Loading…
Loading…
Tender Value
₹1.6 Cr
EMD Value
₹1.6 L
Closing Date
6 Aug 2026, 6:00 pmClosed
Executive Engineer, Panchayat Road and Building Division, Morbi
Construction of Lunsariya SH to Kerala Approach Road (NP) Km.0/000 to 0/450 Ta.Wankaner, Dist.; Morbi (Under MMGSY-Normal-2026-27)
326441
74 / 2026
Open
Civil - All
Works
Morbi
8 documents required · 8 mandatory
₹3,600
Executive Engineer, Panchayat Road and Building Division, MORBI
₹1.6 L
21 Jul 2026
21 Jul 2026
21 Jul 2026
6 Aug 2026
21 Jul 2026
Name of work :- Construction of Lunsariya SH to Kerala Approach Road (NP) Km.0/000 to
0/450 Ta.Wankaner, Dist.; Morbi (Under MMGSY-Normal-2026-27)
BILL OF QUANTITIES
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
1 Earthwork for embankment including 2250.20 One 162.91
breaking clods, dressing with all lead and lift Cum
(Excluding watering and consolidation) (A)
Selected soil should be From borrow area
with all lead and lift and should have CBR
not less than 6.00%.
2 WBM Grading-1 290.90 One 1422.38
Providing, laying, spreading and compacting Cum
stone agg. Of 90mm to 45mm size to water
bound macadam specification including
spreading in uniform thickness, hand
packing, rolling with smooth wheel roller 80-
100 KN in stage to proper grade and camber,
applying and brooming, stone
screening/binding material to fill-up the
intersties of coarse agg., watering and
compacting to the required density grading-
1 as per Technical Specification Clasue.405
By menual means.
3 Rolling and Watering of earthwork with 2181.40 One 22.95
vibratory roller including filling in Cum
depression which occur during the process
and as directed.
4 Excavation for foundation upto 1.5m depth 942.00 One 927.01
including sorting out and stacking of useful Cum
materials and disposing of the excavated
stuff upto all lead. (C) Hard Rock
5 Excavation of foundation in Sand graval caly 482.80 One 511.11
soft soil and murrum etc. including shoring, Cum
struting dewatering as necessary and
disposing of the excavated stuff as directed.
Depth upto 3.00mt.
6 Excavation of foundation in hard murrum 229.20 One 611.32
and boulders and very stiff or sticky clays Cum
and other similar strata including shorting
out and struting and dewatering as
necessary and disposing of the excavated
stuff as directed.
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
7 Providing and laying rubble for apron (Each 75.90 One 1083.81
stone weighting not less than 40kg) Cum
including and packing and filling in the
interstices with quarry spall.
8 Providing and filling in foundation with 121.70 One 3715.62
ordinary cement concrete M-150 mix and Cum
providing necessary vertical pin headers
incl. Formwork, vibrating, ramming and
curing complete.
9 Providing and casting in situ ordinary 1158.00 One 3921.63
cement concrete M-150 mix and providing Cum
necessary pin headers including shuttering,
scafilding, laying vibrating, curing and
finishing complete Without V-Grooves For
10 Providing and filling in foundation with 171.00 One 3345.58
ordinary cement concrete M-100 mix and Cum
providing necessary vertical pin headers
incl. Formwork, vibrating, ramming and
curing complete.
11 Providing parapet of ordinary cement 35.50 One 1082.18
concrete M-200 as per detailed drawing with Rmt.
necessary reqinforcement including
shuttering laying vibrating and finishing to
line and level complete (ii) cast in situ.
12 Dry Lean Cement Concrete Sub base 242.00 One 2557.11
(Construction of dry lean cement concrete Cum
Sub- base over a prepared sub-grade with
coarse and fine aggregate conforming to IS:
383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not
to exceed 15:1, aggregate gradation after
blending to be as per table 600-1, cement
content not to be less than 220 kg/cum,
optimum moisture content to be determined
during trial length construction, concrete
strength not to be less than 10 Mpa at 7 days,
mixed in a batching plant, transported to
site, laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller,
finishing and curing.
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
13 Cement Concrete Pavement M-25 198.00 One 6578.43
(Construction of un- reinforced, dowel Cum
jointed, plain cement concrete pavement
over a prepared sub base with 53 grade
cement @ 380 kg per cum, coarse and fine
aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding
mm, mixed in a batching and mixing plant as
per approved mix design, transported to site,
laid with a fixed form or slip form paver,
spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and
longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod,
admixtures as approved,curing compund
finishing the lines and grade as per drwaing.
14 Providing and casting in situ Controlled 368.10 One 5198.58
cement concrete M-200 for R.C.C. work in Cum
Piers, abutment, returns and riding returs as
per drawing including centering, shuttering,
scafolding where neccesary laying, vibrating
curing and finishing complete (A) For all
15 Providing and casting in situ Controlled 100.80 One 4697.25
Cement Concrete M-250 for R.C.C. Raft and Cum
cut-off walls including neccesary shuttering
laying, vibrating ramming of curing
16 Providing and casting in situ Controlled 41.90 One 5256.06
cement concrete M 25 for R.C.C. Solid slab Cum
including centering, scaffolding, curing and
finishing complete.
17 Providing and casting in situ Contolled 91.00 One 5271.78
cement concrete- M-200 for average Cum
75/150mm thick wearing coat laid as
directed incuding. tamping, vibrating,
finishing, curring and filling in joints with
bitumen complete.
18 Providing and casting in situ Controlled 2.70 One 4842.86
cement concrete- M-20 mix for kerbs/Kerb Cum
blocks including formwork,curing and
finishing complete.
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
19 Providing and casting in situ Contolled 15.80 One 5235.67
cement concrete- M-25 mix for Approach Cum
slab including formwork, curing and
finishing complete.
20 Providing and laying weep hole in 147.00 One 86.69
Abutment and returns by using A.C pipe of No
100mm. Incl. fixing in proper grade and
jointing the complete as per detailed
21 Providing and laying filter media 600mm. 54.70 One 1239.35
thick directed at the back of abutments, Sqm
returns and wing walls as per detailed
specifications.
22 Providing and laying in Position FE - 8.220 One 73858.69
500/500D TMT bar reinforcement including MT
cutting, bending, hooking and tying
complete as per detailed drawings for the
following (A) Piers (B) Abutments (C)
Returns (D) Walls etc.
23 Providing and Fixing in position FE- 18.050 One 73243.01
500/500D TMT bar reinforcement including MT
cutting, bending, hooking, and tying
complete as per detailed drawaing (A)RCC
kerb (B) RCC Footpath (B) RCC Solid Slab/
App. Slab / Wearing coat.
24 Providing 12mm. Thick Pre-moulded asphalt 5.00 One 703.52
filler joints as per drawings Sqm
25 Providing G.I. 100mm. Diameter water 12.00 One 536.02
spouts including necessary iron gratings as No
26 Providing flood gauge marks on sub 9.00 One 167.03
structure as per design including painting Rmt.
27 Filling available excavated earth (excluding 68.80 One 136.91
rock ) in trenches plinth sides of foundation Cum
etc. in layers not exceeding 20cm in depth
consolidating each deposited layer by
ramming and watering.
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
28 Supplying and fixing reinforced concrete 187.50 One 5560.00
heavy duty non presure pipes with collars Rmt.
for culverts carrying heavy traffic as per IS
458-1991 specification including setting and
joinng the pipes in C.M. 1:2 watering and
laying (to level or slope) of I.S. Class NP-3 of
following internal diameter with all lead and
lift. (i) 1200mm Dia.
29 Providing temporary all weather and fair 80.00 One 2465.41
weather diversion suitable for traffic during Rmt.
the construction period of the bridge / Slab
drain including providing necessary drains
and all safety measures including red lamps
/ signals at night for traffic etc. complete..
30 Providing and fixing Precast cement concrete 2.00 One 356.49
Hectometer as per IRC type design incl. No
painting, lettering etc. fixing in C.C. 1:5:10.
31 Providing and fixing Precast cement concrete 120.00 One 350.80
Guard stone as per I.R.C. type design No
including white washing etc. complete.
Fixing in C.C.1:5:10.
32 Providing and fixing Indicator stone of 21.00 One 102.84
approve stone as per I.R.C. type design in No
C.C. 1:4:8 including white washing etc.
complete Fixing in Earth
33 Providing and fixing Flood guage post mark 6.00 One 1140.29
of 'C' angle size 100mm x 50mm x 6mm thick No
(in head wall 0.500mt. And 1.50mt. Out side
with painting and lettering with redeum
color as directed.
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
34 Village/Bump Ahead sign. : Providing and fixing 1.00 One 5045.36
sign boards made out of 2mm Aluminium sheet size No
90x60 cms. Rectangle as per the design of IRC-67-1977
pre treated with phospheting process and acid
etching coated with one coat of apoxy primer and two
coats of best quality epoxy paint reflectorised with
retro reflective sheeting as per latest MOST
specification letter and numbers should be as per
IRC:30-1968, 3.1 Mt. long (2 nos) stand post and frame
fabricated from suitable size iron angle of
50x50x5mm, painted with best quality epoxy coating
in black and white bends, the details of symbole on
inscription/ numerals for each board shall be as per
the instruction of the Engineer in charge. The fixing at
site shall be in C.C 1:2:4 block of size 45x45x60cms. for
each leg including excavation curring etc. complete
under the supervision of engineer in charge (A)
Engineer Grade.
35 Hazard Marker sign : 4.00 One 2423.73
Providing and Fixing sign boards made out of 2mm No
aluminum sheet : size 90*30 cms. rectangle as per
design / Drawing attached (IRC). Pretreated with
phospheting process and acid etching : coated with
one coat of epoxy primer and two coats of best
quality epoxy paint: reflectorised with retro reflective
sheeting as per latest M.O.S.T specification: 3.1 M.
long (2 nos) stand post and frame fabricated from
suitable size iron angle of 35*35*3mm and 50*50*5mm
: painted with best quality epoxy coatings in black
and white bends the details of symbole or inscription
/ numerals for each board shall be as per the
instruction of engineer in charge the fixing at site
shall be in 1:2:4 CC block of size 45*45*60 cms for each
leg: including excvation curing etc. comp.under the
supervision of engineer-in-charge.(B) Engineering
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
36 Direction sign (Junction board):-Providing and fixing 1.00 One 14831.70
sing boards made out of 2mm aluminium sheet; size No
244 x 122cms. rectangle as as per the design of IRC-67-
1977 pre treated with phospheting process & acid
etching; coated with one coat of epoxy primer and
two coats of best quality epoxy paint; reflectorised
with retro refiective sheeting as per latest M.O.S.T.
Specifications; Letters and numerals should be as per
IRC-30-1968, 3.1m long (2 nos) stand post and frame
fabricated from suitable size iron angle of 50 x 50 x
5mm 75x75x6mm as required; painted with best
quality epoxy coatings in black and white bends. the
details of symbol or inscription / numerals for each
board shall be as per the instruction of engineer in
charge. The fixing at site shall be in 1:2:4 CC block of
size 45 x 45 x 60cms. for each leg. including
excavation curing etc. complete under the supervision
of engineer in charge.(A) Engineer Grade(VR)...
37 Sign Board per square Meter :-Providing and fixing 4.00 One 7615.37
sing boards made out of 2mm aluminium sheet; size 1 No
Meter x 1 Meter as as per the design given by
engineer in charge pre treated with phospheting
process & acid etching; coated with one coat of epoxy
primer and two coats of best quality epoxy paint;
reflectorised with retro refiective sheeting as per latest
M.O.S.T. Specifications; Letters and numerals should
be as per IRC-30-1968, 3.1m long (2 nos) stand post
and frame may be fabricated either from suitable size
iron angle of 35 x 35x 3mm & 50 x 50 x 5mm & 75 x
75 x 6mm as required painted with best quality
epoxy coatings in black and white bends. the details
of symbol or inscription / numerals for each board
shall be as per the instruction of engineer in charge.
The fixing at site shall be in 1:2:4 CC block of size 45 x
45 x 60cms. for each leg. including excavation curing
etc. complete under the supervision of engineer in
charge.(A) Engineer Grade(VR)...
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
38 Cautionary Warning Sign : Providing and fixing sign 6.00 One 3808.65
boards made out of 2mm Aluminium sheet size No
90x90x90 cms. Equilateral treangle as per the design
of IRC-67-1977 pre treated with phospheting process
and acid etching coated with one coat of apoxy
primer and two coats of best quality epoxy paint
reflectorised with retro reflective sheeting as per latest
MOST specification 3.1 Mt. long stand post and frame
fabricated from suitable size iron angle of
35x35x3mm, 75x75x6mm. as required painted with
best quality epoxy coating in black and white bends
the details of symbole for each board shall be as per
the instruction of Engineer in charge the fixing at site
shall be in 1:2:4 CC block of size 45x45x60cms. for
each leg including excavation curring etc. complete
under the supervision of engineer in charge (A)
Engineering Grade.
39 Citizen's information Board. Providing and fixing of 1.00 One 7393.20
typical MMGSY information board as per instruction. No
Two MS sheets of 3 mm thick, of 900 mm x 750mm
size fixed at top & bottom duly rivetted with MS
angles of 25 x 25 x 5 mm thick M.S angle shall be
welded by two vertical M.S angle of 5 mm thick to
mm x 75 mm of 12 SWG square tubes posts duly
embedded in cement concrete M-15 grade blocks of
600mm x 600mm x 750mm, below ground level. The
letters & figure of any shade reflectorised with High
Intensity Prismatic Grade Retro Reflective Sheeting of
Type-4 as per ASTM D-4956 and latest MORD
specifications; All sections of framed posts and steel
tube will be painted with primer and two coats of
epoxy paints as per drawing Clause 1701 and
Annexure 1700.1 (10.16). (A) Class-B High intensity
Grade Retro Reflective sheeting.
40 Providing and erecting a "W" metal beam 46.00 One 3723.46
crash barrier comprising of 3mm thick Rmt.
corrugated sheet metal beam rail, 70cm
above road/ground level, fixed on ISMC
series chanel vertical post, 150x75x5mm
spaced 2m center to center, 1.8m high, 1.1m
below ground/road level, all steel parts and
fitments to be galvanised by hot dip process,
all fittings to confirm to IS: 1367 and IS
metal beam rail to be fixed on the vertical
post with a spacer of chanel section
150x75x5mm, 330mm long complete.
Rupees One Crore Sixty Four Lakh(s) Sixty Four Thousand Six Hundred And
Paise Seventy Six Only
Item Description of Item (With brief specification Quantity Unit Rate Amount
No. and reference to book of Specification)
I \ We am \ are willing to carry out the work at ……………………… % above \ bellow percent
( Should be written in figures and words ) of the estimated rate mentioned above. Amount of My
\ Our tender works put as under.
* Estimated Amount * Estimated Amount
Put to tender Rs…………………… Put to tender Rs……………………
Deduct……..……..% Add……..……..%
In words………………….……………… In words………………….………………
1.The Contractor shall exhibit a board with detailed specification and details of work as directed
by the Engineer-In-Charge for which no extra payment shall be made.
2.The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3.GST and Income tax TDS will be deducted at a source while making payments of bills
4.In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per
Govt. G.R.: PRC-10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in
S.O.R. therefore in R.C.C. items where there is a change as per actual mix design the cost
of difference of cement consumption have been deducted from the rate of original item at the
rate of input rate mentioned in all the tender.
Signature of Contractor.
Deputy Executive Engineer Executive Engineer
Panchayat R&B Sub Division Panchayat R&B Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1 SBD Lunsariya-MM-N-NP-Wankane.pdf
2 Speci Lunsariya-MM-N-NP-Wankane.pdf
3 CC Road Condition and photoes etc.pdf
4 Performance Bond and Bitumen date.pdf
5 Sch - B.pdf
6 GR.pdf
7 Envirement MMGSY.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .