| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹22.9 LAccepted-AOC WARD NO 04 SUNHARI KICHHA U S NAGAR | CHAMOLI | UTTARAKHAND | 246401 | ₹22.9 L Quoted ₹24.9 L | L-1 | Accepted-AOC Work Awarded |
| 2 | L-2₹25.0 L+₹6,698 (0.27%)Rejected-Finance KATORATAL STREET KASHIPUR U S NAGAR | DEHRADUN | UTTARAKHAND | 248001 | ₹25.0 L+₹6,698 (0.27%) | L-2 | Rejected-Finance Due to higher rate |
| 3 | L-3₹25.0 L+₹14,976 (0.60%)Rejected-Finance WARD NO 01 PUNJABI COLONY GADARPUR U S NAGAR | LUDHIANA | PUNJAB | 141001 | ₹25.0 L+₹14,976 (0.60%) | L-3 | Rejected-Finance Due to higher rate |
Tender Value
Refer Docs
EMD Value
₹75,000
Closing Date
5 Jun 2023, 11:00 amClosed
Superintending Engineer
Electricity Distribution Circle, Rudrapur
Preventive Maintenance of 25 KVA, 63 KVA, 100 KVA Transformers related to 33/11 KV S/s Lalpur under Electricity Distribution Division, Kichha
2023_UPCL3_58498_1
EDC(USN)17/2023-24
Open Tender
Electrical Works
Item Rate
90 days
Lalpur
Pl. refer tender documents
3 documents required · 3 mandatory
₹1,180
EE ETD Rudrapur
₹75,000
19 Jul 2023
16 May 2023
6 Jun 2023
16 May 2023
5 Jun 2023
16 May 2023
Amount
Annexure -A ( Works )
Cartage of different line materials from Store Center Haldwani/ Rudrapur/ Kashipur to Work Site Including Loading & Unloading safely (Distance upto 70 Km)
Head load cartage of material road side to work site charges of cable and other materilas
Charges of Dismentaling of 25 KVA transformer from double pole, opening of all connections, circuits with help of required T&P as per side requirment As per direction of Engineer-In-Charge.
Charges of Dismentaling of 63 KVA transformer from double pole, opening of all connections, circuits with help of required T&P as per side requirment As per direction of Engineer-In-Charge.
Charges of Dismentaling of 100 KVA transformer from double pole, opening of all connections, circuits with help of required T&P as per side requirment As per direction of Engineer-In-Charge.
Charges of Top up of oil including replacement of LT/HT bushing /bushing rod and gasket including opening of top cover of transformer and refixing of 25 KVA, as per direction of Engineer-In-Charge.
Charges of Top up of oil including replacement of LT/HT bushing /bushing rod and gasket including opening of top cover of transformer and refixing of 63 KVA, as per direction of Engineer-In-Charge.
Charges of Top up of oil including replacement of LT/HT bushing /bushing rod and gasket including opening of top cover of transformer and refixing of 100 KVA, as per direction of Engineer-In-Charge.
Charges of Mounting of 25 KVA Transformer on double pole and LT/HT connections and balancing of load on all three phases and missing current flowing through nutral upto minimum permission limit as per dirrection of Engineer-In-Charge.
Charges of Mounting of 63 KVA Transformer on double pole and LT/HT connections and balancing of load on all three phases and missing current flowing through nutral upto minimum permission limit as per dirrection of Engineer-In-Charge.
Charges of Mounting of 100 KVA Transformer on double pole and LT/HT connections and balancing of load on all three phases and missing current flowing through nutral upto minimum permission limit as per dirrection of Engineer-In-Charge.
Charges of Inspection of transformer body leakeage and repairing of that by Oxy-accetelne gas welding afer lift up of core and drainage of oil and refixing of 25 KVA T/F as per direction of Engineer-In-Charge.
Charges of Inspection of transformer body leakeage and repairing of that by Oxy-accetelne gas welding afer lift up of core and drainage of oil and refixing of 63 KVA T/F as per direction of Engineer-In-Charge.
Charges of Inspection of transformer body leakeage and repairing of that by Oxy-accetelne gas welding afer lift up of core and drainage of oil and refixing of 100 KVA T/F as per direction of Engineer-In-Charge.
Charges for fabrication of fuse set by MS Channel/Angle & fixing all accessories completer job, as per direction of Engineer in charge.
Charges of opening & reconnection of various consumer cable supplied by particular transformer for laod balancing of transformer.
Charges of Replacement of L.T. Cable incduing refixing of new cable with crimping of Lugs with all accessorious complete work.
Charges of erection of M.S. earthing rod 20x2500 mm including fixing of G.I. Strip after cutting/drilling for nuetral and body As per direction of Engineer-In-Charge.
Charges for replacement of 11KV Jumper at double pole structure.
Annexure - B ( Supply )
Supply of Alluminium Lugs 70 Sq. MM (For LT side) ( As per sample ) Sample may be seen at JE Store Rudrapur
Supply of Alluminium Lugs 120 Sq MM (For LT side) ( As per sample ) Sample may be seen at JE Store Rudrapur
Supply of Holding Clamp
Supply of Gasket as per standards (neo k tex type or similar)
Supply of H.T. Bushing Rod (brass) ( As per sample) Sample may be seen at JE Store Rudrapur
Supply of L.T. Bushing rod (brass) (Complete set) (As per sample) Sample may be seen at JE Store Rudrapur.
Supply of Copper strip
Supply of Alluminium Lugs 95 Sq. MM (For HT side) ( As per sample ) Sample may be seen at JE Store Rudrapur
Supply of Nut and Bolt Offsize
M/S J K ELECTRICALS
HIMALAYA BUILDCON
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .