| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.6 LAccepted-AOC MOONIDIH DHANBAD 828129 | DHANBAD | DHANBAD | JHARKHAND | 828129 | ₹16.6 L Quoted ₹12.8 L | L1 | Accepted-AOC L1 |
| 2 | Rejected-Technical COAL INDIA LIMITED | - | - | Rejected-Technical Working Capital was not as per NIT |
Updated dates
Tender Value
₹12.5 L
EMD Value
₹15,671
Closing Date
3 Feb 2026, 5:00 pmClosed
S.K.Panja
Office of the Project Officer,WJ Area
Transportation and laying fitting of 30lb track line from D18 BG / 10 dip to 19 face . Moonidih Colliery, W J Area
2026_BCCL_351518_1
BCCL/WJA/MND/SUR/2025-26/103
Open Tender
Miscellaneous Works
50 days
Moonidih Colliery, WJ Area
Please refer to NIT
11 documents required · 11 mandatory
₹15,671
17 Apr 2026
20 Jan 2026
4 Feb 2026
20 Jan 2026
3 Feb 2026
20 Jan 2026
Transportation and laying fitting of 30lb track line from D18 BG / 10 dip to 19 face . Moonidih Colliery, W J Area
mannual transport 687m distance , 30lb track line from 10dip / d18 BG to face xvi T seam to D18 TG/ 10 th rise . ( laying fitting 212 + 475= 687m track). track reqired 687/5 X 2 = 274 numbers track line . Analyaia mannual trasport 30lb track , 4 unskilled manshift transport 12 numbers of track. Cost/ track= (1402.60x 4)/12= 467.53/track
transport sleeper 687 nos sleeper Analysis 1 unskilled manshift transport 9 sleepers. Cost (1402.6x1) /9= 155.84/ sleeper
laying fitting of 687m 30lb track line, analysis :- 8 unskilled reqired for 40m laying fitting (both) track. Cost /m = (8 x1402.6)/40= Rs 280.52/m
packing of track line, 687m, analysis 6 unskilled requird for 50m packing. Cost/m = (6 x 1402.60)/50= Rs168.31/m
dimantle from 8dip to 10 dip at old RH2 260m 6 unskilled Manshift required for Dismantling of 40mt track line (both track) . Costf for 40 mt 30lbs trackline=6x1402.6/40=Rs.210.39m
transport 260m track line (260/5)X2 = 104 number rail up to d18 bg 10 dip . 4 unskilled manshift transport 12 numbers of track. Cost/ track= (1402.6x 4)/12= Rs467.53/track
tranport 150 numbersleeper up to D18 BG 10 dip Analysis 1 unskilled manshift transport 9 sleepers. Cost (1402.6 x1) /9= 155.84/ sleeper
450m ( 450/5)x2= 180 number 30 lb track line transport from surface pit top to pit bottom mannual lowering , 400 pit bottom mannually loading , and transport by loco and haulage up to to 9dip d18 BG . (a) lowaring 8 skilled manshift is required for 10 numbers 30lb track line
(b) 6 unskilled is required for loading pit bottom and unloading 9 dip 18 BG, 01 arm trolly required for 12 track line, arm trolly is required 180/12= 15 trolly.
transport 550 number of sleeper, from pit top to D18 bg 10 dip . @ 50 numers of sleeper one mine car. 8 unskilled man shift is required for loading at pit top unloading at 9th dip D18 BG sleeper in mine 4 cars. Mine cars required= 550/50=11 mine car. (8x1402.60)/4=2805.2/ mine car
02 number making of curves 30lb analysis 6 unskilled manshift is required for making 3nos curves. Cost/curve= (1402.6x6)/3=Rs 2805.2/curve
mannual transportation of V fro DR3 to D19 BG , 01 numbers, analysis 8 unskilled manshift and 2 shift required for transportation Cost /V= (8x1402.6) x 2 shift= 22441.6/v
laying and fitting of curve and v along with pulley. Analysis for laying and fitting and packing of v and curve , 8 manshift is required cost /fitting curve= (1402.6x8)= 11220.8
Add CP 15% as per clause 4.17.1 of Civil Eng. Manual & BCCL SOR
CMPF, Pension and admin. Charge of Employee Un Skilled
CMPF, Pension and admin. Charge of Employee Skilled
Total impact of GST for the purpose of CTC
stage.html
html • 0.04 MB
techsummary_364273.pdf
BOQ Comparative Chart
xlsx
finsummary_364273.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.61 MB
BOQ_364273.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid