Loading…
Loading…
Tender ID
Tender Value
₹12.4 L
EMD Value
₹13,000
Closing Date
16 Apr 2026, 6:00 pmClosed
Executive Engineer, Panchayat (R&B) Division, Tapi
New Gujarat Pattern 2025-26 Const. of Physical Infrastructure / Inter Facility at in Cricket Ground at Village Kukarmunda Ta.Kukarmunda Dist.Tapi.
295633
33 OF 2025-26
Open
Civil Works - Buildings
Works
Tapi
6 documents required · 6 mandatory
₹900
Executive Engineer, Panchayat (R&B) Division, Tapi-Vyara
₹13,000
9 Apr 2026
9 Apr 2026
9 Apr 2026
16 Apr 2026
9 Apr 2026
It. Rate In
Specification and reference to book of Quantity Unit Amount
No. Figures
specifications)
1 Excavation for foundation upto 1.5 m depth 28.80 Cum. 261.81
including sorting out and stacking of useful
materials and disposing off the excavated stuff
upto 50 Meter lead.(C) Hard Murrum
2 Filling available excavated earth (excluding rock 14.40 Cum. 133.65
in trenches plinth, slides of foundations etc. in
layers not exceeding 20 cm in depth
consolidating each deposited layer by ramming
and watering)
3 Filling in foundation and plinth with murrum or 78.74 Cum. 296.29
including watering ramming and consolidating
etc. complete
4 Providing and laying cement concrete 1:2:4 (1- 14.22 Cum. 3786.47
Cement : 2- Coarse sand : 4- graded stone
aggregates 20 mm nominal size) and curing
complete excluding cost of formwork in (A)
Foundation and Plinth (more than 10 ton)
5 Providing and laying controlled cement concrete 7.02 Cum. 5020.83
M.200 and curing complete the cost of formwork
but excluding reinforcement for reinforced
concrete work in (A) Foundations, footings,
Base of columns and Mass concrete. (more
than 10 ton)
6 Providing and laying controlled cement concrete 0.82 Cum. 8923.24
M-200 and curing complete including the cost of
form work but excluding cost of reinforcement
for reinforced concrete work for Column upto
plinth level.
7 Providing and laying controlled cement concrete 10.62 Cum. 6378.59
M.200 and curing complete the cost of
formwork but excluding reinforcement for
reinforced concrete work in (D) Columns, Pillars
posts and struts, upto floor two level. (more than
8 Brick work using common burnt clay building 5.26 Cum. 4121.55
brick having crushing strength not less than
kg/sq. cm. in foundation and plinth in cement
mortar 1:6 ( 1 Cement: 6 fine sand) (B)
Convention
9 Providing and laying controlled cement concrete 4.32 Cum. 8870.29
M.200 and curing complete the cost of
formwork but excluding reinforcement for
reinforced concrete work in (D) Columns, Pillars
posts and struts, upto floor two level. (more than
10 Providng TMT bars renforcement of FE 3504.74 kg 77.29
500/500D for R.C.C. work including bending
binding and placing in position complete for all
11 Brick work using common burnt clay building 34.48 Cum. 4403.40
brick having crushing strength not less than
kg/sq. cm. in super structure above plinth level
up to floor two level in cement mortar 1:6 (
Cement: 6 fine sand) (B) Convention for G.F
12 Providing 15mm thick cement plaster in single 123.42 Sqmt 222.24
coat on Rough (Similar)side of single or half
brick walls for interior plastering upto floor two
level and finished even and smooth in (ii)
Cement mortar 1:4 (1-cement :4-sand)
13 Providing 20mm thick cement plaster in single 111.64 Sqmt 337.52
coat on single or half brick walls for interior
plastering upto floor two level and finished even
and smooth in (iii) Cement mortar 1:6 (1-
cement:6-sand)
14 Wall painting (two coats) with plastic emulsion 123.42 Sqmt 86.92
paint of approved brand and manufacture with
on undecorated wall surface to give an even
shade including throughly brushing the surface
free from mortar droppings and other foreign
matter and sand papered smooth along ceilings
and sloping roofs.
15 Finishing wall with water proofing cement paint 111.64 Sqmt 117.40
of on wall surface ( Two coats) to give an
approved brand manufacture and of requred
shape even shade after throughtly brushing of
loose powered materials.
16 Steel work, welded in built up sections framed 24.38 Qui 9951.07
work including cutting, hoisting, fixing in position
and applying a priming coat of red lead paint.
(D) In trussses and trussed purlins, upto 25 M.
span and 15 M. ovarall height.
17 Providing corrugated G.I. sheet of class-3 168.10 Sqmt 734.19
roofing fixed with glavanished iron J or L
Hooks, Bolts and nuts 8mm diameter with
bitumen and G.I. limpet washer or G.I. limpet
washer. filled with white lead complete
excluding the cost of purlins, Rafters and
Trusses.(1) 0.80 mm thick sheet.
18 Providing and laying polished Kota stone slab 107.26 Sqmt 1015.82
flooring over 20mm (Average) thick base of
cement mortar 1:6 (1-cement : 6-coarse sand)
or L.M. 1.1.5 (1-Lime putty :1.5 - coarse sand)
laid over and jointed with grey cement slurry
mixed with pigment to match the shade of slab
including rubbing and polishing etc. complete.
(A) 25mm thick
I / Weam / are willing to carryout the work at…………………. % above/ below percent (Should
Be written in figures and words) of the estimated rate mentioned above Amount of my / our
tender works out as under.
*Estimated amount put to tender *Estimated amount put to tender
Deduct ……. % below Rs…………………… Add ………........% Above
Net Rs. …………………….… Total Rs. ………….……....
In words ………………….……………………………. In words ………………….…………………
*( please strike out whichever is not applicable)
1 The Contractor shall exhibition board with detailed specification and details of works
directed by the Engineer – In – Charge for which no extra payment shall bemade.
2 The labourcess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills.
4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as
per Govt G.R.: PRC-10/2017 Cement Consumption/16/C Date: 11/05/2017 as stated in
S.O.R. therefore in R.C.C. items where the reisa change as per actual mix design the cost
of difference of cement consumption have been deducted from the rate of original item at
the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of the contractor Panchayat (R & B) Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD Pavalian shed Kukarmunda.pdf
BOQ_Pavalian shed Kukarmunda.pdf
building booklet.pdf
GRs - SBD with Index.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .