coat, hand railings, expänsion joints, approach slabs, drainages spouts/
downtake pipes, arrangements for fixing light posts, water mains, utilities
etc; provision of suitably designed protective works;providing wing/return
walls; provision of road markings,.road signs etc.; all aspects of quality
the workson completion;
assurance;clearing the site and handing over
rectification of the defects during •the Defects Liability Period and
submission of "As-built" drawings and other related documents; and other
items of work as may be required to be carried out for completing the
works in accordance with the drawings and the provisions of the contract
and to Insure safety
(C) Other Items ICL.I.I]
Any Other Items as required to fulfill all contractual obligations as per the
10. The following documents also form part of the Contract:
As per clause 2-3 [CL.2.3(9)]
11. The law which applies to the Contract is the law ofUnion of India [CL.3.1]
12. The language ofthe Contract documents is English [CL.3.1]
13. Limit of subcontracting 25% of the Initial Contract Price tCL.7.1J
'14. The Schedule of Other Contractors [CL.8]
'1>5. The Schedule of KeyPersonnel AS perAnnex— II to Section I [CL.9]
16. The minimum insurance cover for physical property, injury and death is
Rs. 5 lakhs per occurrence with the number of occurrences limited to four.
After each occurrence, the contractor will pay an additional premium
necessary to make 'insurance valid for four occurrences always. [CL,i3j
Site Investigation report LCL,14]
18. The Site Possession dqtes shall be the CDOMI( [CL.21]
19, The period for submission of programme for approval of the engineer shall
be 21 days from the issue of Letter of Acceptance, [CL. 27, 1]
20. The period between program updates will be .....US......days. [CI-.27.3]
21. The amount to be withheld for late submission of an updated programme
shall be Rs. lakhs [CL. 27.3]
22. The following events shall also be Compensation Events
Substantially adverse ground conditions encountered during the
course of execution of work not provided for in the bidding
docunient, [CL. 44]
Removal of underground utilities detected subsequently
Significant changes in classification of soil requiring additional
mobilization by the contractor, e.g. ordinary soil to rock excavation,
(iii) Removal of unsuitable material like marsh, debris dumps,
etc, not caused by the contractor.
Deput t' Engineer Executiv Engineer
R & B Sub Division R & B Division
(iv) Artesian conditions
(v) Seepage, erosion landslide
(vi) River training requiring protection of permanent work
(vii) Presence of historical, archeological or religious structures,
monuments interfering with the works
(viii) Restriction of access to ground imposed by civil, judicial, or
military authority
23. The currency of the Contract is Indian Rupees [CL. 46]
24. The formula (e) for adjustment of prices are as under: [CL.47]
If any of the commodities like Cement, Steel or Bitumen are not found
applicable in a work, the weight component of that commodities
{i.e. 'Cement' (Pc), 'Steel' (PS) or 'Bitumenj (Pb) as indicated in SBD for
the purpose of Price Adjustment} shall be clubbed with the weight
component of 'Other Material' (Pm), such that the gross % weight of
the components shall remain as 100% .
R = value of work as defined in Clause 47.1 of Conditions of Contract
Adjustment for labour component
(i) Price adjustment for increase or decrease in the cost due to labour
shall be paid in accordance with the following formula:
Increase or decrease in the cost of work during the month under
consideration due to changes in rates for local labour.
The consumer price index for industrial workers for the State on
28 days preceding the scheduled date of opening of technical
Bids as published by Labour Bureau, Ministry of Labour,
Government of India
Li = The consumer price index for industrial workers for the State for
the month under consideration as published by the Labour
Bureau, Ministry of Labour, Government of India.
Percentage of labor component of the work.
Adjustment for cement component.
(ii) Prices adjustment for increase or, decrease in the cost of cement
procured by the contractor
Vc = Increase or decrease in the cost of work during the month
under consideration due to changes in rates for cement.
The all India wholesale price index for Ordinary Portland
Cement on 28 days preceding the scheduled date of opening
of technical bid as published by the Office of the Economic
Adviser Department for Promotion of Industry and
Internal Trade, Ministry of Commerce & Industry.
The all India average wholesale price index for Ordinary
Portland Cement for the month under consideration as
published by Office of the Economic Adviser, Department
for Promotion of Industry and Internal Trade, Ministry of
Commerce & Industry.
Pc = Percentage of cement component of the work
Adjustment for steel component
(iii) Price adjustment forincrease or decrease in the costqf steel procured by the contractor shall
be paid in accordance with the following formula
Vs= Increase or decrease in the cost Of work during themonth under consideration due
to changes in the rates for steel
The all India wholesale price index for steel (Mild Steel • Long Products Rebars)
on 28 days preceding the date of opening of Techn)cal Bids as published by the Office
of the Economic Adviser, Department for Promotion of Industry and Internal
Trade, Ministry of Commerce & Industry.
Si= The all India average wholesale price index for steel (Mild Steel - Long Products
Rebars). for the month under consideration
as published by Office of the Economic
Adviser, Department for Promotion of Industry and internal Trade, Ministry
of Commerce Industry.
Percentage of steel component of the work
Note : For the application of this clause, the index of Mild Steel- Long products Rebars has been
chosen to represent the steel group,
Adjustments of bitumen component
(iv) Price adjustment for increase in the cost of bitumén shall be paid in accordance with the
following formula
Vb= Increase or decrease in the cost of work during the month under consideration due to
changes in rates for bitumem
Bö= The official retail price of bitumen at the IOC depot at the nearest centre on the day
days prior to the scheduled dateof opening oftechnical bid.
Bi= The official retail price of bitumen of IOC depot at the nearest centre for the 15th day of
the month under consideration.
Pb= Percentage of bitumen component ofthe work
Adjustment of POL (fuel and lubricant) component
Price adjustment for increase or decrease in cost of POL (fuel and lubricant) shall be
paid in accordance with the following formula
Increase or decrease in the cost of work during the month under consideration due to
changes in rates forfuel and lubricants.
Foz The official retail price of High Speed Diesel (HSD) at the existing consumer pumps of
IOC at the nearest centre on the day 28 prior to the date of opening of Technical Bids.
The official retail price of HSD at the existing consumer pumps of IOC at the nearest
centre for the 1 5th day of the month ofthe under consideration.
Percentage of fuel and lubricants component of the work
Note: For the application of this clause, the price of High-Speed diesel Oil has been chosen to
represent the fuel and lubricants group.
Adjustment for Construction Machinery
(vi) Price adjustment for increase or decrease in the cost of plant and Machinery spare procured by
the Contractor shall be paid in accordance with the following formula
Increase or decrease in the cost of work during the month under consideration düe to
changes in rates for plant and machinery spares
PO = The all India wholesale price indeTfö7Fnufacturer of machinery for mining,
quarrying and Construction for the month under consideration as published
Office ofthe EconomicAdviser, Department for Promotion of Industry and
Internal Trade, Ministry of Commerce & Industry.
The all India average wholesale price index for manufacturer of machinery for
mining, quarrying and Construction for the month under consideration as
published Office of the Economic Adviser, Department for Promotion of Industry
and Internal Trade, Ministry ofCommerce & Industry.
Pp= Percentage of plant and machinery spares component of the work.
Note: For the application ofthis clause, index of Heavy Machinery and parts has been chosen
to represent the Plant and Machinery Spares group
Adjustment of other materials Component
(vji) Price adjustment for increase or decrease in cost of local materials other than cement, steel,
bitumen and POL procured by the contractor shall be paid in accordance with the following
Vm= Increase or decrease in the cost of work during the month under consideration due to
change in rates for local materials other than cement, steel'bitumen and POL.
MO = •The All Indian wholesale price index (all commodities) on 28 days preceding the
scheduled date Of opening' of technical Bids, as published by the Office of .the
Economic Adviser, Department for Promotion of Industry and Internal Trade,
Ministry of Commerce & Industry.
Mi = The All India wholesale price index (all commodities) for the month under consideration
as published by the Office of the EconomicAdviser, Department for Promotion of
Industry and Internal Trade, Ministry of Commerce & Industry.
Pm= Percentage of local material components'(other than cement, steel, bitumen and POL)
The following percentage will govern the price adjustment for the entire contract:
1. Labour-Pl 16,14.0/0
2. Cement— Pc ocerJ..0/0
5. POL- Pf k.Åk,O/0
6. Plant & Machinery Spares Pp .24..0/0
7. Other Materials - Pm IS.kP.O/0
25, The proportion of payments retained (retention money) shall be 6% {CL. 48}
from each bill subject toea maximum of 5% of final contract price.
26. Amount of Liquidated damages for For Whole of work {CL.49}delay in completion of works
delay in completion work (1/2000)th of the Initial contract pricé, rounded off to the
nearest Thousand, per day, For sectional Completion
(wherever specified In item 6 of Contract data)
(1/2000)th rof initial contract price for #5 km Section,
rounded offto the nearest thousand and per day.
Deput xecut• Engineer
Executiv Engineer
R& B Sub Division R & B Division
27. Maximum limit of liquidated damages 10 percent of the Initial {CL. 49}
For delay in completion work Contract Price rounded off to
the nearest thousand
28. Amount of Bonus for early completion Amount of bonus for early
completion of work shall be given
as per CL.50 of Section-3
29. Maximum limit of bonus for early 5 percent of the Contract {CL. 50}
Completion of work Price
30. The amount of the advance payment are: {CL. 51 & 52}
#Nature of Advances Amount (Rs.) Conditions
to Be fulfilled
Mobilization 10% ofthe contract Price On submission of unconditional Bank
Guarantee. (to be drawn before the end
of 20% of the contract period). The contractor
may furnish four bank guaranteeS of 2.5 % of
each valid for the full period.
ii Equipment 90% for new and 50% of After equipment is brought to site (provided
depreciated Value for old the Engineer is satisfied That the equipment
equipment. Total amount is required for performance of the contract)
equipment. Total amount is required for performance of the contract)
will be subject to a maximum and on submission of unconditional Bank
of 5% Of the Contract Price Guarantee for amount of advance
iii Seéured Deleted
Brought to site
(The advance payment will be paid to the Contractor no later than 28 days after fulfillment of the
above conditions).
31. Repayment of advance payment for mobilization and equipment {CL. 51.3}
The advance loan shall be repaid with percentage deduction from the interim payments certified by
the Engineer under the Contract. Deduction shall commence in the next Interim Payment Certificate
following that in which the total of all Such payments to the Contractor has reached not less than
percent of the Contract Price or 6 (six) months from 'the date of payment of first installment tof
advance, whichever period concludes earlier, and shall be •made at the rate of 20 percent
(collectively_ for both Mobilization Advance and Eauipment Advance) of the amounts of all
Interim Payment Certificate until such time as the loan has been repaid, always provided that the loan
shall be completely repaid prior to the expiry of the original time for completion pursuant to Clause
33, The securities shall be for the following minimum amounts equivalent (CL. 52)
As a percentage of the Contract Price:
Performance Security for 5 percent Of contract price plus Rs (to be decided after
evaluation ofthe bid) as additional security in terms of ITB Clause
The standard form of Performance security acceptable to the Employer shall be
an unconditional
Bank Guarantee ofthe type as presented in Section 8 ofthe Bidding Documents,
34. The Schedule of Operating and maintenance Manuals,. .„N/A.
35. The date by which gas— built" drawings (in scale as directed) jn 2 sets
are required {CL. 58}
within 28 days of the issue of certificate of completion of the whole
or section of the
work, as the case may be.
36. The amount to be withheld for failing to supply "as built" drawings by
the Date required is Rs Lakhs. {CL. 58}
37. The following events shall also be fundamentalsbreach of contract:
"The Contractor has contravened Sub" clause and Clause 9 of GCC"
38. The percentage to apply the value of the work not completed representing
the Employer's additional cost for completing the Works shall be
TECHNICAL SPECIFICATION
Description of the Works:
1. We offer to execute the Works described above and remedy. any defects therein in conformity with the
conditions of Contract, specification, drawings, Bill of Quantities and Addenda for the sum (s) of
2. We undertake, if our Bid is accepted, to commence the Works as soon as is reasonably possible after
the receipt of the Engineer's notiCe to commence, and to complete the whole of the Works in the
Contact within the time stated in the document.
3, We agree to abide by this Bid for the period of 120 Days from the date fixed for receiving the same,
and it shall remain binding upon it and may be accepted at any time before the expiration of that
4. Unless and until a formal Agreement is prepared and executed this Bid, together with your written
acceptance thereof, shall constitute a binding contract between us.
5. We understand that you are not bound to accept the lowest or any tender you may receive.
Dated this day of
Signature in the capacity of
dulyauthorized to sign bids for and on behalf of
(in block capitals or typed)
BILL OF QUANTITIES
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
01-Tender Documents.pdf
02-Tender Documents.pdf
03-Detail Specifications.pdf
04-Road Work Specification Booklet.pdf
05-Government Resolutions.pdf
06-Bill Of Quantities.pdf
Download all tender documents and submit your bid