Loading…
Loading…
Tender Value
₹56.3 Cr
EMD Value
₹1.1 Cr
Closing Date
6 Jun 2026, 11:00 amClosed
Yes (up to 3 members)
Two Packet System
Normal Tender
Yes
15/05/2026 11:00
Lowest to Highest
90 days
Expenditure
Capital (Works)
Above/Below/Par
WORKS
14 conditions · 2 needing a document upload
"Financial Eligibility Criteria: The tenderer must have minimum average annual contractual turnover of V/N or "V" whichever is less crores; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited, The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet, However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover, The tenderers shall submit requisite information as per Annexure-Vlll along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
(a)The tenderer must have successfully completed/substantially complete any of the following during last 07 (seven) years, ending last day of month previous to the one in which tender is invited:(i)Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or(ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work each costing not less than the amount equal to 60% of advertised value of the tender,(b) (i) In case of composite works (e.g. works involving more than one distinct component such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed/substantially completed any of the following during last 07 (seven) years, ending last day of month previous to the one in which tender is invited; Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or Two similar works , each costing not less than the amount equal to 40% of advertised value of each component of tender, or One simitar work, each costing not less than the amount equal to 60% of advertised value of each component of tender. Note: Separate completed works of minimum required values for each component can also be considered for fulfillment of technical eligibility criteria. (b) (ii) In such cases, what constitutes a component in a composite work shall be clearly pre-defined with estimated tender cost of it, as part of the tender documents without any ambiguity. Any work or set of works shall be considered to be a separate component, only when cost of the component is more than Rs. 2 crore each. The tenderer shall submit the completion certificate as per proforma given in annexure-IV-A or IV-B or IV-C as applicable or in the format containing all information as required as per the Annex. IV-A or IV-B or IV-C. Note: Criteria for the completed work/Substantially completed has been given in the General instructions in the tender document.
Definition of Similar Work :- Any RRI/PI/EI/MACLS Supply, Installation Testing, Commissioning Signaling work OR Any RRI/PI/EI/MACLS Alterations Signalling work OR Any CTC/TMS work
66 conditions · 7 needing a document upload
Mandatory in case Bid security amount is prescribed in STD Para 5.1.2 - The Bid Security shall be deposited in cash through e-payment gateway or submitted as Bank Guarantee bond from a scheduled commercial bank of India or as mentioned in tender documents. The Bank Guarantee bond shall be as per Annexure-XXXII and shall be valid for a period of 90days beyond the bid validity period.
In case the tenderer is (i)Any firm recognized by Department of Industrial Policy and Promotion (DIPP) as 'Startups' - shall be exempted from payment of Bid security deposit and shall submit certified copy of the registration/ Valid document issued by DIPP (mandatory if applicable)
In case the tenderer is (iii) Labour Cooperative Societies - shall deposit only 50% of the Earnest Money Deposit and shall submit certified copy of the registration/ Valid document issued by the relevant Ministry/ Labour commission (mandatory if applicable).
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Railway board letter No.2017/CE-I/CT/9 dtd. 31.05.2023regarding implementation of 'Contrator's e-MB' for Measurement and Billing of Works contracts in IR-WCMS on Zonal Railways will be applicable in this contact.
Railway Board letter no.2021/Tele/5(2)/3-Part(1)(3425647) Dated 12.06.2023 regarding Procedure for undertaking digging work in the vicinity of Signalling, Electrical and Telecommunication cables shall be followed.
Supply of material and execution of indoor & outdoor signal and telecom work for provision of Electronic interlocking-MSDAC based Absolute Block Signaling system between Merta Road Jn and RAS Station inconnection with New line of MTD-RAS section of Jodhpur Division of North Western Railway. The work involves provision of new Electronic Interlocking at New Merta city, Dhaneria, Jas nagar, Katyasani, Bhumbhaliya, stations and modification in existing Hitachi make EI at Merta Road Jn, existing Kyosan make EI at Ras station. Provision of MSDAC along with associated works like trenching & laying of signalling and Telecomcables in pre-fabricated ducts/DWC/GI pipes, supply-installation ofpoint machines, Apparatus cases, Signals, Track circuit equipment,Earthing material, Data loggers, ELD, Fuse alarms, fire alarms,Passenger Amenity Telecom Items etc
SnT_C_JU_26-27-02
SnT_C_JU_26-27-02
Open
Works - General
36 Months
Jodhpur, Rajasthan
₹0
₹1.1 Cr
6 Jun 2026
30 Apr 2026
8 May 2026
15 May 2026
419 items across 16 schedules · ₹56,34,04,237.54 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | For Station with routes less than 50 | Per Functional Vital Bit | 750.00 | 1,02,009.43 | 7,65,07,072.5 |
| 2 | For Station with routes more than 50 and less than 200 | Per Functional Vital Bit | 625.00 | 71,099.53 | 4,44,37,206.25 |
| 3 | Installation, wiring, testing and commissioning of EI System with 'Hot Standby' architecture as supplied upto 6 (six) line station. It includes transportation of material from consignee's depot to the site, erection and grouting of EI Relay Racks, fixing and wiring of all the interfacing relays (Vital & Non-Vital), installation and wiring of Microprocessor equipments, interface equipments, power supply equipments and all other associated accessories to make complete EI system to be functional. Note: (i) Technical Requirements are attached with tender document (ii) Contractor has to arrange simulator/simulation testing panel for testing and commissioning by Selection Table and Square Sheet for each Signalling function.(iii) Installation, wiring, testing and commissioning of EI system will be done by OEM after following all the guidelines/directives issued by RDSO from time to time. Inspection: Consignee Inspection charges: None Payment terms: 100% after commissioning | Station | 5.00 | 7,51,843.88 | 37,59,219.4 |
| 4 | Re-Design of EI Systems after FAT/SAT with related to application logic & Interface Circuit. Note: -After FAT/SAT either Minimum 2 functional gear (Addition/Deletion of point/signal/Track) or modification in TOC minimum 5 routes in accordance of 3.47, 5.16 and other issues. | Station | 1.00 | 5,70,471 | 5,70,471 |
| 5 | Supply of work station note book / tablet as per Technical Specifications. It also includes supply of Laser Printer (Only branded). The workstation should be capable of reconfiguring the system in case of any alteration in yard interlocking in future. Technical Specifications should be attached with the tender document by Tendering authority. Inspection: Consignee Inspection charges: None Payment terms: 100% after supply | Station | 5.00 | 1,04,575.4 | 5,22,877 |
| 6 | Supply of Instruments and Tool Kits required for Trouble Shooting and repair of hardware and software for EI system should be supplied for stations. (This includes tools required for EI maintenance sorts of crimping, insertion, removal, general purpose tools like screw drivers, spanners, PCB extractor, temp. controlled soldering iron, wire cutter, nose pliers etc. & measuring instruments with carrying case/ holders/ cabinet for technicians/ J.E. for testing, Maintenance and repair at site). Each set comprises of the following :- * Crimping tool for all types of special cable assembly used in EI system. * Insertion tool for all types of special cable assembly used in EI system. *Removal tool for all types of special cable assembly used in EI system. * Digital multi-meter (Fluke 111 or better) * Steel cabinet/ Almira, Size: 1980mm height, 915 mm width and 485 mm depth (Godrej Make/Jalaram) of good quality to store tool, spare cards and documents. * Steel Book rack Size: 1850mm height, 900 mm width and 316 mm depth for keeping documents. (Godrej Make/Jalaram) * Clamp Earth Tester. (as per specs mentioned in tender document.) * Clamp Current Meter (fluke 362 or superior) * Ferrule tagging printer for cable/wires (Supported label tape sizes: 6 / 9 / 12 / 18 / 24 m m ) . Inspection: Consignee Inspection charges: None Payment terms: 100% after supply | Set | 1.00 | 1,51,338.52 | 1,51,338.52 |
| 7 | Training of Technician/ Jr. Engineer for installation, Commissioning, Testing, Repairs & Troubleshooting of EI system. (Hard copies of training material/ course modules to be given to each participant). Inspection: Consignee Inspection charges: None Payment terms: 100% after execution | Man-Days | 12.00 | 1,331.35 | 15,976.2 |
| 8 | Design, preparation & supply of drawings in computer print copies and original tracing in AUTO CAD FORMAT for Electronic Interlocking at each station. After completion of the work, the completion drawings incorporating completion details are to be supplied as per Technical Specifications given in tender document (upto 6 Line). The technical specifications are as per ANNEXURE-01010100 of SOR. Inspection: Consignee Inspection charges: None Payment terms: 100% after execution | Station | 7.00 | 2,11,776.71 | 14,82,436.97 |
| 9 | Preparation of SWR literature in English along with associated mid-section interlocked gate with all corrections as per approved SWRD & approved SIP. For these all-technical corrections, editing, grammatical correction etc. are to be carried out and one rough print to be given to railways for approval before printing, as required for final processing of CRS sanction. This also includes preparation of maintenance cards in format provided by Rly. Inspection: Consignee Inspection charges: None Payment terms:100% after execution. | Station | 7.00 | 4,330.94 | 30,316.58 |
| 10 | Translation of Station Working Rules from English to Hindi and framing out in DIGLOT form (or similar software) as per extant Rly practice. The required SWR in English will be provided by the contractor and has been covered separately in item no. 01011800 of Chapter 1 of SOR. Inspection: Consignee Inspection charges: None Payment terms:100% after execution. | Station | 7.00 | 5,389.49 | 37,726.43 |
| 11 | Making photocopies & binding of the SWR literature in English/Hindi/Diglot form as per Railway practice. Inspection: Consignee Inspection charges: None Payment terms:100% after execution. | Set | 56.00 | 214.85 | 12,031.6 |
| 12 | Supply of maintainer's furniture of Godrej make or superior and each set consist of (i) executive revolving bearing series low back- floating chair with normal arms cushioned chair-01 Nos. (ii) Executive table size 1650x900x728 mm with 3 drawers one side locker- 01 no. (iii) visitor chair seat & back cushion with high density foam with plastic PVC handle capsule type painted back-03 nos. Inspection: Consignee Inspection charges: None Payment terms:100% after execution. | Set | 5.00 | 27,664.71 | 1,38,323.55 |
| 13 | Supply, Installation, testing & commissioning of new modular control desk size 4102x2576 mm for provision of 02 Nos. Monitors made in "XLAT" system as per approved drawing by Engineer in charge. The control desk should be ANSI-BIFMA e3-2019 certified/tested at least for level 3 (from UL/Intertek). 1. Table Top: The material of the working surface shall be made of thermally treated Aluminium - Trihydrate and acrylic resin material supported on minimum 25mm thick MDF base. 2. Structure: Powder Coated Aluminium Sturdy Structure and extreme side Aesthetic Legs. The structure shall be rigid enough to withstand BIFMA X5.5: 2014 (Latest Edition) 3. Monitor Arm: - UL certified monitor arm assembly shall have auto lock, push & remove feature for quick release of VESA mounts and modular arm extensions for ease in maintenance and fixing of monitor by one technician within 30 seconds without using any tools. 4. Shutters & Side Legs: - Front and back shutters hall be of 18 mm Laminated MDF Board with premium finish. Side leg shall be of 25mm of the same finish. Entire console must be Greenguard Gold certified. 5. Slat Wall shall be made of approx. 2mm thick Extruded Aluminium (HE9WP aluminium alloy) and designed in such a way that no joints or gaps are visible in the entire width of the console. The control desk will be provided for storage in the XLAT system, this includes space for housing two numbers of embedded PC, 2 nos. of inverter, 2 nos. of FDMS and their power supply arrangement with proper ventilation & cooling arrangement for CPR cabinet. (To be got approved from Engineer in Charge before supply). Inspection: Consignee Inspection charges: None Payment terms:100% after execution. | Each Module | 5.00 | 1,54,988.05 | 7,74,940.25 |
| 14 | For Supply of Modular power supply arrangement. Payment Terms: 100% after Supply | Set | 18.00 | 2,18,289.6 | 39,29,212.8 |
| 15 | For Installation of Modular power supply arrangement. Payment Terms: 100% after Commissioning | Set | 18.00 | 54,572.4 | 9,82,303.2 |
| Schedule total | ₹13,33,51,452.25 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
ApprovedESPofBHUMBALIYASTATION.pdf
ATTACHMENT
ApprovedESPofDHANERIASTATION.pdf
ATTACHMENT
ApprovedESPofJASNAGARSTATION.pdf
ATTACHMENT
ApprovedESPofKATSAYANISTATION.pdf
ATTACHMENT
TentativeESPofMertaRoadSTATION.pdf
ATTACHMENT
TentativeESPofNEWMERTACITYSTATION.pdf Tentative ESP of NEW MERTA CITY STN
ATTACHMENT
TentativeESPofRASSTATION.pdf
ATTACHMENT
GCC-2022_1.pdf
ATTACHMENT
ACS-1to11.pdf
ATTACHMENT
Tender Document
ATTACHMENT
NoticeforPre-bidConfrence.pdf
ATTACHMENT
ExistingSIPofMertaRoad.pdf
ATTACHMENT
ExistingSIPofRASStation.pdf
ATTACHMENT
TentativeESPofNEWMERTACITYSTATION.pdf
ATTACHMENT
TenderDocumentofRAS-MTDnewlinework.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .